US3229468A - Method of constructing retaining wall - Google Patents
Method of constructing retaining wall Download PDFInfo
- Publication number
- US3229468A US3229468A US105635A US10563561A US3229468A US 3229468 A US3229468 A US 3229468A US 105635 A US105635 A US 105635A US 10563561 A US10563561 A US 10563561A US 3229468 A US3229468 A US 3229468A
- Authority
- US
- United States
- Prior art keywords
- sheet
- sheets
- berm
- line
- ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0258—Retaining or protecting walls characterised by constructional features
- E02D29/0266—Retaining or protecting walls characterised by constructional features made up of preformed elements
Definitions
- the present invention is especially useful in constructing canal bulkheads in the southern portions of the United States, specifically in States like Florida wherein swampy or low land is being reclaimed for both residential and business building purposes.
- bodies of water such as canals by digging out the swampy or low land and using the dugout earth to build up dry land areas between such canals.
- these slabs are poured on the job site, and following setting of the concrete, the slabs are then jetted in place by standing the slabs on edge and applying water pressure from a hose noule to part the earth and permit the slabs to be partially sunk into the ground along the edge or berm line of the canal.
- berm line means the juncture of the upper end of the canal bed or berm with the surface of the ground adjoining such canal.
- Another object is to provide such a method wherein corrugated sheets, of economical, light weight and rigid material such as asbestos cement, are used instead oi the more costly concrete slabs, thereby eliminating the need for a crane and crane operator in a typical installation, as well as the pouring of such slabs, and also reducing construction time.
- a further object is to provide such a method wherein the corrugated sheets may be readily locked together to prevent one sheet from sinking further into the ground than the previously erected sheet, and thereby readily obtain a level retaining wall.
- Still another object is to provide such a method wherein stabilized soil is used to reduce the horizontal thrust exerted on the corrugated sheets by the backfill, thereby to permit using such sheets of minimum weight and strength for further savings in both material and labor costs.
- FIG. 1 is a perspective view illustrating the inventive method wherein the corrugated sheets are jetted in place along the berm line of a body of water such as a canal, and the adjacent sheets are locked together by a loop of wire;
- FIG. 2 is an enlarged fragmentary horizontal section al view taken on line 2-2 of FIG. 1 and illustrates how the wire passes through an opening provided in the overlapping corrugations of adjacent sheets;
- FIG. 3 is a vertical sectional view taken along line 3-3 of FIG. 1 and also illustrates the completed retaining Wall following (1) formation of the inclined embankrnent of stabilized soil at the foot of the exposed inland sides of the sheets; (2) the formation of the cap on the upper edges of the sheets and the deadman behind the sheets, and the installation of the anchor rod connecting the cap and deadman; and (3) the back filling operation;
- FIG. 4 is an enlarged partial perspective view illustrating a spring wire clip which may be used to lock the sheets together instead of the wire loop of FIGS. 1 and 2, and
- FIG. 5 is a vertical sectional view taken on line 5-5 of FIG. 4 and illustrating how the leg portions of the wire clip are sprung against the opposite sides of overlapping corrugations of adjacent sheets.
- a portion of a body of Water such as a canal is indicated generally at C.
- the berm or sloping upper portion of the bed of the canal is indicated at B, and the intersection or juncture of the berm with the surface of the ground or dry land G is indicated at BL. This juncture will be hereinafter referred to as the berm line.
- the completed retaining wall :01 canal bulkhead W includes a plurality of juxtaposed corrugated sheets 10.
- These sheets are preferably severally made of a rigid, light-weight mineral fiber-cement material such as asbestos cement, and are commercially available.
- the sheets 10 are of elongated rectangular shape, varying in length from about 4 feet to about 12 feet measured longitudinally of the corrugations, and are usually about 42 inches wide.
- each such asbestos cement sheet varies in weight from approximately 4.2 lbs. per square foot to about 5.8 lbs. per square foot.
- each sheet has a modulus of elasticity varying from about 3.4 x 10 psi. from the thinnest sheet to about 5.4 x 10 psi. for the thickest sheet.
- the moment of inertia varies from about 0.764 infi to about 1.26 in.*; the section modulus from about 1.01 in. to about 1.58 in. the modulus of rupture of breaking stress from about 3380 p.s.i. to about 6000 p.s.i., and a shear load per foot width from about 2795 lbs. to about 5880 lbs. Since these saturated strength values are approximately of those for a completely dry product, and since these sheets have a high strength to Weight ratio, their suitability for retaining wall use is evident.
- Each sheet 10 is partially sunk into the ground along the berm line BL, until its corrugations extend downwardly a substantial distance below the surface of the ground as well as a substantial distance above such surface, preferabiy one-half its length below and above ground, and the sheets are arranged with their adjacent end corrugations overlapping.
- This sinking or jetting operation is performed by directing water under pressure to part the earth along the berm line BL, the usual nozzle 11 and hose 12, which are connected to a pump (not shown) drawing the water from the body of water C, being used for this purpose.
