US20240060695A1 - Systems and methods to manage power consumption of a building and storage by controlling a refrigeration system within the building - Google Patents

Systems and methods to manage power consumption of a building and storage by controlling a refrigeration system within the building Download PDF

Info

Publication number
US20240060695A1
US20240060695A1 US18/386,939 US202318386939A US2024060695A1 US 20240060695 A1 US20240060695 A1 US 20240060695A1 US 202318386939 A US202318386939 A US 202318386939A US 2024060695 A1 US2024060695 A1 US 2024060695A1
Authority
US
United States
Prior art keywords
refrigeration unit
temperature
time interval
refrigeration
target
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
US18/386,939
Inventor
Nikhil Saralkar
Anthony Diamond
Amrit Robbins
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Axiom Cloud Inc
Original Assignee
Axiom Cloud Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Axiom Cloud Inc filed Critical Axiom Cloud Inc
Priority to US18/386,939 priority Critical patent/US20240060695A1/en
Assigned to AXIOM CLOUD INC. reassignment AXIOM CLOUD INC. ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: SARALKAR, Nikhil, ROBBINS, Amrit, DIAMOND, Anthony
Publication of US20240060695A1 publication Critical patent/US20240060695A1/en
Pending legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/30Control or safety arrangements for purposes related to the operation of the system, e.g. for safety or monitoring
    • F24F11/46Improving electric energy efficiency or saving
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B49/00Arrangement or mounting of control or safety devices
    • F25B49/02Arrangement or mounting of control or safety devices for compression type machines, plants or systems
    • F25B49/022Compressor control arrangements
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/50Control or safety arrangements characterised by user interfaces or communication
    • F24F11/56Remote control
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/62Control or safety arrangements characterised by the type of control or by internal processing, e.g. using fuzzy logic, adaptive control or estimation of values
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B41/00Fluid-circulation arrangements
    • F25B41/20Disposition of valves, e.g. of on-off valves or flow control valves
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F2120/00Control inputs relating to users or occupants
    • F24F2120/10Occupancy
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F2140/00Control inputs relating to system states
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F2140/00Control inputs relating to system states
    • F24F2140/50Load
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F2140/00Control inputs relating to system states
    • F24F2140/60Energy consumption
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B2600/00Control issues
    • F25B2600/02Compressor control
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B2600/00Control issues
    • F25B2600/02Compressor control
    • F25B2600/025Compressor control by controlling speed
    • F25B2600/0251Compressor control by controlling speed with on-off operation
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B2600/00Control issues
    • F25B2600/02Compressor control
    • F25B2600/026Compressor control by controlling unloaders
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B2700/00Sensing or detecting of parameters; Sensors therefor
    • F25B2700/15Power, e.g. by voltage or current
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B2700/00Sensing or detecting of parameters; Sensors therefor
    • F25B2700/21Temperatures
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B2700/00Sensing or detecting of parameters; Sensors therefor
    • F25B2700/21Temperatures
    • F25B2700/2104Temperatures of an indoor room or compartment
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B2700/00Sensing or detecting of parameters; Sensors therefor
    • F25B2700/21Temperatures
    • F25B2700/2106Temperatures of fresh outdoor air
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B49/00Arrangement or mounting of control or safety devices
    • F25B49/02Arrangement or mounting of control or safety devices for compression type machines, plants or systems

Definitions

  • the present disclosure relates to systems and methods to manage power consumption of a building and storage by controlling a refrigeration system within the building.
  • mass refrigeration systems e.g., warehouses, supermarkets
  • electrochemical batteries to offset electrical consumption.
  • the amount of power required from the electrochemical batteries may be costly given the large amount of power consumed by the mass refrigeration systems.
  • One aspect of the present disclosure relates to optimizing power consumption of a building by instructing a refrigeration system within the building to precool items enclosed within the refrigeration system and load shed.
  • the precooling and the load shedding may occur based on a desired power target for a particular time interval.
  • the desired power target and the time interval may be obtained via user input (e.g., manager of the refrigeration system) or obtained from an external resource.
  • precooling and the load shedding control actions may be determined.
  • a control schedule to effectuate the precooling and the load shedding may be generated based on the power target, the time interval, and information related to the building, and subsequently executed.
  • the building may optimize power consumption and more efficiently store power through excess refrigeration capacity and thermal capacity of the items being refrigerated in addition to operational flexibility of the mass refrigeration systems. As a result, demand charges may be reduced.
  • the system may include one or more hardware processors configured by machine-readable instructions.
  • the machine-readable instructions may include one or more instruction components.
  • the instruction components may include computer program components.
  • the instruction components may include one or more of input receiving component, system information determination component, building information determination component, control action determination component, control component, and/or other instruction components.
  • the input receiving component may be configured to receive input defining an average power target and a time interval.
  • the average power target may be for the time interval.
  • the average power target may be an optimal amount of power consumption or usage of the building during the time interval.
  • the system information determination component may be configured to determine system information characterizing a refrigeration system.
  • the system information may include suction pressures, compressor information, case information, circuit control information, defrost schedules, door information, pressure information, and/or other system information.
  • the building information determination component may be configured to determine building information characterizing power usage of a building that includes the refrigeration system.
  • the building information may include current power information, a required power target based on the average power target and the current power information, a building temperature, and/or other building information.
  • the control action determination component may be configured to determine precooling control actions based on the system information, the average power target, the time interval, and/or other information.
  • the control action determination component may be configured to determine load shedding control actions based on the system information, the average power target, the time interval, and/or other information.
  • the control component may be configured to generate a control schedule for the refrigeration system to effectuate the precooling control actions and/or load shedding control actions based on the average power target, the time interval, the building information, and/or other information.
  • the precooling may control actions and load shedding control actions facilitate acquisition of electrical power or distribution of the electrical power.
  • the control component may be configured to effectuate the precooling control actions and/or load shedding control actions for the refrigeration system in accordance with the control schedule.
  • the term “obtain” may include active and/or passive retrieval, determination, derivation, transfer, upload, download, submission, and/or exchange of information, and/or any combination thereof.
  • the term “effectuate” may include active and/or passive causation of any effect, both local and remote.
  • the term “determine” may include measure, calculate, compute, estimate, approximate, generate, and/or otherwise derive, and/or any combination thereof.
  • FIG. 1 illustrates a system configured to manage power consumption of a building and storage by controlling a refrigeration system within the building, in accordance with one or more implementations.
  • FIG. 2 illustrates a method to manage power consumption of a building and storage by controlling a refrigeration system within the building, in accordance with one or more implementations.
  • FIG. 3 illustrates an example implementation of the system configured to manage power consumption of a building and storage by controlling a refrigeration system within the building, in accordance with one or more implementations.
  • FIG. 1 illustrates a system 100 configured to manage power consumption of a building and storage by controlling a refrigeration system within a building 150 , in accordance with one or more implementations.
  • system 100 may include one or more servers 102 .
  • Server(s) 102 may be configured to communicate with one or more client computing platforms 104 according to a client/server architecture and/or other architectures.
  • Client computing platform(s) 104 may be configured to communicate with other client computing platforms via server(s) 102 and/or according to a peer-to-peer architecture and/or other architectures. Users may access system 100 via client computing platform(s) 104 .
  • a given client computing platform 104 may be associated with, connected via a network 116 , and/or operatively linked via one or more electronic communication links with building 150 , the refrigeration system, and/or other systems within building 150 such that facility operations, the refrigeration system, and/or the other systems may be controlled and/or monitored via client computing platform 104 .
  • the refrigeration system may be operatively linked with building 150 and/or wirelessly connected with building 150 via network 116 .
  • Server(s) 102 may be configured by machine-readable instructions 106 .
  • Machine-readable instructions 106 may include one or more instruction components.
  • the instruction components may include computer program components.
  • the instruction components may include one or more of input receiving component 108 , system information determination component 110 , building information determination component 112 , control action determination component 114 , control component 118 , and/or other instruction components.
  • Input receiving component 108 may be configured to receive input defining an average power target and a time interval.
  • the average power target may refer to an ideal power consumption of building 150 to achieve for or during the time interval.
  • the time interval may be an amount of seconds, an amount of minutes, an amount of hours, an amount of days on a particular date and/or time.
  • the time interval may a time between be a start time and an end time. For example, the time interval may be between 2:00 PM and 2:15 PM (i.e., a 15-minute time interval).
  • the average power target may be determined and received from external resource(s) 124 .
  • the average power target may be received via the input enter by a user (e.g., a manager of building 150 ).
  • System information determination component 110 may be configured to determine system information characterizing the refrigeration system.
  • the refrigeration system may be configured to cool, maintain coldness, freeze, and/or keep frozen products stored within one or more cases of the refrigeration system.
  • all the cases of an individual refrigeration system may cool and/or maintain the coldness of the products stored within.
  • all the cases of an individual refrigeration system may freeze and/or keep frozen of the products stored within.
  • some the cases of an individual refrigeration system may cool and/or maintain the coldness of the products stored within, and some of the cases may freeze and/or keep frozen of the products stored within.
  • the system information may include suction pressures at various times, compressor information, case information, circuit control information, defrost schedules, door information, pressure information, historical facility operations, and/or other system information. In some implementations, some or all of the system information may vary for the individual cases included in the refrigeration system.
  • the compressor information may include current states of individual compressors, historical states of the individual compressors, and/or other compressor information. States of the individual compressors (current and historical) may include a compressor type, run capacity of the individual compressor, run time at the run capacity, and/or other compressor information.
  • the case information may include current case temperatures of the individual cases included in the refrigeration system, historical case temperatures of the individual cases, case types, and/or other case information.
  • a case may refer to a container that stores the products requiring cooling or freezing.
  • the products may include produce, dairy products, meats, among others.
  • the case temperatures, current and historical may be in Celsius, Fahrenheit, or both.
  • the case types may include a forced air case, a gravity coil case, and/or other case types.
  • the individual cases of the refrigeration system may include different access to the products stored inside.
  • the different access may include one or more of a front door access, a rear door access, a partially open front access, an open front access, an open rear access, a top door access, a side door access, and/or other access to the products by consumers and/or employees (e.g., product stockers).
  • the different accesses may affect the case temperatures, functionality of the individual case types, other case information, and/or other system information of the refrigeration system.
  • the circuit control information may include current positions of individual circuit control valves, historical positions of the individual circuit control valves, and/or other information.
  • the positions of the individual circuit control values may control a flow rate of a particular fluid and thus control the case temperature of the corresponding cases, pressure of the particular fluid, a level of the particular fluid, and/or other parameter values related to the refrigeration system.
  • the defrost schedules may characterize a schedule for defrosting the products in the individual cases.
  • the defrost schedules may include one or more dates and/or times at which the case temperatures are set to particular temperatures to gradually progress the case temperatures to a target case temperature.
  • the dates, the times, the particular temperatures, and the target case temperature may be based on user input.
  • the user input may include a target time at which the products should be a target temperature or the target case temperature for a target time. Based on such, the dates, the times, and the particular temperatures may be determined by system information determination component 110 .
  • the defrost schedules may be determined and obtained from external resource(s) 124 .
  • the individual cases may function in accordance with individual defrost schedules. In some implementations, multiple or all cases may function in accordance with a single defrost schedule.
  • the door information may include a date, time, and/or duration at which one or more doors of the individual cases are open and closed.
  • the door information may include an operator who has opened or closed the door at a particular date and/or time.
  • the operator may be a maintenance worker for the refrigeration system, an employee that utilized the refrigeration system (e.g., product stocker, butcher, baker, manager of building 150 that includes the refrigeration system, etc.), a customer, and/or other operators.
  • the door information may be conveyed by one or more door sensors on the individual cases.
  • the pressure information may include a condenser pressure at which refrigerant changes from a gas to a liquid, a compressor discharge pressure, an evaporator pressure at which the refrigerant changes from a liquid to a gas, and/or other pressure information.
  • the pressure information may be for the individual cases or for the refrigeration system as a whole.
  • the historical facility operations may include restocking schedules, work hours, clearance schedules, operational information of other systems included in building 150 , and/or other information.
  • the restocking schedules may include dates and/or times at which the products in all the cases or the individual cases are restocked with other or new products.
  • the work hours may include time periods at which building 150 or individual systems within building 150 (e.g., the refrigeration system) are operated by the operators.
  • the clearance schedules may be dates and/or times at which some or all of the products are cleared from all or individual cases.
  • the other systems included in building 150 may include one or more of a trash compactor, cooking equipment (e.g., mixers, ovens, dish washers, etc.), an elevator, a heating system, a ventilation system, an air conditioning system, a lighting system, a security system (e.g., surveillance systems, alarm systems), an intercom system, and/or other systems.
  • the operational information for the other systems may include operation schedules indicating when the individual other systems are active, inactive, or idle, managers of the individual other systems, historical maintenance of the individual other systems, date of installation, warranty information for the individual other systems, and/or other operational information.
  • Building information determination component 112 may be configured to determine building information characterizing power usage of building 150 that includes the refrigeration system and/or the other systems.
  • the power usage may refer to an amount of energy used per unit of time.
  • the building information may include current power information, a required power target, a building temperature, and/or other building information.
  • the current power information may indicate current power that building 150 is consuming.
  • the current power information may be obtained from an electrical meter coupled with building 150 .
  • the current amount of power may be calculated per unit of time based on a regression model, a time of a day, the day of the week, an occupancy value, an outside air temperature value, and/or other information.
  • the regression models may include linear regression, logistic regression, ridge regression, lasso regression, polynomial regression, Bayesian linear regression, and/or other regression model.
  • the regression model may be based on the historical facility operations.
  • the unit of time may be seconds, minutes, hours, and/or other unit of time.
  • the occupancy may refer to used space of building 150 or particular areas thereof with people, animals, the systems, and/or the products.
  • the occupancy value may be in cubic feet, cubic meters, a particular amount of the people, a particular amount of the animals, a particular amount of the systems, a particular amount of the products, and/or other unit of occupancy.
  • the outside air temperature value may be obtained from external resources 124 .
  • the outside air temperature value may be conveyed by and obtained from one or more temperature sensors associated or coupled with building 150 .
  • the required power target may be power required by building 150 .
