US20110016644A1 - Scour preventive apparatus for pier foundation - Google Patents

Scour preventive apparatus for pier foundation Download PDF

Info

Publication number
US20110016644A1
US20110016644A1 US12/922,507 US92250709A US2011016644A1 US 20110016644 A1 US20110016644 A1 US 20110016644A1 US 92250709 A US92250709 A US 92250709A US 2011016644 A1 US2011016644 A1 US 2011016644A1
Authority
US
United States
Prior art keywords
pier foundation
flow
plate
preventive apparatus
flow guide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US12/922,507
Inventor
Deok-Rae Jo
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of US20110016644A1 publication Critical patent/US20110016644A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B1/00Equipment or apparatus for, or methods of, general hydraulic engineering, e.g. protection of constructions against ice-strains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/0017Means for protecting offshore constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/60Piles with protecting cases

Definitions

  • the present invention relates to a scour preventive apparatus for a pier foundation.
  • a bridge is installed at a river, a lake, and so on and means a high-level structure which vehicles or people can cross.
  • the bridge is largely divided into an upper portion and a lower portion.
  • the upper portion of the bridge is a part directly supporting load of the vehicles or the people, and includes an upper floor system and a mold.
  • the lower portion of the bridge transmits the load of the upper portion to the ground, and includes an abutment, a pier, and a foundation (pile foundation, caisson foundation, and so on).
  • bridge scour occurs at the foundation or the pier by the flowing fluid.
  • Scour means the phenomena that a river bed or a river bank caves in by the fluid, and occurs in a case that amount of earth and sand removed from the foundation which is the lower portion of the bridge is larger than that of earth and sand deposited around the foundation.
  • flows of the river rubbing the pier foundation can be largely divided into two flows.
  • FIG. 1 to FIG. 3 shows occurrence of erosion and scour at the pier foundation.
  • the flows of the river are divided into a direct flow a directly rubbing the foundation 20 and an indirect flow b flowing around the foundation 20 .
  • the direct flow a initially rubs an exterior circumference of the foundation 20 and is separated into two flows. After that, the two flows flow symmetrically along the exterior circumference of the pier foundation and are rubbed and mixed with each other at a rear exterior circumference of the pier foundation such that vortex c occurs.
  • small stones and pebbles lying on the ground are floated by the vortex c and hit against the foundation 20 .
  • Scour occurs by the vortex c occurring as such, and erosion occurs at the ground of the river. Strength of the foundation 20 is weakened by such phenomena, and this becomes causes of collapse of the bridge.
  • An objective of the present invention is that the scour preventive apparatus is installed near the ground of a pier foundation and collects a direct flow of a river directly rubbing the pier and an indirect flow flowing around the pier as one flow such that the flow of the river is stopped at a lower portion of the pier foundation and rub between an exterior circumference of the pier and the flow of the river can be prevented.
  • Another objective of the present invention is that flowing speed of the river is changed to zero by the scour preventive apparatus installed at the ground of the pier so as to prevent erosion of the ground of the pier foundation.
  • a scour preventive apparatus for a pier foundation is the scour preventive apparatus for a pier foundation supporting load of the bridge, and may include a cover plate covering the pier foundation and formed of a plurality of holes, a first flow guide plate having a side connected to a surface of the cover plate, disposed apart from the pier foundation by a predetermined distance, and formed of a plurality of first flow holes, a second flow guide plate having a side connected to the surface of the cover plate, disposed apart from the pier foundation by the predetermined distance, and formed of a plurality of second flow holes, and a blocking plate connecting the first flow guide plate with the second flow guide plate and blocking a flow of fluid, wherein the first flow guide plate and the second flow guide plate are symmetrical to each other with respect to the pier foundation.
  • cover plate may include a first plate member and a second plate member, and the first plate member and the second plate member may be detachable from each other.
  • a bottom plate covering the pier foundation and having one surface laying on the ground and the other surface connected to the flow guide plates and the blocking plate may further be included.
  • the bottom plate may include a third plate member and a fourth plate member, and the third plate member and the fourth plate member may be detachable from each other.
  • An underwater barrage having one side contacting with the blocking plate may further be included, wherein thickness of the one side of the underwater barrage is larger than that of the other side of the underwater barrage.
  • a plurality of dispersing protrusions disposed apart from the other side of the underwater barrage by a predetermined distance may further be included.
  • a surface of the blocking plate where the fluid bumps may be a curved surface.
  • a flow separator abutting an exterior circumference of the pier foundation and having flow-separating surfaces being round and symmetrical to each other may further be included so as to prevent the fluid from rubbing the pier foundation directly.
  • a rubber layer may be formed on surfaces of the flow guide plates.
  • FIG. 1 is a perspective view showing occurrence of erosion and scour at a conventional pier foundation.
  • FIG. 2 is a floor plan showing occurrence of scour at a conventional pier foundation.
  • FIG. 3 is a front view showing occurrence of scour at a conventional pier foundation.
  • FIG. 4 is a perspective view showing an installed state of a scour preventive apparatus according to an exemplary embodiment of the present invention at a pier foundation.
  • FIG. 5 is a front view showing an installed state of a scour preventive apparatus according to an exemplary embodiment of the present invention at a pier foundation.
  • FIG. 6 is an enlarged front view showing an installed state of a scour preventive apparatus according to an exemplary embodiment of the present invention at a pier foundation.
  • FIG. 7 is a perspective view showing an installed state of a scour preventive apparatus and a flow separator according to another exemplary embodiment of the present invention at a pier foundation.
  • FIG. 8 is a cross-sectional floor plan view showing an installed state of a scour preventive apparatus and a flow separator according to another exemplary embodiment of the present invention at a pier foundation.
  • FIG. 9 is a perspective view showing an installed state of a scour preventive apparatus according to another exemplary embodiment of the present invention at a pier foundation.
  • FIG. 10 is a cross-sectional front view showing an installed state of a scour preventive apparatus according to another exemplary embodiment of the present invention at a pier foundation.
  • pier foundation 20 foundation 100: scour preventive apparatus 110: first flow guide plate 110′: second flow guide plate 111: first flow hole 111′: second flow hole 112: rubber layer 120: blocking plate 121: vortex-forming protrusion 130: underwater barrage 131: slanted surface 132: dispersing protrusion 140: bottom plate 140a: first plate member 140b: second plate member 150: flow separator 151: flow-separating surface 160: cover plate 160a: third plate member 160b: fourth plate member 161: through-hole 162: inner space a: direct flow b: indirect flow c: vortex
  • FIG. 4 is a perspective view showing an installed state of a scour preventive apparatus according to an exemplary embodiment of the present invention at a pier foundation.
  • FIG. 5 is a front view showing an installed state of a scour preventive apparatus according to an exemplary embodiment of the present invention at a pier foundation
