US20170297153A1 - Method for decreasing the number of assembly workstations - Google Patents

Method for decreasing the number of assembly workstations Download PDF

Info

Publication number
US20170297153A1
US20170297153A1 US15/641,241 US201715641241A US2017297153A1 US 20170297153 A1 US20170297153 A1 US 20170297153A1 US 201715641241 A US201715641241 A US 201715641241A US 2017297153 A1 US2017297153 A1 US 2017297153A1
Authority
US
United States
Prior art keywords
product
workstation
power source
power
workstations
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US15/641,241
Inventor
Maciej SKRZYPCZAK
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anadex Data Communication LLC
Original Assignee
Advanced Digital Broadcast SA
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Advanced Digital Broadcast SA filed Critical Advanced Digital Broadcast SA
Priority to US15/641,241 priority Critical patent/US20170297153A1/en
Publication of US20170297153A1 publication Critical patent/US20170297153A1/en
Assigned to ANADEX DATA COMMUNICATION LLC reassignment ANADEX DATA COMMUNICATION LLC ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: EQUITABLE IP HOLDINGS, LLC
Assigned to EQUITABLE IP HOLDINGS LLC reassignment EQUITABLE IP HOLDINGS LLC ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: ADVANCED DIGITAL BROADCAST S.A.
Abandoned legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P21/00Machines for assembling a multiplicity of different parts to compose units, with or without preceding or subsequent working of such parts, e.g. with programme control
    • B23P21/004Machines for assembling a multiplicity of different parts to compose units, with or without preceding or subsequent working of such parts, e.g. with programme control the units passing two or more work-stations whilst being composed
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM]
    • G05B19/41805Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM] characterised by assembly
    • HELECTRICITY
    • H05ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
    • H05KPRINTED CIRCUITS; CASINGS OR CONSTRUCTIONAL DETAILS OF ELECTRIC APPARATUS; MANUFACTURE OF ASSEMBLAGES OF ELECTRICAL COMPONENTS
    • H05K13/00Apparatus or processes specially adapted for manufacturing or adjusting assemblages of electric components
    • H05K13/0061Tools for holding the circuit boards during processing; handling transport of printed circuit boards
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • Y02P90/04
    • Y02P90/28
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y10TECHNICAL SUBJECTS COVERED BY FORMER USPC
    • Y10TTECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
    • Y10T29/00Metal working
    • Y10T29/49Method of mechanical manufacture
    • Y10T29/49002Electrical device making
    • Y10T29/49117Conductor or circuit manufacturing
    • Y10T29/49124On flat or curved insulated base, e.g., printed circuit, etc.
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y10TECHNICAL SUBJECTS COVERED BY FORMER USPC
    • Y10TTECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
    • Y10T29/00Metal working
    • Y10T29/53Means to assemble or disassemble
    • Y10T29/5313Means to assemble electrical device
    • Y10T29/53187Multiple station assembly apparatus

