US1867030A - Marine oil well derrick - Google Patents

Marine oil well derrick Download PDF

Info

Publication number
US1867030A
US1867030A US479175A US47917530A US1867030A US 1867030 A US1867030 A US 1867030A US 479175 A US479175 A US 479175A US 47917530 A US47917530 A US 47917530A US 1867030 A US1867030 A US 1867030A
Authority
US
United States
Prior art keywords
beams
piers
derrick
pot
angles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US479175A
Inventor
Charles L Roberts
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to US479175A priority Critical patent/US1867030A/en
Application granted granted Critical
Publication of US1867030A publication Critical patent/US1867030A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B15/00Supports for the drilling machine, e.g. derricks or masts
    • E21B15/02Supports for the drilling machine, e.g. derricks or masts specially adapted for underwater drilling
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor

Definitions

  • This invention is directed to a manne 011 well derrick to be used in drilling and producing oil from submarine floors at great dis- I ter.
  • structure thus has a height of about 200 feet.
  • the present invention is directed to an improvement upon the above construction whereby the cost of the construction is reduced and particularly whereby the wave resistance of the structure is diminished materially.
  • the structure consists of a foundation made up of structural members formed into piers and a central structural member to give a five point pier construction of great rigidity and strength. More specifically. it is constructed of a plurality of vertical H.-beams driven into shale to refusal and cross-connected by structural members to form four compound columns which act as piers. These piers are interconnected by other structural members which act as tie rods. Centrally disposed of these four piers is a ring of vertical H-columns all tied together inaring and cross-braced to the corner piers.
  • Thi-s centra1 ring thus constructed has as one of its functions to act as a vertical compound'column
  • Centrally disposed of this ring oflj columns is a pot suspended and carried by both the central ring of H columns and the corner piers.
  • This pot has a double function. It acts as a sump to collect drilling fluid and oil and also acts as the This pan has the additional to tht pipe passes the drill tube.
  • the rotary table is supported on certain of the H--beams of the central ring.
  • the construction above water level is preferably welded and below water line, clamped and bolted.
  • Fig. 1 is a vertical elevation of the front of the structure.
  • Fig. 3 is a vertical section taken on the line 3-3 of Figs. 5, 6, 7 and 8.
  • Fig. 4 is a vertical section taken on the line 44 of Figs. 5, 6, 7 and 8.
  • Fig. 5 is a plan view of the structure taken on line 55 of Figs. 1, 2, 3 and 4:
  • Fig. 6 is a plan section, taken on line 6.6 of Figs. 1, 2, 3 and 4,
  • Fi 7 is a plan section taken on line 7-7 of Figs. 1, 2, v3 and 4.
  • Fig. 8 is a plan section taken on line 8-8- of Figs. 1, 2, 3 and 4.
  • Fi 9 is a plan section taken on line 99 of F1gs.- 1, 2, 3 and-4.
  • Fig. 10 is a bottom view of the cellar or pot.
  • Fig. 11 is a detail plan view of the clamp r1n ig. 12 is a side view of the plan shown in Fig. 11.
  • Fig. 13 is a detail showing the method of securing the lower end of the turn buckle rod.
  • Fig. 14 is a fragmentary detail showing the matter of attaching a turn buckle rod.
  • the substructure for the marine oil well derrick in this case is substantiall entirely of metallic construction made up 0 standard structural shapes assembled into a unitary structure of great rigidity and presenting a minimum surface to wave impact.
  • the functional elements .of this structure are four corner piers 1, tied together in a number of bays 6, 7, 8 and ,9 by means of internal and external trusses of tension and compression members. Above the water line, the construction may be welded. Below the water line, it is preferably clamped and bolted. These 'are thus formed into compound columns.
  • Fig. 2 is a'vertical elevation of one of the Centrally disposed of the four corner pier is a ring of vertical structure members, such as H-beams, all tied together by means of structural shapes, such as angles, gussets and plates. This forms a compound column of substantial diameter.
  • the H-beams of this ring are connected to the corner piers by concenter ring of the H-beams.
  • the rotary table is carried upon certain others of the central ring of H-beams.
  • a scupper is ositioned beneath the floor and is preferab y rigidly connected to the corner piers and to the central ring of H-beams. This scupper is made of sheet steel. The center of the scupper is provided with a hole which registers with the pot.
  • the piers 1 are composed of four, vertical H-beams 2, 3, 4 and '5, each driven into the submarine floor through the water 151, sand 150 and into the shale 149, until the beam can be driven no further, i. e. to refusal.
  • H-beams are thus driven appropriately Y spaced.
  • the connection and cross-bracing of these vertical H-beams will depend upon the particular conditions tobe met and the i1lus-- tration herein given is merely a description and is not to be taken as limiting.
  • H-beams 2, 3, 4 and 5 of the four piers thus constructed are connected in four ays 6, 7, 8 and 9.
  • columns 2 and 5 are connected by I-beams 13 attached at their upper side to 2 and 3 by means of angle 14 and on their underside by means of angle 21.
  • 5 and 6 are similarly connected by means of a beam 15 and angles 16.