  • FIG. 6 is an enlarged front view showing an installed state of a scour preventive apparatus according to an exemplary embodiment of the present invention at a pier foundation.
  • FIG. 9 is a perspective view showing an installed state of a scour preventive apparatus according to another exemplary embodiment of the present invention at a pier foundation
  • FIG. 10 is a cross-sectional front view showing an installed state of a scour preventive apparatus according to another exemplary embodiment of the present invention at a pier foundation.
  • a scour preventive apparatus 100 protects a pier foundation 10 by covering the pier foundation 10 .
  • Constituent elements of an exemplary embodiment include a cover plate 160 , a first flow guide plate 110 , a second flow guide plate 110 ′, and a blocking plate 120 .
  • a bottom plate 140 an underwater barrage 130 , and a dispersing protrusion 132 are further included.
  • the cover plate 160 covers the pier foundation 10 .
  • the cover plate 160 includes detachable plate members 160 a and 160 b .
  • the plate members 160 a and 160 b can be assembled by insertedly coupling a protrusion portion and an insert portion formed respectively at the plate members 160 a and 160 b or by welding.
  • a plurality of through-holes 163 and 161 is formed at the cover plate 160 .
  • the first flow guide plate 110 and the second flow guide plate 110 ′ respectively have a side connected to a surface of the cover plate 160 and are disposed apart from the pier foundation 10 by a predetermined distance.
  • the first and second flow guide plates 110 and 110 ′ are symmetrical to each other with respect to the pier foundation 10 .
  • first flow holes 111 and second flow holes 111 ′ are formed respectively at the first flow guide plate 110 and the second flow guide plate 110 ′.
  • a rubber layer 112 is coated on surfaces of the first flow guide plate 110 and the second flow guide plate 110 ′.
  • the rubber layer 112 protects the scour preventive apparatus 100 according to an exemplary embodiment from sand and stone swept by fluid.
  • the blocking plate 120 is connected to the first flow guide plate 110 and the second flow guide plate 110 ′. At this time, a surface of the blocking plate 120 is a curved surface.
  • the bottom plate 140 covers the pier foundation 10 , and has one surface laying on the ground and the other surface connected to the first flow guide plate 110 , the second flow guide plate 110 ′, and the blocking plate 120 .
  • the bottom plate 140 includes detachable plate members 140 a and 140 b . This is for facilitating covering the pier foundation 10 , too.
  • the bottom plate 140 may not be used.
  • the first flow guide plate 110 and the second flow guide plate 110 ′ are disposed vertically at both sides of the bottom plate 140 along a flowing direction of the fluid according to an exemplary scour preventive apparatus 100 .
  • the blocking plate 120 is disposed vertically at the rear of the bottom plate 140 .
  • the cover plate 160 is connected on an upper surfaces of the first flow guide plate 110 , the second flow guide plate 110 ′, and the blocking plate 120 .
  • An inner space 162 is formed among the constituent elements in the scour preventive apparatus 100 according to an exemplary embodiment where the constituent elements are connected as described above.
  • a front portion of the bottom plate 140 is open, and the fluid flows in the inner space 162 through the front portion of the bottom plate 140 .
  • the inflow fluid stays in the inner space 162 in a state that a flowing speed thereof is zero by the blocking plate 120 .
  • a direct flow a and an indirect flow b of a river is not generated in the inner space 162 . Accordingly, the scour generated by repetitive rub of the fluid at the rear portion of the exterior circumference of the pier foundation 10 can be prevented.
  • first flow hole 111 , the second flow hole 111 ′, and a plurality of holes 163 are formed respectively at the first flow guide plate 110 , the second flow guide plate 110 ′, and the cover plate 160 so as to prevent increase of hydraulic pressure in the inner space 162 by the fluid continuously flowed in the inner space 162 .
  • the hydraulic pressure in the inner space 162 is controlled not to increase.
  • the surface of the blocking plate 120 where the fluid bumps is a curved surface
  • the fluid flowed in the inner space 162 rotates along the curved surface.
  • the vortex c is formed in the inner space 162 and the hydraulic pressure in the inner space 162 may be reduced.
  • an exemplary embodiment further includes an underwater barrage 130 having a slanted surface 131 connected to the rear portion of the blocking plate 120 . According to the slanted surface 131 , thickness of a side contacting with a side of the blocking plate 120 is larger than that of the other side.
  • the underwater barrage 130 controls the fluid partly flowing out through the first flow hole 111 , the second flow hole 111 ′, and the holes 163 and the fluid flowing along the upper surface of the cover plate 160 to flow quickly toward the rear of the pier foundation 10 along the slanted surface 131 of the underwater barrage 130 .
  • the hydraulic overload may be caused by the fluid with an inverse flow direction or with a slow flow speed.
  • an exemplary embodiment further includes a plurality of dispersing protrusions 132 disposed apart from the other side of the underwater barrage 130 by a predetermined distance.
  • the plurality of protrusions 132 with multiple rows is sequentially protruded.
  • the dispersing protrusions 132 disperse the flow of the fluid flowing along the slanted surface 131 of the underwater barrage 130 . Since dispersing protrusions 132 disperse the flow of the fluid, erosion of the ground at the rear of the underwater barrage 130 can be prevented.
  • the scour preventive apparatus 100 is installed at the pier foundation 10 mounted on the ground of the river, collapse of the exterior circumference of the pier foundation 10 can be prevented and the erosion of the ground near the pier foundation 10 can be prevented.
  • This has a merit that solidity and bearing strength of the pier foundation 10 can be maintained for a very long time in spite of overflow of the river.
  • the flow speed near an inlet portion of the inner space 162 to which the fluid is supplied prevents occurrence of overload to the stopped fluid according to the scour preventive apparatus 100 .
  • FIG. 7 is a perspective view showing an installed state of a scour preventive apparatus and a flow separator according to another exemplary embodiment of the present invention at a pier foundation
  • FIG. 8 is a cross-sectional floor plan view showing an installed state of a scour preventive apparatus and a flow separator according to another exemplary embodiment of the present invention at a pier foundation.
  • Constituent elements of another exemplary embodiment of the present invention are similar to those of an exemplary embodiments described above referring to FIG. 4 to FIG. 6 , FIG. 9 and FIG. 10 , and detailed description thereof will be omitted.
  • a flow separator 150 provided with flow-separating surfaces 151 having round shape and being symmetrical to each other is mounted at the exterior circumference of the pier foundation 10 which receives the flow of an upstream of the river so as to separate the flow of the river. Therefore, it is prevented that the flow of the upstream of the river directly rubs the pier foundation.
  • a scour preventive apparatus for a pier foundation is installed near the ground of the pier foundation and collects the direct flow of the river directly rubbing the pier and the indirect flow flowing around the pier as one flow such that the flow of the river is stopped at a lower portion of the pier foundation and rub between the exterior circumference of the pier and the flow of the river can be prevented. Therefore, erosion of the pier foundation can be prevented.
  • the erosion of the ground of the pier foundation can be prevented by installing the scour preventive apparatus at the ground of the pier.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Bridges Or Land Bridges (AREA)
  • Foundations (AREA)
  • Revetment (AREA)

