US20150089898A1 - Method for erecting a tower - Google Patents

Method for erecting a tower Download PDF

Info

Publication number
US20150089898A1
US20150089898A1 US14/566,433 US201414566433A US2015089898A1 US 20150089898 A1 US20150089898 A1 US 20150089898A1 US 201414566433 A US201414566433 A US 201414566433A US 2015089898 A1 US2015089898 A1 US 2015089898A1
Authority
US
United States
Prior art keywords
foundation
ring
pylon
pairs
segment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US14/566,433
Inventor
Aloys Wobben
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=34962709&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=US20150089898(A1) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by Individual filed Critical Individual
Priority to US14/566,433 priority Critical patent/US20150089898A1/en
Publication of US20150089898A1 publication Critical patent/US20150089898A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/22Sockets or holders for poles or posts
    • E04H12/2253Mounting poles or posts to the holder
    • E04H12/2269Mounting poles or posts to the holder in a socket
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/388Separate connecting elements
    • E04B1/40
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/02Structures made of specified materials
    • E04H12/08Structures made of specified materials of metal
    • E04H12/085Details of flanges for tubular masts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/22Sockets or holders for poles or posts
    • E04H12/2284Means for adjusting the orientation of the post or pole
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/20Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
    • F03D13/22Foundations specially adapted for wind motors
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05BINDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
    • F05B2240/00Components
    • F05B2240/90Mounting on supporting structures or systems
    • F05B2240/91Mounting on supporting structures or systems on a stationary structure
    • F05B2240/912Mounting on supporting structures or systems on a stationary structure on a tower
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/728Onshore wind turbines

Definitions

  • the present invention concerns a method of erecting a tower or pylon and a wind power installation with such a pylon.
  • U.S. Pat. No. 5,826,387 discloses a foundation and a method of producing a foundation which can be used for example for wind power installations.
  • U.S. Pat. No. 6,050,038 discloses a foundation system.
  • DE 100 45 735 A1 discloses a means of fixing a column on a concrete foundation.
  • DE 102 26 996 A1 discloses a method of producing a foundation, in particular for a pylon of a wind power installation.
  • a large crane is required for handling the lower pylon segment. That crane however is only further used for constructing the pylon after the grouting material has set. Shifting the crane for the period during which the gap grouting is setting is however too complicated and expensive and therefore does not happen. Accordingly the costly crane is stopped and inactive for 24 hours.
  • the object of the invention is to efficiently carry out the structure of a pylon, in particular a pylon of a wind power installation.
  • That object is attained by a method of erecting a pylon as set forth in claim 1 , a wind power installation with a pylon as set forth in claim 3 , and a method of using a leveling ring for erecting a pylon as set forth in claim 4 .
  • a method of erecting a pylon, in particular a pylon of a wind power installation which has a foundation with segment anchors, wherein the connecting elements project beyond the top side of the foundation by a predetermined amount.
  • a ring is leveled, aligned and fixed at the top side of the foundation.
  • a gap which has been formed by leveling, aligning and fixing of the ring is underlaid with a grouting material. After the grouting material has set a lower pylon segment is placed on the leveled, aligned and fixed ring and connected thereto.
  • the ring may also be formed from a plurality of segments.
  • the invention is based on the realization that it is not leveling of the lower pylon section that is important, but the fact that it is exactly aligned in situ. That however can also be achieved using a leveling ring.
  • a leveling ring is comparable to a flange ring which can be handled with a markedly lower level of effort and expenditure than the lower pylon section, for example with a vehicle-mounted crane.
  • precise alignment (leveling) of the leveling ring is simpler than the corresponding procedure in relation to a pylon section.
  • the leveling ring when of greater width and/or thickness, can be made from a less high-grade material than the pylon flange.
  • the pylon flange can also be reduced in its width. In that way it is possible to make better use of the transport width.
  • the leveling ring After alignment and fixing the leveling ring can be underlaid with grouting material in known manner and the material can set. During that time however the (vehicle-mounted) crane can already be used for other tasks while the crane required for handling the pylon sections is not yet needed.
  • a particularly rational structure for the pylon can be implemented if prefabricated finished parts, in particular concrete finished parts, are used for the foundation. They are delivered ready for installation on the building site and connected to produce a foundation which can then be further used immediately and thus in such a way as to save time.
  • FIG. 1 is a diagrammatic view in section of a portion of a pylon base
  • FIG. 2A shows a plan view of a pylon base
  • FIG. 2B shows a view in section taken along line A-A of the pylon base of FIG. 2A ,
  • FIG. 2C shows a view on an enlarged scale of the portion X in FIG. 2B .
  • FIG. 3 shows a perspective view of a pylon base.
  • a foundation 10 can be in the form of a prefabricated finished part foundation but also in the form of an on-site mixed concrete foundation or a foundation made from supplied ready-mix concrete.
  • One or more segment anchors 12 are provided in the foundation 10 .
  • Those segment anchors 12 can be adapted in shape and number to the particular demands of the foundation.
  • a segment anchor which for example is in one piece in relation to on-site mixed concrete foundations or foundations produced from ready-mix concrete, that segment anchor being woven into the reinforcement.
  • prefabricated finished part foundations in contrast a plurality of segment anchors are used, which are adapted in respect of their shape to the finished part. It will be appreciated that a plurality of segment anchors can also be used in relation to an on-site mixed concrete structure or a structure produced from supplied ready-mix concrete.
  • Connecting elements 14 are connected to the segment anchor 12 .
  • the connecting elements 14 can be in the form of screwthreaded rods which are fixed with nuts 15 in a predetermined position to the segment anchor 12 .
  • the fixing elements 14 extend a predetermined distance outside the foundation 10 above the top side 11 of the foundation. Instead of a screw connection it is also possible to use a welded connection.
  • a leveling ring 18 which is formed in one piece or a plurality of pieces is then arranged on the top side 11 of the foundation.
  • the leveling ring 18 is exactly leveled so that it forms a perfectly aligned base for the pylon.
  • a gap 16 inevitably occurs between the top side 11 of the foundation and the leveling ring 18 .
  • the leveling ring 18 is fixed in its predetermined position the gap 16 is filled with a grouting material 17 .
  • the leveling ring 18 can be loaded in its desired position and a lower pylon segment with a lower flange ring 20 and an illustrated pylon wall plate 22 can be placed on the leveling ring 18 .
  • the screwthreaded rods 14 engage through suitably positioned holes in the leveling ring 18 and in the lower flange ring 20 of the lower pylon section and nuts 15 are fitted thereon in order to connect the lower pylon section fixedly to the foundation 10 by way of the leveling ring 18 .
  • FIG. 2A shows a plan view of a pylon base.
  • FIG. 2B shows a cross-section taken along line A-A in FIG. 2A .
  • a foundation 10 with a foundation surface 11 .
  • two segment anchors 12 and four screwthreaded rods 14 are shown.
  • the portion X is shown on an enlarged scale in FIG. 2C . That view substantially corresponds to the view in FIG. 1 .
  • FIG. 3 shows a perspective view of the pylon base with a portion thereof cut open. Leveling of the pylon base is effected as described with reference to FIG. 1 .
  • the method according to the invention means that the pylon segments can be delivered in a transport process to the erection point just in time. That also eliminates additional transloading procedures, more specifically firstly from the transport vehicle to intermediate storage on the ground and then later from there to the location of installation. Rather pylon segments which are delivered just in time can be unloaded from the transport vehicle and fitted in place immediately.
  • the above-described solution has been found to be advantageous in terms of efficiently carrying out rationalizing the erection of a pylon, in particular a pylon of a wind power installation.
  • the costs and material properties also play a not insignificant part.
  • the lowermost flange of a pylon segment must be made from a very high-grade material in order to be able to carry the loads originating from the pylon. If a pylon of that kind is set up on a concrete foundation then the concrete is the weaker one of the two aspects of the connection. Accordingly the pylon flange must be broader in width so that the concrete of the foundation is not overloaded. Consequently the flange in the lower pylon segment must be of a width which is oversized in relation to the steel which is used in that respect. That is to be considered as a disadvantage in particular in terms of the costs of the steel used in that respect.
  • the leveling ring can be of a sufficient width to transmit the loads of the wind power installation to the foundation without risk.
  • the flange on the lower pylon segment can be made correspondingly narrower and thus less expensively in terms of material and cost.
  • a further advantage is enjoyed when the leveling ring is made in the form of segments and can thus be stacked and transported in segment-wise manner.
  • the leveling ring is of a large diameter, that is not a problem in accordance with the invention from the point of view of transportation because it can be stacked in segment-wise manner.
  • the lower pylon segment has a narrower base flange of a smaller width as now the base flange can be material-specifically sized. The transport width can thus also be correspondingly reduced.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Chemical & Material Sciences (AREA)
  • Wood Science & Technology (AREA)
  • Materials Engineering (AREA)
  • Sustainable Energy (AREA)
  • Sustainable Development (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Wind Motors (AREA)
  • Foundations (AREA)