  • 3 and 4 are similarly connected by beams 17 and angles 18.
  • 2 and 3 are similarly connected by beam 19 and angles 20.v
  • the beams 2, 3, 4 and 5 are connected by the four I-beams 22 connected to their respective H-beams by angles 23 and 25. Between the sides in bay 7 are the angle braces 24.
  • Bay 8 is of substantially the same construction as bay 7 and is composed of horizontal braces 26 formed by I-beams and contheir respective vertical H-beams.
  • the under water construction in bay 9 is composed of clamps and cross-tension turn buckle rods.
  • the clamps are composedof an upper clamp bar composed of inner clamp plates 30 and 31 and outer clamp plates 32 and 33. These are clamped to the vertical H- beams by means of outer clamp bolts 34 and inner clamp bolts 41. These are rigidly clamped to the vertical H-bea'ms by means of nuts 35.
  • the inner nuts have the function of both clamping the plates and also limiting the amount of pull on the vertical H- beams.
  • turn buckle rods 40 which are connected between the clamp plates 30 and 37 and 31 and 34 and clamped by means of nuts 35 on bolts 34.
  • the cross-connecting members 42 which are cross-connected between the bolts 41- on the outer face of the clamp plates 33.
  • the cross-connection at the top of bay 6 has been described.
  • the cross-connection at the bottom of bay 6 and top of bay 7 is best illustrated in Fig. 6 and in the vertical sections and elevations 1 to 4, inclusive.
  • Between the beams 2 is a cross-connecting I- ing the beam 19 and the'beam 43 is a gusset plate 45.
  • the four inside beams 44 are connected by a gusset plate 46.
  • Cross-connecting beams 43 and 44 are connected by means of a beam 47 and gusset plates 48 and 49.
  • Between the gusset plates and 49 are angle braces 50.
  • the beams 44 and 43 are con- I nected with the H-beams 2 and 3 by means of the angles 51.
  • the beams 43 and 44 are connected to the H-beams 2 and 3 on the underside of beams 43 and 44 by means of angles 52.
  • the bottom of bay 7 is connected in the fashion more specifically shown in plan of Fig. 7 and front and side elevation and section in Figs. 1 to 4.
  • the cross-connections are composed of I-beams 53 connected by angles 54 and 55.
  • I-be-ams 56 are connected by angle 57.
  • Cross-connecting beams 58 are connected to 56 by gusset 60 and to beam 53 by gusset 59. Between the beams 43-and 53 are the external cross-connecting angles 61 and internal cross-connecting angles 62.
  • the bottom of bay 8 is shown more clearly in Fig. 8 and on Figs. 1 to 4. This bay resembles Fig. 6 more nearly than it does Fig. 7.
  • the outside cross-connecting I- beam 63 and'the inside I-beam 66 connect the vertical H-beams 2, 3 and. 4.
  • the beams 63 are connected by means of angles 64 to H-beams and the beams 66 are connected to the H-beams by angle 67.
  • the beams 26 and 63 are connected by gusset plate 65 and the beams 66 are connected by gusset plates 106.
  • the beams 63 and 66 are cross-connected by beam 68 .to beam 63 by gusset 69 and to beam 66 by gusset 70 and angularly crossbraced by beam 71 connected to gussets 65 and 70. i
  • the H-beams are connected by angle 73 clamped onto the plates 38 and on the side elevation by means of an angle 77 clamped .to the plates 33 by means of bolts '34.
  • Between the beam 63 and the angle 73 are two tension members composed of turn buckle rods 75.
  • brackets 76 and clamped between plates 38 and angle 7 3 are two additional brackets 74. Between these brackets are braced the turn buckle rods 75.
  • turn buckles 78 connected to brackets 79 and to bolts 34.
  • H-beams are driven into the shale to refusal in the form of a ring centrally disposed of piers 1.
  • These beams are numbered 80. Their inter-connection and integral construction will be described by reference to Figs. 6, 7, 8 and 9, as previously mentioned.
  • the H-beams 80 are connected by means of H-beams 81 connected and held by angles 82. These angles are in turn connected by means of gussets 83 forming a rigid eight-sided figure.
  • Angular I-beams 87 are provided between the gussets 46 and 83.
  • the H-beams 80 are connected to the beams 44 by means of beams 84 tied to the beams 80 by means of angles 85 and to the beams 44 by means of gusset plates 86.
  • the H-beams 80 are connected by the channel members 88 and are held by U-clamps 92. These members are in turn connected to each other by means of angle 90 and channel braces 91.
  • the channels 88 are connected to the beams 56 in firm fashion by the angles 89. Between the channels 88 and the I-beam 81 are the cross-angular braces 88.
  • the H-beams 80 are connected by means of angles 93 which are, in turn, connected by gussets 94.
  • the beams 80 are cross-braced by means of braces 93'.
  • the central ring' is interconnected by the deformed channels 95 held to the beams 80 by means of U-v bolts 96 and to the clamp bars 32 by through bolts 97.
  • the pot is positioned on the inside of the opening sothat the flange 99 rests upon the I beams 81 and gussets 83 and 83' to which it is attached by appropriate means.
  • the pot is preferably of cast iron.
  • To the lugs 101 are connected angular braces 105 which are, in turn, connected to gussets 106, (see Fig. 8) Referring to Fig. 7, the horizontal bracing I-beams 104 connect the pads 102 to the beams 56 by means of gusset 60. In this manner,
  • the pot is permanently and rigidly attached.
  • an inclined scupper 117 Registering with the openingof the pct 98 is an inclined scupper 117 (see Fig. 4 and also Fig. 5). This is made of sheet steel and is permanently and rigidly 'aflixed to the beams 2.3, 4, 5 and 80, and preferably rigidly afiixed to the pot 98.