Definitions

  • the present invention relates to assembly line system, method and apparatus for decreasing the number of assembly workstations.
  • the device undergoes a series of tests and software downloads to a fresh Flash memory.
  • PCB printed Circuit Board
  • test stages are dedicated to functional verification and quality check of the assembled product.
  • the first test stage is executed in a specific test area, and upon completion of this stage, a device is moved to a next tests area (for example, in another room).
  • the PCBA PCB-Assembly
  • the product undergoes several to many power off to power on cycles in order to change products location between workstations and for the new software to take control over the device and store required/unique data related for example to a conditional access system.
  • the production/assembly line is organized in such that assembled devices being ready for software download are handled in parallel on more than one test bench (a workstation), meaning more than one operator is doing similar task in parallel.
  • the object of the present invention is a method for decreasing the number of assembly workstations, the method comprising the steps of providing a first workstation at a first location, supplied with power from a first power source; providing a product to the first workstation and supplying the product with power from the first power source; providing a second workstation at a second location, supplied with power from a second power source; transporting a product from the first workstation to the second workstation including disconnecting the first power source from the product in order to transport the product; connecting the product to the second power supply at the second workstation; the method further comprising the steps of: prior to supplying the product with power from the first power source placing the product in a device capable of supplying the product with power from a battery; disconnecting the first power source from the device; supplying the product from the battery, so that the product remains supplied with power between the disconnecting the first power source and connecting the product to the second power source.
  • the method further includes a step of rebooting the product before the transporting step.
  • the step of rebooting is executed such that the product reaches the second workstation with the booting stage complete.
  • the method further comprises a step of charging an internal battery while the device is connected to the first power source or the second power source.
  • Another object of the present invention is a device for decreasing the number of assembly workstations, the device comprising: a battery pack; a frame, for carrying a product; a connection configured to supply power from the battery pack to the product; a reboot switch configured to initiate reboot process of the product placed in the device.
  • the device further comprising a charger configured to charge the battery pack while the device is connected to the first power source or the second power source.
  • the frame is adjustable in order to hold products of different dimensions.
  • the product is devoid of an internal power source.
  • FIG. 1 presents a schematic diagram of an assembly line comprising two distinct workstations
  • FIG. 2A presents a first view of a device according to the present invention
  • FIG. 2B presents a second view of a device according to the present invention.
  • FIG. 3 shows a method for decreasing the number of assembly workstations using the device of FIG. 2 .
  • the booting time is increasing due to growing complexity of software with many levels and stages, from booter through loader, CA verifier, Linux OS or Android and middleware (like MHP (Multimedia Home Platform) or JVM (Java Virtual Machine)) and user GUI application itself as the final stage.
  • the booting time may be reduced by means of software optimization. However, since not all software is under manufacturer's control it is rarely possible.
  • FIG. 1 presents a schematic diagram of an assembly line comprising two distinct workstations.
  • a first workstation 101 is connected to a power source at a first location 102 and carries a product 105 .
  • the second workstation is connected to a power source at a second location 104 .
  • the product 105 When the product 105 is assembled on the first workstation, it may be supplied with power from the power source at a first location 102 and when the product 106 is assembled on the second workstation 103 , it may be supplied with power from the power source at a second location 104 .
  • the product 105 does not by design comprise (or in other words is devoid of) an internal power source (for example a battery) i.e. the product 105 is a television set, a set top box, a digital video recorder, a gaming console or similar.
  • an internal power source for example a battery
  • a drawback of this solution is that the product 105 must be switched off before being transferred from the first workstation to the second workstation. Then the product 106 is again powered on and a technician must wait until boot process of the product is complete before further tasks, specific to the given workstation, may be carried out.
  • FIG. 2A presents a first view (perspective view) of a device 200 according to the present invention.
