US20130327525A1 - Thermal pulsing procedure for remediation of cold spots in steam assisted gravity drainage - Google Patents

Thermal pulsing procedure for remediation of cold spots in steam assisted gravity drainage Download PDF

Info

Publication number
US20130327525A1
US20130327525A1 US13/912,463 US201313912463A US2013327525A1 US 20130327525 A1 US20130327525 A1 US 20130327525A1 US 201313912463 A US201313912463 A US 201313912463A US 2013327525 A1 US2013327525 A1 US 2013327525A1
Authority
US
United States
Prior art keywords
sagd
reservoir
steam
well
pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US13/912,463
Inventor
Peter Yang
Richard Kelso Kerr
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CNOOC Petroleum North America ULC
Original Assignee
Nexen Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nexen Inc filed Critical Nexen Inc
Priority to US13/912,463 priority Critical patent/US20130327525A1/en
Assigned to NEXEN INC. reassignment NEXEN INC. ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: KERR, RICHARD KELSO, YANG, PETER
Assigned to NEXEN ENERGY ULC reassignment NEXEN ENERGY ULC CHANGE OF NAME (SEE DOCUMENT FOR DETAILS). Assignors: NEXEN ENERGY INC.
Assigned to NEXEN ENERGY INC. reassignment NEXEN ENERGY INC. CERTIFICATE OF CONTINUATION Assignors: NEXEN INC.
Publication of US20130327525A1 publication Critical patent/US20130327525A1/en
Assigned to CNOOC PETROLEUM NORTH AMERICA ULC reassignment CNOOC PETROLEUM NORTH AMERICA ULC CHANGE OF NAME (SEE DOCUMENT FOR DETAILS). Assignors: NEXEN ENERGY ULC
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/16Enhanced recovery methods for obtaining hydrocarbons
    • E21B43/24Enhanced recovery methods for obtaining hydrocarbons using heat, e.g. steam injection
    • E21B43/2406Steam assisted gravity drainage [SAGD]