  • the required power target may be based on the average power target, the current power information, the building information and/or other information.
  • the required power target may be determined by building information determination component 112 .
  • the required power target may be determined by external resources 124 and received by building information determination component 112 .
  • the building temperature may include an average building temperature of the entire building, temperatures of individual areas of building 150 , a temperature at which building 150 is set at, temperatures at which the individual areas are set at, and/or other building temperatures.
  • Control action determination component 114 may be configured to determine precooling control actions based on the system information, the average power target, the time interval, and/or other information.
  • the precooling control actions may include increasing an amount of active compressors within the refrigeration system, increasing the active compressors, deactivating one or more unloaders of the compressors, increasing frequency of variable frequency drives, controlling circuit control valves connected to evaporators, and/or other precooling control actions.
  • a particular amount of compressors may be included in the refrigeration system. Some or all of the compressors may be active at once. Increasing the amount of active compressors may include activating one or more of the compressors not already active.
  • Increasing the active compressors may include lowering a trigger temperature (of temperature sensors associated with the compressors and/or within the cases of the refrigeration system) that actives the compressors, increasing a motor speed of the compressor, and/or other operations to increase the active compressors.
  • Controlling the circuit control valves may include opening or closing the circuit control valves partially or completely on all the evaporators or some of the evaporators. The circuit control valves may be partially opened or closed by a rotational degree, a flow rate amount, and/or other value.
  • Control action determination component 114 may be configured to determine load shedding control actions based on the system information, the average power target, the time interval, and/or other information.
  • the load shedding control actions may include decreasing the amount of the active compressors (i.e., the opposite of increasing the amount of the active compressors described herein), decreasing the active compressors, activating the unloaders, decreasing frequency of variable frequency drives, and/or other load shedding control actions.
  • Control component 118 may be configured to generate a control schedule for the refrigeration system to effectuate the precooling control actions and/or load shedding control actions.
  • the precooling control actions and the load shedding control actions may facilitate acquisition of electrical power or distribution of the electrical power.
  • the control schedule may be generated in accordance with a generation plan.
  • the generation plan may specify that the control schedule is generated recurring after a particular amount of time (e.g., every 5 days, every 30 days), periodically (e.g., first day of every month, every Monday, etc.), responsive to user input to generate, and/or at other times.
  • the generation plan may specify that a remainder of the control schedule is updated at particular times or periodically based on the building information, the system information, and/or other information. For example, the control schedule may be updated upon half the amount time between the times at which the control schedules are generated at lapsed (e.g., 15 days into the 30 days).
  • Control component 118 may be configured to effectuate the precooling control actions and/or load shedding control actions for the refrigeration system in accordance with the control schedule.
  • the control schedule may be effectuated immediately subsequent to the generation.
  • the control schedule may be transmitted to a different component, building 150 , or the refrigeration system for effectuation. Responsive to the effectuation of the control schedule, power consumption by the refrigeration system and/or the building may be reduced. Reduction of the power consumption, particularly during individual time intervals, may reduce demand charges.
  • An electrical power demand may be based on a highest average amount of energy consumed during a particular time interval by the building (i.e., customer). The electrical power demand may be a larger portion of an electricity bill, billed at a higher rate, and/or other differences that may add expense to a manager/management of the building, i.e., the demand charges.
  • FIG. 3 illustrates an example implementation of building 150 (the same as or similar in FIG. 1 ) that include a refrigeration system 311 .
  • Building 150 may include building information 306 as detailed in FIG. 1 .
  • Refrigeration system 311 may include system information 304 as detailed in FIG. 1 .
  • Refrigeration system 311 may store products within cases 314 included in refrigeration system 311 .
  • the products within cases 314 may include foods that are refrigerated or frozen.
  • Control actions 308 including precooling control actions and load shedding control actions, may be determined for refrigeration system 311 by server(s) 102 (and computer components thereof) based on an average power target 302 , a time interval 312 , and system information 304 received by server(s) 102 (the same as or similar to FIG.
  • a control schedule 310 to effectuate control actions 308 may be determined by server(s) 102 based on average power target 302 , time interval 312 , building information 306 .
  • Control schedule 310 may be subsequently effectuated or may be transmitted to refrigeration system 311 for implementation. As such, power consumption may be optimized for refrigeration system 311 and thus building 150 .
  • server(s) 102 , client computing platform(s) 104 , and/or external resources 124 may be operatively linked via one or more electronic communication links.
  • electronic communication links may be established, at least in part, via a network such as the Internet and/or other networks. It will be appreciated that this is not intended to be limiting, and that the scope of this disclosure includes implementations in which server(s) 102 , client computing platform(s) 104 , and/or external resources 124 may be operatively linked via some other communication media.
  • a given client computing platform 104 may include one or more processors configured to execute computer program components.
  • the computer program components may be configured to enable an expert or user associated with the given client computing platform 104 to interface with system 100 and/or external resources 124 , and/or provide other functionality attributed herein to client computing platform(s) 104 .
  • the given client computing platform 104 may include one or more of a desktop computer, a laptop computer, a handheld computer, a tablet computing platform, a NetBook, a Smartphone, a gaming console, and/or other computing platforms.
  • External resources 124 may include sources of information outside of system 100 , external entities participating with system 100 , and/or other resources. In some implementations, some or all of the functionality attributed herein to external resources 124 may be provided by resources included in system 100 .
  • Server(s) 102 may include electronic storage 126 , one or more processors 128 , and/or other components. Server(s) 102 may include communication lines, or ports to enable the exchange of information with a network and/or other computing platforms. Illustration of server(s) 102 in FIG. 1 is not intended to be limiting. Server(s) 102 may include a plurality of hardware, software, and/or firmware components operating together to provide the functionality attributed herein to server(s) 102 . For example, server(s) 102 may be implemented by a cloud of computing platforms operating together as server(s) 102 .
  • Electronic storage 126 may comprise non-transitory storage media that electronically stores information.
  • the electronic storage media of electronic storage 126 may include one or both of system storage that is provided integrally (i.e., substantially non-removable) with server(s) 102 and/or removable storage that is removably connectable to server(s) 102 via, for example, a port (e.g., a USB port, a firewire port, etc.) or a drive (e.g., a disk drive, etc.).
  • a port e.g., a USB port, a firewire port, etc.
  • a drive e.g., a disk drive, etc.
  • Electronic storage 126 may include one or more of optically readable storage media (e.g., optical disks, etc.), magnetically readable storage media (e.g., magnetic tape, magnetic hard drive, floppy drive, etc.), electrical charge-based storage media (e.g., EEPROM, RAM, etc.), solid-state storage media (e.g., flash drive, etc.), and/or other electronically readable storage media.
  • Electronic storage 126 may include one or more virtual storage resources (e.g., cloud storage, a virtual private network, and/or other virtual storage resources).
  • Electronic storage 126 may store software algorithms, information determined by processor(s) 128 , information received from server(s) 102 , information received from client computing platform(s) 104 , and/or other information that enables server(s) 102 to function as described herein.
  • Processor(s) 128 may be configured to provide information processing capabilities in server(s) 102 .
  • processor(s) 128 may include one or more of a digital processor, an analog processor, a digital circuit designed to process information, an analog circuit designed to process information, a state machine, and/or other mechanisms for electronically processing information.
  • processor(s) 128 is shown in FIG. 1 as a single entity, this is for illustrative purposes only.
  • processor(s) 128 may include a plurality of processing units. These processing units may be physically located within the same device, or processor(s) 128 may represent processing functionality of a plurality of devices operating in coordination.
  • Processor(s) 128 may be configured to execute components 108 , 110 , 112 , 114 , and/or 118 , and/or other components.
  • Processor(s) 128 may be configured to execute components 108 , 110 , 112 , 114 , and/or 118 , and/or other components by software; hardware; firmware; some combination of software, hardware, and/or firmware; and/or other mechanisms for configuring processing capabilities on processor(s) 128 .
  • the term “component” may refer to any component or set of components that perform the functionality attributed to the component. This may include one or more physical processors during execution of processor readable instructions, the processor readable instructions, circuitry, hardware, storage media, or any other components.
  • components 108 , 110 , 112 , 114 , and/or 118 are illustrated in FIG. 1 as being implemented within a single processing unit, in implementations in which processor(s) 128 includes multiple processing units, one or more of components 108 , 110 , 112 , 114 , and/or 118 may be implemented remotely from the other components.
  • the description of the functionality provided by the different components 108 , 110 , 112 , 114 , and/or 118 described below is for illustrative purposes, and is not intended to be limiting, as any of components 108 , 110 , 112 , 114 , and/or 118 may provide more or less functionality than is described.
  • processor(s) 128 may be configured to execute one or more additional components that may perform some or all of the functionality attributed below to one of components 108 , 110 , 112 , 114 , and/or 118 .
  • FIG. 2 illustrates a method 200 to manage power consumption of a building and storage by controlling a refrigeration system within building 150 , in accordance with one or more implementations.
  • the operations of method 200 presented below are intended to be illustrative. In some implementations, method 200 may be accomplished with one or more additional operations not described, and/or without one or more of the operations discussed. Additionally, the order in which the operations of method 200 are illustrated in FIG. 2 and described below is not intended to be limiting.
  • method 200 may be implemented in one or more processing devices (e.g., a digital processor, an analog processor, a digital circuit designed to process information, an analog circuit designed to process information, a state machine, and/or other mechanisms for electronically processing information).
  • the one or more processing devices may include one or more devices executing some or all of the operations of method 200 in response to instructions stored electronically on an electronic storage medium.
  • the one or more processing devices may include one or more devices configured through hardware, firmware, and/or software to be specifically designed for execution of one or more of the operations of method 200 .
  • An operation 202 may include receiving input defining an average power target and a time interval.
  • the average power target may be for the time interval.
  • Operation 202 may be performed by one or more hardware processors configured by machine-readable instructions including a component that is the same as or similar to input receiving component 108 , in accordance with one or more implementations.
  • An operation 204 may include determining system information characterizing a refrigeration system. Operation 204 may be performed by one or more hardware processors configured by machine-readable instructions including a component that is the same as or similar to system information determination component 110 , in accordance with one or more implementations.
  • An operation 206 may include determining building information characterizing power usage of a building that includes the refrigeration system. Operation 206 may be performed by one or more hardware processors configured by machine-readable instructions including a component that is the same as or similar to building information determination component 112 , in accordance with one or more implementations.
  • An operation 208 may include determining precooling control actions based on the system information, the average power target, the time interval, and/or other information. Operation 208 may be performed by one or more hardware processors configured by machine-readable instructions including a component that is the same as or similar to control action determination component 114 , in accordance with one or more implementations.
  • An operation 210 may include determining load shedding control actions based on the system information, the average power target, the time interval, and/or other information. Operation 210 may be performed by one or more hardware processors configured by machine-readable instructions including a component that is the same as or similar to control action determination component 114 , in accordance with one or more implementations.
  • An operation 212 may include generating a control schedule for the refrigeration system to effectuate the precooling control actions and/or load shedding control actions based on the average power target, the time interval, the building information, and/or other information.
  • the precooling may control actions and load shedding control actions facilitate acquisition of electrical power or distribution of the electrical power.
  • Operation 212 may be performed by one or more hardware processors configured by machine-readable instructions including a component that is the same as or similar to control component 118 , in accordance with one or more implementations.
  • An operation 214 may include effectuating the precooling control actions and/or load shedding control actions for the refrigeration system in accordance with the control schedule. Operation 214 may be performed by one or more hardware processors configured by machine-readable instructions including a component that is the same as or similar to control component 118 , in accordance with one or more implementations.

Abstract

Systems and methods to manage power consumption of a building and storage by controlling a refrigeration system within the building are disclosed. Exemplary implementations may: receive input defining an average power target and a time interval; determine system information characterizing a refrigeration system; determine build information characterizing power usage of a building that includes the refrigeration system; determine precooling control actions based on the system information, the average power target, and the time interval; determine load shedding control actions based on the system information, the average power target, and the time interval; generate a control schedule for the refrigeration system to effectuate the precooling control actions and/or load shedding control actions based on the average power target, the time interval, and the building information; and effectuate the precooling control actions and/or load shedding control actions for the refrigeration system in accordance with the control schedule.

Description

    CROSS-REFERENCE TO RELATED APPLICATIONS
  • The Application is a continuation application of U.S. patent application Ser. No. 17/374,958, filed on 13 Jul. 2021, which is incorporated in its entirety by this reference.
  • FIELD OF THE DISCLOSURE
  • The present disclosure relates to systems and methods to manage power consumption of a building and storage by controlling a refrigeration system within the building.
  • BACKGROUND
  • Typically, mass refrigeration systems (e.g., warehouses, supermarkets) utilize electrochemical batteries to offset electrical consumption. However, the amount of power required from the electrochemical batteries may be costly given the large amount of power consumed by the mass refrigeration systems.
  • SUMMARY
  • One aspect of the present disclosure relates to optimizing power consumption of a building by instructing a refrigeration system within the building to precool items enclosed within the refrigeration system and load shed. The precooling and the load shedding may occur based on a desired power target for a particular time interval. The desired power target and the time interval may be obtained via user input (e.g., manager of the refrigeration system) or obtained from an external resource. Based on the power target and the time interval obtained and information related to the refrigeration system obtained, precooling and the load shedding control actions may be determined. Subsequently, and a control schedule to effectuate the precooling and the load shedding may be generated based on the power target, the time interval, and information related to the building, and subsequently executed. As such, the building may optimize power consumption and more efficiently store power through excess refrigeration capacity and thermal capacity of the items being refrigerated in addition to operational flexibility of the mass refrigeration systems. As a result, demand charges may be reduced.
  • One aspect of the present disclosure relates to a system configured to manage power consumption of a building and storage by controlling a refrigeration system within the building. The system may include one or more hardware processors configured by machine-readable instructions. The machine-readable instructions may include one or more instruction components. The instruction components may include computer program components. The instruction components may include one or more of input receiving component, system information determination component, building information determination component, control action determination component, control component, and/or other instruction components.
  • The input receiving component may be configured to receive input defining an average power target and a time interval. The average power target may be for the time interval. The average power target may be an optimal amount of power consumption or usage of the building during the time interval.
  • The system information determination component may be configured to determine system information characterizing a refrigeration system. The system information may include suction pressures, compressor information, case information, circuit control information, defrost schedules, door information, pressure information, and/or other system information.
  • The building information determination component may be configured to determine building information characterizing power usage of a building that includes the refrigeration system. The building information may include current power information, a required power target based on the average power target and the current power information, a building temperature, and/or other building information.
  • The control action determination component may be configured to determine precooling control actions based on the system information, the average power target, the time interval, and/or other information. The control action determination component may be configured to determine load shedding control actions based on the system information, the average power target, the time interval, and/or other information.
  • The control component may be configured to generate a control schedule for the refrigeration system to effectuate the precooling control actions and/or load shedding control actions based on the average power target, the time interval, the building information, and/or other information. The precooling may control actions and load shedding control actions facilitate acquisition of electrical power or distribution of the electrical power. The control component may be configured to effectuate the precooling control actions and/or load shedding control actions for the refrigeration system in accordance with the control schedule.
  • As used herein, the term “obtain” (and derivatives thereof) may include active and/or passive retrieval, determination, derivation, transfer, upload, download, submission, and/or exchange of information, and/or any combination thereof. As used herein, the term “effectuate” (and derivatives thereof) may include active and/or passive causation of any effect, both local and remote. As used herein, the term “determine” (and derivatives thereof) may include measure, calculate, compute, estimate, approximate, generate, and/or otherwise derive, and/or any combination thereof.
  • These and other features, and characteristics of the present technology, as well as the methods of operation and functions of the related elements of structure and the combination of parts and economies of manufacture, will become more apparent upon consideration of the following description and the appended claims with reference to the accompanying drawings, all of which form a part of this specification, wherein like reference numerals designate corresponding parts in the various figures. It is to be expressly understood, however, that the drawings are for the purpose of illustration and description only and are not intended as a definition of the limits of the invention. As used in the specification and in the claims, the singular form of ‘a’, ‘an’, and ‘the’ include plural referents unless the context clearly dictates otherwise.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • FIG. 1 illustrates a system configured to manage power consumption of a building and storage by controlling a refrigeration system within the building, in accordance with one or more implementations.
  • FIG. 2 illustrates a method to manage power consumption of a building and storage by controlling a refrigeration system within the building, in accordance with one or more implementations.
  • FIG. 3 illustrates an example implementation of the system configured to manage power consumption of a building and storage by controlling a refrigeration system within the building, in accordance with one or more implementations.
  • DETAILED DESCRIPTION
  • FIG. 1 illustrates a system 100 configured to manage power consumption of a building and storage by controlling a refrigeration system within a building 150, in accordance with one or more implementations. In some implementations, system 100 may include one or more servers 102. Server(s) 102 may be configured to communicate with one or more client computing platforms 104 according to a client/server architecture and/or other architectures. Client computing platform(s) 104 may be configured to communicate with other client computing platforms via server(s) 102 and/or according to a peer-to-peer architecture and/or other architectures. Users may access system 100 via client computing platform(s) 104. A given client computing platform 104 may be associated with, connected via a network 116, and/or operatively linked via one or more electronic communication links with building 150, the refrigeration system, and/or other systems within building 150 such that facility operations, the refrigeration system, and/or the other systems may be controlled and/or monitored via client computing platform 104. In some implementations, the refrigeration system may be operatively linked with building 150 and/or wirelessly connected with building 150 via network 116.
  • Server(s) 102 may be configured by machine-readable instructions 106. Machine-readable instructions 106 may include one or more instruction components. The instruction components may include computer program components. The instruction components may include one or more of input receiving component 108, system information determination component 110, building information determination component 112, control action determination component 114, control component 118, and/or other instruction components.
  • Input receiving component 108 may be configured to receive input defining an average power target and a time interval. The average power target may refer to an ideal power consumption of building 150 to achieve for or during the time interval. The time interval may be an amount of seconds, an amount of minutes, an amount of hours, an amount of days on a particular date and/or time. In some implementations, the time interval may a time between be a start time and an end time. For example, the time interval may be between 2:00 PM and 2:15 PM (i.e., a 15-minute time interval). In some implementations, the average power target may be determined and received from external resource(s) 124. In some implementations, the average power target may be received via the input enter by a user (e.g., a manager of building 150).
  • System information determination component 110 may be configured to determine system information characterizing the refrigeration system. The refrigeration system may be configured to cool, maintain coldness, freeze, and/or keep frozen products stored within one or more cases of the refrigeration system. In some implementations, all the cases of an individual refrigeration system may cool and/or maintain the coldness of the products stored within. In some implementations, all the cases of an individual refrigeration system may freeze and/or keep frozen of the products stored within. In some implementations, some the cases of an individual refrigeration system may cool and/or maintain the coldness of the products stored within, and some of the cases may freeze and/or keep frozen of the products stored within. The system information may include suction pressures at various times, compressor information, case information, circuit control information, defrost schedules, door information, pressure information, historical facility operations, and/or other system information. In some implementations, some or all of the system information may vary for the individual cases included in the refrigeration system.
  • The compressor information may include current states of individual compressors, historical states of the individual compressors, and/or other compressor information. States of the individual compressors (current and historical) may include a compressor type, run capacity of the individual compressor, run time at the run capacity, and/or other compressor information.
  • The case information may include current case temperatures of the individual cases included in the refrigeration system, historical case temperatures of the individual cases, case types, and/or other case information. A case may refer to a container that stores the products requiring cooling or freezing. For example, the products may include produce, dairy products, meats, among others. The case temperatures, current and historical, may be in Celsius, Fahrenheit, or both. The case types may include a forced air case, a gravity coil case, and/or other case types. The individual cases of the refrigeration system may include different access to the products stored inside. For example, the different access may include one or more of a front door access, a rear door access, a partially open front access, an open front access, an open rear access, a top door access, a side door access, and/or other access to the products by consumers and/or employees (e.g., product stockers). The different accesses may affect the case temperatures, functionality of the individual case types, other case information, and/or other system information of the refrigeration system.
  • The circuit control information may include current positions of individual circuit control valves, historical positions of the individual circuit control valves, and/or other information. The positions of the individual circuit control values may control a flow rate of a particular fluid and thus control the case temperature of the corresponding cases, pressure of the particular fluid, a level of the particular fluid, and/or other parameter values related to the refrigeration system.
  • The defrost schedules may characterize a schedule for defrosting the products in the individual cases. The defrost schedules may include one or more dates and/or times at which the case temperatures are set to particular temperatures to gradually progress the case temperatures to a target case temperature. In some implementations, the dates, the times, the particular temperatures, and the target case temperature may be based on user input. In some implementations, the user input may include a target time at which the products should be a target temperature or the target case temperature for a target time. Based on such, the dates, the times, and the particular temperatures may be determined by system information determination component 110. In some implementations, the defrost schedules may be determined and obtained from external resource(s) 124. In some implementations, the individual cases may function in accordance with individual defrost schedules. In some implementations, multiple or all cases may function in accordance with a single defrost schedule.
  • The door information may include a date, time, and/or duration at which one or more doors of the individual cases are open and closed. In some implementations, the door information may include an operator who has opened or closed the door at a particular date and/or time. For example, the operator may be a maintenance worker for the refrigeration system, an employee that utilized the refrigeration system (e.g., product stocker, butcher, baker, manager of building 150 that includes the refrigeration system, etc.), a customer, and/or other operators. In some implementations, the door information may be conveyed by one or more door sensors on the individual cases.
  • The pressure information may include a condenser pressure at which refrigerant changes from a gas to a liquid, a compressor discharge pressure, an evaporator pressure at which the refrigerant changes from a liquid to a gas, and/or other pressure information. In some implementations, the pressure information may be for the individual cases or for the refrigeration system as a whole.
  • The historical facility operations may include restocking schedules, work hours, clearance schedules, operational information of other systems included in building 150, and/or other information. The restocking schedules may include dates and/or times at which the products in all the cases or the individual cases are restocked with other or new products. The work hours may include time periods at which building 150 or individual systems within building 150 (e.g., the refrigeration system) are operated by the operators. The clearance schedules may be dates and/or times at which some or all of the products are cleared from all or individual cases. The other systems included in building 150 may include one or more of a trash compactor, cooking equipment (e.g., mixers, ovens, dish washers, etc.), an elevator, a heating system, a ventilation system, an air conditioning system, a lighting system, a security system (e.g., surveillance systems, alarm systems), an intercom system, and/or other systems. The operational information for the other systems may include operation schedules indicating when the individual other systems are active, inactive, or idle, managers of the individual other systems, historical maintenance of the individual other systems, date of installation, warranty information for the individual other systems, and/or other operational information.
  • Building information determination component 112 may be configured to determine building information characterizing power usage of building 150 that includes the refrigeration system and/or the other systems. The power usage may refer to an amount of energy used per unit of time. The building information may include current power information, a required power target, a building temperature, and/or other building information.
  • The current power information may indicate current power that building 150 is consuming. In some implementations, the current power information may be obtained from an electrical meter coupled with building 150. In some implementations, the current amount of power may be calculated per unit of time based on a regression model, a time of a day, the day of the week, an occupancy value, an outside air temperature value, and/or other information. For example, the regression models may include linear regression, logistic regression, ridge regression, lasso regression, polynomial regression, Bayesian linear regression, and/or other regression model. In some implementations, the regression model may be based on the historical facility operations. The unit of time may be seconds, minutes, hours, and/or other unit of time. The occupancy may refer to used space of building 150 or particular areas thereof with people, animals, the systems, and/or the products. The occupancy value may be in cubic feet, cubic meters, a particular amount of the people, a particular amount of the animals, a particular amount of the systems, a particular amount of the products, and/or other unit of occupancy. The outside air temperature value may be obtained from external resources 124. The outside air temperature value may be conveyed by and obtained from one or more temperature sensors associated or coupled with building 150.
  • The required power target may be power required by building 150. The required power target may be based on the average power target, the current power information, the building information and/or other information. In some implementations, the required power target may be determined by building information determination component 112. In some implementations, the required power target may be determined by external resources 124 and received by building information determination component 112. The building temperature may include an average building temperature of the entire building, temperatures of individual areas of building 150, a temperature at which building 150 is set at, temperatures at which the individual areas are set at, and/or other building temperatures.
  • Control action determination component 114 may be configured to determine precooling control actions based on the system information, the average power target, the time interval, and/or other information. The precooling control actions may include increasing an amount of active compressors within the refrigeration system, increasing the active compressors, deactivating one or more unloaders of the compressors, increasing frequency of variable frequency drives, controlling circuit control valves connected to evaporators, and/or other precooling control actions. In some implementations, a particular amount of compressors may be included in the refrigeration system. Some or all of the compressors may be active at once. Increasing the amount of active compressors may include activating one or more of the compressors not already active. Increasing the active compressors may include lowering a trigger temperature (of temperature sensors associated with the compressors and/or within the cases of the refrigeration system) that actives the compressors, increasing a motor speed of the compressor, and/or other operations to increase the active compressors. Controlling the circuit control valves may include opening or closing the circuit control valves partially or completely on all the evaporators or some of the evaporators. The circuit control valves may be partially opened or closed by a rotational degree, a flow rate amount, and/or other value.
  • Control action determination component 114 may be configured to determine load shedding control actions based on the system information, the average power target, the time interval, and/or other information. The load shedding control actions may include decreasing the amount of the active compressors (i.e., the opposite of increasing the amount of the active compressors described herein), decreasing the active compressors, activating the unloaders, decreasing frequency of variable frequency drives, and/or other load shedding control actions.
  • Control component 118 may be configured to generate a control schedule for the refrigeration system to effectuate the precooling control actions and/or load shedding control actions. The precooling control actions and the load shedding control actions may facilitate acquisition of electrical power or distribution of the electrical power. The control schedule may be generated in accordance with a generation plan. The generation plan may specify that the control schedule is generated recurring after a particular amount of time (e.g., every 5 days, every 30 days), periodically (e.g., first day of every month, every Monday, etc.), responsive to user input to generate, and/or at other times. The generation plan may specify that a remainder of the control schedule is updated at particular times or periodically based on the building information, the system information, and/or other information. For example, the control schedule may be updated upon half the amount time between the times at which the control schedules are generated at lapsed (e.g., 15 days into the 30 days).
  • Control component 118 may be configured to effectuate the precooling control actions and/or load shedding control actions for the refrigeration system in accordance with the control schedule. In some implementations, the control schedule may be effectuated immediately subsequent to the generation. In some implementations, the control schedule may be transmitted to a different component, building 150, or the refrigeration system for effectuation. Responsive to the effectuation of the control schedule, power consumption by the refrigeration system and/or the building may be reduced. Reduction of the power consumption, particularly during individual time intervals, may reduce demand charges. An electrical power demand may be based on a highest average amount of energy consumed during a particular time interval by the building (i.e., customer). The electrical power demand may be a larger portion of an electricity bill, billed at a higher rate, and/or other differences that may add expense to a manager/management of the building, i.e., the demand charges.
  • FIG. 3 illustrates an example implementation of building 150 (the same as or similar in FIG. 1 ) that include a refrigeration system 311. Building 150 may include building information 306 as detailed in FIG. 1 . Refrigeration system 311 may include system information 304 as detailed in FIG. 1 . Refrigeration system 311 may store products within cases 314 included in refrigeration system 311. For example, the products within cases 314 may include foods that are refrigerated or frozen. Control actions 308, including precooling control actions and load shedding control actions, may be determined for refrigeration system 311 by server(s) 102 (and computer components thereof) based on an average power target 302, a time interval 312, and system information 304 received by server(s) 102 (the same as or similar to FIG. 1 ). Furthermore, a control schedule 310 to effectuate control actions 308 may be determined by server(s) 102 based on average power target 302, time interval 312, building information 306. Control schedule 310 may be subsequently effectuated or may be transmitted to refrigeration system 311 for implementation. As such, power consumption may be optimized for refrigeration system 311 and thus building 150.
  • Referring back to FIG. 1 , in some implementations, server(s) 102, client computing platform(s) 104, and/or external resources 124 may be operatively linked via one or more electronic communication links. For example, such electronic communication links may be established, at least in part, via a network such as the Internet and/or other networks. It will be appreciated that this is not intended to be limiting, and that the scope of this disclosure includes implementations in which server(s) 102, client computing platform(s) 104, and/or external resources 124 may be operatively linked via some other communication media.
  • A given client computing platform 104 may include one or more processors configured to execute computer program components. The computer program components may be configured to enable an expert or user associated with the given client computing platform 104 to interface with system 100 and/or external resources 124, and/or provide other functionality attributed herein to client computing platform(s) 104. By way of non-limiting example, the given client computing platform 104 may include one or more of a desktop computer, a laptop computer, a handheld computer, a tablet computing platform, a NetBook, a Smartphone, a gaming console, and/or other computing platforms.
  • External resources 124 may include sources of information outside of system 100, external entities participating with system 100, and/or other resources. In some implementations, some or all of the functionality attributed herein to external resources 124 may be provided by resources included in system 100.
  • Server(s) 102 may include electronic storage 126, one or more processors 128, and/or other components. Server(s) 102 may include communication lines, or ports to enable the exchange of information with a network and/or other computing platforms. Illustration of server(s) 102 in FIG. 1 is not intended to be limiting. Server(s) 102 may include a plurality of hardware, software, and/or firmware components operating together to provide the functionality attributed herein to server(s) 102. For example, server(s) 102 may be implemented by a cloud of computing platforms operating together as server(s) 102.
  • Electronic storage 126 may comprise non-transitory storage media that electronically stores information. The electronic storage media of electronic storage 126 may include one or both of system storage that is provided integrally (i.e., substantially non-removable) with server(s) 102 and/or removable storage that is removably connectable to server(s) 102 via, for example, a port (e.g., a USB port, a firewire port, etc.) or a drive (e.g., a disk drive, etc.). Electronic storage 126 may include one or more of optically readable storage media (e.g., optical disks, etc.), magnetically readable storage media (e.g., magnetic tape, magnetic hard drive, floppy drive, etc.), electrical charge-based storage media (e.g., EEPROM, RAM, etc.), solid-state storage media (e.g., flash drive, etc.), and/or other electronically readable storage media. Electronic storage 126 may include one or more virtual storage resources (e.g., cloud storage, a virtual private network, and/or other virtual storage resources). Electronic storage 126 may store software algorithms, information determined by processor(s) 128, information received from server(s) 102, information received from client computing platform(s) 104, and/or other information that enables server(s) 102 to function as described herein.
  • Processor(s) 128 may be configured to provide information processing capabilities in server(s) 102. As such, processor(s) 128 may include one or more of a digital processor, an analog processor, a digital circuit designed to process information, an analog circuit designed to process information, a state machine, and/or other mechanisms for electronically processing information. Although processor(s) 128 is shown in FIG. 1 as a single entity, this is for illustrative purposes only. In some implementations, processor(s) 128 may include a plurality of processing units. These processing units may be physically located within the same device, or processor(s) 128 may represent processing functionality of a plurality of devices operating in coordination. Processor(s) 128 may be configured to execute components 108, 110, 112, 114, and/or 118, and/or other components. Processor(s) 128 may be configured to execute components 108, 110, 112, 114, and/or 118, and/or other components by software; hardware; firmware; some combination of software, hardware, and/or firmware; and/or other mechanisms for configuring processing capabilities on processor(s) 128. As used herein, the term “component” may refer to any component or set of components that perform the functionality attributed to the component. This may include one or more physical processors during execution of processor readable instructions, the processor readable instructions, circuitry, hardware, storage media, or any other components.
  • It should be appreciated that although components 108, 110, 112, 114, and/or 118 are illustrated in FIG. 1 as being implemented within a single processing unit, in implementations in which processor(s) 128 includes multiple processing units, one or more of components 108, 110, 112, 114, and/or 118 may be implemented remotely from the other components. The description of the functionality provided by the different components 108, 110, 112, 114, and/or 118 described below is for illustrative purposes, and is not intended to be limiting, as any of components 108, 110, 112, 114, and/or 118 may provide more or less functionality than is described. For example, one or more of components 108, 110, 112, 114, and/or 118 may be eliminated, and some or all of its functionality may be provided by other ones of components 108, 110, 112, 114, and/or 118. As another example, processor(s) 128 may be configured to execute one or more additional components that may perform some or all of the functionality attributed below to one of components 108, 110, 112, 114, and/or 118.
  • FIG. 2 illustrates a method 200 to manage power consumption of a building and storage by controlling a refrigeration system within building 150, in accordance with one or more implementations. The operations of method 200 presented below are intended to be illustrative. In some implementations, method 200 may be accomplished with one or more additional operations not described, and/or without one or more of the operations discussed. Additionally, the order in which the operations of method 200 are illustrated in FIG. 2 and described below is not intended to be limiting.
  • In some implementations, method 200 may be implemented in one or more processing devices (e.g., a digital processor, an analog processor, a digital circuit designed to process information, an analog circuit designed to process information, a state machine, and/or other mechanisms for electronically processing information). The one or more processing devices may include one or more devices executing some or all of the operations of method 200 in response to instructions stored electronically on an electronic storage medium. The one or more processing devices may include one or more devices configured through hardware, firmware, and/or software to be specifically designed for execution of one or more of the operations of method 200.
  • An operation 202 may include receiving input defining an average power target and a time interval. The average power target may be for the time interval. Operation 202 may be performed by one or more hardware processors configured by machine-readable instructions including a component that is the same as or similar to input receiving component 108, in accordance with one or more implementations.
  • An operation 204 may include determining system information characterizing a refrigeration system. Operation 204 may be performed by one or more hardware processors configured by machine-readable instructions including a component that is the same as or similar to system information determination component 110, in accordance with one or more implementations.
  • An operation 206 may include determining building information characterizing power usage of a building that includes the refrigeration system. Operation 206 may be performed by one or more hardware processors configured by machine-readable instructions including a component that is the same as or similar to building information determination component 112, in accordance with one or more implementations.
  • An operation 208 may include determining precooling control actions based on the system information, the average power target, the time interval, and/or other information. Operation 208 may be performed by one or more hardware processors configured by machine-readable instructions including a component that is the same as or similar to control action determination component 114, in accordance with one or more implementations.
  • An operation 210 may include determining load shedding control actions based on the system information, the average power target, the time interval, and/or other information. Operation 210 may be performed by one or more hardware processors configured by machine-readable instructions including a component that is the same as or similar to control action determination component 114, in accordance with one or more implementations.
  • An operation 212 may include generating a control schedule for the refrigeration system to effectuate the precooling control actions and/or load shedding control actions based on the average power target, the time interval, the building information, and/or other information. The precooling may control actions and load shedding control actions facilitate acquisition of electrical power or distribution of the electrical power. Operation 212 may be performed by one or more hardware processors configured by machine-readable instructions including a component that is the same as or similar to control component 118, in accordance with one or more implementations.
  • An operation 214 may include effectuating the precooling control actions and/or load shedding control actions for the refrigeration system in accordance with the control schedule. Operation 214 may be performed by one or more hardware processors configured by machine-readable instructions including a component that is the same as or similar to control component 118, in accordance with one or more implementations.
  • Although the present technology has been described in detail for the purpose of illustration based on what is currently considered to be the most practical and preferred implementations, it is to be understood that such detail is solely for that purpose and that the technology is not limited to the disclosed implementations, but, on the contrary, is intended to cover modifications and equivalent arrangements that are within the spirit and scope of the appended claims. For example, it is to be understood that the present technology contemplates that, to the extent possible, one or more features of any implementation can be combined with one or more features of any other implementation.

Claims (20)

1. A method comprising:
accessing a target temperature of an interior volume of a refrigeration unit;
accessing a lower temperature limit of the interior volume of the refrigeration unit;
accessing a power consumption target of the refrigeration unit within a target time interval;
predicting a nominal power consumption of the refrigeration unit during the target time interval to maintain the interior volume of the refrigeration unit at the target temperature;
in response to the nominal power consumption exceeding the power consumption target:
calculating a precooling temperature, less than the target temperature and greater than the lower temperature limit, of the refrigeration unit prior to target time interval;
generating an electronic refrigeration schedule specifying:
activation of a refrigeration system within the refrigeration unit to cool the interior volume of the refrigeration unit to the precooling temperature prior to the target time interval;
deactivation of the refrigeration system during the target time interval while a temperature of the interior volume of the refrigeration unit is less than the target temperature; and
reactivation of the refrigeration system to cool the interior volume of the refrigeration unit during the target time interval in response to the temperature of the interior volume of the refrigeration unit approaching the target temperature; and
loading the electronic refrigeration schedule onto the refrigeration unit for execution by the refrigeration unit.
2. The method of claim 1, wherein generating the electronic refrigeration schedule comprises:
generating the electronic refrigeration schedule specifying cooling the interior volume of the refrigeration unit, arranged in a refrigeration system occupying a building, to the precooling temperature prior to the target time interval to:
reduce a power consumption of the refrigeration unit occupying the building; and
shed an electrical load of the refrigeration unit on the building during the target time interval.
3. The method of claim 1, wherein generating the electronic refrigeration schedule comprises:
generating the electronic refrigeration schedule specifying cooling the interior volume of the refrigeration unit to the precooling temperature prior to target time interval to:
shift power consumption of the refrigeration unit from the target time interval to a second time interval preceding the target time interval.
4. The method of claim 1:
wherein calculating the nominal power consumption comprises:
accessing a historical power consumption of the refrigeration unit corresponding to the refrigeration unit maintaining interior temperature proximal target temperature during a previous instance of the target time interval; and
wherein generating the electronic refrigeration schedule comprises:
generating a control schedule of the refrigeration unit configured to shed the electrical load of the refrigeration unit from the target time interval to a second target interval not including the target time interval.
5. The method of claim 1, wherein calculating the precooling temperature comprises:
accessing a historical environmental temperature proximal the refrigeration unit during a previous instance of the target time interval;
accessing a historical temperature within the interior volume of the refrigeration unit at a start time of the previous instance of the target time interval;
accessing a forecasted environmental temperature proximal the refrigeration unit during a next instance of target time interval;
in response to the historical environmental temperature greater than forecasted environmental temperature, calculating the precooling temperature greater than the historical temperature within the interior volume of the refrigeration unit; and
in response to the historical environmental temperature less than forecasted environmental temperature, calculating the precooling temperature less than the historical temperature within the interior volume of the refrigeration unit.
6. The method of claim 1, further comprising:
in response to the nominal power consumption of the refrigeration unit during the target time interval less than power consumption target:
calculating a first total daily power consumption for a current day including the target time interval;
calculating a second total daily power consumption on prior day with prior target time interval;
in response to the first total daily power consumption exceeding the second total daily power consumption:
calculating a second precooling temperature, less than the target temperature and greater than the lower temperature limit, of the refrigeration unit prior to target time interval;
in response to the first total daily power consumption exceeding the second total daily power consumption, generating a second electronic refrigeration schedule specifying:
activation of the refrigeration system within the refrigeration unit to cool the interior volume of the refrigeration unit to the second precooling temperature prior to the target time interval;
deactivation of the refrigeration system during the target time interval while the temperature of the interior volume of the refrigeration unit is less than the target temperature; and
reactivation of the refrigeration system to cool the interior volume of the refrigeration unit during the target time interval in response to the temperature of the interior volume of the refrigeration unit approaching the target temperature; and
loading the second electronic refrigeration schedule onto the refrigeration unit for execution by the refrigeration unit.
7. The method of claim 1:
further comprising accessing a target power consumption buffer between the power consumption target and the nominal power consumption of the refrigeration unit; and
wherein calculating the precooling temperature comprises:
deriving the precooling temperature predicted to yield a revised power consumption, by the refrigeration unit, less than and differing from the power consumption target by the target power consumption buffer.
8. The method of claim 1, wherein calculating the precooling temperature of the refrigeration unit comprises:
calculating the precooling temperature predicted to yield null power consumption during the target time interval.
9. The method of claim 1:
wherein accessing the target temperature of the interior volume of the refrigeration unit comprises:
accessing the target temperature of unfrozen foodstuffs stored in the refrigeration unit; and
wherein accessing the lower temperature limit of the interior volume of the refrigeration unit comprises:
accessing a minimum temperature of the interior volume of the refrigeration unit predicted to avoid freezing of foodstuffs stored in the refrigeration unit.
10. The method of claim 1:
wherein accessing the target temperature of the interior volume of the refrigeration unit comprises:
accessing the target temperature of frozen foodstuffs stored in the refrigeration unit; and
wherein accessing the lower temperature limit of the interior volume of the refrigeration unit comprises:
accessing a lower operating temperature limit of the refrigeration unit.
11. The method of claim 1, wherein accessing the lower temperature limit comprises:
deriving a predict minimum operating temperature of the refrigeration unit based on:
an age of the refrigeration unit;
a historical power consumption of the refrigeration unit; and
a maintenance history of the refrigeration unit.
12. The method of claim 1, wherein generating the electronic refrigeration schedule comprises:
generating the electronic refrigeration schedule specifying:
deactivation of a compressor of the refrigeration unit to reduce a power consumption of the refrigeration unit during the target time interval.
13. The method of claim 1, wherein predicting the nominal power consumption of the refrigeration unit during the target time interval comprises:
accessing a set of historical data generated prior to the target time interval, the set of historical data comprising:
suction pressures of the refrigeration unit;
compressor information of the refrigeration unit;
case information of the refrigeration unit;
circuit control information of the refrigeration unit;
defrost schedules of the refrigeration unit;
door information of the refrigeration unit; and
pressure information of the refrigeration unit; and
predicting the nominal power consumption during the target time interval based on the set of historical data.
14. The method of claim 1:
wherein calculating the precooling temperature comprises:
accessing a type of food stored within the internal volume of the refrigeration unit;
accessing a thermal capacity of the type of food stored within the internal volume;
predicting an increase in a temperature of the internal volume of the refrigeration unit during the target time internal based on the thermal capacity of the type of food given reduction in power consumption of the refrigeration unit during the target time interval; and
calculating the precooling temperature predicted to:
offset the increase in the temperature, of the internal volume of the refrigeration unit during the target time internal, due to reduction in power consumption of the refrigeration unit during the target time interval; and
maintain the temperature, of the internal volume of the refrigeration unit, below the target temperature.
15. A method comprising:
during first time period:
selectively activation of a refrigeration system to maintain an interior volume of a refrigeration unit at target temperature;
detecting first power consumption during first time interval;
accessing a lower temperature limit of the interior volume of the refrigeration unit;
accessing a power consumption target of the refrigeration unit within a second time interval;
predicting a second power consumption of the refrigeration unit to maintain the interior volume of the refrigeration unit at the target temperature during the second time interval based on the first power consumption;
in response to the nominal power consumption exceeding the power consumption target:
calculating a precooling temperature, less than the target temperature and greater than the lower temperature limit, of the refrigeration unit prior to the target time interval;
generating an electronic refrigeration schedule specifying:
activation of the refrigeration system to cool the interior volume of the refrigeration unit to the precooling temperature prior to the target time interval;
deactivation of the refrigeration system during the target time interval while a temperature of the interior volume of the refrigeration unit is less than the target temperature; and
reactivation of the refrigeration system to cool the interior volume of the refrigeration unit during the target time interval in response to the temperature of the interior volume of the refrigeration unit approaching the target temperature; and
loading the electronic refrigeration schedule onto the refrigeration unit for execution by the refrigeration unit.
16. The method of claim 15 wherein generating the electronic refrigeration schedule comprises:
generating the electronic refrigeration schedule specifying cooling the interior volume of the refrigeration unit, arranged in a refrigeration system occupying a building, to the precooling temperature prior to the target time interval to:
reduce a power consumption of the refrigeration unit occupying the building; and
shed an electrical load of the refrigeration unit on the building during the target time interval.
17. The method of claim 15, wherein calculating the precooling temperature comprises:
accessing a historical environmental temperature proximal the refrigeration unit during a previous instance of the target time interval;
accessing a historical temperature within the interior volume of the refrigeration unit at a start time of the previous instance of the target time interval;
accessing a forecasted environmental temperature proximal the refrigeration unit during a next instance of target time interval;
in response to the historical environmental temperature greater than forecasted environmental temperature, calculating the precooling temperature greater than the historical temperature within the interior volume of the refrigeration unit; and
in response to the historical environmental temperature less than forecasted environmental temperature, calculating the precooling temperature less than the historical temperature within the interior volume of the refrigeration unit.
18. The method of claim 15, further comprising:
in response to the nominal power consumption of the refrigeration unit during the target time interval less than power consumption target:
calculating a first total daily power consumption for a current day including the target time interval;
calculating a second total daily power consumption on prior day with prior target time interval;
in response to the first total daily power consumption exceeding the second total daily power consumption:
calculating a second precooling temperature, less than the target temperature and greater than the lower temperature limit, of the refrigeration unit prior to target time interval;
in response to the first total daily power consumption exceeding the second total daily power consumption, generating a second electronic refrigeration schedule specifying:
activation of the refrigeration system within the refrigeration unit to cool the interior volume of the refrigeration unit to the second precooling temperature prior to the target time interval;
deactivation of the refrigeration system during the target time interval while the temperature of the interior volume of the refrigeration unit is less than the target temperature; and
reactivation of the refrigeration system to cool the interior volume of the refrigeration unit during the target time interval in response to the temperature of the interior volume of the refrigeration unit approaching the target temperature; and
loading the second electronic refrigeration schedule onto the refrigeration unit for execution by the refrigeration unit.
19. A method comprising:
accessing a target temperature of an interior volume of a refrigeration unit;
accessing a lower temperature limit of the interior volume of the refrigeration unit;
accessing a power consumption target of the refrigeration unit within a target time interval;
calculating a precooling temperature, less than the target temperature and greater than the lower temperature limit, of the refrigeration unit prior to target time interval
generating an electronic refrigeration schedule specifying:
activation of a refrigeration system within the refrigeration unit to cool the interior volume of the refrigeration unit to the precooling temperature prior to target time interval
deactivation of the refrigeration system during the target time interval while a temperature of the interior volume of the refrigeration unit is less than the target temperature; and
reactivation of the refrigeration system to cool the interior volume of the refrigeration unit during the target time interval in response to the temperature of the interior volume of the refrigeration unit approaching the target temperature; and
loading the electronic refrigeration schedule onto the refrigeration unit for execution by the refrigeration unit.
20. The method of claim 19, wherein generating the electronic refrigeration schedule comprises:
generating the electronic refrigeration schedule specifying cooling the interior volume of the refrigeration unit, arranged in a refrigeration system occupying a building, to the precooling temperature prior to the target time interval to:
a reduce a power consumption of the refrigeration unit occupying the building; and
shed an electrical load of the refrigeration unit on the building during the target time interval.
US18/386,939 2021-07-13 2023-11-03 Systems and methods to manage power consumption of a building and storage by controlling a refrigeration system within the building Pending US20240060695A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US18/386,939 US20240060695A1 (en) 2021-07-13 2023-11-03 Systems and methods to manage power consumption of a building and storage by controlling a refrigeration system within the building

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US17/374,958 US11841178B1 (en) 2021-07-13 2021-07-13 Systems and methods to manage power consumption of a building and storage by controlling a refrigeration system within the building
US18/386,939 US20240060695A1 (en) 2021-07-13 2023-11-03 Systems and methods to manage power consumption of a building and storage by controlling a refrigeration system within the building

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
US17/374,958 Continuation US11841178B1 (en) 2021-07-13 2021-07-13 Systems and methods to manage power consumption of a building and storage by controlling a refrigeration system within the building

Publications (1)

Publication Number Publication Date
US20240060695A1 true US20240060695A1 (en) 2024-02-22

Family

ID=89123522

Family Applications (2)

Application Number Title Priority Date Filing Date
US17/374,958 Active US11841178B1 (en) 2021-07-13 2021-07-13 Systems and methods to manage power consumption of a building and storage by controlling a refrigeration system within the building
US18/386,939 Pending US20240060695A1 (en) 2021-07-13 2023-11-03 Systems and methods to manage power consumption of a building and storage by controlling a refrigeration system within the building

Family Applications Before (1)

Application Number Title Priority Date Filing Date
US17/374,958 Active US11841178B1 (en) 2021-07-13 2021-07-13 Systems and methods to manage power consumption of a building and storage by controlling a refrigeration system within the building

Country Status (1)

Country Link
US (2) US11841178B1 (en)

Family Cites Families (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3872688A (en) * 1974-06-13 1975-03-25 Whirlpool Co Refrigeration apparatus divider wall mounting means
US4807443A (en) 1987-10-20 1989-02-28 Battson R Kenneth Refrigeration control system
US5586444A (en) 1995-04-25 1996-12-24 Tyler Refrigeration Control for commercial refrigeration system
DE19750053A1 (en) 1997-11-12 1999-05-20 Etc Energietechnik Und Chemie Household refrigerator
US6631622B1 (en) 2002-03-22 2003-10-14 Whirlpool Corporation Demand side management of freezer systems
US7142949B2 (en) 2002-12-09 2006-11-28 Enernoc, Inc. Aggregation of distributed generation resources
US7617695B2 (en) 2006-03-29 2009-11-17 Hussmann Corporation Control method for variable capacity compressors
US8350697B2 (en) * 2009-05-18 2013-01-08 Alarm.Com Incorporated Remote device control and energy monitoring by analyzing data and applying rules
US8280556B2 (en) 2009-12-22 2012-10-02 General Electric Company Energy management of HVAC system
US8869546B2 (en) 2010-11-03 2014-10-28 General Electric Company Refrigeration demand response recovery
US20130145781A1 (en) 2011-05-16 2013-06-13 Carrier Corporation Multi-Compressor Refrigeration System and Method for Operating It
US20120296711A1 (en) 2011-05-20 2012-11-22 Lee Huffman Methods for reducing the peak demand of electric utilities during air conditioning season
EP2738482B1 (en) 2012-11-30 2020-11-18 Danfoss A/S A method for matching refrigeration load to compressor capacity
WO2014124353A1 (en) 2013-02-11 2014-08-14 Siemens Aktiengesellschaft Cloud enabled building automation system
US9599118B2 (en) 2013-04-04 2017-03-21 Trane International Inc. System and method for controlling a system that includes fixed speed and variable speed compressors
US10902531B1 (en) * 2013-08-07 2021-01-26 Promanthan Brains LLC Predictive thermostat
US10690364B2 (en) * 2015-09-08 2020-06-23 International Business Machines Corporation Predictive analytics to determine optimal structure control
US10190793B2 (en) 2015-10-08 2019-01-29 Johnson Controls Technology Company Building management system with electrical energy storage optimization based on statistical estimates of IBDR event probabilities
US20170241690A1 (en) 2016-02-19 2017-08-24 Emerson Climate Technologies, Inc. Compressor Capacity Modulation System For Multiple Compressors
US10324483B2 (en) 2017-01-12 2019-06-18 Johnson Controls Technology Company Building energy storage system with peak load contribution cost optimization
US10674638B2 (en) * 2017-01-26 2020-06-02 Dell Products L.P. Fail-on cooling system
WO2018200861A1 (en) 2017-04-27 2018-11-01 Johnson Controls Technology Company Building energy system with stochastic model predictive control
US10876754B2 (en) 2017-07-28 2020-12-29 Johnson Controls Technology Company Dynamic central plant control based on load prediction
EP3457513A1 (en) 2017-09-13 2019-03-20 Johnson Controls Technology Company Building energy system with load balancing
US11009252B2 (en) 2018-05-07 2021-05-18 Johnson Controls Technology Company HVAC control system with cost target optimization
US10323878B1 (en) 2018-05-30 2019-06-18 Lineage Logistics, LLC Thermal control system
US10870333B2 (en) * 2018-10-31 2020-12-22 Thermo King Corporation Reconfigurable utility power input with passive voltage booster
US10558937B1 (en) 2019-04-22 2020-02-11 Lineage Logistics Llc Scheduled thermal control system

Also Published As

Publication number Publication date
US11841178B1 (en) 2023-12-12

Similar Documents

Publication Publication Date Title
US20220003475A1 (en) Refrigeration System with Condenser Temperature Differential Setpoint Control
JP5979546B2 (en) Energy management device, management device, program
JP6745872B2 (en) Refrigerator and network system including the same
JP5967541B2 (en) Energy management device, management device, remote management device, energy management method, program
WO2014057613A1 (en) Energy management device
US11790292B2 (en) Scheduled thermal control system
EP3598044B1 (en) Method for generating schedule information on basis of operation information, and server for implementing same
US20180180340A1 (en) Dynamic power sensing system
TW202045870A (en) Store air-conditioning system
US20200217534A1 (en) Digital smart real showcase control system, method, and program
Glavan et al. Cost optimisation of supermarket refrigeration system with hybrid model
US20240060695A1 (en) Systems and methods to manage power consumption of a building and storage by controlling a refrigeration system within the building
US20190086145A1 (en) Freezer with remote management
CN109668375A (en) Control method, device and the refrigeration equipment of refrigeration equipment
US9170628B2 (en) Energy-savings control system for showcases, refrigerators and freezers
JP2023089435A (en) Information processing device, program, abnormality detection method, abnormality detection system, and cooling storage shed
CN104969137B (en) Control system for refrigerated equipment and apparatus with energy saving features
US20230418276A1 (en) Dynamic Real Time Average Monthly Energy Management System
JP2014082810A (en) Energy management apparatus, management unit and remote management device
JP4073390B2 (en) Operating state management device
Vinther et al. Control strategies and challenges for utilizing supermarket refrigeration systems in a smart energy context
WO2014057614A1 (en) Energy management device, management device, remote management device
CN116745788A (en) Food material storage device, demand linked inventory replenishment service providing system, and demand linked inventory replenishment service providing program
Scott The Impact of Control Technology on the Demand Response Potential of California Industrial
US20170030625A1 (en) Systems and methods of icemaker control

Legal Events

Date Code Title Description
STPP Information on status: patent application and granting procedure in general

Free format text: DOCKETED NEW CASE - READY FOR EXAMINATION

AS Assignment

Owner name: AXIOM CLOUD INC., CALIFORNIA

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:SARALKAR, NIKHIL;DIAMOND, ANTHONY;ROBBINS, AMRIT;SIGNING DATES FROM 20210630 TO 20210713;REEL/FRAME:065763/0061