  • Through thehub 100 and forming a snug fittherewith is driven an v outer pipe 107 and by means of a drive point manently and tightly attached to the pct 98.
  • an inner conductor pipe 132 Through this outer pipe or caisson 107 is driven an inner conductor pipe 132after sand and some of the shale had been excavated from the inside of pipe 107.
  • the pipe 132 is then cemented within the pipe 107 from shale to the pot.
  • the caisson is supported from the corner piers in the following fashion: At the level of the top of bay 9 is positioned a concentric flange ring 109, (see Figs. 11 and 12). It is composed of two parts and has a. flange 109 and a hub 108 and lugs 110. It is clamped to the pipe 107. Between the In 110 and the beam 3 is a tension turn buck e rod 112. At its upper end the rod is connected by means of through bolts to lugs 110 and is connected at its lower end to beam 3 by means of an angle 113 formed at the end of the clamp bar 38, (see Fig.
  • the floor construction will be next described by reference to Figs. 1 to 4 and more particularly to Fig. 5.
  • the piers are capped 'vention.
  • T e derrick 135 is positioned onthe caps 119 and carries, as is usual, a crown block 136, a. swivel block 137, swivel hook 138 and swivel 139.
  • the ier 118 surrounds the whole structure an on the pier is positioned a mud trough 145 and a mud pump 142 which is connected to the mud trough 145 and by means of flexible hose 143 to the swivel 139.
  • the mud is pumped by means of pump 142 through the hose 143 through the swivel 139, the drill pipe 140, the drill 141, up the conductor pipe 132 through the overflow 144 backto the mud trough 145.
  • Any drilling fluid collecting oli load on the rotary table is carried by o'ertain of the H-beams of the central ring. During drilling, theload is on the corner piers.
  • a scupper 117 and a. pct 98 is provided.
  • the scupper has the additional function of acting as a buffer to prevent the uplift of the floor and the inundation of the floor by the running seas.
  • cementing of the conductor pipe prevents seepage of the water into the well bore and during drilling it avoids the passage of drilling fluid through the conductor pipe and seepage into the ocean and resultant polution.
  • a marine oil well derrick comprising a i plurality of vertical beams extendinginto the ocean bottom, structural shapes for tying said beams into a plurality of compound col- .umns to act as piers, a derrick mounted on said piers, means to interconnect said piers to form a rigid foundation, a plurality of vertical structural shapes extending into the ocean bottom tied together in a compound column disposed centrally of said piers, means for interconecting said center column with said piers, a metallic. pot' centrally disposed of center compound column and carried thereby, a caisson concentric with'said pot and carried 'by said piers, and a conductor pipe cemented within said caisson above and low waterline.
  • a marine oil well derrick comprisinga lurality of piers extending into the ocean Bottom, a derrick mounted on said piers, a of structural shapes driven into the pluralit bottom in a rin centrally disposed marine of said piers, means for interconnecting said I ring and said piers, a metallic pot centrally disposed of saidring and carried thereby, a
  • caisson concentric with said pot and a conductor pipe cemented in said caisson above and below water line.
  • a marine oil well derrick comprising a plurality of vertical beams extending into the ocean bottom, structural shapes for tying said beams into a plurality of compound columns to act as piers, .a-derrickmounted on said piers, means to interconnect said piers to form arigid foundation, a plurality of vertical structural shapes extending into the ocean bottom tied together in a compound column disposed centrally of said piers, means for interconnecting saidcenter column with said piers, a metallic pot centrally disposed of sad centercompound column and carried thereby; a fioor for said derrick supported by saidpiers, a sub-floor for said derrick supported by said piers and an opening in said sub-floor registering with the opening in said pot.
  • a caisson concentric with said pot a conductor pipe cemented in saidcaisson above and below water line, a floor for said derrick supported by said piers, a subfloor for said derrick supported by said piers and an opening in said sub-floor registering with the opening in said pot.
  • a plurality of piers consisting of one or more vertical beams driven into the ocean bottom, a plurality of structuralelements positioned within the ocean bottom and contained within said first mentioned piers, structural elements connecting said first mentioned structural elements to said piers, a
  • caisson carried within said first mentioned plurality of structural elements and connected to said metallic pot, a conductor pipe within the caisson cemented within said caisson above, and below the water line and a derrick disposed upon said piers.
  • a marine oil well derrick comprising a plurality of piers, a derrick mounted on said piers, a pluralit of structural shapes driven mto the marine ottom in a ring centrally disposed of said iers, means for interconnecting said ring an said piers, a metallic pot cen-v trally disposed of said ring and carried thereby, a caisson concentric with said pot, a conductor pipe cemented in said caisson above and below water line, a'derrick floor carried by said piers and a rotary support on certain of said structural members forming said ring.