  • the device is a powered holder comprising a battery pack integrated with electronic circuit 205 , a dedicated, preferably adjustable frame 203 , which carries the PCBA 201 or a product in final chassis (not shown), an appropriate DC jack 206 , which fits a DC socket of the product 105 being assembled (a connection for supplying power from the battery pack 205 to the product 105 ), and optionally an AC or DC socket 204 to power and charge the holder on test bench or when not used (in other words the device 200 includes a charger for charging the battery pack 205 ).
  • the frame may be adjustable in order to fit in, different products having different physical dimensions. Making the frame adjustable will be within routine tasks of a skilled person.
  • the holder has preferably adjustable clamps 202 for holding the product under processing, replaceable with adjustable clamps for final chassis holding.
  • the holder may comprise a boot switch, connected with the product 105 , configured to initiate reboot process of the product 105 .
  • the device 200 may comprise an external port, connected to the device 200 , for connecting an external memory to which the assembled device may write logs obtained during its testing on the assembly line.
  • FIG. 2B presents a second view (top view) of a device 200 according to the present invention.
  • FIG. 3 shows a method for decreasing the number of assembly workstations using the device of FIG. 2A and FIG. 2B .
  • the new process is designed to avoid assembly line bottleneck caused by long reboot times of complex software. Since most of the time is wasted on device booting on the operator workstation (sometimes referred to as a test bench), instead of reducing the booting time, the new process is based on reducing the time of the device stays on a conveyor belt while not booted.
  • the device after software download stage is put into a holder, which keeps the device running in order to reduce the number of booting operations from one stage to another.
  • the device may remain in the holder for the complete software download and testing period, which is organized on different physical workstations.
  • the first case occurs when the product 105 is not powered on at the first workstation 101 and must be powered on at the second workstation 103 .
  • the product 105 may be put in the holder of FIG. 2 and powered on sufficiently ahead, in order to arrive, at the second workstation 103 , fully operational, thereby reducing assembly time.
  • the second case is when the product 105 is powered on at the first workstation 101 and must be powered on at the second workstation 103 .
  • the product 105 may remain powered on due to use of the holder in order to arrive at the second workstation 103 fully operational without the need for booting, thereby reducing assembly time.
  • the process starts at step 301 where there is executed an action of receiving a product on a first workstation 101 connectable to a first power source 102 at a first location.
  • the product 105 , 201 is placed 302 in the holder of FIG. 2 and at step 303 the holder and the device are supplied with power from the first power source 102 , which at such an arrangement may charge the battery of the holder. From this moment on i.e. step 302 , a disconnection from the first power source 102 will not result in power off for the product 105 , 201 as it will be supplied with power from the batten 205 .
  • step 304 it is verified whether a boot will be necessary before arriving at the second workstation 103 .
  • step 304 In case reboot is not necessary, at step 304 , Next, at step 305 , there is executed an action of disconnecting the holder of FIG. 2 from external power source 102 and subsequently, at step 306 , the holder, with the product 105 , is moved to the second workstation 103 while being constantly supplied with power from the internal battery before it may be supplied with power from the second power source 104 of the second workstation 103 .
  • booting time is preferably determined 307 or read from parameters memory (the determining step may be optional and some arbitrary time may be set). In real life cases the booting time will be determined for the first time by some calculation of measurement and then determined by reading a stored reference value.
  • step 308 there is executed an action of initiating rebooting of the product.
  • the rebooting is preferably made sufficiently ahead of the product reaching the second workstation 103 so that the product may be fully operational when arriving at the second workstation 103 .
  • step 309 the process returns to step 305 or alternatively directly to 306 as the reboot may be executed during transportation of the product from the first workstation 101 to the second workstation 103 .
  • step 303 may be omitted, for example in case when power supply is not required for the product 105 , 201 at the first workstation 101 . Consequently step 305 may also be skipped in this particular embodiment.
  • the key aspect is that the product 105 , 201 will arrive at the second workstation 103 with the booting operations complete i.e. the booting will happen at the first workstation 101 and/or during moving of the product 105 , 201 to the second workstation 103 .
  • the apparatus and method presented herein allow for decreasing the number of workstations on an assembly line, since the complete time to test a device is significantly decreased (due to reduced count of boot sequences) and the same number of products will be tested on fewer workstations.