Definitions

  • SAGD Steam Assisted Gravity Drainage
  • EOR enhanced oil recovery
  • SAGD is executed in 3 phases—(i) at least one start-up phase, where steam circulation from the steam injector well and production well is used to establish communication between the parallel horizontal wells; (ii) at least one ramp-up phase where a steam chamber is formed in the pattern recovery zone and grows both laterally and vertically until it hits the pay ceiling; and (iii) a wind-up phase where vertical growth is stopped by the pay ceiling but lateral growth continues and productivity slows down as the slope of the chamber walls decrease.
  • bitumen is produced at/near saturated steam temperature, it is predominantly the latent heat of steam that drives the SAGD process. As pressure and temperature are increased, the latent heat content in saturated steam drops, so efficiency is lost. Also, at higher temperature and pressure conditions, the reservoir matrix requires heating to higher temperatures. This increased heat demand also reduces efficiencies.
  • a Type B reservoir may behave like a Type A reservoir.
  • reservoir types above may change as a SAGD project matures, particularly if the growing steam chamber encounters an active water zone or even a limited water zone.
  • the objective of the SAGD start-up phase is to establish communications between the two horizontal wells and to heat/mobilize the bitumen between the wells, uniformly to a target temperature, usually about 100° C.
  • the start-up phase is accomplished by circulating steam in both the upper (injector) and lower (producer) horizontal wells.
  • the start-up may also be broken into phases. If steam is injected at the well heel, for circulation, the first hurdle is to reach steam temperature at the well toe. To reach steam temperature it may take, at least, a few days (Vanegas (2006)). Then steam injection/circulation is continued for several weeks (or a few months), with both wells at the same pressure. Heat is transferred to the reservoir by conduction.
  • the operator may establish a pressure differential between upper/lower wells, while still circulating steam in each well, with the upper well at the higher pressure.
  • This well pressure differential is modest ( ⁇ 100 Kpa), so preferential flow channels are not created.
  • the objective is to add a convection mechanism to heat transfer to speed up communications (Vanegas P. et al, ‘Impact of Operational Parameters and Reservoir Variables during the Start-up Phase of a SAGD Process’, Pet. J. Online, Nov. 16, 2006, Yuan, J. Y. et al ‘Evaluation of Steam Circulation Strategies for SAGD Start-up’ Can. Intl. Pet. Conf., Calgary, Jun. 16, 2009, and Parmar, G. et al, ‘Start-up of SAGD Wells: History Match, Wellbore Design and Operation’, JCPT, January 2009).
  • SAGD may be started by injecting steam only in the upper well (injector) producing hot fluids in the lower well (hot bitumen+condensed steam).
  • injector producing hot fluids in the lower well
  • hot bitumen+condensed steam hot fluids in the lower well
  • start-up phase time is longer for reservoirs with heavier, more viscous bitumen.
  • a small steam chamber is formed and the ramp-up SAGD phase starts and matures as the chamber grows upward and outward. Production increases as the chamber grows and peaks when the ceiling of the pay zone is reached.
  • a pressure target which can be higher than native reservoir pressure. Pressure is monitored by down-hole sensors. The steam injection rate is adjusted to attain pressure target. The production rate is controlled (electric submersible pump (“ESP”) or gas lift) to meet a temperature target in the production well, monitored by down-hole thermocouples. The temperature target is set at a sub-cool target compared to saturated steam temperature in the reservoir (usually 10-20° C. sub-cool), to ensure that the production well is producing only liquids (bitumen+water) and not live steam. Sub-cool is the difference between the saturated steam temperature at the producer pressure and the actual temperature at where pressure is measured. This is also called steam-trap control (VanderValk, P. A. et al ‘Investigation of Key Parameters in SAGD Wellbore Design and Operation’, JCPT, June, 2007).
  • steam-trap control may be much more difficult. Overpressure operation of SAGD may not be feasible. If cold water or cold spots are in part of the production well (or producer well), steam-trap control may be lost.
  • temperature in the production well will also increase as hotter production fluids or some steam are drawn to the production well. This directionality is used as the basis of steam-trap control. If there is a cold zone in the production well formed as the result of reservoir water incursion, and if production rate is increased, temperature in the production well may drop if more cold water is drawn in.
  • start-up or ramp-up phases have created or established non-homogeneous heat distribution, a manifest measurement of the condition is “cold spots” in the production well. If cold spots are formed, they can be surprisingly resilient (Larter (2010)). In the ramp-up (or wind-up) phase of SAGD the operator has limited tools to remediate the “cold spots” (VanderValk (2007)). Sub-cool may be varied, injection tubing size may be varied (or insulated), or pressure targets may be altered. These remedies are not very successful.
  • SAGD is now the dominant in-situ EOR process to recover bitumen from Canadian oil sands.
  • SAGD comprises two parallel horizontal wells, about five metres apart, completed near the bottom of a bitumen reservoir.
  • the upper well continuously injects steam and the lower well produces heated bitumen and condensed steam (water).
  • all parts of the producer well should be hot and contribute to production. If cold spots form in this well it is an indication of reduced productivity and poor conformance.
  • the thermal pulse procedure comprises shutting in the producer well, increasing or maintaining steam injection rates from a steam injector well, opening up the producer well and reinstating normal SAGD operation.
  • a method for remediation of at least one cold spot in a SAGD process comprising:
  • This remediation method increases hydrocarbon recovery from a hydrocarbon deposit.
  • steam injection rate to reach and/or maintain a preferred pressure target.
  • fluid withdrawal rate from the producer well is adjusted to reach and/or maintain a preferred sub cool target.
  • SAGD Steam Assisted Gravity Drainage
  • the at least one cold spot has a temperature of about 10° C. to about 20° C. lower than SAGD sub-cool targets, more preferably at least 20° C. lower than SAGD sub-cool targets.
  • said sub-cool target in SAGD is in the range of from about 0° C. to about 25° C., more preferably from about 5° C. to about 20° C.
  • the cold spots are formed by cold water incursion from the reservoir water zone, preferably the water recharge rates from the reservoir water zone are less than about 500 m 3 /d, more preferably less than about 50 m 3 /d.
  • said bitumen reservoir is selected from the group consisting of a homogenous Type A reservoir, heterogeneous Type B reservoir, Type C reservoir and mixtures thereof
  • At least one cold spot is monitored at some point, preferably throughout said process.
  • said remediation process is carried out during the ramp-up phase of SAGD.
  • FIG. 1 depicts a typical SAGD Well Configuration known in the art.
  • FIG. 2 depicts a typical ramp-up phase in a SAGD process.
  • FIG. 3 depicts a typical wind-up phase in a SAGD process.
  • FIG. 4 depicts Saturated steam properties.
  • FIG. 5 depicts steam injection rates, electrical submersible pump rates of bitumen and water, and well heel temperatures when incorporating one embodiment of the present invention.
  • FIG. 6 depicts well heel temperature response when incorporating an embodiment of the present invention.
  • FIG. 7 depicts the Steam to Oil Ratio (SOR) and Oil rates when incorporating an embodiment of the present invention.
  • FIG. 8 depicts the Oil rates when incorporating an embodiment of the present invention.
  • FIG. 9 depicts well pair performance over a period of 4 years when incorporating an embodiment of the present invention.
  • FIG. 10 depicts a proposed well pair configuration and monitoring layout according to one embodiment of the invention
  • SAGD Steam Assisted Gravity Drainage
  • EOR enhanced oil recovery
  • SAGD has two parallel horizontal wells (a producer well ( 10 ) and a steam injector well ( 20 )), about 5 metres apart, with the lower producer well ( 10 ) completed in the pay zone ( 30 ), close to the bottom of the pattern recovery zone ( 40 ), and a steam injector well ( 20 ) above the lower producer well ( 10 ).
  • the pattern recovery zone ( 40 ) volume is about 100 metres wide (100 metres spacing) ( 50 ) and up to 1000 metres long (1000 metres well length).
  • SAGD is executed in 3 phases—(i) a start-up phase, where steam circulation from the steam injector well is used to establish communication between the parallel horizontal wells; (ii) a ramp-up phase (as best seen in FIG. 2 ) where a steam chamber ( 60 ) is formed in the pattern recovery zone ( 70 )) and grows both laterally ( 61 ) and vertically ( 62 ) until it hits the pay ceiling ( 80 ); and (iii) a wind-up phase (as best seen in FIG. 3 ) where vertical growth is stopped by the pay ceiling ( 80 ) but lateral growth continues and productivity slows down as the slope of the chamber walls ( 61 ) decrease.
  • bitumen is produced at/near saturated steam temperature, it is predominantly the latent heat of steam that drives the SAGD process.
  • the latent heat content in saturated steam drops (as best seen in FIG. 4 ), so efficiency is lost.
  • the reservoir matrix requires heating to higher temperatures. This increased heat demand also reduces efficiencies.
  • thermo pulse remediation process (TPP) of the present invention may be applied to a SAGD process with at least one cold spot in a production well, as follows:
  • the present invention relies firstly on a slow/limited recharge rate of cold water and a fast saturation with hot production fluids. Secondly, the remediation based on the present invention may be temporary or permanent depending on the reservoir type and operating strategy following remediation. Thirdly, if the water recharge rate is rapid (i.e. Type C reservoir) the present invention may not produce ideal results. Thirdly, if the water recharge rate is rapid (i.e. Type C reservoir) the present invention may not produce ideal results. Fourth, the present invention relies on ability to increase reservoir pressure. Again, this condition may not produce ideal results for a Type C reservoir.
  • FIGS. 5-8 show process measurements over the two day testing period.
  • thermocouples in the heel of the producer well registered temperatures from about 140° C. to 160° C. Given the temperature of saturated steam is about 213° C., the temperature fluctuation of from about 140° C. to 160° C. indicates a cold spot is present in the heel of the producer well, given the heel zone is expected to be hot given the heel zone is the first zone to receive steam and collects all the production fluids. It is also observed that subsequent to the remediation process, the heel temperature rose quickly to between 180° C. and 190° C. and this increased temperature was maintained for a period of time. As best seen in FIGS.
  • FIG. 9 shows the total history of the well pair prior to, during, and post testing.
  • SAGD was initiated in January 2008.
  • the SAGD pair was in the ramp-up phase of SAGD.
  • the instrumentation in the well pair ( 10 , 20 ) is shown, including 6 thermocouples ( 90 ) in the production well, pressure measurement at the producer heel ( 100 ) and toe ( 110 ) and at the injector heel ( 120 ) subsequent to implementation of the present invention.
  • the present invention when incorporating the present invention in a type B reservoir, it is preferred that there are limited leaks and there is some ability to increase pressure; when incorporating the present invention during the ramp-up phase of SAGD, it is preferred to remediate the cold spot(s) as early as possible; it is preferred to limit repressurization to no more than about +0.5MPa; and the cold spot in the production well is preferably greater than about 10° C. below sub cool target temperature.

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Production Of Liquid Hydrocarbon Mixture For Refining Petroleum (AREA)

Abstract

A method for remediation of at least one cold spot in a producer well in a Steam Assisted Gravity Drainage (SAGD) process to increase hydrocarbon recovery from a hydrocarbon reservoir, wherein the SAGD process occurs at a site including an injection well, a production well and a steam chamber. The method includes shutting the production well and maintaining or increasing steam injection through the injection well until pressure in the steam chamber increases. The production well is then resumed while continuing steam injection at rates for normal SAGD or greater until reservoir pressure reaches normal operational pressure. Optionally, the injection/production is adjusted to return to normal SAGD operation.

Description

    BACKGROUND
  • Steam Assisted Gravity Drainage (“SAGD”) is currently the dominant in situ enhanced oil recovery (“EOR”) process to recover bitumen from Canadian oil sands. SAGD has two parallel horizontal wells (a producer well and a steam injector well), about 5 metres apart, with the lower producer well completed in the pay zone, close to the bottom of the pattern recovery zone, and a steam injector well above the lower producer well. The pattern recovery zone volume is about 100 metres wide (100 metres spacing) and up to 1000 metres long (1000 metres well length).
  • SAGD is executed in 3 phases—(i) at least one start-up phase, where steam circulation from the steam injector well and production well is used to establish communication between the parallel horizontal wells; (ii) at least one ramp-up phase where a steam chamber is formed in the pattern recovery zone and grows both laterally and vertically until it hits the pay ceiling; and (iii) a wind-up phase where vertical growth is stopped by the pay ceiling but lateral growth continues and productivity slows down as the slope of the chamber walls decrease.
  • In the at least one ramp-up phase of SAGD, there are 3 measures of performance, namely the steam-to-oil ratio (“SOR”) (a measure of energy efficiency); bitumen productivity; and water return ratio (how much steam injected is returned as produced water). The dominant economic factors, in descending order, are: bitumen productivity; start-up time before SAGD can be started; SOR; and water return ratio.
  • Because SAGD is a saturated-steam process wherein temperature and pressure are linked, an operator will always have a strong incentive to operate SAGD at the highest pressure possible, even if the operating pressure is higher than native reservoir pressure (i.e. overpressure operation). The reason is simple. At higher pressure saturated steam temperature is higher and bitumen is heated to a higher temperature, reducing viscosity significantly, allowing for ease of flow of bitumen. Bitumen viscosity is a strong function of temperature. Bitumen productivity is proportional to the inverse square root of viscosity (Butler (1991)), so higher pressure results in higher bitumen productivity—the dominant economic factor. The choice of increasing temperature in SAGD may reduce process efficiency for two reasons. Since bitumen is produced at/near saturated steam temperature, it is predominantly the latent heat of steam that drives the SAGD process. As pressure and temperature are increased, the latent heat content in saturated steam drops, so efficiency is lost. Also, at higher temperature and pressure conditions, the reservoir matrix requires heating to higher temperatures. This increased heat demand also reduces efficiencies.
  • Bitumen reservoirs may be characterized by their hydraulic behaviour as follows:
      • (1) Type A bitumen reservoir—is essentially homogeneous, with no bottom/top water, no top gas, no lean zones and few shale baffles. Prior to bitumen production, water injection tests (Aherne, A. L. et al ‘Fluid Movement in the SAGD Process: A Review of the Dover Project’, Can. Int'l Pet. Conf., Jun. 13, 2006) show no/little injectivity into the pay zone. A typical SAGD steam chambers is regular-shaped and pressure contained. Over-pressurization (i.e. operating SAGD at pressures greater than native reservoir pressure) is feasible and it is the normal procedure.
      • (2) Type B bitumen reservoir—exhibits some heterogeneities (shale baffles, lean zones . . . ) but there is no “active” water from lean zones, and no “active” water from bottom/top water. There are “limited” lean zones and/or “limited” water incursion. SAGD steam injection volumes, at peak, are about 500 m3/d so “significant” water incursion is more than about 50 m3/d (i.e. “active” water zones). Prior to bitumen production, water injection tests show some injectivity (i.e. linked to a “limited” water zone). The degree of impact of water incursion and/or water recharge rates is also a function of pressure. At higher SAGD operating pressure compared to native reservoir pressure, water loss/recharge may become more significant. Over pressure operation of SAGD may be feasible, but with increasing fluid losses. The usual remedy to reduce fluid losses is to reduce SAGD operating pressures to/near native reservoir pressure.
      • (3) Type C bitumen reservoir—has significant active water zones from either bottom/top water or lean zones—that may act as thief zones during SAGD. Prior to production, water injection tests show significant injectivity (connection to active water zones). Fluid loss rates or recharge rates are greater than about 50 m3/d. Overpressure SAGD operation is not possible. SAGD must be operated at/near native reservoir pressure. Even then, operation may be difficult if natural pressure gradients (i.e. pressure differentials in the production well or pressure differentials produces as a result of formation of a gas gravity drainage chamber) cause influx or egress of significant fluid volumes.
  • Given the above reservoir categorization by hydraulic behaviour, the type of classification of each reservoir is sensitive to hydraulic factors. For example, at lower SAGD pressure a Type B reservoir may behave like a Type A reservoir. Also, reservoir types above may change as a SAGD project matures, particularly if the growing steam chamber encounters an active water zone or even a limited water zone.
  • The objective of the SAGD start-up phase is to establish communications between the two horizontal wells and to heat/mobilize the bitumen between the wells, uniformly to a target temperature, usually about 100° C. The start-up phase is accomplished by circulating steam in both the upper (injector) and lower (producer) horizontal wells. The start-up may also be broken into phases. If steam is injected at the well heel, for circulation, the first hurdle is to reach steam temperature at the well toe. To reach steam temperature it may take, at least, a few days (Vanegas (2006)). Then steam injection/circulation is continued for several weeks (or a few months), with both wells at the same pressure. Heat is transferred to the reservoir by conduction. Then, the operator may establish a pressure differential between upper/lower wells, while still circulating steam in each well, with the upper well at the higher pressure. This well pressure differential is modest (−100 Kpa), so preferential flow channels are not created. The objective is to add a convection mechanism to heat transfer to speed up communications (Vanegas P. et al, ‘Impact of Operational Parameters and Reservoir Variables during the Start-up Phase of a SAGD Process’, Pet. J. Online, Nov. 16, 2006, Yuan, J. Y. et al ‘Evaluation of Steam Circulation Strategies for SAGD Start-up’ Can. Intl. Pet. Conf., Calgary, Jun. 16, 2009, and Parmar, G. et al, ‘Start-up of SAGD Wells: History Match, Wellbore Design and Operation’, JCPT, January 2009).
  • After a few (several) months, SAGD may be started by injecting steam only in the upper well (injector) producing hot fluids in the lower well (hot bitumen+condensed steam). In SAGD, the start-up phase time is longer for reservoirs with heavier, more viscous bitumen. A small steam chamber is formed and the ramp-up SAGD phase starts and matures as the chamber grows upward and outward. Production increases as the chamber grows and peaks when the ceiling of the pay zone is reached.