Abstract

A scour preventive apparatus for a pier foundation according to an exemplary embodiment of the present invention is the scour preventive apparatus for a pier foundation supporting load of the bridge, and may include a cover plate covering the pier foundation and formed of a plurality of holes, a first flow guide plate having a side connected to a surface of the cover plate, disposed apart from the pier foundation by a predetermined distance, and formed of a plurality of first flow holes, a second flow guide plate having a side connected to the surface of the cover plate, disposed apart from the pier foundation by the predetermined distance, and formed of a plurality of second flow holes, and a blocking plate connecting the first flow guide plate with the second flow guide plate and blocking a flow of fluid, wherein the first flow guide plate and the second flow guide plate are symmetrical to each other with respect to the pier foundation.

Description

    TECHNICAL FIELD
  • The present invention relates to a scour preventive apparatus for a pier foundation.
  • BACKGROUND ART
  • Generally, a bridge is installed at a river, a lake, and so on and means a high-level structure which vehicles or people can cross. The bridge is largely divided into an upper portion and a lower portion. The upper portion of the bridge is a part directly supporting load of the vehicles or the people, and includes an upper floor system and a mold. The lower portion of the bridge transmits the load of the upper portion to the ground, and includes an abutment, a pier, and a foundation (pile foundation, caisson foundation, and so on).
  • At this time, bridge scour occurs at the foundation or the pier by the flowing fluid. Scour means the phenomena that a river bed or a river bank caves in by the fluid, and occurs in a case that amount of earth and sand removed from the foundation which is the lower portion of the bridge is larger than that of earth and sand deposited around the foundation. As shown in FIG. 1 to FIG. 3, flows of the river rubbing the pier foundation can be largely divided into two flows. FIG. 1 to FIG. 3 shows occurrence of erosion and scour at the pier foundation.
  • The flows of the river are divided into a direct flow a directly rubbing the foundation 20 and an indirect flow b flowing around the foundation 20. The direct flow a initially rubs an exterior circumference of the foundation 20 and is separated into two flows. After that, the two flows flow symmetrically along the exterior circumference of the pier foundation and are rubbed and mixed with each other at a rear exterior circumference of the pier foundation such that vortex c occurs. At this time, small stones and pebbles lying on the ground are floated by the vortex c and hit against the foundation 20. Scour occurs by the vortex c occurring as such, and erosion occurs at the ground of the river. Strength of the foundation 20 is weakened by such phenomena, and this becomes causes of collapse of the bridge.
  • The above information disclosed in this Background section is only for enhancement of understanding of the background of the invention and therefore it may contain information that does not form the prior art that is already known in this country to a person of ordinary skill in the art.
  • SUMMARY OF THE INVENTION
  • An objective of the present invention is that the scour preventive apparatus is installed near the ground of a pier foundation and collects a direct flow of a river directly rubbing the pier and an indirect flow flowing around the pier as one flow such that the flow of the river is stopped at a lower portion of the pier foundation and rub between an exterior circumference of the pier and the flow of the river can be prevented.
  • In addition, another objective of the present invention is that flowing speed of the river is changed to zero by the scour preventive apparatus installed at the ground of the pier so as to prevent erosion of the ground of the pier foundation.
  • Also, other objective of the present invention is that overload that may occur in the scour preventive apparatus maintaining the flow speed to be zero is minimized.
  • Further, other objective of the present invention is that the flow of the river passing through a flow hole and an upper surface of a blocking plate for preventing the overload of the scour preventive apparatus quickly flows to the rear of the pier foundation.
  • A scour preventive apparatus for a pier foundation according to an exemplary embodiment of the present invention is the scour preventive apparatus for a pier foundation supporting load of the bridge, and may include a cover plate covering the pier foundation and formed of a plurality of holes, a first flow guide plate having a side connected to a surface of the cover plate, disposed apart from the pier foundation by a predetermined distance, and formed of a plurality of first flow holes, a second flow guide plate having a side connected to the surface of the cover plate, disposed apart from the pier foundation by the predetermined distance, and formed of a plurality of second flow holes, and a blocking plate connecting the first flow guide plate with the second flow guide plate and blocking a flow of fluid, wherein the first flow guide plate and the second flow guide plate are symmetrical to each other with respect to the pier foundation.
  • In addition, the cover plate may include a first plate member and a second plate member, and the first plate member and the second plate member may be detachable from each other.
  • In addition, a bottom plate covering the pier foundation and having one surface laying on the ground and the other surface connected to the flow guide plates and the blocking plate may further be included.
  • In addition, the bottom plate may include a third plate member and a fourth plate member, and the third plate member and the fourth plate member may be detachable from each other.
  • An underwater barrage having one side contacting with the blocking plate may further be included, wherein thickness of the one side of the underwater barrage is larger than that of the other side of the underwater barrage.
  • In addition, a plurality of dispersing protrusions disposed apart from the other side of the underwater barrage by a predetermined distance may further be included.
  • In addition, a surface of the blocking plate where the fluid bumps may be a curved surface.
  • A flow separator abutting an exterior circumference of the pier foundation and having flow-separating surfaces being round and symmetrical to each other may further be included so as to prevent the fluid from rubbing the pier foundation directly.
  • In addition, a rubber layer may be formed on surfaces of the flow guide plates.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • FIG. 1 is a perspective view showing occurrence of erosion and scour at a conventional pier foundation.
  • FIG. 2 is a floor plan showing occurrence of scour at a conventional pier foundation.
  • FIG. 3 is a front view showing occurrence of scour at a conventional pier foundation.
  • FIG. 4 is a perspective view showing an installed state of a scour preventive apparatus according to an exemplary embodiment of the present invention at a pier foundation.
  • FIG. 5 is a front view showing an installed state of a scour preventive apparatus according to an exemplary embodiment of the present invention at a pier foundation.
  • FIG. 6 is an enlarged front view showing an installed state of a scour preventive apparatus according to an exemplary embodiment of the present invention at a pier foundation.
  • FIG. 7 is a perspective view showing an installed state of a scour preventive apparatus and a flow separator according to another exemplary embodiment of the present invention at a pier foundation.
  • FIG. 8 is a cross-sectional floor plan view showing an installed state of a scour preventive apparatus and a flow separator according to another exemplary embodiment of the present invention at a pier foundation.
  • FIG. 9 is a perspective view showing an installed state of a scour preventive apparatus according to another exemplary embodiment of the present invention at a pier foundation.
  • FIG. 10 is a cross-sectional front view showing an installed state of a scour preventive apparatus according to another exemplary embodiment of the present invention at a pier foundation.
  • DESCRIPTION OF REFERENCE NUMERALS INDICATING PRIMARY ELEMENTS IN THE DRAWINGS
  •  10: pier foundation  20: foundation
    100: scour preventive apparatus
    110: first flow guide plate 110′: second flow guide plate
    111: first flow hole 111′: second flow hole
    112: rubber layer 120: blocking plate
    121: vortex-forming protrusion 130: underwater barrage
    131: slanted surface 132: dispersing protrusion
    140: bottom plate 140a: first plate member
    140b: second plate member 150: flow separator
    151: flow-separating surface 160: cover plate
    160a: third plate member 160b: fourth plate member
    161: through-hole 162: inner space
    a: direct flow b: indirect flow
    c: vortex
  • DETAILED DESCRIPTION OF THE INVENTION
  • Hereinafter, an exemplary embodiment of the present invention will be described in detail with reference to the attached drawings.
  • Firstly, it is kept in mind that the same constituent elements or components will be represented by the same reference numerals in the drawings. When explaining the present invention, a detailed description related to well-known functions or components will be omitted so as to prevent the spirit of the present invention from being obscured.
  • FIG. 4 is a perspective view showing an installed state of a scour preventive apparatus according to an exemplary embodiment of the present invention at a pier foundation. FIG. 5 is a front view showing an installed state of a scour preventive apparatus according to an exemplary embodiment of the present invention at a pier foundation, and FIG. 6 is an enlarged front view showing an installed state of a scour preventive apparatus according to an exemplary embodiment of the present invention at a pier foundation. In addition, FIG. 9 is a perspective view showing an installed state of a scour preventive apparatus according to another exemplary embodiment of the present invention at a pier foundation, and FIG. 10 is a cross-sectional front view showing an installed state of a scour preventive apparatus according to another exemplary embodiment of the present invention at a pier foundation.
  • As shown in FIG. 4 to FIG. 6, FIG. 9 and FIG. 10, a scour preventive apparatus 100 according to an exemplary embodiment protects a pier foundation 10 by covering the pier foundation 10.
  • Constituent elements of an exemplary embodiment include a cover plate 160, a first flow guide plate 110, a second flow guide plate 110′, and a blocking plate 120. In addition, a bottom plate 140, an underwater barrage 130, and a dispersing protrusion 132 are further included.
  • Firstly, the cover plate 160 covers the pier foundation 10. At this time, the cover plate 160 includes detachable plate members 160 a and 160 b. The plate members 160 a and 160 b can be assembled by insertedly coupling a protrusion portion and an insert portion formed respectively at the plate members 160 a and 160 b or by welding.
  • This is for facilitating covering the pier foundation 10. In addition, a plurality of through- holes 163 and 161 is formed at the cover plate 160.
  • The first flow guide plate 110 and the second flow guide plate 110′ respectively have a side connected to a surface of the cover plate 160 and are disposed apart from the pier foundation 10 by a predetermined distance. The first and second flow guide plates 110 and 110′ are symmetrical to each other with respect to the pier foundation 10. At this time, first flow holes 111 and second flow holes 111′ are formed respectively at the first flow guide plate 110 and the second flow guide plate 110′.
  • In addition, a rubber layer 112 is coated on surfaces of the first flow guide plate 110 and the second flow guide plate 110′. The rubber layer 112 protects the scour preventive apparatus 100 according to an exemplary embodiment from sand and stone swept by fluid.
  • The blocking plate 120 is connected to the first flow guide plate 110 and the second flow guide plate 110′. At this time, a surface of the blocking plate 120 is a curved surface.
  • The bottom plate 140 covers the pier foundation 10, and has one surface laying on the ground and the other surface connected to the first flow guide plate 110, the second flow guide plate 110′, and the blocking plate 120. The bottom plate 140 includes detachable plate members 140 a and 140 b. This is for facilitating covering the pier foundation 10, too. The bottom plate 140 may not be used.
  • After the bottom plate 140 is disposed on the ground of the pier foundation 10, the first flow guide plate 110 and the second flow guide plate 110′ are disposed vertically at both sides of the bottom plate 140 along a flowing direction of the fluid according to an exemplary scour preventive apparatus 100. The blocking plate 120 is disposed vertically at the rear of the bottom plate 140. In addition, the cover plate 160 is connected on an upper surfaces of the first flow guide plate 110, the second flow guide plate 110′, and the blocking plate 120. An inner space 162 is formed among the constituent elements in the scour preventive apparatus 100 according to an exemplary embodiment where the constituent elements are connected as described above. In addition, a front portion of the bottom plate 140 is open, and the fluid flows in the inner space 162 through the front portion of the bottom plate 140.
  • If the fluid flows in the inner space 162, the inflow fluid stays in the inner space 162 in a state that a flowing speed thereof is zero by the blocking plate 120. At this time, as the fluid flowed in the inner space 162 is stopped, a direct flow a and an indirect flow b of a river is not generated in the inner space 162. Accordingly, the scour generated by repetitive rub of the fluid at the rear portion of the exterior circumference of the pier foundation 10 can be prevented.
  • In addition, the first flow hole 111, the second flow hole 111′, and a plurality of holes 163 are formed respectively at the first flow guide plate 110, the second flow guide plate 110′, and the cover plate 160 so as to prevent increase of hydraulic pressure in the inner space 162 by the fluid continuously flowed in the inner space 162. As a consequence that the fluid of the inner space 162 flows out through the first flow hole 111, the second flow hole 111′, and the holes 163, the hydraulic pressure in the inner space 162 is controlled not to increase.
  • In addition, since the surface of the blocking plate 120 where the fluid bumps is a curved surface, the fluid flowed in the inner space 162 rotates along the curved surface. Thereby, the vortex c is formed in the inner space 162 and the hydraulic pressure in the inner space 162 may be reduced.
  • In addition, an exemplary embodiment further includes an underwater barrage 130 having a slanted surface 131 connected to the rear portion of the blocking plate 120. According to the slanted surface 131, thickness of a side contacting with a side of the blocking plate 120 is larger than that of the other side.
  • The underwater barrage 130 controls the fluid partly flowing out through the first flow hole 111, the second flow hole 111′, and the holes 163 and the fluid flowing along the upper surface of the cover plate 160 to flow quickly toward the rear of the pier foundation 10 along the slanted surface 131 of the underwater barrage 130. This prevents hydraulic overload from being applied to the scour preventive apparatus 100. The hydraulic overload may be caused by the fluid with an inverse flow direction or with a slow flow speed.
  • In addition, an exemplary embodiment further includes a plurality of dispersing protrusions 132 disposed apart from the other side of the underwater barrage 130 by a predetermined distance. The plurality of protrusions 132 with multiple rows is sequentially protruded. The dispersing protrusions 132 disperse the flow of the fluid flowing along the slanted surface 131 of the underwater barrage 130. Since dispersing protrusions 132 disperse the flow of the fluid, erosion of the ground at the rear of the underwater barrage 130 can be prevented.
  • As described above, if the scour preventive apparatus 100 is installed at the pier foundation 10 mounted on the ground of the river, collapse of the exterior circumference of the pier foundation 10 can be prevented and the erosion of the ground near the pier foundation 10 can be prevented. This has a merit that solidity and bearing strength of the pier foundation 10 can be maintained for a very long time in spite of overflow of the river.
  • In addition, the flow speed near an inlet portion of the inner space 162 to which the fluid is supplied prevents occurrence of overload to the stopped fluid according to the scour preventive apparatus 100.
  • FIG. 7 is a perspective view showing an installed state of a scour preventive apparatus and a flow separator according to another exemplary embodiment of the present invention at a pier foundation, and FIG. 8 is a cross-sectional floor plan view showing an installed state of a scour preventive apparatus and a flow separator according to another exemplary embodiment of the present invention at a pier foundation. Constituent elements of another exemplary embodiment of the present invention are similar to those of an exemplary embodiments described above referring to FIG. 4 to FIG. 6, FIG. 9 and FIG. 10, and detailed description thereof will be omitted.
  • As shown in FIG. 7 and FIG. 8, a flow separator 150 provided with flow-separating surfaces 151 having round shape and being symmetrical to each other is mounted at the exterior circumference of the pier foundation 10 which receives the flow of an upstream of the river so as to separate the flow of the river. Therefore, it is prevented that the flow of the upstream of the river directly rubs the pier foundation.
  • A scour preventive apparatus for a pier foundation according the present invention is installed near the ground of the pier foundation and collects the direct flow of the river directly rubbing the pier and the indirect flow flowing around the pier as one flow such that the flow of the river is stopped at a lower portion of the pier foundation and rub between the exterior circumference of the pier and the flow of the river can be prevented. Therefore, erosion of the pier foundation can be prevented.
  • In addition, according to the scour preventive apparatus for the pier foundation of the present invention, the erosion of the ground of the pier foundation can be prevented by installing the scour preventive apparatus at the ground of the pier.
  • Also, since the overload in the scour preventive apparatus caused by stopping the flow at the pier foundation of the present invention is minimized, bearing strength of the scour preventive apparatus can be improved.
  • Further, since the flow of the river passing through the first and second flow holes and the upper surface of the blocking plate and preventing the overload in the scour preventive apparatus is flowed quickly toward the rear of the pier foundation according to the scour preventive apparatus for the pier foundation of the present invention, the flow direction of the river is not changed to an inverse direction by the scour preventive apparatus.
  • While this invention has been described in connection with what is presently considered to be practical exemplary embodiments, it is to be understood that the invention is not limited to the disclosed embodiments, but, on the contrary, is intended to cover various modifications and equivalent arrangements included within the spirit and scope of the appended claims.

Claims (9)

1. A scour preventive apparatus for a pier foundation supporting load of a bridge, comprising
a cover plate covering the pier foundation and formed of a plurality of holes,
a first flow guide plate having a side connected to a surface of the cover plate, disposed apart from the pier foundation by a predetermined distance, and formed of a plurality of first flow holes,
a second flow guide plate having a side connected to the surface of the cover plate, disposed apart from the pier foundation by the predetermined distance, and formed of a plurality of second flow holes, and
a blocking plate connecting the first flow guide plate with the second flow guide plate and blocking a flow of fluid,
wherein the first flow guide plate and the second flow guide plate are symmetrical to each other with respect to the pier foundation.
2. The scour preventive apparatus for a pier foundation of claim 1, wherein the cover plate comprises a first plate member and a second plate member, and the first plate member and the second plate member are detachable from each other.
3. The scour preventive apparatus for a pier foundation of claim 1, further comprising a bottom plate covering the pier foundation and having one surface laying on the ground and the other surface connected to the flow guide plates and the blocking plate.
4. The scour preventive apparatus for a pier foundation of claim 3, wherein the bottom plate comprises a third plate member and a fourth plate member, and the third plate member and the fourth plate member are detachable from each other.
5. The scour preventive apparatus for a pier foundation of claim 1, further comprising an underwater barrage having one side contacting with the blocking plate, wherein thickness of the one side of the underwater barrage is larger than that of the other side of the underwater barrage.
6. The scour preventive apparatus for a pier foundation of claim 5, further comprising a plurality of dispersing protrusions disposed apart from the other side of the underwater barrage by a predetermined distance.
7. The scour preventive apparatus for a pier foundation of claim 1, wherein a surface of the blocking plate where the fluid bumps is a curved surface.
8. The scour preventive apparatus for a pier foundation of claim 1, further comprising a flow separator abutting an exterior circumference of the pier foundation and having flow-separating surfaces being round and symmetrical to each other so as to prevent the fluid from rubbing the pier foundation directly.
9. The scour preventive apparatus for a pier foundation of claim 1, wherein a rubber layer is formed on surfaces of the flow guide plates.
US12/922,507 2008-03-14 2009-09-14 Scour preventive apparatus for pier foundation Abandoned US20110016644A1 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
KR10-2008-0024013 2008-03-14
KR1020080024013A KR100982023B1 (en) 2008-03-14 2008-03-14 Apparatus for preventing scour on bridge pier foundation
PCT/KR2009/001241 WO2009113817A2 (en) 2008-03-14 2009-03-12 Scour preventive apparatus for pier foundation

Publications (1)

Publication Number Publication Date
US20110016644A1 true US20110016644A1 (en) 2011-01-27

Family

ID=41065672

Family Applications (1)

Application Number Title Priority Date Filing Date
US12/922,507 Abandoned US20110016644A1 (en) 2008-03-14 2009-09-14 Scour preventive apparatus for pier foundation

Country Status (6)

Country Link
US (1) US20110016644A1 (en)
EP (1) EP2270283A4 (en)
JP (1) JP5022500B2 (en)
KR (1) KR100982023B1 (en)
CN (1) CN101970760B (en)
WO (1) WO2009113817A2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016079591A (en) * 2014-10-10 2016-05-16 五洋建設株式会社 Work caisson and cut-off method for the same
US9453319B2 (en) 2013-10-08 2016-09-27 Applied University Research, Inc. Scour preventing apparatus for hydraulics structures
US20240068184A1 (en) * 2022-08-24 2024-02-29 Zaozhuang University Debris flow anti-collision device with high-speed water curtain for mountain bridge

Families Citing this family (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101806041B (en) * 2010-03-25 2012-07-04 四川省交通厅公路规划勘察设计研究院 Rolling stone collision protective structure for bridge pier
KR101384165B1 (en) * 2012-05-02 2014-04-10 한국해양과학기술원 A cap for protecting foundation scouring for offshore wind turbine
CN103233429A (en) * 2013-05-11 2013-08-07 天津二十冶建设有限公司 Construction method of local scour prevention of piers in water
CN103243639A (en) * 2013-05-13 2013-08-14 牟献友 Annular-wing pier capable of preventing scouring
CN104631307A (en) * 2013-11-07 2015-05-20 成都凯裕电子电器有限公司 Impact-prevention drainage device of pier
CN103556658A (en) * 2013-11-14 2014-02-05 中国海洋石油总公司 Scour-prevention structure of underwater infrastructure
NL2017059B1 (en) * 2016-06-28 2018-01-05 Pile Fabrics Gmbh Scour protector and method of arranging a scour protector on a seabed
CN109338909B (en) * 2018-11-20 2020-04-28 广东工业大学 Integral pier reinforcing structure and construction method thereof
CN109372006B (en) * 2018-11-27 2023-11-10 中国电建集团华东勘测设计研究院有限公司 Scour prevention protection structure for offshore wind turbine foundation and construction method thereof
KR102226796B1 (en) * 2019-01-07 2021-03-10 이형만 Bridge protection device
CN109914224B (en) * 2019-04-18 2021-01-12 台州佳沃科技有限公司 Assembled bridge substructure
CN110656588B (en) * 2019-10-12 2021-03-26 孔令绅 Portable supporting and protecting structure for elevated road and bridge and assembling method thereof
CN111424730B (en) * 2020-03-18 2021-07-02 石家庄铁道大学 Comb flow tooth device for resisting scouring of heavy-duty railway bridge pier column foundation
CN111778877B (en) * 2020-07-07 2021-09-28 河北宝力工程装备股份有限公司 Bridge reinforcing device for load transfer
CN112746556B (en) 2021-01-12 2022-04-19 浙江大学 Pier scouring protection method combining concave rotating normal curved surface and granular particles
CN114197299B (en) * 2022-01-07 2024-01-26 中铁大桥勘测设计院集团有限公司 Pier with subregion vortex that disappears and scour protection assembled guard ring
CN115233744B (en) * 2022-06-13 2024-01-19 郑州大学 Sacrificial folded plate group for reducing scour of pier bearing platform
KR102543637B1 (en) * 2022-10-05 2023-06-14 한국해양과학기술원 pier for marine bridge with function of scour protection
CN116122189A (en) * 2023-04-20 2023-05-16 中铁二十二局集团第二工程有限公司 Arch bridge dismantling method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3529427A (en) * 1968-11-05 1970-09-22 Delta Diving Ltd Device for preventing or reducing scours at the lower ends of members supporting marine structures
US3859803A (en) * 1973-12-17 1975-01-14 Sofec Inc Anti-scour means for submarine structures
US4019332A (en) * 1974-12-31 1977-04-26 C. G. Doris Devices for protecting the bases of structures immersed in a volume of water against undermining
US4036022A (en) * 1971-04-13 1977-07-19 Larsen Ole Fjord Method of producing and protecting deposits of sedimentary material on floors of bodies of water
US4632600A (en) * 1985-09-25 1986-12-30 Nippon Kokan Kabushiki Kaisha Movable fixed-type semi-submerged construction
US4717286A (en) * 1982-11-10 1988-01-05 Gulf Applied Technologies, Inc. Anti-scour apparatus and method
US5673449A (en) * 1993-05-26 1997-10-07 Vattenfall Utveckling Ab Flow compensation device for bridge pillars
US5839853A (en) * 1991-10-02 1998-11-24 Oppenheimer; M. Leonard Buoyant matter diverting system
US6186445B1 (en) * 1998-03-06 2001-02-13 Paul F. Batcho Method and apparatus for mitigating junction flows

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE898209A (en) * 1982-11-10 1984-03-01 Gulf Applied Tech Erosion control method and device.
JPS61162607A (en) * 1985-01-09 1986-07-23 株式会社ブリヂストン Bridge leg washing and digging preventing apparatus
JP3075999B2 (en) * 1997-03-21 2000-08-14 株式会社ピー・エス Reinforcement method of bridge pier with circular columnar frame
JP4215916B2 (en) * 1999-12-15 2009-01-28 早川ゴム株式会社 Pier structure and construction method
JP2001295245A (en) * 2000-04-17 2001-10-26 World Engineering Kk Protecting method for structure
KR100530273B1 (en) * 2005-08-04 2005-11-22 (주)천일기술단 Apparatus of protect boring using a pier
KR100570921B1 (en) * 2006-01-06 2006-04-14 동부엔지니어링 주식회사 Structure of protection erosion for pier foundation
KR100743478B1 (en) * 2006-12-08 2007-07-30 동남이엔씨(주) Structure for preventing scouring of river

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3529427A (en) * 1968-11-05 1970-09-22 Delta Diving Ltd Device for preventing or reducing scours at the lower ends of members supporting marine structures
US4036022A (en) * 1971-04-13 1977-07-19 Larsen Ole Fjord Method of producing and protecting deposits of sedimentary material on floors of bodies of water
US3859803A (en) * 1973-12-17 1975-01-14 Sofec Inc Anti-scour means for submarine structures
US4019332A (en) * 1974-12-31 1977-04-26 C. G. Doris Devices for protecting the bases of structures immersed in a volume of water against undermining
US4717286A (en) * 1982-11-10 1988-01-05 Gulf Applied Technologies, Inc. Anti-scour apparatus and method
US4632600A (en) * 1985-09-25 1986-12-30 Nippon Kokan Kabushiki Kaisha Movable fixed-type semi-submerged construction
US5839853A (en) * 1991-10-02 1998-11-24 Oppenheimer; M. Leonard Buoyant matter diverting system
US5673449A (en) * 1993-05-26 1997-10-07 Vattenfall Utveckling Ab Flow compensation device for bridge pillars
US6186445B1 (en) * 1998-03-06 2001-02-13 Paul F. Batcho Method and apparatus for mitigating junction flows

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9453319B2 (en) 2013-10-08 2016-09-27 Applied University Research, Inc. Scour preventing apparatus for hydraulics structures
JP2016079591A (en) * 2014-10-10 2016-05-16 五洋建設株式会社 Work caisson and cut-off method for the same
US20240068184A1 (en) * 2022-08-24 2024-02-29 Zaozhuang University Debris flow anti-collision device with high-speed water curtain for mountain bridge

Also Published As

Publication number Publication date
JP2011516756A (en) 2011-05-26
JP5022500B2 (en) 2012-09-12
CN101970760B (en) 2012-03-21
KR20090098554A (en) 2009-09-17
WO2009113817A2 (en) 2009-09-17
KR100982023B1 (en) 2010-09-13
EP2270283A2 (en) 2011-01-05
EP2270283A4 (en) 2013-03-20
CN101970760A (en) 2011-02-09
WO2009113817A3 (en) 2010-01-14

Similar Documents

Publication Publication Date Title
US20110016644A1 (en) Scour preventive apparatus for pier foundation
JP5702276B2 (en) Self-closing flood barrier and method for protecting hinterland using it
JP2017072020A (en) Installation method of capturing body and weir structure
KR100743478B1 (en) Structure for preventing scouring of river
US9624636B2 (en) Multi-stage suspended wave screen and coastal protection system
KR101096094B1 (en) Combination method of gravity type caisson structures
JP5896519B2 (en) Breakwater structure and wave reinforcement mechanism
US20200048853A1 (en) Undulating gate
JP5488125B2 (en) Filling reinforcement structure
KR100615720B1 (en) Structure preventing from erode of foundation of road pier
KR101124409B1 (en) Revetment block
Donnelly et al. Straight drop spillway stilling basin
KR100699710B1 (en) Structure of shore protection block for river
CN109306646B (en) Road with guard and overlapped side ditches
JP3987830B2 (en) Floating wave structure
CN109267446B (en) Stacked side ditch structure, stacked side ditch component and highway
KR101018298B1 (en) Rivers infrastructure care facility
KR100685715B1 (en) The upper end reinforcement structure that is the basics group of a load bridge beam
US20090269136A1 (en) Hooked Collar for Piers and Bridge including the same
JP3987831B2 (en) Connecting structure of floating wave structure
KR200378199Y1 (en) Dig prevent member of underwater bottom face for river
US6984006B2 (en) Elastic flat tread
KR100545923B1 (en) The flow velocity reduction institution installation structure of the river side
JP6457296B2 (en) Bridge
TWM620758U (en) Precast block

Legal Events

Date Code Title Description
STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION