US2655845A - Concrete pavement - Google Patents

Concrete pavement Download PDF

Info

Publication number
US2655845A
US2655845A US650814A US65081446A US2655845A US 2655845 A US2655845 A US 2655845A US 650814 A US650814 A US 650814A US 65081446 A US65081446 A US 65081446A US 2655845 A US2655845 A US 2655845A
Authority
US
United States
Prior art keywords
area
gap
concrete
pavement
gaps
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US650814A
Inventor
Freyssinet Eugene
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Application granted granted Critical
Publication of US2655845A publication Critical patent/US2655845A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/10Coherent pavings made in situ made of road-metal and binders of road-metal and cement or like binders
    • E01C7/14Concrete paving
    • E01C7/16Prestressed concrete paving
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/02Arrangement or construction of joints; Methods of making joints; Packing for joints
    • E01C11/04Arrangement or construction of joints; Methods of making joints; Packing for joints for cement concrete paving
    • E01C11/045Arrangement or construction of joints; Methods of making joints; Packing for joints for cement concrete paving specially adapted for prestressed paving

Definitions

  • an uninterrupted pavement is capable of withstanding localized moving loads under much better conditions than a pavement having interruptions or gaps (either provided in advance or resulting from the breaking of the pavement) due to the considerable stresses which develop in the pavement when the load passes over such an interruption.
  • the object of my invention is the provision o a concrete pavement which, although having gaps which allow for expansion, behaves as a continuous pavement under loads.
  • the pavement is prestressed by being subjected to permanent compressive stress in two different directions, and in said pavement there is provided at least one interruption forming a gap which is oblique with respect to the directions of compressive stress, the two parts of the area located on either side of the said gap being urged against each other by the compressive stress and being capable of sliding with as low a friction as possible with respect to each other.
  • the pressure is exerted positively along one direction, for instance by means of armatures under tension parallel to the surface of the area which pass through the gap surface or surfaces, while the precompression in the other direction is a result of the first precompression and is obtained by abutment of the parallel ends of the area against rigid supports firmly anchored in the ground.
  • the dimensions of the parts of this area divided by the gaps are capable of varying under the action of the temperature or the humidity while the members which are intended toassure the permanent compression of this area behave like springs and permanently maintain the edges of these parts applied against each other, thus assuring the continuity of the surface of the pavement.
  • the different parts intersected by the gaps are preferably wedge-shaped, the apices being arranged opposite each other in pairs. Upon the expansion of the members, these wedges tend to move away from each other while, if the mem- 2
  • the surface of the ground is conditioned in such a way as to reduce as much as possible the friction of the pavement with respect to the ground.
  • the surface of the ground may, for instance, be previously covered with a layer of fine sand on which there is spread, before applying the pavement, a sheet of paper or felt impregnated with bitumen or asphalt.
  • Figure l is a general plan view of an elon ated area, for instance, a runway for heavy airplanes.
  • Figures2 and 3 show variants of concrete areas partially in plan view, Figure 3 illustrating alternative wedge arrangements.
  • Figure 4 is a'vertical section of a first example of a gap between two pavement parts.
  • Figure 5 is a section through a horizontal plane of a variant of a gap.
  • Figure 6 shows a method of forming concrete rollers.
  • Figure '1 is likewise a section along a horizontal plane (corresponding to the line VII-VII 01' Fi ure 8) of another variant of a gap.
  • Figure 8 is a section along line VIII-VIII of Fi ure 7.-
  • the concrete area shown in Figure 1 has the shape of a very elon ated rectangle oriented along the direction XX. At its two ends, this area rests against. two abutments 10 and H anchored in the ground. This area is transversely compressed by cables 16 and 16a anchored at their ends on the ed es of the area at 11 and 11a. Sections parallel to the abutments l0 and I I, such as AB, CD, EF, are provided in this area, in which are provided jacks I4 which permit the compressing bf the area in lon itudinal direction, the thrusts obtained from the jacks I4 being maintained by wedges l5.