Abstract

A method of erecting a pylon, in particular a pylon of a wind power installation, which has a foundation with segment anchors, wherein connecting elements project beyond the top side of the foundation by a predetermined amount. A ring is leveled, aligned and fixed at the top side of the foundation. A gap produced by leveling, aligning and fixing of the ring is underlaid with a grouting material. The grouting material is set and a lower pylon segment is placed on the leveled, aligned and fixed ring and connected thereto.

Description

    BACKGROUND
  • 1. Technical Field
  • The present invention concerns a method of erecting a tower or pylon and a wind power installation with such a pylon.
  • 2. Description of the Related Art
  • U.S. Pat. No. 5,826,387 discloses a foundation and a method of producing a foundation which can be used for example for wind power installations. U.S. Pat. No. 6,050,038 discloses a foundation system. DE 100 45 735 A1 discloses a means of fixing a column on a concrete foundation. DE 102 26 996 A1 discloses a method of producing a foundation, in particular for a pylon of a wind power installation.
  • It is known in the state of the art, when erecting a pylon in particular for a wind power installation, for a lower pylon segment to be placed on the connecting elements which project out of a foundation, with a base flange. That lower pylon segment is properly aligned (leveled) and fixed in the aligned position. In that case there is a gap between the base flange of the lower pylon segment and the top side of the foundation. That gap is filled with a grouting material which then has to set before it can be loaded and the pylon further constructed thereon. Setting can certainly take up to 24 hours.
  • A large crane is required for handling the lower pylon segment. That crane however is only further used for constructing the pylon after the grouting material has set. Shifting the crane for the period during which the gap grouting is setting is however too complicated and expensive and therefore does not happen. Accordingly the costly crane is stopped and inactive for 24 hours.
  • BRIEF SUMMARY
  • Therefore the object of the invention is to efficiently carry out the structure of a pylon, in particular a pylon of a wind power installation.
  • That object is attained by a method of erecting a pylon as set forth in claim 1, a wind power installation with a pylon as set forth in claim 3, and a method of using a leveling ring for erecting a pylon as set forth in claim 4.
  • Therefore there is provided a method of erecting a pylon, in particular a pylon of a wind power installation, which has a foundation with segment anchors, wherein the connecting elements project beyond the top side of the foundation by a predetermined amount. A ring is leveled, aligned and fixed at the top side of the foundation. A gap which has been formed by leveling, aligning and fixing of the ring is underlaid with a grouting material. After the grouting material has set a lower pylon segment is placed on the leveled, aligned and fixed ring and connected thereto. In that case the ring may also be formed from a plurality of segments.
  • In that respect the invention is based on the realization that it is not leveling of the lower pylon section that is important, but the fact that it is exactly aligned in situ. That however can also be achieved using a leveling ring. Such a leveling ring is comparable to a flange ring which can be handled with a markedly lower level of effort and expenditure than the lower pylon section, for example with a vehicle-mounted crane. Also precise alignment (leveling) of the leveling ring is simpler than the corresponding procedure in relation to a pylon section. In addition the leveling ring, when of greater width and/or thickness, can be made from a less high-grade material than the pylon flange. The pylon flange can also be reduced in its width. In that way it is possible to make better use of the transport width.
  • After alignment and fixing the leveling ring can be underlaid with grouting material in known manner and the material can set. During that time however the (vehicle-mounted) crane can already be used for other tasks while the crane required for handling the pylon sections is not yet needed.
  • It is only when the material in the gap has hardened that the large crane must be ready to erect the pylon, for example of a wind power installation, and can then relatively quickly erect the pylon segment by segment.
  • A particularly rational structure for the pylon can be implemented if prefabricated finished parts, in particular concrete finished parts, are used for the foundation. They are delivered ready for installation on the building site and connected to produce a foundation which can then be further used immediately and thus in such a way as to save time.
  • BRIEF DESCRIPTION OF THE SEVERAL VIEWS OF THE DRAWING(S)
  • The invention is described hereinafter with reference to the Figures.
  • FIG. 1 is a diagrammatic view in section of a portion of a pylon base,
  • FIG. 2A shows a plan view of a pylon base,
  • FIG. 2B shows a view in section taken along line A-A of the pylon base of FIG. 2A,
  • FIG. 2C shows a view on an enlarged scale of the portion X in FIG. 2B, and
  • FIG. 3 shows a perspective view of a pylon base.
  • DETAILED DESCRIPTION
  • A foundation 10 can be in the form of a prefabricated finished part foundation but also in the form of an on-site mixed concrete foundation or a foundation made from supplied ready-mix concrete. One or more segment anchors 12 are provided in the foundation 10. Those segment anchors 12 can be adapted in shape and number to the particular demands of the foundation. Thus it is possible to use a segment anchor which for example is in one piece in relation to on-site mixed concrete foundations or foundations produced from ready-mix concrete, that segment anchor being woven into the reinforcement. In the case of prefabricated finished part foundations in contrast a plurality of segment anchors are used, which are adapted in respect of their shape to the finished part. It will be appreciated that a plurality of segment anchors can also be used in relation to an on-site mixed concrete structure or a structure produced from supplied ready-mix concrete.
