Prior art keywords
metal
monolithic
crossbar
precast
support
Prior art date
Application number
UAA201601845A
Other languages
Ukrainian (uk)
Inventor
Валерій Борисович Нікулін
Олександр Віталійович Конюхов
Валерій Самуїлович Шмуклер
Ольга Миколаївна Лавриненко
Сергій Олександрович Бугаєвський
Original Assignee
Валерій Борисович Нікулін
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Валерій Борисович Нікулін filed Critical Валерій Борисович Нікулін
Priority to UAA201601845A priority Critical patent/UA115707C2/en
Publication of UA115707C2 publication Critical patent/UA115707C2/en

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

Винахід належить до галузі будівництва і може бути використаний при зведенні збірно-монолітних перекриттів житлових будинків з безригельним монолітним каркасом. В основу винаходу поставлена задача удосконалення способу монтажу опалубки за рахунок застосування модульних елементів, що дозволяють бетонувати збірно-монолітне перекриття і забезпечувати несучу здатність для сприйняття власної ваги збірних залізобетонних плит перекриття і ваги монолітного бетону перекриття, а також короткочасних навантажень від ваги людей, обладнання та снігового навантаження. Поставлена задача в запропонованому способі монтажу опалубки для зведення збірно-монолітних перекриттів, який включає улаштування робочого шару палуби у вигляді прямокутних листів з багатошарової фанери, встановлення дерев'яних балок двотаврового перерізу, а також металевих стійок, вирішується таким чином: на заздалегідь забетоновані колони встановлюють опорні столики у вигляді металевої обойми для обпирання від одного до чотирьох металевих шпренгельних ригелів довжиною, рівною половині кроку колон, а посилені металеві опорні стійки з елементами для кріплення зв'язків, що підтримують вільний кінець шпренгельних ригелів, об'єднують попарно зв'язевими ригелями, шпренгельний ригель виготовляють з балки у вигляді металевої труби квадратного перерізу з приварюванням посередині прольоту перпендикулярно осі шпренгеля фрагмента металевої труби і шпренгеля з двох арматурних стержнів, причому конструкція замка з'єднує посилені металеві опорні стійки зі зв'язевим ригелем з чотирьох сторін симетрично відносно осі стійки.The invention relates to the field of construction and can be used for the erection of precast monolithic floors of residential buildings with bezrigelny monolithic frame. The object of the invention is to improve the method of mounting formwork by the use of modular elements that allow to concrete precast-monolithic flooring and provide bearing capacity for the perception of the own weight of precast reinforced concrete slabs and weight of monolithic concrete overlap, as well as short-term equipment snow load. The object of the proposed method of mounting formwork for the erection of precast-monolithic floors, which includes the arrangement of the working layer of the deck in the form of rectangular sheets of multilayer plywood, the installation of wooden beams of cross-section, and metal racks, is solved as follows: support tables in the form of a metal clip for support from one to four metal sprungel crossbars with a length equal to half a step of columns, and the strengthened metal support columns and with the elements for fastening the ties supporting the free end of the spherical crossbar, are combined in pairs with the connecting crossbar, the crossbar crossbar is made of a beam in the form of a metal tube square section with welding in the middle of the span perpendicular to the axis of the spherical barrel fragment reinforcing rods, and the design of the lock connects the reinforced metal support struts with a connecting bolt on four sides symmetrically relative to the axis of the strut.

UAA201601845A 2016-02-26 2016-02-26 METHOD OF METAL INSTALLATION FOR PREFABRICATION UA115707C2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
UAA201601845A UA115707C2 (en) 2016-02-26 2016-02-26 METHOD OF METAL INSTALLATION FOR PREFABRICATION

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
UAA201601845A UA115707C2 (en) 2016-02-26 2016-02-26 METHOD OF METAL INSTALLATION FOR PREFABRICATION

Publications (1)

Publication Number Publication Date
UA115707C2 true UA115707C2 (en) 2017-12-11

Family

ID=60571523

Family Applications (1)

Application Number Title Priority Date Filing Date
UAA201601845A UA115707C2 (en) 2016-02-26 2016-02-26 METHOD OF METAL INSTALLATION FOR PREFABRICATION

Country Status (1)

Country Link
UA (1) UA115707C2 (en)

Similar Documents

Publication Publication Date Title
RU165473U1 (en) STEEL-CONCRETE PRE-STRESSED BEAM
CN101851984B (en) Prefabricated steel-concrete composite beam
RU155802U1 (en) STEEL CONCRETE PRE-STRESSED BEAM
AU2015100669A4 (en) Hollow Wall
Tedia et al. Cost, analysis and design of steel-concrete composite structure Rcc structure
JP2018520285A (en) Prefabricated column and beam type construction
Szydlowski et al. New Concept of Semi-precast Concrete Slab on Pre-tensioned Boards
CN107965053B (en) Anti-seismic frame structure formed by combining upright columns and connecting beams and construction method thereof
RU160846U1 (en) PRELIMINARY-TENSIONED REINFORCED-MONOLITHIC REINFORCED CONCRETE PLATE OF THE ROADWAY OF THE UNRACKED STEEL-REINFORCED CONCRETE BRIDGE
Bhojkar et al. Seismic evaluation of high-rise structure by using steel bracing system
Monisha et al. Experimental behaviour of prestress hollow core slab, RC hollow core slab and normal RC solid slab
UA115707C2 (en) METHOD OF METAL INSTALLATION FOR PREFABRICATION
Zhao et al. Application technology of bamboo reinforced concrete in building structure
Maraveas et al. Assessment and restoration of the first Greek power plant–registered monument of industrial heritage
RU115796U1 (en) WOOD AND FOAM CONCRETE overlapping
RU2547035C2 (en) Nodal coupling of pillar with monolithic slab
RU151169U1 (en) SPAN STRUCTURE OF A CURTAIN BRIDGE
RU2611661C1 (en) Metal frame of monolithic reinforced concrete slab
Desai et al. Seismic behaviour of flat slab framed structure with and without masonry infill wall
Park et al. Corner Steel plate-Reinforced Core Wall System
RU82726U1 (en) STEEL REINFORCED CONCRETE FRAME
RU2514075C1 (en) Building-bridge
RU171833U1 (en) Cottage
EA200602233A3 (en) TEAM AND MONOLITH COVERAGE FRAME BUILDING (VARIANTS)
RU2550624C1 (en) Combined joint of girders and columns