  • the two portions of the area adjacent each other along a gap 18 are applied against each other by the pressure bers contract, the wedges approach each other. exerted by the cables 16a, but these two adjacent portions are capable of sliding parallel to gap I8 with respect to each other.
  • the area portions divided by the gap I8 can be of triangular shape.
  • these cables near the place where they pass over the gap can be housed in sleeves having without passing through the gaps I8.
  • the elements 8I may furthermore be replaced by elements such as 8la, the edges of which are sawtoothed and cooperate with gaps 18b, also sawtoothed.
  • the gaps I8 may be treated in various ways.
  • the two opposite edges may be fiat, smooth and vertical and may be in contact with each other through the intermediary of any lubricantwhatsoever. In order to permit resistance to shearing stresses, this gap must be supported on a foundation.
  • the gap as shown in Figure 4, in the form of two grooved surfaces which telescope into each other.
  • the grooves I8 provided in the edgeof one of the members receive ribs II provided in the other member.
  • the faces I21: and III) of these members may be lined with sheet metal (for instance, anti-frictional metal), the contact surfaces being lubri- ,an expanded portion in the vicinity of the gap,
  • a rubber sheet I3 capable of transmitting the compression forces from one member to the other and permitting the relative displacement in direction parallel to the gaps of the two members.
  • the pavement is supported on the ground by a layer of sand I l and a sheet of asphalt paper 20.
  • the sliding can bereplaced by a rolling by inserting in the gap or joint members capable of rotating, for instance rollers, balls or rods.
  • rollers I8 i. e., solid cylinders, or, as shown in Figure 5, portions of cylinders truncated by planes parallel to the cylinder axis.
  • rollers may be of cast iron or of any hard material.
  • the rollers l9b are obtained by providing, prior to the pouring of the concrete of the area, a row of cores 8
  • b can be provided, the cores remaining imbedded in the concrete after it has set.
  • the concrete of the tapered zones I90 deforms elastically and permits the relative displacement of the two parts of the area separated by the row of rollers I 9b.
  • the concrete of zones He may be reinforced by vertical reinforcements 32.
  • rods may also be used for the transmission of the compression from one side to the other of the elements in contact with each other.
  • the facing edges are covered with a scalloped metal sheet 29 between which are arranged flat rods 28.
  • the metal sheets 29 may furthermore be replaced by small members such as He.
  • the space between the rods 28 is filled with plastic material 23.
  • the gaps shown in Figures 5 and '7 may serve as forms for the pouring of the concrete of the area.
  • the entire unit consisting of the rollers l9, the plates 24 and the filling material can be made in advance.
  • the concrete is then poured in contact with the outer faces of the plates 24.
  • the rods 28 can be welded at 30, for instance to scalloped metal sheets 29.
  • the assembly thus obtained, filled with plastic material 23, serves as a form.
  • the weld points 30 break and do notprevent the free relative displacement of the members with respect to each other.
  • the precompression values can be lower than in the usual technical means, without going beyond the scope of the present invention.
  • a concrete pavement comprising at least two consecutive separate sections having spaced
  • spacing means in said gap for reducing friction between said adjacent edges on reverse displacements of both sections along the direction of said gap, and two devices, at least one of which is elastic, for applying simultaneous permanent compressive force on said pavement in two directions substantially at right angles to one another; said elastic device obliquely crossing said gap, and extending parallel to the surface of said pavement, said spacing means comprising a plurality of rollers interposed between the consecutive sections, and means supporting said rollers for rotation on axes substantially perpendicular to the pavement surface.
  • the spacing means comprise a plurality of rollers interposed between the consecutive slabs, and means supporting said rollers for rotation on axes substantially perpendicular to the upper surface of the concrete area.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Description