  • Connecting elements 14 are connected to the segment anchor 12. The connecting elements 14 can be in the form of screwthreaded rods which are fixed with nuts 15 in a predetermined position to the segment anchor 12. The fixing elements 14 extend a predetermined distance outside the foundation 10 above the top side 11 of the foundation. Instead of a screw connection it is also possible to use a welded connection.
  • A leveling ring 18 which is formed in one piece or a plurality of pieces is then arranged on the top side 11 of the foundation. The leveling ring 18 is exactly leveled so that it forms a perfectly aligned base for the pylon. When the leveling ring 18 is aligned a gap 16 inevitably occurs between the top side 11 of the foundation and the leveling ring 18. As soon as the leveling ring 18 is fixed in its predetermined position the gap 16 is filled with a grouting material 17. After setting or hardening of that grouting material 17 the leveling ring 18 can be loaded in its desired position and a lower pylon segment with a lower flange ring 20 and an illustrated pylon wall plate 22 can be placed on the leveling ring 18. The screwthreaded rods 14 engage through suitably positioned holes in the leveling ring 18 and in the lower flange ring 20 of the lower pylon section and nuts 15 are fitted thereon in order to connect the lower pylon section fixedly to the foundation 10 by way of the leveling ring 18.
  • FIG. 2A shows a plan view of a pylon base. FIG. 2B shows a cross-section taken along line A-A in FIG. 2A. As in FIG. 1, shown here is a foundation 10 with a foundation surface 11. In particular two segment anchors 12 and four screwthreaded rods 14 are shown. The portion X is shown on an enlarged scale in FIG. 2C. That view substantially corresponds to the view in FIG. 1.
  • FIG. 3 shows a perspective view of the pylon base with a portion thereof cut open. Leveling of the pylon base is effected as described with reference to FIG. 1.
  • As the pylon for example of a wind power installation can now be constructed in one go a crane only has to be provided once for speedy pylon erection, but until then the crane can perform other tasks.
  • Logistical tasks are also simplified. Hitherto the lower pylon section had to be on site at least 24 hours before the other parts of the pylon in order to be able to satisfactorily install it. It will be appreciated that the other parts of the pylon could also be supplied at the same time. They however could not be constructed at the same time and therefore took up additional space on the building site, for the waiting time.
  • The method according to the invention means that the pylon segments can be delivered in a transport process to the erection point just in time. That also eliminates additional transloading procedures, more specifically firstly from the transport vehicle to intermediate storage on the ground and then later from there to the location of installation. Rather pylon segments which are delivered just in time can be unloaded from the transport vehicle and fitted in place immediately.
  • With the above-described solution care is to be taken to ensure that the grouting material must always be applied with at least a minimum thickness, which is dependent on the material used for the grout, because that grouting material is required to transmit the forces from the pylon to the foundation. If the grouting material is applied too thinly, that layer can fracture and give rise to considerable damage.
  • The above-described solution has been found to be advantageous in terms of efficiently carrying out rationalizing the erection of a pylon, in particular a pylon of a wind power installation. On the other hand the costs and material properties also play a not insignificant part. It should be pointed out that the lowermost flange of a pylon segment must be made from a very high-grade material in order to be able to carry the loads originating from the pylon. If a pylon of that kind is set up on a concrete foundation then the concrete is the weaker one of the two aspects of the connection. Accordingly the pylon flange must be broader in width so that the concrete of the foundation is not overloaded. Consequently the flange in the lower pylon segment must be of a width which is oversized in relation to the steel which is used in that respect. That is to be considered as a disadvantage in particular in terms of the costs of the steel used in that respect.
  • By virtue of the insertion of the leveling ring it is now possible in accordance with the invention to insert a kind of transitional step between the highly loadable but cost-intensive steel of the lower pylon segment and the lower-loadable concrete of the foundation. Thus the leveling ring can be of a sufficient width to transmit the loads of the wind power installation to the foundation without risk. On the other hand it is possible to use better or cheaper steel at that location and thus the flange on the lower pylon segment can be made correspondingly narrower and thus less expensively in terms of material and cost. A further advantage is enjoyed when the leveling ring is made in the form of segments and can thus be stacked and transported in segment-wise manner. If the leveling ring is of a large diameter, that is not a problem in accordance with the invention from the point of view of transportation because it can be stacked in segment-wise manner. The lower pylon segment has a narrower base flange of a smaller width as now the base flange can be material-specifically sized. The transport width can thus also be correspondingly reduced.
  • Erection for example of a pylon of a wind power installation on land was described in the example set forth hereinbefore. Erecting a pylon of a wind power installation off-shore, that is to say in the water or in the sea, can also be effected by means of the above-described leveling ring and a corresponding leveling procedure before a lower pylon segment is mounted in place.
  • All of the above U.S. patents, U.S. patent application publications, U.S. patent applications, foreign patents, foreign patent applications and non-patent publications referred to in this specification and/or listed in the Application Data Sheet, are incorporated herein by reference, in their entirety.
  • From the foregoing it will be appreciated that, although specific embodiments of the invention have been described herein for purposes of illustration, various modifications may be made without deviating from the spirit and scope of the invention. Accordingly, the invention is not limited except as by the appended claims.