Landscapes

  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Earth Drilling (AREA)

Description

9 Sheets-Shet l C. L. ROBERTS MARINE on. WELL DERRICK Filed Sept. 2, 1950 Jul 12,- 1932.
INVENTOR (Zar/eslfoiezfi ORNEY July 12, 1932, c. ROBERTS MARINE OIL WELL DERRICK 9 Sheets-Shea 2 Filed Sept 1 2, 1930 ORNE Y.
July 12, 1 3 c. ROBERTS 1,867,030
'MARINE OIL WELL DERRICK Filed Sept. 2. 1950 Q'Shets-Sheefb :s
INVENTOR. fia'r/eJL Fake/'13 4% ORNEY.
July 12, 1932.
c. L. ROBERTS MARINE OIL WELL DERRICK Filed Sept. 2, 1950 9 sheets-sheet 4 INMENTFOR. ar/esL/Yahri July 12, 1932. c. ROBERTS 1,867,030
MARINE OIL WELL DERRICK I Q Filed Sept. 2. 1950 9 sheets-sheet 5 INVENTOR. mar/e6 l Fab/f? BY ATTORNEY.
y 12, 1932. c. L. ROBERTS 1,867,030
MARINE OIL WELL DERRICK Filed'Sept. 2, 1930 9' Sheets-Sheet s INVENTOR.
CZarkJZ. F kri 2%QRNEY.
July 12, 1932.
[EL fifi C. L. ROBERTS MARINE OIL WELL DERRICK Filed Sept. 2, 1930 9 Sheets-Sheet 9 INVENTOR.
v A ORNEY.
v i i l I L -"-"nn I w Patented July 12', 1932 PATENT orrrcr:
CHARLES L. ROBERTS,1OI LOS ANGELES, CALIFORNIA EARINE OIL DERRICK Application filed September 2, 1930. Serial No. 479,175.
This application is a continuation, in part, of application Serial No. 426,863, filed Feb.
8th, 1930, which is in turn a continuation,
.inpart, of patent application Serial No.
353,308, filed April 8th, 1929, which has eventuated in Patent No. 1,7 69,858, issued July 1st, 1930.
This invention is directed to a manne 011 well derrick to be used in drilling and producing oil from submarine floors at great dis- I ter.
tances from shore and .in great depths of wa- In the previous application, I have described foundation structures suitable for th1s purpose. This invention is an 1mprovement thereon.
The drilling in deep water, espec1ally 1n the Pacific Ocean where the ma or submarine oil formations are found, involves peculiar problems not heretofore encountered.
.Well locations are now being discovered at depths in the neighborhood of 50 feet of water and as far as 2000 feet from shore. The
necessity of practical operation requires that the derrick floorsbe elevated 25 or 30 feet above the high tide line. The ordinary derr-ick now employed is 122 feet in height. The
structure thus has a height of about 200 feet.
It must be recognized that such derricks cannot be guyed and the over-turning moment, due to wind pressure, is enormous. In addition, the wave action creates a tremendous force tending to upset the, staunchest derricks. Additionally, the derrick is subject to eccentric loads of tremendous amounts.
In the previous applications, I have desinned a derrick which is particularly directed to resist these conditionsby employing a peculiar arrangement of concrete piers and caissons. I have employed, in actual constructions, concrete piers 7 feet in diameter and center caissons 10 and 12 feet in diameter. The present invention is directed to an improvement upon the above construction whereby the cost of the construction is reduced and particularly whereby the wave resistance of the structure is diminished materially. I employ a foundation madeup of entirely structural steel members presenting a minimum surface to wave action.
Drilling in the ocean has developed an fluid. This, while easily avoided on shore,
is a serious problem when drilling at distances of 2000 feet or more at sea. In the previous applications, I have designed a construction that obviates any such difliculties. This invention is an improvement upon that construction. I
It is, therefore, an object of this invention to design a foundation for a submarine oil' well derrick whic'hwill withst: nd the tremendous wave and wind action and high eccentric loads at a minimum cost and which, at the same time, would present a minimum of surface to the wave action.
It is another object of this invention to provide for means for segregating drilling fluid and oil to prevent contamination of the water. y
In general, the structure consists of a foundation made up of structural members formed into piers and a central structural member to give a five point pier construction of great rigidity and strength. More specifically. it is constructed of a plurality of vertical H.-beams driven into shale to refusal and cross-connected by structural members to form four compound columns which act as piers. These piers are interconnected by other structural members which act as tie rods. Centrally disposed of these four piers is a ring of vertical H-columns all tied together inaring and cross-braced to the corner piers. Thi-s centra1 ring thus constructed has as one of its functions to act as a vertical compound'column Centrally disposed of this ring oflj columns is a pot suspended and carried by both the central ring of H columns and the corner piers. This pot has a double function. It acts as a sump to collect drilling fluid and oil and also acts as the This pan has the additional to tht pipe passes the drill tube. The rotary table is supported on certain of the H--beams of the central ring. The construction above water level is preferably welded and below water line, clamped and bolted.
The construction will be more specifically described by reference to the accompanying figures.
Fig. 1 is a vertical elevation of the front of the structure.
sides. v A
Fig. 3 is a vertical section taken on the line 3-3 of Figs. 5, 6, 7 and 8.
Fig. 4 is a vertical section taken on the line 44 of Figs. 5, 6, 7 and 8.
Fig. 5 is a plan view of the structure taken on line 55 of Figs. 1, 2, 3 and 4:
Fig. 6 is a plan section, taken on line 6.6 of Figs. 1, 2, 3 and 4,
Fi 7 is a plan section taken on line 7-7 of Figs. 1, 2, v3 and 4.
Fig. 8 is a plan section taken on line 8-8- of Figs. 1, 2, 3 and 4.
Fi 9 is a plan section taken on line 99 of F1gs.- 1, 2, 3 and-4.
Fig. 10 is a bottom view of the cellar or pot.
Fig. 11 is a detail plan view of the clamp r1n ig. 12 is a side view of the plan shown in Fig. 11.
Fig. 13 is a detail showing the method of securing the lower end of the turn buckle rod.
Fig. 14 is a fragmentary detail showing the matter of attaching a turn buckle rod.
The substructure for the marine oil well derrick in this case is substantiall entirely of metallic construction made up 0 standard structural shapes assembled into a unitary structure of great rigidity and presenting a minimum surface to wave impact.
It will be observed that the structure is substantially completely symmetrical. It is substantially identical on all four sides except in minor details hereinafter more specifically specified.
The functional elements .of this structure are four corner piers 1, tied together in a number of bays 6, 7, 8 and ,9 by means of internal and external trusses of tension and compression members. Above the water line, the construction may be welded. Below the water line, it is preferably clamped and bolted. These 'are thus formed into compound columns.
Fig. 2 is a'vertical elevation of one of the Centrally disposed of the four corner pier is a ring of vertical structure members, such as H-beams, all tied together by means of structural shapes, such as angles, gussets and plates. This forms a compound column of substantial diameter. The H-beams of this ring are connected to the corner piers by concenter ring of the H-beams. The rotary table is carried upon certain others of the central ring of H-beams. A scupper is ositioned beneath the floor and is preferab y rigidly connected to the corner piers and to the central ring of H-beams. This scupper is made of sheet steel. The center of the scupper is provided with a hole which registers with the pot.
Describing the structure in detail and referring to the figures:
The piers 1 are composed of four, vertical H- beams 2, 3, 4 and '5, each driven into the submarine floor through the water 151, sand 150 and into the shale 149, until the beam can be driven no further, i. e. to refusal.
Six-
teen H-beams are thus driven appropriately Y spaced. The connection and cross-bracing of these vertical H-beams will depend upon the particular conditions tobe met and the i1lus-- tration herein given is merely a description and is not to be taken as limiting. As illustrated, H- beams 2, 3, 4 and 5 of the four piers thus constructed are connected in four ays 6, 7, 8 and 9.
In bay 6 they are connected by two angles 10 on the front and back of the structure, and two angles 11 on the two sides of the structure. The two angles 11 are longer than the two angles 10. At the bottom of bay 6, the
columns 2 and 5 are connected by I-beams 13 attached at their upper side to 2 and 3 by means of angle 14 and on their underside by means of angle 21. 5 and 6 are similarly connected by means of a beam 15 and angles 16. 3 and 4 are similarly connected by beams 17 and angles 18. 2 and 3 are similarly connected by beam 19 and angles 20.v
In bay 7 the beams 2, 3, 4 and 5 are connected by the four I-beams 22 connected to their respective H-beams by angles 23 and 25. Between the sides in bay 7 are the angle braces 24.
Bay 8 is of substantially the same construction as bay 7 and is composed of horizontal braces 26 formed by I-beams and contheir respective vertical H-beams.
. beam 43 and a similar I-beam 44. Connectnected by means of the angles 27 and 28 to Angle brace 29 is also provided.
The under water construction in bay 9 is composed of clamps and cross-tension turn buckle rods. The clamps are composedof an upper clamp bar composed of inner clamp plates 30 and 31 and outer clamp plates 32 and 33. These are clamped to the vertical H- beams by means of outer clamp bolts 34 and inner clamp bolts 41. These are rigidly clamped to the vertical H-bea'ms by means of nuts 35. The inner nuts have the function of both clamping the plates and also limiting the amount of pull on the vertical H- beams. On the elevation of the structure are provided turn buckle rods 40 which are connected between the clamp plates 30 and 37 and 31 and 34 and clamped by means of nuts 35 on bolts 34. In the side elevation willbeseen the cross-connecting members 42 which are cross-connected between the bolts 41- on the outer face of the clamp plates 33.
The cross-connection between, the piers thus constructed will be next described.
The cross-connection at the top of bay 6 has been described. The cross-connection at the bottom of bay 6 and top of bay 7 is best illustrated in Fig. 6 and in the vertical sections and elevations 1 to 4, inclusive. Between the beams 2 is a cross-connecting I- ing the beam 19 and the'beam 43 is a gusset plate 45. The four inside beams 44 are connected by a gusset plate 46. Cross-connecting beams 43 and 44 are connected by means of a beam 47 and gusset plates 48 and 49. Between the gusset plates and 49 are angle braces 50. The beams 44 and 43 are con- I nected with the H- beams 2 and 3 by means of the angles 51. The beams 43 and 44 are connected to the H- beams 2 and 3 on the underside of beams 43 and 44 by means of angles 52. The bottom of bay 7 is connected in the fashion more specifically shown in plan of Fig. 7 and front and side elevation and section in Figs. 1 to 4. The cross-connections are composed of I-beams 53 connected by angles 54 and 55. I-be-ams 56 are connected by angle 57. Cross-connecting beams 58 are connected to 56 by gusset 60 and to beam 53 by gusset 59. Between the beams 43-and 53 are the external cross-connecting angles 61 and internal cross-connecting angles 62.
The bottom of bay 8 is shown more clearly in Fig. 8 and on Figs. 1 to 4. This bay resembles Fig. 6 more nearly than it does Fig. 7. The outside cross-connecting I- beam 63 and'the inside I-beam 66 connect the vertical H- beams 2, 3 and. 4. The beams 63 are connected by means of angles 64 to H-beams and the beams 66 are connected to the H-beams by angle 67. The beams 26 and 63 are connected by gusset plate 65 and the beams 66 are connected by gusset plates 106. The beams 63 and 66 are cross-connected by beam 68 .to beam 63 by gusset 69 and to beam 66 by gusset 70 and angularly crossbraced by beam 71 connected to gussets 65 and 70. i
The under water construction is more clearly shown in Figs. 9, 1 to 4, inclusive.
On front elevation, the H-beams are connected by angle 73 clamped onto the plates 38 and on the side elevation by means of an angle 77 clamped .to the plates 33 by means of bolts '34. Between the beam 63 and the angle 73 are two tension members composed of turn buckle rods 75. To the underside of beam 63 are attached brackets 76 and clamped between plates 38 and angle 7 3 are two additional brackets 74. Between these brackets are braced the turn buckle rods 75. In a like manner, on the side elevation are turn buckles 78 connected to brackets 79 and to bolts 34.
The internal construction of the structure will be described next.
As stated before, eight H-beams are driven into the shale to refusal in the form of a ring centrally disposed of piers 1. These beams are numbered 80. Their inter-connection and integral construction will be described by reference to Figs. 6, 7, 8 and 9, as previously mentioned. At the bottom of bay 6 (seeFig. 6) the H-beams 80 are connected by means of H-beams 81 connected and held by angles 82. These angles are in turn connected by means of gussets 83 forming a rigid eight-sided figure. Angular I-beams 87 are provided between the gussets 46 and 83. The H-beams 80 are connected to the beams 44 by means of beams 84 tied to the beams 80 by means of angles 85 and to the beams 44 by means of gusset plates 86.
At the bottom of bay 7, that is, at'the top of bay 8, the H-beams 80 are connected by the channel members 88 and are held by U-clamps 92. These members are in turn connected to each other by means of angle 90 and channel braces 91. The channels 88 are connected to the beams 56 in firm fashion by the angles 89. Between the channels 88 and the I-beam 81 are the cross-angular braces 88.
- At the bottom of bay 8, that is, at the top of bay 9, (see Fig. 8), the internal ring 1S connected in thefollowing fashion:
The H-beams 80 are connected by means of angles 93 which are, in turn, connected by gussets 94. The beams 80 are cross-braced by means of braces 93'. In bay 9 the central ring'is interconnected by the deformed channels 95 held to the beams 80 by means of U-v bolts 96 and to the clamp bars 32 by through bolts 97.
I will next describe the positioning of the sump, pot or cellar 98. It is the function of this pot to act as a reservoir for the drainage l tor pipe and caisson45 lugs 101 and I-beam into the shale. It is welded or otherwise perof the valves and'in general to function as the cellar for the oil well. This pot is shown in bottom view of Fig, and in section on Fig. 4. It has a flange 99 of size to register with the openin and supporting structure of the beams 81, see Fig. 6). At the bottom of the pot is a hub 100 to receive the conducpads 102 containing taped holes 103. The pot is positioned on the inside of the opening sothat the flange 99 rests upon the I beams 81 and gussets 83 and 83' to which it is attached by appropriate means. The pot is preferably of cast iron. To the lugs 101 are connected angular braces 105 which are, in turn, connected to gussets 106, (see Fig. 8) Referring to Fig. 7, the horizontal bracing I-beams 104 connect the pads 102 to the beams 56 by means of gusset 60. In this manner,
the pot is permanently and rigidly attached.
Registering with the openingof the pct 98 is an inclined scupper 117 (see Fig. 4 and also Fig. 5). This is made of sheet steel and is permanently and rigidly 'aflixed to the beams 2.3, 4, 5 and 80, and preferably rigidly afiixed to the pot 98. Through thehub 100 and forming a snug fittherewith is driven an v outer pipe 107 and by means of a drive point manently and tightly attached to the pct 98. Through this outer pipe or caisson 107 is driven an inner conductor pipe 132after sand and some of the shale had been excavated from the inside of pipe 107. The pipe 132 is then cemented within the pipe 107 from shale to the pot. a
The caisson is supported from the corner piers in the following fashion: At the level of the top of bay 9 is positioned a concentric flange ring 109, (see Figs. 11 and 12). It is composed of two parts and has a. flange 109 and a hub 108 and lugs 110. It is clamped to the pipe 107. Between the In 110 and the beam 3 is a tension turn buck e rod 112. At its upper end the rod is connected by means of through bolts to lugs 110 and is connected at its lower end to beam 3 by means of an angle 113 formed at the end of the clamp bar 38, (see Fig. 13), and by means of the pin and cotters 114 near the bottom of bay 9 is a like ring 109 which is connected to the top of bay 9 by means of tension turn buckle rods 115. These are connected to the 45 lugs 110 and to the H-beams 3 by means of a bracket 116,(see Fig. 14).
The floor construction will be next described by reference to Figs. 1 to 4 and more particularly to Fig. 5. The piers are capped 'vention.
by means of cap 119 held to the beams 2, 3, 4 and 5 by means of angles 11 and 120. The caps are interconnected by means of I-beams 121 and- 122 held by means of the 'U-bolt clamps 123. To the underside of beams 121 are connected the cross-beams 124 by means of gussets 125 Between the beams 122 and passing over the beams 124 are cross-beams 128 connected to the beams122 by means of gussets 129 to channels 124 by gussets 125 and to the H-beams by means of angles 130. In similar manne gchannels 124 are connected by means of angles to the H-beams 80. Between the inside four beams 80 are -,laid cross-beams 127 connected to the beams 80 by means of angles 126. Across beams 127 is laid the supporting structure 131 upon which is to be positioned rotary table 134.
. The drill pipe 140 passes through the rotary 134 through the conductor pipe 132. At the end of the drill ipe is a bit 141 of conventional design. T e derrick 135 is positioned onthe caps 119 and carries, as is usual, a crown block 136, a. swivel block 137, swivel hook 138 and swivel 139. The ier 118 surrounds the whole structure an on the pier is positioned a mud trough 145 and a mud pump 142 which is connected to the mud trough 145 and by means of flexible hose 143 to the swivel 139. The mud is pumped by means of pump 142 through the hose 143 through the swivel 139, the drill pipe 140, the drill 141, up the conductor pipe 132 through the overflow 144 backto the mud trough 145. Any drilling fluid collecting oli load on the rotary table, especially at such times as when the drill string hangs in the slips of the rotary table, is carried by o'ertain of the H-beams of the central ring. During drilling, theload is on the corner piers.
It will be further observed that the drilling fluid and oil is carefully segregated. For this purpose a scupper 117 and a. pct 98 is provided. As stated before, the scupper has the additional function of acting as a buffer to prevent the uplift of the floor and the inundation of the floor by the running seas. The
cementing of the conductor pipe, both above and below waten line, prevents seepage of the water into the well bore and during drilling it avoids the passage of drilling fluid through the conductor pipe and seepage into the ocean and resultant polution.
The above description is not to be taken as limiting but as merely illustrative of the inthemselves to the man skilled in the art claim to be:
Many modifications will suggest 1. A marine oil well derrick comprising a i plurality of vertical beams extendinginto the ocean bottom, structural shapes for tying said beams into a plurality of compound col- .umns to act as piers, a derrick mounted on said piers, means to interconnect said piers to form a rigid foundation, a plurality of vertical structural shapes extending into the ocean bottom tied together in a compound column disposed centrally of said piers, means for interconecting said center column with said piers, a metallic. pot' centrally disposed of center compound column and carried thereby, a caisson concentric with'said pot and carried 'by said piers, and a conductor pipe cemented within said caisson above and low waterline. p 2. A marine oil well derrick comprisinga lurality of piers extending into the ocean Bottom, a derrick mounted on said piers, a of structural shapes driven into the pluralit bottom in a rin centrally disposed marine of said piers, means for interconnecting said I ring and said piers, a metallic pot centrally disposed of saidring and carried thereby, a
caisson concentric with said pot and a conductor pipe cemented in said caisson above and below water line. j
3. A marine oil well derrick comprising a plurality of vertical beams extending into the ocean bottom, structural shapes for tying said beams into a plurality of compound columns to act as piers, .a-derrickmounted on said piers, means to interconnect said piers to form arigid foundation, a plurality of vertical structural shapes extending into the ocean bottom tied together in a compound column disposed centrally of said piers, means for interconnecting saidcenter column with said piers, a metallic pot centrally disposed of sad centercompound column and carried thereby; a fioor for said derrick supported by saidpiers, a sub-floor for said derrick supported by said piers and an opening in said sub-floor registering with the opening in said pot.
ried thereby, a caisson concentric with said pot, a conductor pipe cemented in saidcaisson above and below water line, a floor for said derrick supported by said piers, a subfloor for said derrick supported by said piers and an opening in said sub-floor registering with the opening in said pot.
6. In a marine oil well derrick, in combination, a plurality of piers consisting of one or more vertical beams driven into the ocean bottom, a plurality of structuralelements positioned within the ocean bottom and contained within said first mentioned piers, structural elements connecting said first mentioned structural elements to said piers, a
metallic pot carried by said first mentioned contained I within said first mentioned piers, structural elements connecting said first mentioned structural elements to said piers, a metallic pot carried by said first mentioned plurality of structural elements,
'a caisson carried within said first mentioned plurality of structural elements and connected to said metallic pot, a conductor pipe within the caisson cemented within said caisson above, and below the water line and a derrick disposed upon said piers.
Signed at Los Angeles, in the county of 'Los Angeles, and State of California, this 28th day of August, A. D. 1930.
CHARLES L. ROBERTS.
4. A marine oil well derrick comprising a plurality of piers, a derrick mounted on said piers, a pluralit of structural shapes driven mto the marine ottom in a ring centrally disposed of said iers, means for interconnecting said ring an said piers, a metallic pot cen-v trally disposed of said ring and carried thereby, a caisson concentric with said pot, a conductor pipe cemented in said caisson above and below water line, a'derrick floor carried by said piers and a rotary support on certain of said structural members forming said ring.
5. A marine oil 'well derrick com rising a plurality of piers, a derrick mounte on said PlOl'S, a plurality of structural shapes driven into the marine bottom in a ring centrally disposed of said columns, means for interconnectmg sa d ring and said piers, a metallic pot centrally disposed of said ring and car-
US479175A 1930-09-02 1930-09-02 Marine oil well derrick Expired - Lifetime US1867030A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US479175A US1867030A (en) 1930-09-02 1930-09-02 Marine oil well derrick

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US479175A US1867030A (en) 1930-09-02 1930-09-02 Marine oil well derrick

Publications (1)

Publication Number Publication Date
US1867030A true US1867030A (en) 1932-07-12

Family

ID=23902956

Family Applications (1)

Application Number Title Priority Date Filing Date
US479175A Expired - Lifetime US1867030A (en) 1930-09-02 1930-09-02 Marine oil well derrick

Country Status (1)

Country Link
US (1) US1867030A (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2586966A (en) * 1949-08-08 1952-02-26 Theodore M Kuss Deep water oil well drilling system
US2612025A (en) * 1949-07-07 1952-09-30 William A Hunsucker Prefabricated marine structure
US2688848A (en) * 1949-09-26 1954-09-14 Signal Oil & Gas Co Portable drilling equipment
US2772539A (en) * 1951-01-18 1956-12-04 Sandberg William Andrew Foundation for off-shore drilling rig
US2981346A (en) * 1957-08-30 1961-04-25 Shell Oil Co Rotary drilling table mounting
US3023808A (en) * 1958-03-24 1962-03-06 Texaco Inc Deep well drilling apparatus
US3181628A (en) * 1963-05-20 1965-05-04 William P Verville Conductor sleeve and packing gland for sub-aqueous marine drilling
US3282336A (en) * 1962-09-25 1966-11-01 Richfield Oil Corp Production method and apparatus
US3657895A (en) * 1971-02-12 1972-04-25 Warren Petroleum Corp Offshore platform
US3698198A (en) * 1971-02-12 1972-10-17 Warren Petroleum Corp Deep-water drilling, production and storage system
US4958960A (en) * 1989-05-22 1990-09-25 Exxon Production Research Company Well conductor support structure and method for using
US5377748A (en) * 1993-09-23 1995-01-03 Pool Company Spill container for wells with improved mounting
WO2009143520A1 (en) * 2008-05-23 2009-11-26 Transocean Offshore Deepwater Drilling Inc. Method and apparatus for improving the lateral support provided by the legs of a jack-up drilling rig
US20140196948A1 (en) * 2013-01-11 2014-07-17 A.P. Moller - Maersk A/S Drilling rig

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2612025A (en) * 1949-07-07 1952-09-30 William A Hunsucker Prefabricated marine structure
US2586966A (en) * 1949-08-08 1952-02-26 Theodore M Kuss Deep water oil well drilling system
US2688848A (en) * 1949-09-26 1954-09-14 Signal Oil & Gas Co Portable drilling equipment
US2772539A (en) * 1951-01-18 1956-12-04 Sandberg William Andrew Foundation for off-shore drilling rig
US2981346A (en) * 1957-08-30 1961-04-25 Shell Oil Co Rotary drilling table mounting
US3023808A (en) * 1958-03-24 1962-03-06 Texaco Inc Deep well drilling apparatus
US3282336A (en) * 1962-09-25 1966-11-01 Richfield Oil Corp Production method and apparatus
US3181628A (en) * 1963-05-20 1965-05-04 William P Verville Conductor sleeve and packing gland for sub-aqueous marine drilling
US3657895A (en) * 1971-02-12 1972-04-25 Warren Petroleum Corp Offshore platform
US3698198A (en) * 1971-02-12 1972-10-17 Warren Petroleum Corp Deep-water drilling, production and storage system
US4958960A (en) * 1989-05-22 1990-09-25 Exxon Production Research Company Well conductor support structure and method for using
US5377748A (en) * 1993-09-23 1995-01-03 Pool Company Spill container for wells with improved mounting
WO2009143520A1 (en) * 2008-05-23 2009-11-26 Transocean Offshore Deepwater Drilling Inc. Method and apparatus for improving the lateral support provided by the legs of a jack-up drilling rig
US20100040418A1 (en) * 2008-05-23 2010-02-18 Transocean Offshore Deepwater Drilling Inc. Method and apparatus for improving the lateral support provided by the legs of a jack-up drilling rig
US8292548B2 (en) 2008-05-23 2012-10-23 Transocean Offshore Deepwater Drilling Inc. Method and apparatus for improving the lateral support provided by the legs of a jack-up drilling rig
CN102037189B (en) * 2008-05-23 2013-06-26 越洋离岸深海钻探公司 Method and apparatus for improving the lateral support provided by the legs of a jack-up drilling rig
EA022591B1 (en) * 2008-05-23 2016-01-29 Трансоушен Оффшор Дипвотер Дриллинг Инк. Method and apparatus for improving the lateral support provided by the legs of a jack-up drilling rig
US20140196948A1 (en) * 2013-01-11 2014-07-17 A.P. Moller - Maersk A/S Drilling rig
US9458680B2 (en) * 2013-01-11 2016-10-04 Maersk Drilling A/S Drilling rig

Similar Documents

Publication Publication Date Title
US1867030A (en) Marine oil well derrick
US2574140A (en) Marine oil well derrick foundation
US4161376A (en) Offshore fixed platform and method of erecting the same
US2939291A (en) Anchoring system for floating drill structure
US2422168A (en) Marine tower and method of placing same
US2907172A (en) Method and apparatus for constructing offshore drilling platforms
US3927535A (en) Jack-up type offshore oil production platform apparatus and method
DE2543293C3 (en) Underwater drilling device
US6299385B1 (en) Mini-jacket and method for installation using caisson
US4618286A (en) Composite platform for petroleum workings in polar seas
US4607983A (en) Method of constructing an offshore tower structure
US2429952A (en) Underwater foundation and method of erecting the same
US3976021A (en) Installation of vertically moored platform
US3094847A (en) Offshore platform structure
US2318685A (en) Portable marine foundation
US5051036A (en) Method of installing lean-to well protector
US2946566A (en) Subaqueous drilling apparatus
US2901890A (en) Submarine structure
US2863293A (en) Marine drilling rig
US2482788A (en) Portable marine drilling structure
US3624702A (en) Offshore platform support
US2612025A (en) Prefabricated marine structure
US2077044A (en) Marine derrick structure
US3390531A (en) Offshore drilling platform
US2580911A (en) Foundation structure for derricks