  • For a Type A reservoir, operating control for SAGD is simple. The operator chooses a pressure target, which can be higher than native reservoir pressure. Pressure is monitored by down-hole sensors. The steam injection rate is adjusted to attain pressure target. The production rate is controlled (electric submersible pump (“ESP”) or gas lift) to meet a temperature target in the production well, monitored by down-hole thermocouples. The temperature target is set at a sub-cool target compared to saturated steam temperature in the reservoir (usually 10-20° C. sub-cool), to ensure that the production well is producing only liquids (bitumen+water) and not live steam. Sub-cool is the difference between the saturated steam temperature at the producer pressure and the actual temperature at where pressure is measured. This is also called steam-trap control (VanderValk, P. A. et al ‘Investigation of Key Parameters in SAGD Wellbore Design and Operation’, JCPT, June, 2007).
  • For type B and/or C reservoirs, steam-trap control may be much more difficult. Overpressure operation of SAGD may not be feasible. If cold water or cold spots are in part of the production well (or producer well), steam-trap control may be lost. For homogeneous SAGD operation, if production is increased, temperature in the production well will also increase as hotter production fluids or some steam are drawn to the production well. This directionality is used as the basis of steam-trap control. If there is a cold zone in the production well formed as the result of reservoir water incursion, and if production rate is increased, temperature in the production well may drop if more cold water is drawn in.
  • In an ideal world, during SAGD at the end of the start-up phase and in the early ramp-up phase, there would be a homogeneous distribution of heat in the reservoir and a flat temperature profile in the production well. Each segment of the reservoir would contribute equally to bitumen production. Steam chamber shape would be smooth and regular. Unfortunately, homogeneous production for SAGD is rare, even for Type A reservoirs, for the following reasons:
      • (1) Steam circulation during start-up is not homogeneous throughout the well. Most heat is delivered to the well heel.
      • (2) Bitumen reservoirs may have gross inhomogeneities—top/bottom water, top gas, shale baffles, shale barriers, lean zones . . . etc.
      • (3) Bitumen reservoirs may also have subtle inhomogeneities—lateral and vertical permeability variations, porosity variations, matrix composition—that may influence conformance.
      • (4) A pressure gradient (between the parallel horizontal wells) used during the start-up phase may create high-permeability channels that transport steam, bitumen, water and heat between the parallel horizontal wells.
      • (5) Bitumen properties are not homogeneous within a reservoir. Vertical and lateral variation of bitumen quality may be significant and variations may easily influence start-up and ramp-up conformance (Larter, S. ‘Viscous Variations and Asphaltic Aspirations’, Gushor Inc. Newsletter, October 2010).
      • (6) Lean zones, where bitumen saturation is low, water saturation is high and water has some mobility, are a particular concern (Vanderklippe, N. ‘Long Lake Project hits Sticky Patch’, Globe & Mail, Feb. 10, 2011, Reuters, ‘Update 3—Long Lake Oil Sands, Output may lag Targets’, Feb. 10, 2011). Many operators are concerned about lean zone effects (Oilsands Quest, ‘Axe Lake, SAGD Test Horizontal Well Pair Configuration: Project Summary Document’, Jul. 14, 2010, Peterson, J. A. et al, ‘conducting SAGD in Shoreface Oil Sands with Associated Basal Water’, Laricina Energy, 2009, Oilsands Quest, ‘Management Presentation’, January 2011, Akram, F. ‘Reservoir Simulation Optimizes SAGD’, O&G Reporter, September 2010, and Johnson, M. D. et al, ‘Production Optimization at Connacher's Pod One (Great Divide) Oil Sands Project’, SPE Conf., Jul. 19, 2011).
  • If start-up or ramp-up phases have created or established non-homogeneous heat distribution, a manifest measurement of the condition is “cold spots” in the production well. If cold spots are formed, they can be surprisingly resilient (Larter (2010)). In the ramp-up (or wind-up) phase of SAGD the operator has limited tools to remediate the “cold spots” (VanderValk (2007)). Sub-cool may be varied, injection tubing size may be varied (or insulated), or pressure targets may be altered. These remedies are not very successful.
  • There is need for a method to remediate cold spots in the production well, and in particular a production well undergoing SAGD.
  • SUMMARY OF THE INVENTION
  • SAGD is now the dominant in-situ EOR process to recover bitumen from Canadian oil sands. SAGD comprises two parallel horizontal wells, about five metres apart, completed near the bottom of a bitumen reservoir. The upper well continuously injects steam and the lower well produces heated bitumen and condensed steam (water). For a healthy process, all parts of the producer well should be hot and contribute to production. If cold spots form in this well it is an indication of reduced productivity and poor conformance.
  • According to one aspect of the invention, there is provided a procedure to heat up at least one cold spot, preferably a plurality of cold spots, in a producer (or production) well of a SAGD process, to increase production and improve conformance by introducing a “thermal pulse procedure” to the SAGD process. The thermal pulse procedure (TPP) comprises shutting in the producer well, increasing or maintaining steam injection rates from a steam injector well, opening up the producer well and reinstating normal SAGD operation.
  • According to another aspect of the invention there is provided a method for remediation of at least one cold spot in a SAGD process, said SAGD process comprising a steam injector well, a production well, a steam chamber, and at least one cold spot, preferably a plurality of cold spots, proximate said production well, the remediation method comprising:
      • (1) shutting the production well;
      • (2) maintaining or increasing steam injection through the steam injector well until pressure in the steam chamber increases, preferably less than or equal to a 0.3 MPa increase, more preferably up to a 0.5 MPa increase;
      • (3) resuming the production well while continuing steam injection through the steam injector well at rates for normal SAGD or greater, until reservoir pressure reaches normal operational pressure; and optionally
      • (4) adjusting injection/production to return to normal SAGD operation;
  • This remediation method increases hydrocarbon recovery from a hydrocarbon deposit. Typically when adjusting steam injection, the following parameters are adjusted: steam injection rate to reach and/or maintain a preferred pressure target. Typically, when adjusting the producer well, fluid withdrawal rate from the producer well is adjusted to reach and/or maintain a preferred sub cool target.
  • According to yet another aspect of the invention, there is provided an improvement in Steam Assisted Gravity Drainage (“SAGD”) for increasing hydrocarbon recovery from a bitumen reservoir, wherein said SAGD comprises at least one steam injector well, at least one producer well with at least one cold spot, and at least one steam chamber, said improvement comprising:
      • (1) shutting the at least one producer well;
      • (2) maintaining or increasing steam injection through the at least one steam injector well until pressure in the at least one steam chamber increases, preferably less than or equal to a 0.3 MPa increase, more preferably up to a 0.5 MPa increase;
      • (3) resuming the at least one producer well while continuing steam injection through the at least one steam injector well at rates for normal SAGD or greater, until bitumen reservoir pressure reaches normal operational pressure; and optionally
      • (4) adjusting injection/production to return to normal SAGD operation