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • General Engineering & Computer Science (AREA)
  • Quality & Reliability (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Automation & Control Theory (AREA)
  • Microelectronics & Electronic Packaging (AREA)
  • Mechanical Engineering (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)
  • Automatic Assembly (AREA)

Abstract

A method for decreasing the number of assembly workstations, the method comprising the steps of providing a first workstation at a first location, supplied with power from a first power source; providing a product to the first workstation and supplying the product with power from the first power source; providing a second workstation at a second location, supplied with power from a second power source; transporting a product from the first workstation to the second workstation including disconnecting the first power source from the product in order to transport the product; connecting the product to the second power supply at the second workstation; the method further comprising the steps of: prior to supplying the product with power from the first power source placing the product in a device capable of supplying the product with power from a battery; disconnecting the first power source from the device; supplying the product from the battery, so that the product remains supplied with power between the disconnecting the first power source and connecting the product to the second power source.

Description

  • The present invention relates to assembly line system, method and apparatus for decreasing the number of assembly workstations.
  • Manufacturing of electronic devices having embedded, complex, multilayer software, requires more time than with respect to similar devices in the past when software was simpler.
  • Typically, after the last stage of the PCB (Printed Circuit Board) assembly (being an SMD (surface-mount device) oven or hand insertion soldering) the device undergoes a series of tests and software downloads to a fresh Flash memory.
  • Subsequently, various test stages are dedicated to functional verification and quality check of the assembled product. For example, the first test stage is executed in a specific test area, and upon completion of this stage, a device is moved to a next tests area (for example, in another room).
  • During some of these stages, the PCBA (PCB-Assembly) is inserted into a final chassis and tested during the further stages. During these tests, the product undergoes several to many power off to power on cycles in order to change products location between workstations and for the new software to take control over the device and store required/unique data related for example to a conditional access system.
  • In order to optimize the production time and effort, the production/assembly line is organized in such that assembled devices being ready for software download are handled in parallel on more than one test bench (a workstation), meaning more than one operator is doing similar task in parallel.
  • Splitting the production and test into more than one line is the solution for reducing the production bottleneck, however increases the overall production cost, which is a problem. Typically however, there are different test stages utilizing a plurality of workstations operating in parallel.
  • It would be thus desirable to provide method and apparatus for decreasing the number of assembly workstations that increases production costs.
  • The object of the present invention is a method for decreasing the number of assembly workstations, the method comprising the steps of providing a first workstation at a first location, supplied with power from a first power source; providing a product to the first workstation and supplying the product with power from the first power source; providing a second workstation at a second location, supplied with power from a second power source; transporting a product from the first workstation to the second workstation including disconnecting the first power source from the product in order to transport the product; connecting the product to the second power supply at the second workstation; the method further comprising the steps of: prior to supplying the product with power from the first power source placing the product in a device capable of supplying the product with power from a battery; disconnecting the first power source from the device; supplying the product from the battery, so that the product remains supplied with power between the disconnecting the first power source and connecting the product to the second power source.
  • Preferably there is a plurality of second workstations at the second location.
  • Favorably, the method further includes a step of rebooting the product before the transporting step.
  • Preferably, the step of rebooting is executed such that the product reaches the second workstation with the booting stage complete.
  • Preferably, the method further comprises a step of charging an internal battery while the device is connected to the first power source or the second power source.
  • Another object of the present invention is a device for decreasing the number of assembly workstations, the device comprising: a battery pack; a frame, for carrying a product; a connection configured to supply power from the battery pack to the product; a reboot switch configured to initiate reboot process of the product placed in the device.
  • Preferably, the device further comprising a charger configured to charge the battery pack while the device is connected to the first power source or the second power source.
  • Preferably, the frame is adjustable in order to hold products of different dimensions.
  • Preferably, the product is devoid of an internal power source.
  • The present invention is shown by means of exemplary embodiments on a drawing, in which:
  • FIG. 1 presents a schematic diagram of an assembly line comprising two distinct workstations;
  • FIG. 2A presents a first view of a device according to the present invention;
  • FIG. 2B presents a second view of a device according to the present invention; and
  • FIG. 3 shows a method for decreasing the number of assembly workstations using the device of FIG. 2.
  • The origin of the problem with increasing number of workstations on a production line is caused by long booting time of the powered device on test benches. Frequently the test itself is much shorter that the booting time of the device being manufactured.
  • The booting time is increasing due to growing complexity of software with many levels and stages, from booter through loader, CA verifier, Linux OS or Android and middleware (like MHP (Multimedia Home Platform) or JVM (Java Virtual Machine)) and user GUI application itself as the final stage. The booting time may be reduced by means of software optimization. However, since not all software is under manufacturer's control it is rarely possible.
  • FIG. 1 presents a schematic diagram of an assembly line comprising two distinct workstations. A first workstation 101 is connected to a power source at a first location 102 and carries a product 105. At a given time during assembly there is a need to transfer the product 105 to a different, second workstation 103, wherein the second workstation is connected to a power source at a second location 104. When the product 105 is assembled on the first workstation, it may be supplied with power from the power source at a first location 102 and when the product 106 is assembled on the second workstation 103, it may be supplied with power from the power source at a second location 104.