Claims (10)

1. A method of erecting a pylon of a wind power installation, the method comprising:
forming a foundation that includes a plurality of segment anchors, the plurality of segment anchors including pairs of connecting elements having first and second ends, the first ends of the pairs of connecting elements coupled to the segment anchors, respectively, the second ends of the pairs of connecting elements extending from the foundation;
leveling, aligning, and fixing a ring structure relative to an upper surface of the foundation, wherein leveling, aligning, and fixing includes producing a gap between a surface of the ring structure and an upper surface of the foundation, the ring structure having openings, the second ends of the pairs of connecting elements extending through the openings of the ring structure;
placing a grouting material in the gap;
setting of the grouting material;
placing a lower flange ring of a pylon segment on an upper surface of the ring, the lower flange ring having openings, the second ends of the pairs of connecting elements extending through the openings of the lower flange ring; and
coupling the lower flange ring to the ring structure.
2. The method according to claim 1, wherein coupling the lower flange ring to the ring structure comprises fixing nuts to the second ends of the pairs of connecting elements above the lower flange ring of the pylon segment.
3. The method according to claim 1, wherein forming the foundation comprises using concrete finished parts for at least part of the foundation.
4. The method according to claim 1, wherein the openings of the lower flange ring are pairs of openings, the lower flange ring include a wall plate that extends between each opening in each pair of openings.
5. The method according to claim 1, wherein the pairs of segment anchors are spaced apart from each other in the foundation.
6. The method according to claim 1, wherein forming the foundation comprises placing the pairs of segment anchors radially about a central axis of the foundation.
7. A method of erecting a pylon, the method comprising:
forming a foundation that includes a plurality of segment anchors that are spaced apart from each other and radially arranged about a central axis of the foundation, wherein forming the foundation includes coupling first ends of pairs of connecting elements to the plurality of segment anchors, respectively, so that second ends of the pairs of connecting elements extend from the foundation;
leveling, aligning, and fixing a leveling ring over an upper surface of the foundation and thereby forming one or more gaps between a surface of the leveling ring and an upper surface of the foundation;
filling the one or more gaps with a grouting material;
setting the grouting material;
placing a lower pylon segment with a lower flange ring on the leveling ring; and
coupling the lower flange ring to the leveling ring.
8. The method according to claim 7, wherein coupling the lower flange ring to the leveling ring comprises placing the second ends of the pairs of the connecting elements through first openings in the leveling ring and through second openings of the lower pylon segment and securing connection devices to the second ends of the pairs of the connecting elements above the lower pylon segment.
9. The method according to claim 7, wherein the connection devices are nuts.
10. The method according to claim 7, wherein forming the foundation comprises using concrete finished parts for at least part of the foundation.
US14/566,433 2004-04-02 2014-12-10 Method for erecting a tower Abandoned US20150089898A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US14/566,433 US20150089898A1 (en) 2004-04-02 2014-12-10 Method for erecting a tower

Applications Claiming Priority (5)

Application Number Priority Date Filing Date Title
DE102004017006A DE102004017006B4 (en) 2004-04-02 2004-04-02 Method of erecting a tower
DE102004017006.1 2004-04-02
PCT/EP2005/003499 WO2005095792A1 (en) 2004-04-02 2005-04-04 Method for erecting a tower
US54738708A 2008-08-19 2008-08-19
US14/566,433 US20150089898A1 (en) 2004-04-02 2014-12-10 Method for erecting a tower

Related Parent Applications (2)

Application Number Title Priority Date Filing Date
PCT/EP2005/003499 Division WO2005095792A1 (en) 2004-04-02 2005-04-04 Method for erecting a tower
US11/547,387 Division US9206617B2 (en) 2004-04-02 2005-04-04 Tower and foundation

Publications (1)

Publication Number Publication Date
US20150089898A1 true US20150089898A1 (en) 2015-04-02

Family

ID=34962709

Family Applications (2)

Application Number Title Priority Date Filing Date
US11/547,387 Active 2028-08-20 US9206617B2 (en) 2004-04-02 2005-04-04 Tower and foundation
US14/566,433 Abandoned US20150089898A1 (en) 2004-04-02 2014-12-10 Method for erecting a tower

Family Applications Before (1)

Application Number Title Priority Date Filing Date
US11/547,387 Active 2028-08-20 US9206617B2 (en) 2004-04-02 2005-04-04 Tower and foundation

Country Status (19)