  • In a preferred embodiment, the at least one cold spot has a temperature of about 10° C. to about 20° C. lower than SAGD sub-cool targets, more preferably at least 20° C. lower than SAGD sub-cool targets. Preferably said sub-cool target in SAGD is in the range of from about 0° C. to about 25° C., more preferably from about 5° C. to about 20° C. In yet another preferred embodiment, the cold spots are formed by cold water incursion from the reservoir water zone, preferably the water recharge rates from the reservoir water zone are less than about 500 m3/d, more preferably less than about 50 m3/d.
  • Preferably, said bitumen reservoir is selected from the group consisting of a homogenous Type A reservoir, heterogeneous Type B reservoir, Type C reservoir and mixtures thereof
  • Preferably said at least one cold spot is monitored at some point, preferably throughout said process.
  • More preferably, said remediation process is carried out during the ramp-up phase of SAGD.
  • BRIEF DESCRIPTION OF THE FIGURES
  • FIG. 1 depicts a typical SAGD Well Configuration known in the art.
  • FIG. 2 depicts a typical ramp-up phase in a SAGD process.
  • FIG. 3 depicts a typical wind-up phase in a SAGD process.
  • FIG. 4 depicts Saturated steam properties.
  • FIG. 5 depicts steam injection rates, electrical submersible pump rates of bitumen and water, and well heel temperatures when incorporating one embodiment of the present invention.
  • FIG. 6 depicts well heel temperature response when incorporating an embodiment of the present invention.
  • FIG. 7 depicts the Steam to Oil Ratio (SOR) and Oil rates when incorporating an embodiment of the present invention.
  • FIG. 8 depicts the Oil rates when incorporating an embodiment of the present invention.
  • FIG. 9 depicts well pair performance over a period of 4 years when incorporating an embodiment of the present invention.
  • FIG. 10 depicts a proposed well pair configuration and monitoring layout according to one embodiment of the invention
  • DETAILED DESCRIPTION OF THE INVENTION
  • According to FIG. 1, as discussed above, Steam Assisted Gravity Drainage (“SAGD”) is currently the dominant in situ enhanced oil recovery (“EOR”) process to recover bitumen from Canadian oil sands. SAGD has two parallel horizontal wells (a producer well (10) and a steam injector well (20)), about 5 metres apart, with the lower producer well (10) completed in the pay zone (30), close to the bottom of the pattern recovery zone (40), and a steam injector well (20) above the lower producer well (10). The pattern recovery zone (40) volume is about 100 metres wide (100 metres spacing) (50) and up to 1000 metres long (1000 metres well length).
  • SAGD is executed in 3 phases—(i) a start-up phase, where steam circulation from the steam injector well is used to establish communication between the parallel horizontal wells; (ii) a ramp-up phase (as best seen in FIG. 2) where a steam chamber (60) is formed in the pattern recovery zone (70)) and grows both laterally (61) and vertically (62) until it hits the pay ceiling (80); and (iii) a wind-up phase (as best seen in FIG. 3) where vertical growth is stopped by the pay ceiling (80) but lateral growth continues and productivity slows down as the slope of the chamber walls (61) decrease.
  • As discussed above, the choice of increasing temperature in SAGD may reduce process efficiency for two reasons. Since bitumen is produced at/near saturated steam temperature, it is predominantly the latent heat of steam that drives the SAGD process. As pressure and temperature are increased, the latent heat content in saturated steam drops (as best seen in FIG. 4), so efficiency is lost. Also, at higher temperature and pressure conditions, the reservoir matrix requires heating to higher temperatures. This increased heat demand also reduces efficiencies.
  • The “thermal pulse” remediation process (TPP) of the present invention may be applied to a SAGD process with at least one cold spot in a production well, as follows:
      • (1) shut-in the production well;
      • (2) increase or maintain steam injection rates;
      • (3) when pressure increases up to about 0.5 MPa (a few days or a week), produce the production well at/near maximum rates (gas lift or ESP) for a few days, up to about 1 week; and
      • (4) Restart normal SAGD operations optionally monitoring the at least one cold spot temperature.
  • Although not wanting to be limited by the following, it is believed the invention is effective due to as follows:
      • a. during the shut-in/steam injection phases ((1) and (2) above), steam will displace water in the zone proximate the at least one cold spot;
      • b. hot production fluids (hot bitumen+condensed steam) builds up at/near the bottom of the steam chamber;
      • c. during the production phase (3) above), steam is removed quickly from the water zone creating a cold spot and before recharging by cold water can occur, hot production fluids (hot bitumen+condensed steam) will be drawn into the zone with the cold spot; and
      • d. the hot production fluids inhibit recharging by cold water.
  • The present invention relies firstly on a slow/limited recharge rate of cold water and a fast saturation with hot production fluids. Secondly, the remediation based on the present invention may be temporary or permanent depending on the reservoir type and operating strategy following remediation. Thirdly, if the water recharge rate is rapid (i.e. Type C reservoir) the present invention may not produce ideal results. Fourth, the present invention relies on ability to increase reservoir pressure. Again, this condition may not produce ideal results for a Type C reservoir.
  • EXAMPLE 1
      • (1) A field test of the thermal pulse process (TPP) according to the present invention in a SAGD well pair near Long Lake, Alberta was conducted over a period of two days. The pressure pulse for the test was about 260 kPa during the two day test. Prior to the test, the steam injector pressure was about 2000 kPa (saturated steam temperature=213° C.).
  • FIGS. 5-8 show process measurements over the two day testing period.
  • As best seen in FIG. 5, prior to incorporating the remediation process in an existing SAGD well pair, the thermocouples in the heel of the producer well registered temperatures from about 140° C. to 160° C. Given the temperature of saturated steam is about 213° C., the temperature fluctuation of from about 140° C. to 160° C. indicates a cold spot is present in the heel of the producer well, given the heel zone is expected to be hot given the heel zone is the first zone to receive steam and collects all the production fluids. It is also observed that subsequent to the remediation process, the heel temperature rose quickly to between 180° C. and 190° C. and this increased temperature was maintained for a period of time. As best seen in FIGS. 6, 7, 8 and 9, the oil recovery rate increased concurrently with remediation of the cold spot. Referring now to FIGS. 7 and 9, the SOR varies considerably. FIG. 9 shows the total history of the well pair prior to, during, and post testing. SAGD was initiated in January 2008. The SAGD pair was in the ramp-up phase of SAGD. As best seen in FIG. 10, the instrumentation in the well pair (10, 20) is shown, including 6 thermocouples (90) in the production well, pressure measurement at the producer heel (100) and toe (110) and at the injector heel (120) subsequent to implementation of the present invention.
  • It is clear from the above that the current invention increases productivity in SAGD processes when a producer well has at least one cold spot.
  • Preferably, when incorporating the present invention in a type B reservoir, it is preferred that there are limited leaks and there is some ability to increase pressure; when incorporating the present invention during the ramp-up phase of SAGD, it is preferred to remediate the cold spot(s) as early as possible; it is preferred to limit repressurization to no more than about +0.5MPa; and the cold spot in the production well is preferably greater than about 10° C. below sub cool target temperature.
  • As many changes can be made to the preferred embodiment of the invention without departing from the scope thereof; it is intended that all matter contained herein be considered illustrative of the invention and not in a limiting sense.

Claims (13)

1. A method for remediation of at least one cold spot in a producer well in a Steam Assisted Gravity Drainage (SAGD) process, to increase hydrocarbon recovery from a hydrocarbon reservoir, said SAGD process occurring at a site comprising an injection well, a production well, and a steam chamber, wherein said method comprises:
(a) shutting the production well;
(b) maintaining or increasing steam injection through the injection well until pressure in the steam chamber increases;
(c) resuming the production well while continuing steam injection at rates for normal SAGD or greater, until reservoir pressure reaches normal operational pressure; and optionally
(d) adjusting injection/production to return to normal SAGD operation.
2. The method of claim 1 wherein the pressure in the steam chamber increases up to about 0.5 MPa.
3. The method of claim 1 wherein the at least one cold spot has a temperature of about 10° C. to 20° C. lower than a SAGD sub cool target temperature.
4. The method of claim 1 wherein the at least one cold spot is formed by cold water incursion from a water zone in said reservoir.
5. The method of claim 4 wherein the cold water incursion has a water recharge rate from the water zone of less that about 500 m3/d.
6. The method of claim 1 wherein the reservoir is a heterogeneous Type B reservoir.
7. The method of claim 1 wherein the reservoir is a homogeneous Type A reservoir.
8. The method of claim 1 wherein the reservoir is a homogeneous Type C reservoir.
9. The method of claim 4 wherein the cold water incursion has a water recharge rate from the water zone of less than about 50 m3/d.
10. The method of claim 1 wherein the pressure in the steam chamber pressure increases up to less than or equal to about 0.3 MPa.
11. The method of claim 3 wherein the at least one cold spot is at least about 20° C. lower than SAGD sub cool target temperature.
12. The method of claim 2 wherein the at least one cold spot is formed by cold water incursion from a water zone in said reservoir.
13. The method of claim 3 wherein the at least one cold spot is formed by cold water incursion from a water zone in said reservoir.
US13/912,463 2012-06-08 2013-06-07 Thermal pulsing procedure for remediation of cold spots in steam assisted gravity drainage Abandoned US20130327525A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US13/912,463 US20130327525A1 (en) 2012-06-08 2013-06-07 Thermal pulsing procedure for remediation of cold spots in steam assisted gravity drainage

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US201261657071P 2012-06-08 2012-06-08
US13/912,463 US20130327525A1 (en) 2012-06-08 2013-06-07 Thermal pulsing procedure for remediation of cold spots in steam assisted gravity drainage

Publications (1)

Publication Number Publication Date
US20130327525A1 true US20130327525A1 (en) 2013-12-12

Family

ID=49711243

Family Applications (1)

Application Number Title Priority Date Filing Date
US13/912,463 Abandoned US20130327525A1 (en) 2012-06-08 2013-06-07 Thermal pulsing procedure for remediation of cold spots in steam assisted gravity drainage

Country Status (3)

Country Link
US (1) US20130327525A1 (en)
CA (1) CA2818293A1 (en)
WO (1) WO2013181750A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150354330A1 (en) * 2014-05-30 2015-12-10 Suncor Energy Inc. In situ hydrocarbon recovery using distributed flow control devices for enhancing temperature conformance

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105273750B (en) * 2014-12-16 2017-03-22 新疆科力新技术发展股份有限公司 Supper heavy oil SAGD circulation preheating liquid processing system
CN106545321B (en) * 2015-09-18 2019-06-07 中国石油化工股份有限公司 A kind of method and its application of the gravity auxiliary displacement of reservoir oil

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3946810A (en) * 1973-05-24 1976-03-30 The Ralph M. Parsons Company In situ recovery of hydrocarbons from tar sands
US4612989A (en) * 1985-06-03 1986-09-23 Exxon Production Research Co. Combined replacement drive process for oil recovery
US4961467A (en) * 1989-11-16 1990-10-09 Mobil Oil Corporation Enhanced oil recovery for oil reservoir underlain by water
US4986352A (en) * 1989-09-28 1991-01-22 Mobil Oil Corporation Intermittent steam injection
US5215146A (en) * 1991-08-29 1993-06-01 Mobil Oil Corporation Method for reducing startup time during a steam assisted gravity drainage process in parallel horizontal wells
US20030196789A1 (en) * 2001-10-24 2003-10-23 Wellington Scott Lee In situ thermal processing of a hydrocarbon containing formation and upgrading of produced fluids prior to further treatment
US20060175061A1 (en) * 2005-08-30 2006-08-10 Crichlow Henry B Method for Recovering Hydrocarbons from Subterranean Formations
US20090260809A1 (en) * 2008-04-18 2009-10-22 Scott Lee Wellington Method for treating a hydrocarbon containing formation

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4819724A (en) * 1987-09-03 1989-04-11 Texaco Inc. Modified push/pull flood process for hydrocarbon recovery
US5626193A (en) * 1995-04-11 1997-05-06 Elan Energy Inc. Single horizontal wellbore gravity drainage assisted steam flooding process
US5931230A (en) * 1996-02-20 1999-08-03 Mobil Oil Corporation Visicous oil recovery using steam in horizontal well

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3946810A (en) * 1973-05-24 1976-03-30 The Ralph M. Parsons Company In situ recovery of hydrocarbons from tar sands
US4612989A (en) * 1985-06-03 1986-09-23 Exxon Production Research Co. Combined replacement drive process for oil recovery
US4986352A (en) * 1989-09-28 1991-01-22 Mobil Oil Corporation Intermittent steam injection
US4961467A (en) * 1989-11-16 1990-10-09 Mobil Oil Corporation Enhanced oil recovery for oil reservoir underlain by water
US5215146A (en) * 1991-08-29 1993-06-01 Mobil Oil Corporation Method for reducing startup time during a steam assisted gravity drainage process in parallel horizontal wells
US20030196789A1 (en) * 2001-10-24 2003-10-23 Wellington Scott Lee In situ thermal processing of a hydrocarbon containing formation and upgrading of produced fluids prior to further treatment
US20060175061A1 (en) * 2005-08-30 2006-08-10 Crichlow Henry B Method for Recovering Hydrocarbons from Subterranean Formations
US20090260809A1 (en) * 2008-04-18 2009-10-22 Scott Lee Wellington Method for treating a hydrocarbon containing formation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Edmunds, "Investigation of SAGD Steam Trap Control in Two and Three Dimensions" Society of Petroleum Engineers (1998) *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150354330A1 (en) * 2014-05-30 2015-12-10 Suncor Energy Inc. In situ hydrocarbon recovery using distributed flow control devices for enhancing temperature conformance
US9702233B2 (en) * 2014-05-30 2017-07-11 Suncor Energy Inc. In situ hydrocarbon recovery using distributed flow control devices for enhancing temperature conformance

Also Published As

Publication number Publication date
WO2013181750A1 (en) 2013-12-12
CA2818293A1 (en) 2013-12-08

Similar Documents

Publication Publication Date Title
CA2757125C (en) Establishing communication between well pairs in oil sands by dilation with steam or water circulation at elevated pressures
US20140000876A1 (en) Sagd control in leaky reservoirs
US5931230A (en) Visicous oil recovery using steam in horizontal well
US9033039B2 (en) Producer snorkel or injector toe-dip to accelerate communication between SAGD producer and injector
US7090014B2 (en) Process for sequentially applying SAGD to adjacent sections of a petroleum reservoir
WO2019218798A1 (en) Extra-heavy oil development method for strengthening sagd steam chamber so as to break through low-physical-property reservoir
US20110272152A1 (en) Operating Wells In Groups In Solvent-Dominated Recovery Processes
US20130327525A1 (en) Thermal pulsing procedure for remediation of cold spots in steam assisted gravity drainage
US20140000887A1 (en) Sagdox operation in leaky bitumen reservoirs
CN105178931B (en) Method for improving initial production speed of SAGD (steam assisted gravity drainage)
RU2431744C1 (en) Procedure for extraction of high viscous oil and bitumen with application of horizontal producing and horizontal-inclined wells
US20160061014A1 (en) Hydraulically unitary well system and recovery process (huwsrp)
CN104141479B (en) The thermal process of a kind of carbonate rock heavy crude reservoir and application thereof
WO2000025002A1 (en) Process for sequentially applying sagd to adjacent sections of a petroleum reservoir
RU2440489C1 (en) Development method of high-viscosity oil deposit
CA2902591C (en) Axially segmented depletion operations in horizontal wells
US20150198023A1 (en) Systems and methods for producing viscous hydrocarbons
CN109025920A (en) Method for improving yield of horizontal well in low-permeability oil field
RU2720725C1 (en) Development method of super-viscous oil deposit
RU2486335C1 (en) Method of development for ultraviscous oil deposits with thermal influence
CA2313837C (en) Positioning of the tubing string in a steam injection well
CN105756643B (en) SAGD horizontal well system and starting method thereof
CN108643874A (en) A kind of oil production method of cold and hot pulse alternate water injection
Kyanpour Kalkhajeh Thermal energy distribution in the steam assisted gravity drainage
CA2240786C (en) Viscous oil recovery using steam in horizontal well

Legal Events

Date Code Title Description
AS Assignment

Owner name: NEXEN INC., CANADA

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:YANG, PETER;KERR, RICHARD KELSO;SIGNING DATES FROM 20130430 TO 20130606;REEL/FRAME:030567/0001

AS Assignment

Owner name: NEXEN ENERGY INC., CANADA

Free format text: CERTIFICATE OF CONTINUATION;ASSIGNOR:NEXEN INC.;REEL/FRAME:031644/0988

Effective date: 20130618

Owner name: NEXEN ENERGY ULC, CANADA

Free format text: CHANGE OF NAME;ASSIGNOR:NEXEN ENERGY INC.;REEL/FRAME:031611/0627

Effective date: 20130618

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION

AS Assignment

Owner name: CNOOC PETROLEUM NORTH AMERICA ULC, CANADA

Free format text: CHANGE OF NAME;ASSIGNOR:NEXEN ENERGY ULC;REEL/FRAME:048366/0576

Effective date: 20181231