1953 E. FREYSSINET CONCRETE PAVEMENT 3 Sheets-Sheet 1 Filed Feb. 28, 1946 Inventor Oct. 20, 1953 E. FREYSSINET CONCRETE PAVEMENT 3 Sheets-Sheet 2 Filed Feb. 28, 1946 inventor- E an e qregssl'nft E. FREYSSINET CONCRETE PAVEMENT Oct. 20, 1953 3 Sheets-Shaev 5 Filed Feb. 28, 1946 wit/$01 Patented Oct. 20, 1953 UNITED STATE s PATENT OFFICE CONCRETE PAVEMENT Eugene Freyssinet, Neuilly-sur-Seine, France Application February 28, 1946, Serial No. 650,814 In France August 14, 1945 4 Claims.
create areas of large dimensions capable of receiving heavy loads. It also relates to areas produced by this method and in particular landing strips for heavy airplanes.
It is known that an uninterrupted pavement is capable of withstanding localized moving loads under much better conditions than a pavement having interruptions or gaps (either provided in advance or resulting from the breaking of the pavement) due to the considerable stresses which develop in the pavement when the load passes over such an interruption.
The object of my invention is the provision o a concrete pavement which, although having gaps which allow for expansion, behaves as a continuous pavement under loads.
In accordance with my invention, the pavement is prestressed by being subjected to permanent compressive stress in two different directions, and in said pavement there is provided at least one interruption forming a gap which is oblique with respect to the directions of compressive stress, the two parts of the area located on either side of the said gap being urged against each other by the compressive stress and being capable of sliding with as low a friction as possible with respect to each other.
Preferably, the pressure is exerted positively along one direction, for instance by means of armatures under tension parallel to the surface of the area which pass through the gap surface or surfaces, while the precompression in the other direction is a result of the first precompression and is obtained by abutment of the parallel ends of the area against rigid supports firmly anchored in the ground.
Due to the breaking up of the area by the gap surfaces, the dimensions of the parts of this area divided by the gaps are capable of varying under the action of the temperature or the humidity while the members which are intended toassure the permanent compression of this area behave like springs and permanently maintain the edges of these parts applied against each other, thus assuring the continuity of the surface of the pavement.
The different parts intersected by the gaps are preferably wedge-shaped, the apices being arranged opposite each other in pairs. Upon the expansion of the members, these wedges tend to move away from each other while, if the mem- 2 In order to facilitate the relative movement of the divided parts, the surface of the ground is conditioned in such a way as to reduce as much as possible the friction of the pavement with respect to the ground. For this purpose, the surface of the ground may, for instance, be previously covered with a layer of fine sand on which there is spread, before applying the pavement, a sheet of paper or felt impregnated with bitumen or asphalt.
One of the great advantages of the prestressed areas of my invention is that they can be produced, due to their mechanical continuity, with concrete thicknesses much lower than the thicknesses customary in non-prestressed areas.
In the attached drawings there have been shown by way of example a few embodiments of concrete pavements in accordance with the invention, as well as some examples of gaps between parts of these pavements.
' Figure l is a general plan view of an elon ated area, for instance, a runway for heavy airplanes.
Figures2 and 3 show variants of concrete areas partially in plan view, Figure 3 illustrating alternative wedge arrangements.
Figure 4 is a'vertical section of a first example of a gap between two pavement parts.
Figure 5 is a section through a horizontal plane of a variant of a gap.
Figure 6 shows a method of forming concrete rollers.
Figure '1 is likewise a section along a horizontal plane (corresponding to the line VII-VII 01' Fi ure 8) of another variant of a gap.
Figure 8 is a section along line VIII-VIII of Fi ure 7.-
The concrete area shown in Figure 1 has the shape of a very elon ated rectangle oriented along the direction XX. At its two ends, this area rests against. two abutments 10 and H anchored in the ground. This area is transversely compressed by cables 16 and 16a anchored at their ends on the ed es of the area at 11 and 11a. Sections parallel to the abutments l0 and I I, such as AB, CD, EF, are provided in this area, in which are provided jacks I4 which permit the compressing bf the area in lon itudinal direction, the thrusts obtained from the jacks I4 being maintained by wedges l5. Oblique gaps 18, which are at an angle to the axis XX, ide this area into trapezoids. The two portions of the area adjacent each other along a gap 18 are applied against each other by the pressure bers contract, the wedges approach each other. exerted by the cables 16a, but these two adjacent portions are capable of sliding parallel to gap I8 with respect to each other.
Various embodiments illustrative of this type of gap are described with reference to Figures 4 to 8. Y
As shown in Figure 2, the area portions divided by the gap I8 can be of triangular shape.
In this case, all the cables 18a pass through the planes of the gaps.
Upon varying the dimensions of two nei ghboring parts separated by a gap 18, these two parts tend, in the examples shown in Figures 1 and 2. to move perpendicularly to the general Y direction XX. In this movement, the cable 16a which passes through the gaps areelongated and behave as springs and tend to return the elements into their original position.
In order to permit the two parts of the cable located on opposite sides of a gap 18 to give in case of variations in dimension of the elements, these cables near the place where they pass over the gap can be housed in sleeves having without passing through the gaps I8. The elements 8I may furthermore be replaced by elements such as 8la, the edges of which are sawtoothed and cooperate with gaps 18b, also sawtoothed.
In the case shown in Figure 1, by the action of the jacks 14 there is developed in the concrete a compression in the direction XX and at the same time the opposing trapezoids which constitute the area tend to move away from each other, perpendicularly to XX',-thus increasing the distance between the anchoring means 'IIa at the end of each cable 16a which intersects a gap 18; since this cable is not directly embedded within concrete, but extends through a plastic sheath. and is only fast with the concrete through its anchored ends, it will be tensioned throughout (the cables 16, which do not pass through the gaps, must be tensioned directly). On the other hand, if abutments such as 10, II in Figure 1 are provided at the ends of the area, the tensioning of cables 16a or 85 sufilces to impose upon the area a prestressing not only in the transverse direction but also in the longitudinal direction since, due to the tension of these cables, the wedge-shaped elements are brought closer to each other.
The gaps I8 may be treated in various ways.
In the simplest gap or joint, the two opposite edges may be fiat, smooth and vertical and may be in contact with each other through the intermediary of any lubricantwhatsoever. In order to permit resistance to shearing stresses, this gap must be supported on a foundation.
The use of a foundation can be avoided by making the gap. as shown in Figure 4, in the form of two grooved surfaces which telescope into each other. Thus, in this figure, the grooves I8 provided in the edgeof one of the members receive ribs II provided in the other member. The faces I21: and III) of these members may be lined with sheet metal (for instance, anti-frictional metal), the contact surfaces being lubri- ,an expanded portion in the vicinity of the gap,
cated,to facilitate relative sliding. There can also be provided in the gap a rubber sheet I3 capable of transmitting the compression forces from one member to the other and permitting the relative displacement in direction parallel to the gaps of the two members. It will benoted that the pavement is supported on the ground by a layer of sand I l and a sheet of asphalt paper 20. In order to facilitate the relative movement of the contacting faces of the gap, the sliding can bereplaced by a rolling by inserting in the gap or joint members capable of rotating, for instance rollers, balls or rods. v
In Figure 5, the two opposite faces of the members are coated with metal plates 24, between the surfaces 2| and 22 of which are arranged rollers I8, i. e., solid cylinders, or, as shown in Figure 5, portions of cylinders truncated by planes parallel to the cylinder axis.
Between two consecutive rollers a plastic protective substance may be introduced, such as bitumen, etc., indicated by 23 in Figure 5. The rollers may be of cast iron or of any hard material. In particular, it may be advantageous to make them with the same concrete as the area itself. In this case, the rollers l9b are obtained by providing, prior to the pouring of the concrete of the area, a row of cores 8| of I-shape which are removed after the setting of the concrete and for which there is substituted a filling of plastic material such as bitumen, impregnated porous wood, rubber, etc. Also, cores of such material, wrapped previously with a metal sheet such as 3|b, can be provided, the cores remaining imbedded in the concrete after it has set.
The concrete of the tapered zones I90 deforms elastically and permits the relative displacement of the two parts of the area separated by the row of rollers I 9b. The concrete of zones He may be reinforced by vertical reinforcements 32.
As shown in Figures 7 and 8, rods may also be used for the transmission of the compression from one side to the other of the elements in contact with each other. The facing edges are covered with a scalloped metal sheet 29 between which are arranged flat rods 28. The metal sheets 29 may furthermore be replaced by small members such as He. The space between the rods 28 is filled with plastic material 23.
The gaps shown in Figures 5 and '7 may serve as forms for the pouring of the concrete of the area. For instance, the entire unit consisting of the rollers l9, the plates 24 and the filling material can be made in advance. The concrete is then poured in contact with the outer faces of the plates 24. In the case of Figure 7, the rods 28 can be welded at 30, for instance to scalloped metal sheets 29. The assembly thus obtained, filled with plastic material 23, serves as a form. Upon the first displacement of the area, the weld points 30 break and do notprevent the free relative displacement of the members with respect to each other.
In' view of the fact that a construction of this type does not run the risk of caving in, the precompression values can be lower than in the usual technical means, without going beyond the scope of the present invention.
What I claim is:
1. A concrete pavement comprising at least two consecutive separate sections having spaced,
contiguous, angular edges, having a gap therebetween, spacing means in said gap for reducing friction between said adjacent edges on reverse displacements of both sections along the direction of said gap, and two devices, at least one of which is elastic, for applying simultaneous permanent compressive force on said pavement in two directions substantially at right angles to one another; said elastic device obliquely crossing said gap, and extending parallel to the surface of said pavement, said spacing means comprising a plurality of rollers interposed between the consecutive sections, and means supporting said rollers for rotation on axes substantially perpendicular to the pavement surface.
2. The combination with two spaced apart abutments facing one another, of a concrete area interposed between and engaged at its opposite ends by said abutments, said area comprising at least two slabs disposed in end-to-end relationship, said slabs having contiguous planar ends exending from one side of said area to the other, said ends being spaced to provide a gap therebetween, said slabs having substantially undistortable wedge-shaped outlines which taper in opposite directions, whereby the slabs tend to move laterally of the area upon the application thereto by said abutments of compressive forces such as occur on expansion of the slabs, a stretched cable extending laterally of the area and crossing the gap between the contiguous ends of the slabs at an oblique angle, anchoring means for the ends of said cable, said anchoring means engaging the outer faces of the opposite sides of said area so as to maintain said slabs under permanent preliminary compression tending to oppose relative lateral displacement of said slabs; means for preventing bonding of said cable with the concrete, and spacing means in said gap for reducing friction between the contiguous ends of the slabs on relative lateral displacement of the slabs in the direction of said gap.
3. The combination as claimed in claim 2, wherein the spaced apart abutments include Jacks adapted to appl compressive forces to the concrete area longitudinally thereof thereby tending to cause lateral displacement of the slabs and further compression of same through the v agency of the stretched cable.
4. The combination as claimed in claim 2, wherein the spacing means comprise a plurality of rollers interposed between the consecutive slabs, and means supporting said rollers for rotation on axes substantially perpendicular to the upper surface of the concrete area.
EUGENE FREYSSINE'I.
References Cited in the file of this patent UNITED STATES PATENTS Number Name Date 1,375,960 Harris Apr. 26, 1921 1,557,165 Hooper Oct. 13, 1925 1,646,997 Gelder Oct. 25, 1927- 1,660,421 Knight Feb. 28, 1928 1,916,620 Johnson July 4, 1933 2,036,379 Woodward -Apr. 7, 1936 2,071,299 Gammeter Feb. 16, 1937 2,072,381 Post Mar. 2, 1937 2,078,693 Simrall Apr. 27, 1937 I 2,107,351 Taubensee Feb. 8, 1938 2,122,167 Wettenberg June 28, 1938 2,130,992 Clemmons Sept. 20, 1938 2,155,121 Finsterwolder Apr. 18, 1939 2,184,137 Brewer Dec. 19, 1939 2,192,246 strube Mar. 5, 1940 2,201,824 Brickman et al. May 21, 1940 2,226,201 Freyssinet Dec. 24, 1940 2,251,672 Friberg Aug. 5, 1941 2,280,455 Seuberling Apr. 21, 1942 2,323,848 Schaefler July 6, 1943 2,329,189 Dill Sept. 14, 1943 2,329,670 Sanchez Sept. 14, 1943 2,340,526 Green 1 Feb. 1, 1944 2,413,990 Muntz Jan. 7, 1947 2,414,738 Henderson Jan. 21, 1947 FOREIGN PATENTS Number Country Date 225,148 Germany Aug. 17, 1910 126,100 Great Britain Sept. 7, 1918 455,467 Great Britain Oct. 21, 1936 557,025 Great Britain Nov. 2, 1943 OTHER REFERENCES Engineering News Record, Sept. 6, 1948.
US650814A 1945-08-14 1946-02-28 Concrete pavement Expired - Lifetime US2655845A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
FR2655845X 1945-08-14

Publications (1)

Publication Number Publication Date
US2655845A true US2655845A (en) 1953-10-20

Family

ID=9687616

Family Applications (1)

Application Number Title Priority Date Filing Date
US650814A Expired - Lifetime US2655845A (en) 1945-08-14 1946-02-28 Concrete pavement

Country Status (1)

Country Link
US (1) US2655845A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2852991A (en) * 1953-12-03 1958-09-23 Preload Co Inc Prestressed pavements
US3182109A (en) * 1962-08-17 1965-05-04 Gerald G Greulich Method of making prestressed concrete pavement
US7556208B1 (en) * 1999-10-06 2009-07-07 Max Bogl Bauunternehmung GmbH & Company KG Pre-assembled plate consisting of armoured concrete

Citations (29)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE225148C (en) *
GB126100A (en) * 1918-03-28 1919-04-28 Frederick Bolton Improvements in the Manufacture of Reinforced Concrete Structures.
US1375960A (en) * 1919-04-15 1921-04-26 Herbert C Harris Highway construction
US1557165A (en) * 1922-11-01 1925-10-13 Elmer G Hooper Pavement for highways
US1646997A (en) * 1926-04-26 1927-10-25 Royal W Gelder Concrete pavement for reservoirs, dams, levees, and the like
US1660421A (en) * 1921-08-10 1928-02-28 Herbert M Knight Pavement
US1916620A (en) * 1931-06-19 1933-07-04 Johnson Warren Pavement and paving unit
US2036379A (en) * 1932-06-06 1936-04-07 Translode Joint Company Concrete pavement
GB455467A (en) * 1935-01-29 1936-10-21 Fr Du Vialit Soc Improvements in pavements
US2071299A (en) * 1933-12-22 1937-02-16 John R Gammeter Joint for roadways
US2072381A (en) * 1934-06-08 1937-03-02 Chester L Post Concrete slab joint
US2078693A (en) * 1934-05-18 1937-04-27 Riley M Simrall Expansion, contraction, and construction joint for concrete pavements and the like
US2107351A (en) * 1935-11-01 1938-02-08 Ernest H Geyer Joint for concrete structures
US2122167A (en) * 1934-03-21 1938-06-28 Barrett Co Expansion joint
US2130992A (en) * 1936-04-08 1938-09-20 Ralph W Clemmons Load-distributing expansion joint for adjacent solid sections
US2155121A (en) * 1936-01-11 1939-04-18 Finsterwalder Ulrich Ferro-concrete beam
US2184137A (en) * 1936-12-01 1939-12-19 Nat Fireproofing Corp Composite building member
US2192246A (en) * 1935-12-10 1940-03-05 Ind En Bouwmaterialenhandelmij Highway construction
US2201824A (en) * 1938-01-15 1940-05-21 American Steel & Wire Co Pavement joint
US2226201A (en) * 1938-08-01 1940-12-24 Freyssinet Eugene Jack apparatus
US2251672A (en) * 1936-06-04 1941-08-05 Bengt F Friberg Method of casting concrete pavements
US2280455A (en) * 1940-05-10 1942-04-21 Harry P Seuberling Road joint
US2323848A (en) * 1941-02-13 1943-07-06 Schaeffer Frederick William Pavement
US2329189A (en) * 1941-09-02 1943-09-14 Richard E Dill Reinforced concrete construction
US2329670A (en) * 1940-07-10 1943-09-14 Sanchez Jose Maria Valles Process for making pavements and the like
GB557025A (en) * 1941-12-17 1943-11-02 Josef Enar Lundholm Method of producing walls, carcass floorings, ceilings or roofs from concrete blocks or from blocks of porous concrete or other suitable material
US2340526A (en) * 1942-07-10 1944-02-01 Norvin H Green Paving block
US2413990A (en) * 1943-01-25 1947-01-07 Eric P Muntz Process of making prestressed reinforced concrete
US2414738A (en) * 1945-05-12 1947-01-21 William P Witherow Precast concrete corrugated connection

Patent Citations (29)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE225148C (en) *
GB126100A (en) * 1918-03-28 1919-04-28 Frederick Bolton Improvements in the Manufacture of Reinforced Concrete Structures.
US1375960A (en) * 1919-04-15 1921-04-26 Herbert C Harris Highway construction
US1660421A (en) * 1921-08-10 1928-02-28 Herbert M Knight Pavement
US1557165A (en) * 1922-11-01 1925-10-13 Elmer G Hooper Pavement for highways
US1646997A (en) * 1926-04-26 1927-10-25 Royal W Gelder Concrete pavement for reservoirs, dams, levees, and the like
US1916620A (en) * 1931-06-19 1933-07-04 Johnson Warren Pavement and paving unit
US2036379A (en) * 1932-06-06 1936-04-07 Translode Joint Company Concrete pavement
US2071299A (en) * 1933-12-22 1937-02-16 John R Gammeter Joint for roadways
US2122167A (en) * 1934-03-21 1938-06-28 Barrett Co Expansion joint
US2078693A (en) * 1934-05-18 1937-04-27 Riley M Simrall Expansion, contraction, and construction joint for concrete pavements and the like
US2072381A (en) * 1934-06-08 1937-03-02 Chester L Post Concrete slab joint
GB455467A (en) * 1935-01-29 1936-10-21 Fr Du Vialit Soc Improvements in pavements
US2107351A (en) * 1935-11-01 1938-02-08 Ernest H Geyer Joint for concrete structures
US2192246A (en) * 1935-12-10 1940-03-05 Ind En Bouwmaterialenhandelmij Highway construction
US2155121A (en) * 1936-01-11 1939-04-18 Finsterwalder Ulrich Ferro-concrete beam
US2130992A (en) * 1936-04-08 1938-09-20 Ralph W Clemmons Load-distributing expansion joint for adjacent solid sections
US2251672A (en) * 1936-06-04 1941-08-05 Bengt F Friberg Method of casting concrete pavements
US2184137A (en) * 1936-12-01 1939-12-19 Nat Fireproofing Corp Composite building member
US2201824A (en) * 1938-01-15 1940-05-21 American Steel & Wire Co Pavement joint
US2226201A (en) * 1938-08-01 1940-12-24 Freyssinet Eugene Jack apparatus
US2280455A (en) * 1940-05-10 1942-04-21 Harry P Seuberling Road joint
US2329670A (en) * 1940-07-10 1943-09-14 Sanchez Jose Maria Valles Process for making pavements and the like
US2323848A (en) * 1941-02-13 1943-07-06 Schaeffer Frederick William Pavement
US2329189A (en) * 1941-09-02 1943-09-14 Richard E Dill Reinforced concrete construction
GB557025A (en) * 1941-12-17 1943-11-02 Josef Enar Lundholm Method of producing walls, carcass floorings, ceilings or roofs from concrete blocks or from blocks of porous concrete or other suitable material
US2340526A (en) * 1942-07-10 1944-02-01 Norvin H Green Paving block
US2413990A (en) * 1943-01-25 1947-01-07 Eric P Muntz Process of making prestressed reinforced concrete
US2414738A (en) * 1945-05-12 1947-01-21 William P Witherow Precast concrete corrugated connection

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2852991A (en) * 1953-12-03 1958-09-23 Preload Co Inc Prestressed pavements
US3182109A (en) * 1962-08-17 1965-05-04 Gerald G Greulich Method of making prestressed concrete pavement
US7556208B1 (en) * 1999-10-06 2009-07-07 Max Bogl Bauunternehmung GmbH & Company KG Pre-assembled plate consisting of armoured concrete

Similar Documents

Publication Publication Date Title
US2590685A (en) Prestressed concrete structure
US3165986A (en) Expansion joints
Shim et al. Design of shear connection in composite steel and concrete bridges with precast decks
US2655846A (en) Large sized concrete area adapted for airplane runways and the like
US3932051A (en) Highway construction
Fang et al. Behavior of isotropic R/C bridge decks on steel girders
CN110130220B (en) Novel concrete bridge surface continuous structure applied to beam bridge
GB1043421A (en) Prestressed concrete bridge-like elevated highway
Tayabji et al. Improved rigid pavement joints
US2655845A (en) Concrete pavement
US2833186A (en) Reinforced pavements
KR20190112451A (en) Construction Method of Expansion Joints Device with Improved Durability using Elastomeric Pad
US4856930A (en) Pavement and methods for producing and resurfacing pavement
US3259932A (en) Cable-stayed bridge
US2723607A (en) Pavement
US3237537A (en) Prestressed concrete highway
Sayed-Ahmed et al. Structural behavior of UHPFRC-filled, transverse C-joint in full-depth, GFRP-reinforced, precast bridge deck panels resting over steel girders
US2158953A (en) Load transferring and aligning device
KR101381974B1 (en) Concrete deck slab assembly, Method for making the same and Temporary bridge using the same
USRE21880E (en) Road join
US2885882A (en) Prestressed concrete deck
US2852991A (en) Prestressed pavements
Hossain et al. Cross tensioned concrete pavement
GB623729A (en) Method of constructing concrete surfaces adapted to accommodate heavy loads, and applicable more particularly to runways for heavy aircraft
WO2017203548A1 (en) Expansion joint for road structures and construction method thereof