- each sheet may be provided with an opening 13 extending through its end corrugation near its top edge, and a wire 14 may be looped through the alined openings 13, to extend along the opposite sides of and over the top edges of the overlapping corrugations, after which the ends of the wire are tied together.
- the purpose of such tie wire 14 is to prevent a later erected sheet from settling further into the ground than the previously erected sheet, and thereby provide a level wall.
- the sheets may be locked together by a generally U-shaped, spring wire clip 15.
- This clip may be driven in place so that its flat base or closed end portion 16 straddles the top edges of the overlapping end corrugations of adjacent sheets 10, while its longer, straight leg 17 extends down along the outside of one sheet and its shorter bent leg 18 extends down along the outer side of the other sheet.
- the shortest distance between legs 17 and 18 of clip is slightly smaller than the combined thickness of the sheets 10.
- the legs 17 and 18 are sprung into frictional engagement with the opposite sides of the overlapping corrugations, in order to securely lock the sheets together.
- the bending of leg 18 enhances this function, and its diverging outer end portion facilitates installation of the clip.
- this stabilized soil is a mixture of from 3 to 12 percent self-setting cementitious material, i.e. Portland cement or equivalent, and from 88 to 97 percent of the available soil.
- the precise ration of cementitious material to soil will depend on the type of soil available and the strength desired.
- the stabilized soil S is formed into an inclined embankment E of generally triangular cross section and is bounded by the berm line BL, the exposed inland sides of sheets 10 and the surface of the ground G leading inland from the berm line BL. While the embankment E of stabilized soil S may extend almost to the top edges of the sheets 10, it has been found sufiicient to make the height of such embankment about one-half the height of the exposed portions of sheets 10. Likewise, the cross section of the embankment forms generally an isosceles right triangle when the sheets are sunk in a vertical position, which is usually, but not necessarily the case.
- top edges of the sheets are reinforced by a concrete cap 20 which is poured in place by employing temporary forms (not shown) secured to the top portions of the sheets 10 in any suitable manner. These caps are in turn reinforced by the usual rods 21.
- a block of concrete 22, commonly known as a deadman is sunk into the ground G the desired distance inland from sheets 10.
- Each deadman 22 and the cap 20 are connected by an anchor rod 23 provided with a larger hook 24 at its lower end which is embedded in deadman 22, and a smaller hook 25 which is secured around a reinforcing rod 21 and embeded in cap 20.
- the anchor rods 23 are loaded to reinforce the upper portion of the retaining wall W.
- the inventive method is practiced by standing the sheets 10 on edge with their corrugations extending upwardly, along the berm line BL.
- Each sheet is sunk or jetted into the ground by water pressure from nozzle 11 which parts the earth along the berm line BL and permits each sheet to settle to the desired level.
- nozzle 11 which parts the earth along the berm line BL and permits each sheet to settle to the desired level.
- two men initially position and guide the sheet as the third man uses the nozzle 11 and hose 12 to perform the jetting operation. Normally, the jetting takes place on the seaward side of the sheets, but it could also be done on the inland side thereof.
- the next or second sheet is positioned adjacent the sunken sheet in the same manner, but with its end corrugation overlapping, either on the inland or seaward side, the end corrugation of the sunken sheet.
- this second sheet is sunk to the same level as the first sheet, these sheets are locked together to prevent further settling of the second sheet.
- this locking operation can be performed by use of the tie wire 14 which is passed through the alined holes 13 in the overlapping corrugations, and these holes may be either preformed in the sheets prior to the jetting operation, or drilled following such jetting operation, as desired.
- this locking operation can be performed by utilizing the spring or clip 15 illustrated in FIGS. 4 and 5, the clip being driven in place by any suitable means such as a hammer.
- the concrete cap 20 is formed on the top edges of the sheets, and the desired number of deadmen each in the form of a concrete block 22 are embedded in the ground G; the cap 20 and each deadman 22 being connected by an anchor rod 23. Once the cap 20, deadmen 22 and another rods 23 are in place, the joints between sheets 10 are sealed in any suitable manner, such as with tar or tar paper, or mortar grout.
- a stabilized soil mixture S may be arranged at the base of the exposed inland sides of the sheets in the desired quantity to form the inclined embankment E. While the use of such an embankment is not absolutely necessary for every installation, it is quite advantageous because it permits sheets 10 of minimum thickness and strength to be used.
- the backfill BF exerts a horizontal thrust on the sheets 10, and this thrust increases toward the base of the exposed portions of the sheets, thereby forming a generally triangular force pattern.
- the inventive method accomplishes its various objects.
- the light-weight rigid corrugated sheets of asbestos cement are easy to handle normally without the need for a crane or a crane operator to position them for the jetting or sinking operation.
- such sheets are economical to manufacture and are preformed prior to being located on the job site.
- the sheets may be effectively locked together to prevent one sheet from sinking further than the adjacent sheet, thereby facilitating the formation of a level wall, as well as the formation of the concrete cap 20 along the top of the wall.
- sheets of minimum thickness and strength can be employed, thereby further reducing cost of installation of such retaining wall.
- a first corrugated sheet of light weight and rigid, mineral fiber-cement material on edge along said berm line with the corrugations extending upwardly; sinking said first sheet into said ground by applying fluid pressure to part the earth along said berm line, until the corrugations of said sheet extend downwardly a substantial distance below the surface of said ground as well as a substantial distance above the surface; arranging and sinking a second sheet of said material in the same manner and to the same level as said first sheet; but with a corrugation overlapping a corrugation of said first sheet; as said second sheet is sunk to said level, locking said sheets together adjacent their upper ends by attaching unitary Wire fastening means extending over the top edges and along the opposite sides of said overlapping corrugations, in order to prevent said second sheet from sinking further into the ground than said first sheet; and after said locking step, forming an inclined embankment of stabilize
- the steps comprising: arranging a first corrugated sheet of light Weight and rigid, mineral fiber-cement material on edge along said berm line with the corrugations extending upwardly; sinking said first sheet into said ground by applying fluid pressure to part the earth along said berm line, until the corrugations of said sheet extend downwardly a substantial distance below the surface of said ground as well as a substantial distance above said surface; arranging and sinking a second sheet of said material in the same manner and to the same level as said first sheet, but with a corrugation overlapping a corrugation of said first sheet; as said second sheet is sunk to said level, locking said sheets together adjacent their upper ends by attaching a unitary Wire loop fastener extending over the top edges of, along the opposite sides of and through an opening provided in said overlapping corrugations, in order to prevent said second sheet from sinking further into said ground than said first sheet; and after said locking step,
- steps comprising: arranging a first corrugated sheet of light Weight and rigid, mineral fiber-cement material on edge along said berm line with the corrugations extending upwardly; sinking said first sheet into said ground by applying fluid pressure to part the earth along said berm line, until the corrugations of said sheet extend downwardly a substantial distance below the surface of said ground as well as a substantial distance above said surface; arranging and sinking a second sheet of said material in the same manner and to the same level as said first sheet, but with a corrugation overlapping a corrugation of said first sheet; as said second sheet is sunk to said level, locking said sheets together adjacent their upper ends by attaching a generally U-shaped, unitary spring Wire clip having its closed end portion extending over the top edges of and its leg portions extending along and sprung into frictional engagement With the opposite sides of said overlapping corrugations, in order to prevent said second sheet from sinking
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Description
L C a ga &% M v C m5 m AV w w M 4 W P G M Jan. 18, 1966 J. w. SCHNELLER METHOD OF GONSTRUCTING RETAINING WALL Filed April 26, 1961 United States Patent Ofitice 3,229,453 Patented Jan. 18, 1966 3,229,468 METHOD F CONSTRUCTING RETAINHNG WALL Joseph W. Schneller, Eggertsville, N.Y., assignor to National Gypsum Company, Buffalo, N.Y., a corporation of Delaware Filed Apr. 26, 1961, Ser. No. 105,635 3 Claims. (Cl. 61-49) This invention relates to a new and improved method of constructing a retaining wall along the berm line of a body of water such as a canal.
The present invention is especially useful in constructing canal bulkheads in the southern portions of the United States, specifically in States like Florida wherein swampy or low land is being reclaimed for both residential and business building purposes. In such areas it is common practice to form bodies of water such as canals by digging out the swampy or low land and using the dugout earth to build up dry land areas between such canals. Once this initial operation is completed, it is then necessary to prevent erosion of the soil adjourning the canals by building retaining walls or bulkheads, and a primary consideration in constructing such retaining walls is cost, from both the material and labor standpoints.
While reinforced concrete slabs have been used in the past to form such retaining walls, this is a rather expensive process. In a typical installation, these slabs are poured on the job site, and following setting of the concrete, the slabs are then jetted in place by standing the slabs on edge and applying water pressure from a hose noule to part the earth and permit the slabs to be partially sunk into the ground along the edge or berm line of the canal. As used herein, the term berm line means the juncture of the upper end of the canal bed or berm with the surface of the ground adjoining such canal.
As will be apparent, these concrete slabs are quite heavy, requiring for a typical installation on a crane and a crane operator to initially position the slabs on edge, two men working on the slab to hold it upright during the sinking operation, and another man using the nozzle of a hose which is connected to a pump supplying water under pressure from the canal for jetting the slabs into place. Moreover, a considerable amount of labor is required to pour the slabs on the job site and a substantial amount of time is lost while the slabs are setting, all adding to the cost of construction. In addition, because of the great weight of such concrete slabs it is extremely difficult to obtain a level wall, as one slab will have a tendency to sink further into the ground than the previously sunk slab.
Accordingly, it is a general object of the present invention to provide a new and improved method of constructing a retaining wall, such as a canal bulkhead, which method results in substantial savings in both material and labor costs.
Another object is to provide such a method wherein corrugated sheets, of economical, light weight and rigid material such as asbestos cement, are used instead oi the more costly concrete slabs, thereby eliminating the need for a crane and crane operator in a typical installation, as well as the pouring of such slabs, and also reducing construction time.
A further object is to provide such a method wherein the corrugated sheets may be readily locked together to prevent one sheet from sinking further into the ground than the previously erected sheet, and thereby readily obtain a level retaining wall.
Still another object is to provide such a method wherein stabilized soil is used to reduce the horizontal thrust exerted on the corrugated sheets by the backfill, thereby to permit using such sheets of minimum weight and strength for further savings in both material and labor costs.
Other objects and advantages of the invention will become apparent upon consideration of the following detailed description and the accompanying drawing wherein:
FIG. 1 is a perspective view illustrating the inventive method wherein the corrugated sheets are jetted in place along the berm line of a body of water such as a canal, and the adjacent sheets are locked together by a loop of wire;
FIG. 2 is an enlarged fragmentary horizontal section al view taken on line 2-2 of FIG. 1 and illustrates how the wire passes through an opening provided in the overlapping corrugations of adjacent sheets;
FIG. 3 is a vertical sectional view taken along line 3-3 of FIG. 1 and also illustrates the completed retaining Wall following (1) formation of the inclined embankrnent of stabilized soil at the foot of the exposed inland sides of the sheets; (2) the formation of the cap on the upper edges of the sheets and the deadman behind the sheets, and the installation of the anchor rod connecting the cap and deadman; and (3) the back filling operation;
FIG. 4 is an enlarged partial perspective view illustrating a spring wire clip which may be used to lock the sheets together instead of the wire loop of FIGS. 1 and 2, and
FIG. 5 is a vertical sectional view taken on line 5-5 of FIG. 4 and illustrating how the leg portions of the wire clip are sprung against the opposite sides of overlapping corrugations of adjacent sheets.
Referring to the drawing, and particularly FIGS. 1 and 3, a portion of a body of Water such as a canal is indicated generally at C. The berm or sloping upper portion of the bed of the canal is indicated at B, and the intersection or juncture of the berm with the surface of the ground or dry land G is indicated at BL. This juncture will be hereinafter referred to as the berm line.
The completed retaining wall :01 canal bulkhead W includes a plurality of juxtaposed corrugated sheets 10. These sheets are preferably severally made of a rigid, light-weight mineral fiber-cement material such as asbestos cement, and are commercially available. Typically, the sheets 10 are of elongated rectangular shape, varying in length from about 4 feet to about 12 feet measured longitudinally of the corrugations, and are usually about 42 inches wide. Depending upon the thickness of sheet desired, which usually varies from about 0.4 inch to about 0.61 inch, each such asbestos cement sheet varies in weight from approximately 4.2 lbs. per square foot to about 5.8 lbs. per square foot. As for their pertinent strength characteristics, when saturated with water and measured on a per foot Width basis, each sheet has a modulus of elasticity varying from about 3.4 x 10 psi. from the thinnest sheet to about 5.4 x 10 psi. for the thickest sheet. Similarly, the moment of inertia varies from about 0.764 infi to about 1.26 in.*; the section modulus from about 1.01 in. to about 1.58 in. the modulus of rupture of breaking stress from about 3380 p.s.i. to about 6000 p.s.i., and a shear load per foot width from about 2795 lbs. to about 5880 lbs. Since these saturated strength values are approximately of those for a completely dry product, and since these sheets have a high strength to Weight ratio, their suitability for retaining wall use is evident.
Each sheet 10 is partially sunk into the ground along the berm line BL, until its corrugations extend downwardly a substantial distance below the surface of the ground as well as a substantial distance above such surface, preferabiy one-half its length below and above ground, and the sheets are arranged with their adjacent end corrugations overlapping. This sinking or jetting operation is performed by directing water under pressure to part the earth along the berm line BL, the usual nozzle 11 and hose 12, which are connected to a pump (not shown) drawing the water from the body of water C, being used for this purpose.
The sheets are locked together adjacent their upper ends by suitable unitary wire fastening means. For example, as shown in FIGS. 1 and 2, each sheet may be provided with an opening 13 extending through its end corrugation near its top edge, and a wire 14 may be looped through the alined openings 13, to extend along the opposite sides of and over the top edges of the overlapping corrugations, after which the ends of the wire are tied together. The purpose of such tie wire 14 is to prevent a later erected sheet from settling further into the ground than the previously erected sheet, and thereby provide a level wall.
Alternatively, as shown in FIGS. 4 and 5, the sheets may be locked together by a generally U-shaped, spring wire clip 15. This clip may be driven in place so that its flat base or closed end portion 16 straddles the top edges of the overlapping end corrugations of adjacent sheets 10, while its longer, straight leg 17 extends down along the outside of one sheet and its shorter bent leg 18 extends down along the outer side of the other sheet. As will be apparent, the shortest distance between legs 17 and 18 of clip is slightly smaller than the combined thickness of the sheets 10. Thus, the legs 17 and 18 are sprung into frictional engagement with the opposite sides of the overlapping corrugations, in order to securely lock the sheets together. The bending of leg 18 enhances this function, and its diverging outer end portion facilitates installation of the clip.
Referring specifically to FIG. 3, it will be noted that the base or lower portions of the exposed inland sides of sheets 10 are reinforced by a quantity of stabilized soil S. Typically, this stabilized soil is a mixture of from 3 to 12 percent self-setting cementitious material, i.e. Portland cement or equivalent, and from 88 to 97 percent of the available soil. The precise ration of cementitious material to soil will depend on the type of soil available and the strength desired.
The stabilized soil S is formed into an inclined embankment E of generally triangular cross section and is bounded by the berm line BL, the exposed inland sides of sheets 10 and the surface of the ground G leading inland from the berm line BL. While the embankment E of stabilized soil S may extend almost to the top edges of the sheets 10, it has been found sufiicient to make the height of such embankment about one-half the height of the exposed portions of sheets 10. Likewise, the cross section of the embankment forms generally an isosceles right triangle when the sheets are sunk in a vertical position, which is usually, but not necessarily the case.
The top edges of the sheets are reinforced by a concrete cap 20 which is poured in place by employing temporary forms (not shown) secured to the top portions of the sheets 10 in any suitable manner. These caps are in turn reinforced by the usual rods 21.
In addition, at spaced points along the length of the wall a block of concrete 22, commonly known as a deadman is sunk into the ground G the desired distance inland from sheets 10. Each deadman 22 and the cap 20 are connected by an anchor rod 23 provided with a larger hook 24 at its lower end which is embedded in deadman 22, and a smaller hook 25 which is secured around a reinforcing rod 21 and embeded in cap 20. As will be apparent, when the space behind the exposed inland portions of the sheets 10 is filled by the earth backfill BF, the anchor rods 23 are loaded to reinforce the upper portion of the retaining wall W.
The inventive method is practiced by standing the sheets 10 on edge with their corrugations extending upwardly, along the berm line BL. Each sheet is sunk or jetted into the ground by water pressure from nozzle 11 which parts the earth along the berm line BL and permits each sheet to settle to the desired level. Typically, two men initially position and guide the sheet as the third man uses the nozzle 11 and hose 12 to perform the jetting operation. Normally, the jetting takes place on the seaward side of the sheets, but it could also be done on the inland side thereof.
Assuming that a first sheet has been sunk to the desired level, the next or second sheet is positioned adjacent the sunken sheet in the same manner, but with its end corrugation overlapping, either on the inland or seaward side, the end corrugation of the sunken sheet. As this second sheet is sunk to the same level as the first sheet, these sheets are locked together to prevent further settling of the second sheet.
As referred to above, this locking operation can be performed by use of the tie wire 14 which is passed through the alined holes 13 in the overlapping corrugations, and these holes may be either preformed in the sheets prior to the jetting operation, or drilled following such jetting operation, as desired. Alternatively, this locking operation can be performed by utilizing the spring or clip 15 illustrated in FIGS. 4 and 5, the clip being driven in place by any suitable means such as a hammer.
The aforedescribed sinking or jetting and locking operations are repeated until the desired length of retaining wall or bulkhead W is obtained.
Following the erection of sheets 10, the concrete cap 20 is formed on the top edges of the sheets, and the desired number of deadmen each in the form of a concrete block 22 are embedded in the ground G; the cap 20 and each deadman 22 being connected by an anchor rod 23. Once the cap 20, deadmen 22 and another rods 23 are in place, the joints between sheets 10 are sealed in any suitable manner, such as with tar or tar paper, or mortar grout.
Following this, and prior to backfilling, a stabilized soil mixture S may be arranged at the base of the exposed inland sides of the sheets in the desired quantity to form the inclined embankment E. While the use of such an embankment is not absolutely necessary for every installation, it is quite advantageous because it permits sheets 10 of minimum thickness and strength to be used. As is well known, the backfill BF exerts a horizontal thrust on the sheets 10, and this thrust increases toward the base of the exposed portions of the sheets, thereby forming a generally triangular force pattern. By employing the inclined embankment of stabilized soil S, much of the horizontal thrust from the backfill BF is directed vertically through the stabilized soil S toward the ground, and thereby removed from sheets 10.
Finally, the backfill BF is moved into place to build up the land behind the sheets 10 of retaining wall W.
It will now be seen how the inventive method accomplishes its various objects. 'For example, the light-weight rigid corrugated sheets of asbestos cement are easy to handle normally without the need for a crane or a crane operator to position them for the jetting or sinking operation. Likewise, such sheets are economical to manufacture and are preformed prior to being located on the job site. In addition, the sheets may be effectively locked together to prevent one sheet from sinking further than the adjacent sheet, thereby facilitating the formation of a level wall, as well as the formation of the concrete cap 20 along the top of the wall. Moreover, by using an inclined embankment of stabilized soil, sheets of minimum thickness and strength can be employed, thereby further reducing cost of installation of such retaining wall.
While the invention has been described and illustrated with reference to certain preferred embodiments, it is to be understood that various changes and modifications may be made in the invention by those skilled in the art without departing therefrom, and that the scope of the invention is to be determined by the appended claims.
What is claimed is:
1. In the method of constructing a retaining wall above ground along the berm line of a body of water, the steps comprising: arranging a first corrugated sheet of light weight and rigid, mineral fiber-cement material on edge along said berm line with the corrugations extending upwardly; sinking said first sheet into said ground by applying fluid pressure to part the earth along said berm line, until the corrugations of said sheet extend downwardly a substantial distance below the surface of said ground as well as a substantial distance above the surface; arranging and sinking a second sheet of said material in the same manner and to the same level as said first sheet; but with a corrugation overlapping a corrugation of said first sheet; as said second sheet is sunk to said level, locking said sheets together adjacent their upper ends by attaching unitary Wire fastening means extending over the top edges and along the opposite sides of said overlapping corrugations, in order to prevent said second sheet from sinking further into the ground than said first sheet; and after said locking step, forming an inclined embankment of stabilized soil of triangular cross section and bounded by said berm line, at least about one-half the height of the exposed inland sides of said sheets and said surface leading inland from said berm line, in order to reduce the horizontal thrust exerted on said sheets by the later applied backfill, said stabilized soil being a mixture of from 3 to 12% self-setting cementitious material and from 97 to 88% soil.
2. In the method of constructing a retaining Wall above ground along the berm line of a body of water, the steps comprising: arranging a first corrugated sheet of light Weight and rigid, mineral fiber-cement material on edge along said berm line with the corrugations extending upwardly; sinking said first sheet into said ground by applying fluid pressure to part the earth along said berm line, until the corrugations of said sheet extend downwardly a substantial distance below the surface of said ground as well as a substantial distance above said surface; arranging and sinking a second sheet of said material in the same manner and to the same level as said first sheet, but with a corrugation overlapping a corrugation of said first sheet; as said second sheet is sunk to said level, locking said sheets together adjacent their upper ends by attaching a unitary Wire loop fastener extending over the top edges of, along the opposite sides of and through an opening provided in said overlapping corrugations, in order to prevent said second sheet from sinking further into said ground than said first sheet; and after said locking step, forming an inclined embankment of stabilized soil of triangular cross section and bounded by said berm line, at least about one-half the height of the exposed inland sides of said sheets and said surface leading inland from said berm line, in order to reduce the horizontal thrust exerted on said sheets by the later applied backfill, said stabilized soil being a mixture of 6 from 3 to 12% self-setting cementitious material and from 97 to 88% soil.
3. In the method of constructing a retaining Wall above ground along the berm line of a body of Water, the steps comprising: arranging a first corrugated sheet of light Weight and rigid, mineral fiber-cement material on edge along said berm line with the corrugations extending upwardly; sinking said first sheet into said ground by applying fluid pressure to part the earth along said berm line, until the corrugations of said sheet extend downwardly a substantial distance below the surface of said ground as well as a substantial distance above said surface; arranging and sinking a second sheet of said material in the same manner and to the same level as said first sheet, but with a corrugation overlapping a corrugation of said first sheet; as said second sheet is sunk to said level, locking said sheets together adjacent their upper ends by attaching a generally U-shaped, unitary spring Wire clip having its closed end portion extending over the top edges of and its leg portions extending along and sprung into frictional engagement With the opposite sides of said overlapping corrugations, in order to prevent said second sheet from sinking further into said ground than said first sheet; and after said locking step, forming an inclined embankment of stabilized soil of triangular cross section and bounded by said berm line, at least about one-half the height of the exposed inland sides of said sheets and said surface leading inland from said berm line, in order to reduce the horizontal thrust exerted on said sheets by the later applied backfill, said stabilized soil being a mixture of from 3 to 12% self-setting cementitious material and from 97 to 88% soil.
References Cited by the Examiner OTHER REFERENCES Roads and Streets (pub), February 1948, pp. -82. Aircraft Engineering of March 1948, p. VIII.
Engineering News-Record (pub), July 7, 1955, pp. 33- 34 American Builder (pub.) of February 1960, pp. 164- 165.
CHARLES E. OCONNELL, Primary Examiner.
JACOB L. NACKENOFF, JACOB SHAPIRO,
Examiners.
Claims (1)
1. IN THE METHOD OF CONSTRUCTING A RETAINING WALL ABOVE GROUND ALONG THE BERM LINE OF A BODY OF WATER, THE STEPS COMPRISING: ARRANGING A FIRST CORRUGATED SHEET OF LIGHT WEIGHT AND RIGID, MINERAL FIBER-CEMENT MATERIAL ON EDGE ALONG SAID BERM LINE WITH THE CORRUGATIONS EXTENDING UPWARDLY; SINKING SAID FIRST SHEET INTO SAID GROUND BY APPLYING FLUID PRESSURE TO PART THE EARTH ALONG SAID BERM LINE, UNITL THE CORRUGATIONS OF SAID SHEET EXTEND DOWNWARDLY A SUBSTANTIAL DISTANCE BELOW THE SURFACE OF SAID GROUND AS WELL AS A SUBSTANTIAL DISTANCE ABOVE THE SURFACE; ARRANGING AND SINKING A SECOND SHEEET OF SAID MATERIAL IN THE SAME MANNER AND TO THE SAME LEVEL AS SAID FIRST SHEET; BUT WITH A CORRUGATION OVERLAPPING A CORRUGATION OF SAID FIRST SHEET; AS SAID SECOND SHEET IS SUNK TO SAID LEVEL, LOCKING SAID SHEETS TOGETHER ADJACENT THEIR UPPER ENDS BY ATTACHING UNITARY WIRE FASTENING MEANS EXTENDING OVER THE TOP EDGES AND ALONG THE OPPOSITE SIDES OF SAID OVERLAPPING CORRUGATIONS, IN ORDER TO PREVENT SAID SECOND SHEET FROM SINKING FURTHER INTO THE GROUND THAN SAID FIRST SHEET; AND AFTER SAID LOCKING STEP, FORMING AN INCLINED EMBANKMENT OF STABILIZED SOIL OF TRIANGULAR CROSS SECTION AND BOUNDED BY SAID BERM LINE, AT LEAST ABOUT ONE-HALF THE HEIGHT OF THE EXPOSED INLAND SIDES OF SAID SHEETS AND SAID SURFACE LEADING INLAND FROM SAID BERM LINE, IN ORDER TO REDUCE THE HORIZONTAL THRUST EXERTED ON SAID SHEETS BY THE LATER APPLIED BACKFILL, SAID STABILIZED SOIL BEING A MIXTURE OF FROM 3 TO 12% SELF-SETTING CEMENTITIOUS MATERIAL AND FROM 97 TO 88% SOIL.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US105635A US3229468A (en) | 1961-04-26 | 1961-04-26 | Method of constructing retaining wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US105635A US3229468A (en) | 1961-04-26 | 1961-04-26 | Method of constructing retaining wall |
Publications (1)
Publication Number | Publication Date |
---|---|
US3229468A true US3229468A (en) | 1966-01-18 |
Family
ID=22306947
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US105635A Expired - Lifetime US3229468A (en) | 1961-04-26 | 1961-04-26 | Method of constructing retaining wall |
Country Status (1)
Country | Link |
---|---|
US (1) | US3229468A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3712069A (en) * | 1971-03-22 | 1973-01-23 | N Rasmussen | Beach protection system |
US3747289A (en) * | 1971-10-22 | 1973-07-24 | E Collins | Cantilevered support system for structures |
US3959938A (en) * | 1973-07-02 | 1976-06-01 | John Zachariassen | Wall system of corrugated sections |
FR2463836A2 (en) * | 1979-08-20 | 1981-02-27 | Malie Louis | Prefabricated reinforced concrete retaining wall segment - has undulating vertical wall and tapered section cast in situ with base section |
US4407611A (en) * | 1980-09-04 | 1983-10-04 | The Secretary Of State For Transport In Her Britannic Majesty's Government Of The United Kingdom Of Great Britain And Northern Ireland | Anchored earth structure |
US4674921A (en) * | 1984-05-04 | 1987-06-23 | Berger Lawrence E | Seawall |
US4690588A (en) * | 1984-05-04 | 1987-09-01 | C-Lock Retention Systems, Inc. | Seawall |
US5368414A (en) * | 1991-07-19 | 1994-11-29 | Miller; Vincent G. | Method and system for rehabilitating a bulkhead |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR399601A (en) * | 1909-02-18 | 1909-07-02 | Charles Carriere | Reinforced cement hollow casing with compressed air chamber for the construction of quayside walls, dykes, jetties, dams, bridge piers and the like |
US975665A (en) * | 1910-04-25 | 1910-11-15 | Julius R Wemlinger | Shoring. |
US1058211A (en) * | 1912-09-25 | 1913-04-08 | Henry D Whipple | Reinforced-concrete retaining-wall. |
US1422821A (en) * | 1915-07-07 | 1922-07-18 | Lackawanna Steel Co | Sheet-piling wall construction |
US1812364A (en) * | 1927-11-29 | 1931-06-30 | George Oursler | Retaining wall structure |
FR785120A (en) * | 1934-04-13 | 1935-08-02 | Pont A Mousson Fond | Process for the construction of metal curtains for banks, banks of canals and others, elements for the implementation of this process and resulting constructions |
US2769277A (en) * | 1953-01-15 | 1956-11-06 | William B Keelor | Terrace barrier or curbing |
US2898741A (en) * | 1950-05-09 | 1959-08-11 | Bowerston Shale Company | Spring clip for perforated pipes and the combination |
US2941371A (en) * | 1958-02-11 | 1960-06-21 | Benedict Louis Neal | Bulkhead and method of forming |
US3031801A (en) * | 1956-12-14 | 1962-05-01 | Edward G Leuthesser | Method of installing swimming pools |
-
1961
- 1961-04-26 US US105635A patent/US3229468A/en not_active Expired - Lifetime
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR399601A (en) * | 1909-02-18 | 1909-07-02 | Charles Carriere | Reinforced cement hollow casing with compressed air chamber for the construction of quayside walls, dykes, jetties, dams, bridge piers and the like |
US975665A (en) * | 1910-04-25 | 1910-11-15 | Julius R Wemlinger | Shoring. |
US1058211A (en) * | 1912-09-25 | 1913-04-08 | Henry D Whipple | Reinforced-concrete retaining-wall. |
US1422821A (en) * | 1915-07-07 | 1922-07-18 | Lackawanna Steel Co | Sheet-piling wall construction |
US1812364A (en) * | 1927-11-29 | 1931-06-30 | George Oursler | Retaining wall structure |
FR785120A (en) * | 1934-04-13 | 1935-08-02 | Pont A Mousson Fond | Process for the construction of metal curtains for banks, banks of canals and others, elements for the implementation of this process and resulting constructions |
US2898741A (en) * | 1950-05-09 | 1959-08-11 | Bowerston Shale Company | Spring clip for perforated pipes and the combination |
US2769277A (en) * | 1953-01-15 | 1956-11-06 | William B Keelor | Terrace barrier or curbing |
US3031801A (en) * | 1956-12-14 | 1962-05-01 | Edward G Leuthesser | Method of installing swimming pools |
US2941371A (en) * | 1958-02-11 | 1960-06-21 | Benedict Louis Neal | Bulkhead and method of forming |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3712069A (en) * | 1971-03-22 | 1973-01-23 | N Rasmussen | Beach protection system |
US3747289A (en) * | 1971-10-22 | 1973-07-24 | E Collins | Cantilevered support system for structures |
US3959938A (en) * | 1973-07-02 | 1976-06-01 | John Zachariassen | Wall system of corrugated sections |
FR2463836A2 (en) * | 1979-08-20 | 1981-02-27 | Malie Louis | Prefabricated reinforced concrete retaining wall segment - has undulating vertical wall and tapered section cast in situ with base section |
US4407611A (en) * | 1980-09-04 | 1983-10-04 | The Secretary Of State For Transport In Her Britannic Majesty's Government Of The United Kingdom Of Great Britain And Northern Ireland | Anchored earth structure |
US4674921A (en) * | 1984-05-04 | 1987-06-23 | Berger Lawrence E | Seawall |
US4690588A (en) * | 1984-05-04 | 1987-09-01 | C-Lock Retention Systems, Inc. | Seawall |
US5368414A (en) * | 1991-07-19 | 1994-11-29 | Miller; Vincent G. | Method and system for rehabilitating a bulkhead |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3226935A (en) | Retaining wall and method of constructing same | |
US3802204A (en) | Retaining wall and method for construction of the same | |
US5551810A (en) | Retaining wall with an outer face and method of forming the same | |
US3934422A (en) | Pile splicing apparatus and method | |
CN108301273A (en) | The fore-telling shaped pile anchor structure and its construction method of guardrail reinforcing integrated with roadbed | |
US5588784A (en) | Soil or rock nail wall with outer face and method of constructing the same | |
US3229468A (en) | Method of constructing retaining wall | |
CN107130608A (en) | Without basement construction method for supporting of the concrete to support | |
US3247673A (en) | Laminated retaining wall and method of constructing same | |
DE2545572A1 (en) | BUILDING ANCHORING | |
USRE28977E (en) | Method for the construction of a retaining wall | |
US3638435A (en) | Method for the construction of a retaining wall | |
JPH11303062A (en) | Soil-cement wall | |
JPS63277319A (en) | Setting of friction pile | |
KR102505365B1 (en) | Support for tunnel shotcrete drop prevention | |
KR102285635B1 (en) | Double line retaining wall self-reliance composite wall construction method for reinforcement pile wall | |
KR100479500B1 (en) | The slope tree-planting structure using socket type steel pipe, and his construction method | |
AU708031B2 (en) | Screeding devices and methods of use | |
CN109183828A (en) | A kind of steel tube-concrete series connection stake combination multi-column pier foundation and its construction method | |
JPH10317381A (en) | Structure for protecting face of slope by retaining wall and method for constructing the same | |
JP2622312B2 (en) | Construction method of double cofferdam | |
CN209066470U (en) | A kind of steel tube-concrete series connection stake combination multi-column pier foundation | |
CN217105151U (en) | Compound high slope supporting construction | |
KR102657512B1 (en) | System blocks and building structures constructed using them | |
CN211973510U (en) | Steel sheet pile and root pile composite foundation pit supporting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AS | Assignment |
Owner name: INTERNATIONAL BUILDING PRODUCTS, INC., 5300 TCHOUP Free format text: ASSIGNMENT OF ASSIGNORS INTEREST.;ASSIGNOR:NATIONAL GYPSUM COMPANY;REEL/FRAME:003939/0922 Effective date: 19810311 |