  • The product 105 does not by design comprise (or in other words is devoid of) an internal power source (for example a battery) i.e. the product 105 is a television set, a set top box, a digital video recorder, a gaming console or similar.
  • A drawback of this solution is that the product 105 must be switched off before being transferred from the first workstation to the second workstation. Then the product 106 is again powered on and a technician must wait until boot process of the product is complete before further tasks, specific to the given workstation, may be carried out.
  • FIG. 2A presents a first view (perspective view) of a device 200 according to the present invention. The device is a powered holder comprising a battery pack integrated with electronic circuit 205, a dedicated, preferably adjustable frame 203, which carries the PCBA 201 or a product in final chassis (not shown), an appropriate DC jack 206, which fits a DC socket of the product 105 being assembled (a connection for supplying power from the battery pack 205 to the product 105), and optionally an AC or DC socket 204 to power and charge the holder on test bench or when not used (in other words the device 200 includes a charger for charging the battery pack 205).
  • The frame may be adjustable in order to fit in, different products having different physical dimensions. Making the frame adjustable will be within routine tasks of a skilled person.
  • The holder has preferably adjustable clamps 202 for holding the product under processing, replaceable with adjustable clamps for final chassis holding.
  • Optionally the holder may comprise a boot switch, connected with the product 105, configured to initiate reboot process of the product 105.
  • Further, as an option, the device 200 may comprise an external port, connected to the device 200, for connecting an external memory to which the assembled device may write logs obtained during its testing on the assembly line.
  • FIG. 2B presents a second view (top view) of a device 200 according to the present invention.
  • FIG. 3 shows a method for decreasing the number of assembly workstations using the device of FIG. 2A and FIG. 2B.
  • The new process is designed to avoid assembly line bottleneck caused by long reboot times of complex software. Since most of the time is wasted on device booting on the operator workstation (sometimes referred to as a test bench), instead of reducing the booting time, the new process is based on reducing the time of the device stays on a conveyor belt while not booted.
  • That means, the device after software download stage is put into a holder, which keeps the device running in order to reduce the number of booting operations from one stage to another. The device may remain in the holder for the complete software download and testing period, which is organized on different physical workstations.
  • This process reduces the number of parallel test stands, since there is no more waiting for software to boot on the desk as it comes already booted and running ready for testing. Different holder variants are used for PCBA and for final enclosure holding.
  • There may be two use cases identified. The first case occurs when the product 105 is not powered on at the first workstation 101 and must be powered on at the second workstation 103. In such case the product 105 may be put in the holder of FIG. 2 and powered on sufficiently ahead, in order to arrive, at the second workstation 103, fully operational, thereby reducing assembly time.
  • The second case is when the product 105 is powered on at the first workstation 101 and must be powered on at the second workstation 103. In such case the product 105 may remain powered on due to use of the holder in order to arrive at the second workstation 103 fully operational without the need for booting, thereby reducing assembly time.
  • Referring to FIG. 3, the process starts at step 301 where there is executed an action of receiving a product on a first workstation 101 connectable to a first power source 102 at a first location. The product 105, 201 is placed 302 in the holder of FIG. 2 and at step 303 the holder and the device are supplied with power from the first power source 102, which at such an arrangement may charge the battery of the holder. From this moment on i.e. step 302, a disconnection from the first power source 102 will not result in power off for the product 105, 201 as it will be supplied with power from the batten 205.
  • Subsequently, at step 304, it is verified whether a boot will be necessary before arriving at the second workstation 103.
  • In case reboot is not necessary, at step 304, Next, at step 305, there is executed an action of disconnecting the holder of FIG. 2 from external power source 102 and subsequently, at step 306, the holder, with the product 105, is moved to the second workstation 103 while being constantly supplied with power from the internal battery before it may be supplied with power from the second power source 104 of the second workstation 103.
  • In case reboot is necessary, at step 304, booting time is preferably determined 307 or read from parameters memory (the determining step may be optional and some arbitrary time may be set). In real life cases the booting time will be determined for the first time by some calculation of measurement and then determined by reading a stored reference value.
  • Next, at step 308, there is executed an action of initiating rebooting of the product. The rebooting is preferably made sufficiently ahead of the product reaching the second workstation 103 so that the product may be fully operational when arriving at the second workstation 103. After step 309 the process returns to step 305 or alternatively directly to 306 as the reboot may be executed during transportation of the product from the first workstation 101 to the second workstation 103.
  • In another embodiment step 303 may be omitted, for example in case when power supply is not required for the product 105, 201 at the first workstation 101. Consequently step 305 may also be skipped in this particular embodiment. The key aspect is that the product 105, 201 will arrive at the second workstation 103 with the booting operations complete i.e. the booting will happen at the first workstation 101 and/or during moving of the product 105, 201 to the second workstation 103.
  • The apparatus and method presented herein allow for decreasing the number of workstations on an assembly line, since the complete time to test a device is significantly decreased (due to reduced count of boot sequences) and the same number of products will be tested on fewer workstations.
  • While the invention presented herein has been depicted, described, and has been defined with reference to particular preferred embodiments, such references and examples of implementation in the foregoing specification do not imply any limitation on the invention. It will, however, be evident that various modifications and changes may be made thereto without departing from the broader scope of the technical concept. The presented preferred embodiments are exemplary only, and are not exhaustive of the scope of the technical concept presented herein.
  • Accordingly, the scope of protection is not limited to the preferred embodiments described in the specification, but is only limited by the claims that follow.

Claims (4)

1. A device for decreasing a number of assembly workstations, the device comprising:
a battery pack;
a frame for carrying a product;
a connection configured to supply electrical power from said battery pack to said product; and
a reboot switch configured to initiate a reboot process of said product placed in said device.
2. A device according to claim 1 further comprising a charger configured to charge said battery pack while said device is connected to a first power source or a second power source.
3. A device according to claim 1 wherein said frame is adjustable in order to hold products of different dimensions.
4. A device according to claim 1 wherein said product is devoid of an internal power source.
US15/641,241 2013-08-26 2017-07-04 Method for decreasing the number of assembly workstations Abandoned US20170297153A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US15/641,241 US20170297153A1 (en) 2013-08-26 2017-07-04 Method for decreasing the number of assembly workstations

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
EP13181643.1A EP2793092B1 (en) 2013-08-26 2013-08-26 Assembly line system, method and apparatus for decreasing the number of assembly workstations
EP13181643 2013-08-26
US14/462,593 US9751169B2 (en) 2013-08-26 2014-08-19 Method for decreasing the number of assembly workstations
US15/641,241 US20170297153A1 (en) 2013-08-26 2017-07-04 Method for decreasing the number of assembly workstations

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
US14/462,593 Continuation US9751169B2 (en) 2013-08-26 2014-08-19 Method for decreasing the number of assembly workstations

Publications (1)

Publication Number Publication Date
US20170297153A1 true US20170297153A1 (en) 2017-10-19

Family

ID=49123639

Family Applications (2)

Application Number Title Priority Date Filing Date
US14/462,593 Expired - Fee Related US9751169B2 (en) 2013-08-26 2014-08-19 Method for decreasing the number of assembly workstations
US15/641,241 Abandoned US20170297153A1 (en) 2013-08-26 2017-07-04 Method for decreasing the number of assembly workstations

Family Applications Before (1)

Application Number Title Priority Date Filing Date
US14/462,593 Expired - Fee Related US9751169B2 (en) 2013-08-26 2014-08-19 Method for decreasing the number of assembly workstations

Country Status (3)

Country Link
US (2) US9751169B2 (en)
EP (1) EP2793092B1 (en)
CN (1) CN104422877B (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6078503A (en) * 1997-06-30 2000-06-20 Emc Corporation Partitionable cabinet

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4845843A (en) * 1985-10-28 1989-07-11 Cimm, Inc. System for configuring, automating and controlling the test and repair of printed circuit boards
JPH11298137A (en) * 1998-04-13 1999-10-29 Fuji Photo Film Co Ltd Part replacing device for circuit board
JP2000047728A (en) * 1998-07-28 2000-02-18 Denso Corp Electric charging controller in moving robot system
JP2000155158A (en) * 1998-11-24 2000-06-06 Toshiba Fa Syst Eng Corp Printed board testing device
US6449523B1 (en) * 1999-10-15 2002-09-10 Data I/O Corporation Feeder/programming/buffer operating system
IES20000322A2 (en) * 2000-04-28 2001-11-14 Viveen Ltd Apparatus for testing a light source
US7220222B2 (en) * 2005-01-19 2007-05-22 Multi-Shifter Inc. Cart for die transportation
JP2007121163A (en) * 2005-10-28 2007-05-17 Advantest Corp Testing system, program, and recording medium
US7906935B2 (en) * 2007-06-06 2011-03-15 Kissel Jr Waldemar F Method and apparatus for charging electric devices
KR20120041369A (en) * 2010-10-21 2012-05-02 삼성전기주식회사 System and method for management of transportations

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6078503A (en) * 1997-06-30 2000-06-20 Emc Corporation Partitionable cabinet

Also Published As

Publication number Publication date
CN104422877A (en) 2015-03-18
US9751169B2 (en) 2017-09-05
CN104422877B (en) 2017-06-27
EP2793092A1 (en) 2014-10-22
US20150052744A1 (en) 2015-02-26
EP2793092B1 (en) 2015-07-08

Similar Documents

Publication Publication Date Title
US8924769B2 (en) Software burning system and burning control method
US8090569B2 (en) Apparatus and method for testing electronic apparatuses
US20090313512A1 (en) Apparatus and method for memory card testing
CN105988843A (en) Firmware upgrade method and firmware upgrade device for mobile terminal
WO2009148942A3 (en) Processing storage devices
WO2017193882A1 (en) Method and device for upgrading embedded memory and related terminal
TW201341811A (en) Adapter module and motherboard testing device using the same
EP0646801A1 (en) Testing apparatus for testing and handling a multiplicity of devices
CN108271150B (en) Method and system for supporting simultaneous flashing or data clearing of multiple mobile phones
CN104317612B (en) The method of Loongson processor Memory Controller Hub parameter interactive mode debugging
CN1996262A (en) Mainboard testing program processing system and method therefor
EP2133771A3 (en) Electronic device, power-on method for an electronic device, and program
WO2019041662A1 (en) Dram test device and method
CN106201636A (en) A kind of DSP off-chip code dynamic loading method and device
TWI591479B (en) Apparatus and method for initializing port of electronic device
CN101145121B (en) Computer test method
CN104375866A (en) Single board driving updating method and device
US9751169B2 (en) Method for decreasing the number of assembly workstations
CN103916498B (en) Serial port camera and parallel port camera compatible method
US9619355B2 (en) Booting verification method of computer and electronic device
WO2008142752A1 (en) Tray storage device and electronic part test apparatus
CN102736976B (en) Debugging system and debugging method thereof
WO2019080003A1 (en) Method for testing a chip, test platform, and test system
TWI573080B (en) Mobile phone packaging automation manufacturing line and automation method for forming mobile phone
CN111417114B (en) Automatic upgrading method based on network port under U-boot

Legal Events

Date Code Title Description
STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION

AS Assignment

Owner name: EQUITABLE IP HOLDINGS LLC, NEVADA

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:ADVANCED DIGITAL BROADCAST S.A.;REEL/FRAME:052191/0802

Effective date: 20190308

Owner name: ANADEX DATA COMMUNICATION LLC, NEW JERSEY

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:EQUITABLE IP HOLDINGS, LLC;REEL/FRAME:052192/0046

Effective date: 20191001