Country Link
US (2) US9206617B2 (en)
EP (1) EP1735533B2 (en)
JP (2) JP4726891B2 (en)
KR (1) KR20060130755A (en)
CN (1) CN1965165B (en)
AR (1) AR048458A1 (en)
AT (1) ATE521804T1 (en)
AU (1) AU2005229135B2 (en)
BR (1) BRPI0509286B1 (en)
CA (1) CA2561431C (en)
CY (1) CY1111928T1 (en)
DE (1) DE102004017006B4 (en)
DK (1) DK1735533T4 (en)
ES (1) ES2369669T5 (en)
NZ (1) NZ550073A (en)
PL (1) PL1735533T3 (en)
PT (1) PT1735533E (en)
SI (1) SI1735533T1 (en)
WO (1) WO2005095792A1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150143765A1 (en) * 2012-02-28 2015-05-28 Ms Enertech, S.L. Connection between a wind turbine tower and its foundation
CN105350565A (en) * 2015-12-07 2016-02-24 湖南皓诺工程有限公司 Wind power plant fan tower foundation repairing and reinforcing method
CN106592660A (en) * 2016-12-21 2017-04-26 神华集团有限责任公司 Draught fan foundation restoration method
US11236727B2 (en) 2015-12-21 2022-02-01 Vestas Wind Systems A/S Method for forming a wind turbine foundation and related system for forming such a foundation
US20230279841A1 (en) * 2022-03-03 2023-09-07 Barr Engineering Co. Spreader box

Families Citing this family (59)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102004017006B4 (en) 2004-04-02 2012-03-29 Aloys Wobben Method of erecting a tower
DE102004017008B4 (en) 2004-04-02 2009-10-22 Aloys Wobben Method for erecting a tower
EP1866484A1 (en) * 2005-03-16 2007-12-19 Densit A/S Tower foundation system and method for providing such system
US8051627B2 (en) * 2006-04-30 2011-11-08 General Electric Company Tower adapter, method of producing a tower foundation and tower foundation
ES2326010B2 (en) * 2006-08-16 2011-02-18 Inneo21, S.L. STRUCTURE AND PROCEDURE FOR ASSEMBLING CONCRETE TOWERS FOR WIND TURBINES.
WO2010138978A2 (en) 2009-05-05 2010-12-02 Ahmed Phuly Engineering & Consulting, Inc. Fatigue resistant foundation
DE102006058668A1 (en) * 2006-12-13 2008-06-19 Kleinsorge Verbindungstechnik Gmbh Anchoring rod for a wind power installation comprises a shaft with threads provided with a cathodic corrosion protection in sections
WO2009056898A1 (en) 2007-11-02 2009-05-07 Alejandro Cortina-Cordero Post-tensioned concrete tower for wind turbines
JP5198011B2 (en) * 2007-08-10 2013-05-15 前田建設工業株式会社 Tower foundation
DE102007060379C5 (en) * 2007-12-12 2018-11-15 Senvion Gmbh Anchoring a tower of a wind turbine
US8555600B2 (en) 2008-12-10 2013-10-15 Cortina Innovations, S.A. De C.V. Method for mounting in sections an annular tower for wind power generator, heliostatic power generator or chimney composed from three concrete segments or more
EP2199469B1 (en) * 2008-12-16 2012-06-06 Vestas Wind Systems A/S Foundation for enabling anchoring of a wind turbine tower thereto by means of replaceable through-bolts
US8220214B1 (en) * 2009-05-02 2012-07-17 Purdy Charles L Prefabricated weight distribution element
DE102009019709A1 (en) 2009-05-05 2010-11-11 Wobben, Aloys Process for building a tower and tower
US20110027100A1 (en) * 2009-07-30 2011-02-03 Daniel Francis Cummane Mobile wind power station
DE102009049435A1 (en) * 2009-10-14 2011-04-28 Wobben, Aloys Process for the manufacture of precast concrete elements and formwork unit for the production of precast concrete parts
DK2375057T3 (en) * 2010-03-31 2016-08-15 Siemens Ag wind farms
US20110131899A1 (en) * 2010-04-30 2011-06-09 Stefan Voss Apparatus and method for producing a concrete foundation
CA2722226A1 (en) * 2010-08-24 2012-02-24 Mitsubishi Heavy Industries, Ltd. Wind turbine generator and construction method for wind turbine tower
FI125153B (en) 2010-09-16 2015-06-15 Peikko Group Oy Method and apparatus for attaching a tower structure to a foundation
CN102095052B (en) * 2010-11-25 2013-06-12 华锐风电科技(集团)股份有限公司 Installing method of foundation bolt anchoring system and method for installing industrial equipment
DE102011001250A1 (en) 2011-03-14 2012-09-20 Strabag Offshore Wind Gmbh Apparatus and method for the transition between a steel tower section and a prestressed concrete tower section
ES2400902B1 (en) * 2011-05-25 2014-02-18 Esteyco Energía S.L. SETTLEMENT PROCEDURE OF A TOWER.
EP2541059A2 (en) * 2011-06-28 2013-01-02 Gamesa Innovation & Technology, S.L. Footing for wind turbine towers
GB2494674B (en) * 2011-09-15 2018-09-05 Ronald Chambers Peter A connection formed under water between a wind turbine tower and a wind turbine foundation
DE102011085947A1 (en) 2011-11-08 2013-05-08 Wobben Properties Gmbh Tower foot section of a wind turbine
ES2405034B1 (en) 2011-11-17 2014-04-15 Acciona Windpower, S.A. PROCEDURE AND UNIT FOR THE SETTING OF A TOWER FROM AN AIRCRAFT TO A FOUNDATION AND AEROGENERATOR THAT INCLUDES SUCH UNIT
CN103114604B (en) * 2012-03-09 2015-04-22 中国电建集团西北勘测设计研究院有限公司 Prestressed concrete tubular type wind generating set foundation
KR101358213B1 (en) * 2012-07-05 2014-02-05 삼성중공업 주식회사 Tower support structure and method for constructing the structure
CN102777334A (en) * 2012-07-21 2012-11-14 广东明阳风电产业集团有限公司 Wind generating set leveling device
US10100548B2 (en) * 2012-10-01 2018-10-16 Valmont Industries, Inc. Base angle attachment assemblies
CN102979109B (en) * 2012-12-17 2015-06-17 中国电建集团西北勘测设计研究院有限公司 Design method of assembled-type prestressed concrete cylindrical column base
EP2746578B1 (en) * 2012-12-21 2016-11-30 Siemens Aktiengesellschaft Segmented tower bottom flange and method of assembly
CN103046575B (en) * 2013-01-28 2015-07-29 中国电建集团西北勘测设计研究院有限公司 A kind of blower fan spread footing structure of land four leaf plum types
EP2981654B1 (en) * 2013-03-29 2020-07-01 Tindall Corporation Tower assembly for a tower structure
DE102013211750A1 (en) 2013-06-21 2014-12-24 Wobben Properties Gmbh Wind turbine and wind turbine foundation
DE102013213976A1 (en) * 2013-07-17 2015-01-22 Wobben Properties Gmbh A method of manufacturing a precast concrete segment of a wind turbine tower
US9003721B1 (en) 2013-11-08 2015-04-14 Siemens Aktiengesellschaft Leveling arrangement for a tower
US9869300B2 (en) * 2014-01-16 2018-01-16 Pacadar S.A.U. Foundation for wind turbine tower and pre-assembly method of wind turbine tower
KR101687972B1 (en) * 2014-11-20 2017-01-02 대우조선해양 주식회사 Foundation for Wind Generator and Construction Method Thereof
DE102015203574A1 (en) 2015-02-27 2016-09-01 Wobben Properties Gmbh Wind turbine foundation and wind turbine
CN104895101B (en) * 2015-06-10 2016-08-24 杭州江润科技有限公司 The construction method of raft foundation high accuracy integral built-in large diameter bolt group structure
DE102015216444A1 (en) * 2015-08-27 2017-03-02 Wobben Properties Gmbh Wind turbine
EP3329119A2 (en) * 2015-08-31 2018-06-06 Siemens Gamesa Renewable Energy, Inc. Equipment tower having a concrete plinth
US9518402B1 (en) * 2015-09-04 2016-12-13 Kundel Industries, Inc. Anchoring system
DE102015014070A1 (en) 2015-10-30 2017-05-04 Senvion Gmbh Wind energy plant, load distribution system of a wind turbine and method for erecting a tower of a wind turbine
KR101888231B1 (en) * 2015-12-21 2018-09-06 고려대학교 산학협력단 A tower-substructure connecting structure for reinforced concrete substructure capable of correcting vertical misalignment
WO2018051427A1 (en) * 2016-09-14 2018-03-22 三菱重工コンプレッサ株式会社 Supporting table, rotating machine unit, and method for manufacturing rotating machine unit
CN106626048A (en) * 2016-10-08 2017-05-10 霍尔果斯新国金新能源科技有限公司 Grouting mold and method for wind driven generator tower drum and foundation
US10544559B2 (en) * 2016-11-02 2020-01-28 Inventus Holdings, Llc Pier and mat foundation fortification and monitoring system
CN106702907B (en) * 2016-12-19 2018-05-01 中交路桥建设有限公司 A kind of Bridge guardrail base adjustable flange disk construction method
CN107130628A (en) * 2017-05-31 2017-09-05 中国二十冶集团有限公司 The construction method of embedding anchor bolts flange and embedding anchor bolts
DE102017125716A1 (en) * 2017-11-03 2019-05-09 Eno Energy Systems Gmbh Method for erecting a tower with a multi-part tower section and sub-section of a multi-part tower section of a tower
US20190257075A1 (en) * 2018-02-22 2019-08-22 Joseph W. Ball Anchor bolt assembly and arrangement for concrete foundation designs
EP3810863A4 (en) * 2018-05-18 2021-06-30 Cetres Holdings LLC. Concrete boss anchor
DE102019109904A1 (en) 2019-04-15 2020-10-15 Wobben Properties Gmbh Tower segment and method of building a tower
WO2020249852A1 (en) * 2019-06-14 2020-12-17 Peikko Group Oy Method for mounting a prefabricated construction element to another construction element and connection arrangement
RU197237U1 (en) * 2020-02-03 2020-04-14 Николай Валентинович МЕДВЕДЕВ FOUNDATION ANCHOR FASTENING OF THE TOWER CRANE
CN113187305A (en) * 2021-05-26 2021-07-30 新余学院 Electronic information engineering communication tower connecting device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3503165A (en) * 1967-06-12 1970-03-31 Arrowall Corp Prefabricated light weight panels of cementitious material
US4228627A (en) * 1979-04-16 1980-10-21 Neill Joseph C O Reinforced foundation structure
US4910930A (en) * 1988-10-28 1990-03-27 Base Isolation Consultants, Inc. Seismic isolation structure
US5953864A (en) * 1997-04-23 1999-09-21 Rapid Wall Systems Prefabricated modular concrete foundation wall systems and methods of constructing prefabricated modular concrete foundation wall systems
US20040035073A1 (en) * 2002-08-26 2004-02-26 Bravinski Leonid G 3-D construction modules

Family Cites Families (73)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US962699A (en) 1909-01-09 1910-06-28 Unit Construction Co Concrete construction.
US1506173A (en) 1919-11-17 1924-08-26 Hagen Hans Engelhart Method of producing concrete poles
GB606545A (en) 1946-02-26 1948-08-16 William Hubert James Miller Improved shuttering for adjustable location of anchor bolts and anchor plates in concrete foundations, walls, floors and like supports
US2724261A (en) 1951-05-24 1955-11-22 Egil M Rensaa Precast column attaching means
DE1045735B (en) * 1957-09-27 1958-12-04 Knorr Bremse Gmbh Sliding axle bearing with oil circuit guided through the lowest edges
US3645057A (en) 1970-10-13 1972-02-29 Seymour M Kaplan Base for mounting a traffic light pole in rotatable and vertically adjustable relation
US3829540A (en) * 1970-12-07 1974-08-13 J Cox Technique for aligning anchor bolts
US3713262A (en) 1970-12-10 1973-01-30 J Jatcko Taper lock break-away pole structure
JPS5312672B2 (en) * 1972-11-15 1978-05-02
US3834094A (en) 1973-09-12 1974-09-10 B Ferguson Track system wall assembly for houses or the like
AT347189B (en) * 1977-04-06 1978-12-11 Voest Ag FOUNDATION ANCHORING FOR HEAVY MACHINERY
JPS6043925B2 (en) 1977-07-15 1985-10-01 日特建設株式会社 Fertilization method for slope greening
JPS5578722A (en) 1978-12-11 1980-06-13 Mitsubishi Heavy Ind Ltd Groundwork construction of steel smoke stuck
US4327703A (en) 1979-10-09 1982-05-04 Destree Allen L Method of preparing concrete column for attachment to beam
US4331314A (en) * 1980-05-22 1982-05-25 Allis-Chalmers Corporation Hydraulic pump/turbine discharge ring support anchorage
US4365929A (en) 1981-01-16 1982-12-28 Philip Retz Vertical wind turbine power generating tower
US4438607A (en) * 1982-03-29 1984-03-27 A. O. Smith Harvestore Products, Inc. Method and apparatus for leveling a storage structure
JPS5968432A (en) * 1982-10-08 1984-04-18 Hitoshi Mori Laying of anchor bolt
US4785593A (en) 1986-10-27 1988-11-22 Munoz Jr Jose C Structural building system
DE3809113A1 (en) 1988-03-18 1989-09-28 Mehne Fa Erwin Method of erecting the steel-framed superstructure of storage racking and steel structure for it
US5110082A (en) * 1988-09-21 1992-05-05 Rowan Jr Robert L Adjustable apparatus for supporting machinery or other load
US4887691A (en) 1988-11-04 1989-12-19 Rotondo/Penn-Cast Modular wall construction using posts and panels
US5505033A (en) * 1988-12-06 1996-04-09 501 Hitachi Metals Ltd. Column base structure and connection arrangement
DE8910744U1 (en) 1989-09-08 1991-01-17 Schmidt, René P., Oberweningen Sealing device for concrete joints
FR2659685A1 (en) 1990-03-16 1991-09-20 Puglia Emilio DEVICE FOR IMPROVING THE ATTACHMENT OF A SUPPORT AND THE ADJUSTMENT OF ITS VERTICALITY ON AN ANCHORING MASSIVE.
GB9024500D0 (en) * 1990-11-10 1991-01-02 Peace Steven J A vertical axis wind turbine unit capable of being mounted on or to an existing chimney,tower or similar structure
JPH0739665B2 (en) * 1992-04-24 1995-05-01 茂樹 林 Basic structure of retaining wall block
FR2692611B1 (en) 1992-06-17 1999-03-05 Prefatlantique FIXING PLATE FOR PYLON.
US5437519A (en) * 1992-08-26 1995-08-01 Roger Bullivant Of Texas, Inc. Piles and pile forming methods
GB2273310A (en) * 1992-12-10 1994-06-15 Thomas Steel Craik Improvements relating to buildings
US5308195A (en) 1993-02-12 1994-05-03 The Reinforced Earth Company Coping construction for a retaining wall
US5379563A (en) * 1993-09-13 1995-01-10 Eastman Chemical Company Anchoring assembly
JP3362809B2 (en) * 1994-05-13 2003-01-07 積水ハウス株式会社 Pillar support device
US5586417A (en) * 1994-11-23 1996-12-24 Henderson; Allan P. Tensionless pier foundation
JP3002107B2 (en) * 1994-12-19 2000-01-24 勤伍 内藤 Column base structure and column base construction method
JP3622119B2 (en) * 1995-01-09 2005-02-23 日本鋳造株式会社 Basic bar arrangement method
JP3458179B2 (en) 1995-02-03 2003-10-20 日本鋳造株式会社 Column base fixing structure
JPH09158215A (en) * 1995-12-07 1997-06-17 Toshiba Eng & Constr Co Ltd Construction method for installing large-sized machine
US5707180A (en) 1995-12-26 1998-01-13 Vickars Developments Co. Ltd. Method and apparatus for forming piles in-situ
US6264402B1 (en) 1995-12-26 2001-07-24 Vickars Developments Co. Ltd. Method and apparatus for forming piles in place
JPH09302675A (en) * 1996-05-20 1997-11-25 Sumitomo Forestry Co Ltd Anchor bolt installation method and metal fitting
JP3752310B2 (en) * 1996-05-20 2006-03-08 住友林業株式会社 Anchor bolt positioning tool and method
JPH10121576A (en) 1996-10-16 1998-05-12 Tomoe Corp Fixing structure of pedestal
US6050038A (en) * 1998-09-11 2000-04-18 Fey; James M. Foundation system for supporting a superstructure
AU2093200A (en) 1999-01-22 2000-08-07 Neg Micon A/S A method and an assembly for casting a tower foundation
US6705058B1 (en) 1999-02-12 2004-03-16 Newmark International Inc. Multiple-part pole
JP3381031B2 (en) * 1999-03-31 2003-02-24 日本鋳造株式会社 Method of designing base plate for steel pipe column and base plate for steel pipe column
JP2000034733A (en) * 1999-06-25 2000-02-02 Okabe Co Ltd Footing structure
IL134724A0 (en) 2000-02-24 2001-04-30 Giltek Telecomm Ltd Foundation for a tower and a method for its deployment on site
DE10009072A1 (en) * 2000-02-25 2001-08-30 Sms Demag Ag Method for anchoring machine to floor uses casing pipes) and anchor plates and bolts with sealing rings made from polymer, especially polyurethane
US6503024B2 (en) * 2000-03-06 2003-01-07 Stan Rupiper Concrete foundation pierhead and method of lifting a foundation using a jack assembly
US6318034B1 (en) 2000-03-08 2001-11-20 Tindall Corporation Elevated storage tank
DK174190B1 (en) * 2000-04-12 2002-09-09 Spaencom As Foundation for a windmill and procedure for installation hereof
DE10045735B4 (en) * 2000-09-15 2008-04-03 Vetter Fördertechnik GmbH Fixing the column of a column slewing crane on a concrete foundation
WO2002027105A1 (en) * 2000-09-27 2002-04-04 Allan P Henderson Perimeter weighted foundation for wind turbines and the like
US6470645B1 (en) 2000-11-09 2002-10-29 Beaird Industries, Inc. Method for making and erecting a wind tower
US6443656B1 (en) 2001-03-30 2002-09-03 Abt, Inc. Trench forming assembly having removable pin anchoring mechanism
DE10226996B4 (en) * 2001-10-09 2014-07-03 Aloys Wobben Method for creating a foundation, in particular for a tower of a wind energy plant
JP2003293938A (en) 2002-04-02 2003-10-15 Tetra Co Ltd Construction method of wind power generating device
US20030196393A1 (en) * 2002-04-22 2003-10-23 Bowman Joseph M. Weldless pole mounting structure and method of providing same
DE10238033A1 (en) 2002-08-20 2004-03-04 Alpine Project Technology Gmbh Concrete foundation for road sign support has flat foundation block with concrete shuttering elements of different height, filled with poured concrete with anchors for carrier fittings
US7222464B2 (en) * 2002-12-18 2007-05-29 Suehiro-System Co., Ltd. Anchor bolt and installing method thereof
FI20022235A (en) * 2002-12-19 2002-12-19 Rautaruukki Oyj Foundation of a transversely loaded tower
US7533505B2 (en) * 2003-01-06 2009-05-19 Henderson Allan P Pile anchor foundation
US6808350B1 (en) * 2003-01-27 2004-10-26 Norman L. Tooman Anchor bolt cap and method of use
US7025176B1 (en) * 2003-06-09 2006-04-11 Tooman Norman L Bolt greaser unit
DE502004009257D1 (en) * 2003-06-27 2009-05-14 Alstom Technology Ltd Fastening device of a machine base of a machine and method for fixing the same
WO2005015013A1 (en) 2003-08-09 2005-02-17 General Electric Company Tower foundation, in particular for a wind energy turbine
NL1024581C2 (en) 2003-10-21 2005-04-22 Gmb Beton En Ind Noord West B Windmill foundation.
DE102004017006B4 (en) 2004-04-02 2012-03-29 Aloys Wobben Method of erecting a tower
DE102004017008B4 (en) 2004-04-02 2009-10-22 Aloys Wobben Method for erecting a tower
US8801370B2 (en) 2006-10-12 2014-08-12 General Electric Company Turbine case impingement cooling for heavy duty gas turbines
DE102007060379C5 (en) 2007-12-12 2018-11-15 Senvion Gmbh Anchoring a tower of a wind turbine

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3503165A (en) * 1967-06-12 1970-03-31 Arrowall Corp Prefabricated light weight panels of cementitious material
US4228627A (en) * 1979-04-16 1980-10-21 Neill Joseph C O Reinforced foundation structure
US4910930A (en) * 1988-10-28 1990-03-27 Base Isolation Consultants, Inc. Seismic isolation structure
US5953864A (en) * 1997-04-23 1999-09-21 Rapid Wall Systems Prefabricated modular concrete foundation wall systems and methods of constructing prefabricated modular concrete foundation wall systems
US20040035073A1 (en) * 2002-08-26 2004-02-26 Bravinski Leonid G 3-D construction modules

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150143765A1 (en) * 2012-02-28 2015-05-28 Ms Enertech, S.L. Connection between a wind turbine tower and its foundation
CN105350565A (en) * 2015-12-07 2016-02-24 湖南皓诺工程有限公司 Wind power plant fan tower foundation repairing and reinforcing method
US11236727B2 (en) 2015-12-21 2022-02-01 Vestas Wind Systems A/S Method for forming a wind turbine foundation and related system for forming such a foundation
US12000378B2 (en) 2015-12-21 2024-06-04 Vestas Wind Systems A/S System for forming a wind turbine foundation
CN106592660A (en) * 2016-12-21 2017-04-26 神华集团有限责任公司 Draught fan foundation restoration method
US20230279841A1 (en) * 2022-03-03 2023-09-07 Barr Engineering Co. Spreader box
US11905924B2 (en) * 2022-03-03 2024-02-20 Barr Engineering Co. Spreader box

Also Published As

Publication number Publication date
WO2005095792A1 (en) 2005-10-13
DE102004017006B4 (en) 2012-03-29
EP1735533A1 (en) 2006-12-27
CN1965165A (en) 2007-05-16
SI1735533T1 (en) 2011-10-28
ES2369669T5 (en) 2020-11-16
AU2005229135A1 (en) 2005-10-13
JP4726891B2 (en) 2011-07-20
DE102004017006A1 (en) 2005-10-27
PT1735533E (en) 2011-10-18
AR048458A1 (en) 2006-04-26
JP2007535634A (en) 2007-12-06
CN1965165B (en) 2011-08-10
AU2005229135B2 (en) 2010-12-16
EP1735533B2 (en) 2020-03-25
CA2561431C (en) 2010-11-30
DK1735533T4 (en) 2020-06-02
CA2561431A1 (en) 2005-10-13
DK1735533T3 (en) 2011-11-21
JP2010159625A (en) 2010-07-22
US9206617B2 (en) 2015-12-08
EP1735533B1 (en) 2011-08-24
US20080302038A1 (en) 2008-12-11
CY1111928T1 (en) 2015-11-04
BRPI0509286B1 (en) 2018-06-05
KR20060130755A (en) 2006-12-19
ES2369669T3 (en) 2011-12-02
PL1735533T3 (en) 2012-04-30
NZ550073A (en) 2011-07-29
BRPI0509286A (en) 2007-09-18
ATE521804T1 (en) 2011-09-15

Similar Documents

Publication Publication Date Title
US20150089898A1 (en) Method for erecting a tower
US8037646B2 (en) Method for erecting a tower
US7416367B2 (en) Lateral force resistance device
US20070181767A1 (en) Foundation for a wind energy plant
EP2981654B1 (en) Tower assembly for a tower structure
WO2001040585A1 (en) Foundation structure and erection of towers
US10060087B2 (en) Fully adjustable suspended post and panel modules and installation methods
US9238921B2 (en) Method and arrangements relating to foundation for antenna mast of wireless communication system
CN111197318B (en) Foundation for a tower of a wind turbine
US9828739B2 (en) In-line battered composite foundations
CN212052262U (en) Prefabricated pier body and bridge
EP4294987A1 (en) Mold part set for wind turbine ground foundation and wind turbine ground foundation
WO1995026444A1 (en) Multiple pier foundation and method of constructing same

Legal Events

Date Code Title Description
STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION