TWM593625U - Green building engineering inspection management system - Google Patents

Green building engineering inspection management system Download PDF

Info

Publication number
TWM593625U
TWM593625U TW108207710U TW108207710U TWM593625U TW M593625 U TWM593625 U TW M593625U TW 108207710 U TW108207710 U TW 108207710U TW 108207710 U TW108207710 U TW 108207710U TW M593625 U TWM593625 U TW M593625U
Authority
TW
Taiwan
Prior art keywords
inspection
project
data
database
equipment
Prior art date
Application number
TW108207710U
Other languages
Chinese (zh)
Inventor
王獻堂
莊智凱
Original Assignee
冠呈能源環控有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 冠呈能源環控有限公司 filed Critical 冠呈能源環控有限公司
Priority to TW108207710U priority Critical patent/TWM593625U/en
Publication of TWM593625U publication Critical patent/TWM593625U/en

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

一種綠建築工程查驗管理系統,包括有一伺服主機、一伺服資料庫及至少一移動電子裝置,透過比對內建之各式綠建築設備標準性能資料,能自動生成專案專屬之查驗表單,供查驗人員能輕鬆地依表單項目進行設備檢測,有助於降低專業人力之需求並提升查驗效率,且利用能現場運算性能查驗結果,即時提供雙方核實,能大幅降低事後爭議,遲滯查驗流程之問題。 A green building engineering inspection management system, including a servo host, a servo database and at least one mobile electronic device, by comparing the built-in various green building equipment standard performance data, a project-specific inspection form can be automatically generated for inspection The personnel can easily carry out the equipment inspection according to the form items, which helps reduce the demand for professional manpower and improve the inspection efficiency, and utilizes the on-site computing performance inspection results to provide immediate verification by both parties, which can greatly reduce post-event disputes and delay the inspection process.

Description

綠建築工程查驗管理系統 Green building engineering inspection management system

本創作係有關綠建築工程查驗之管理系統,特別是一種能提升綠建築工程查驗效率與便利性之綠建築工程查驗管理系統。 This creation is a management system related to green building engineering inspection, especially a green building engineering inspection management system that can improve the efficiency and convenience of green building engineering inspection.

綠建築概念約源自1999年,我國(台灣)繼英國BREEAM、美國LEED、加拿大GBTOOL後推動綠建築評鑑制度,綠建築標章EEWH(Ecology(生態)、Energy Saving(節能)、Waste Reduction(減廢)和Health(健康)之簡稱)制度開始實施,建立有七項指標,並依優劣分有五種等級。 The concept of green building originated in 1999. China (Taiwan) promoted the green building evaluation system after the British BREEAM, the US LEED, and the Canadian GBTOOL. The green building seal EEWH (Ecology, Energy Saving, Waste Reduction Waste reduction) and Health (abbreviation of health) systems have been implemented, with seven indicators established and five grades according to their merits.

綠建築的評鑑,主要是針對綠建築機電工程之性能狀態進行評鑑,評斷綠建築的工程是否達設計之標準;而機電工程產業,一直以來都是大量倚賴經驗之產業,工程業者必須運用其豐富之實務經驗來滿足客戶之需求,為滿足客戶對機電系統或設備多樣性、多變性需求,機電工程不斷開發各式各樣的工法與多種實用性的理念,但在理念實現與工法施作的過程中,由於機電的構件數量龐大與施工作業複雜,資訊一貫化、管理自動化及作業標準化難以被顧及的面面俱到。 The evaluation of green buildings is mainly to evaluate the performance status of green building electromechanical engineering, to judge whether the green building engineering meets the design standards; and the electromechanical engineering industry has always been an industry that relies heavily on experience, and the engineering industry must use Its rich practical experience meets the needs of customers. In order to meet the needs of customers for the diversity and variability of electromechanical systems or equipment, electromechanical engineering continues to develop various construction methods and a variety of practical concepts, but in the realization of concepts and construction methods In the course of work, due to the large number of electromechanical components and the complexity of construction operations, the consistency of information, automation of management, and standardization of operations are difficult to be taken into account.

綠建築機電工程之規劃,即在基本設計、實施設計、發包、 施工過程中,實施一連串管制措施,使機電控制在規劃階段所擬定的目標範圍內;但機電之開發、施作過程所可能面臨到的問題相當繁多,且連帶關係甚為複雜,並非每一個綠建築工程案,皆可輕易隨設計方案確實達到預期成果;因此,如何能夠使業主能夠確實掌握設備,施工安裝運行流程,正確掌握施工狀態,係當下機電工程產業必須要面臨的問題。 The planning of green building mechanical and electrical engineering, namely in basic design, implementation design, contracting, During the construction process, a series of control measures were implemented to make the electromechanical control within the target range set in the planning stage; however, the problems that may be encountered in the development and implementation of electromechanical are quite numerous, and the associated relationship is very complicated, not every green Construction projects can easily achieve the expected results with the design plan; therefore, how to enable the owner to truly grasp the equipment, construction, installation and operation processes, and correctly grasp the construction status is a problem that the electromechanical engineering industry must face today.

再者,綠建築的機電工程流程大致可分為多種階段,例如:於工程之規劃階段擬定規範、工程之設計方案是否有可選定之商源設備、工程在預算內是否可完成發包,以及得標廠商在預定工期及預算內完成標地建物興建,並獲得合理利潤,如何如期如值得完成規劃設計之機電性能為先決條件等。 In addition, the green building electromechanical engineering process can be roughly divided into various stages, such as: drawing up specifications at the planning stage of the project, whether the design of the project has selectable source equipment, whether the project can be completed within the budget, and The bidder completes the construction of the landmark buildings within the scheduled time limit and budget, and obtains a reasonable profit. How to complete the mechanical and electrical performance of the planning and design as scheduled is a prerequisite.

在台灣傳統機電工程產業體制中,設備安裝、材料保護、試運轉、運行性能測試、系統調整、控制點對點查驗、控制系統測試,大都由人工拍攝紀錄,不但費工、費時、容易產生錯誤,且一旦產生錯誤,更正亦較為費時。再者,目前大多數工地工期管理現行方法,為工程負責人於開工前,以人力製作簡單的施工紀錄表,對於設備性能計算、檔案歸檔、文件製作精細度皆未效率的規範。 In Taiwan’s traditional electromechanical engineering industry system, equipment installation, material protection, trial operation, operation performance testing, system adjustment, control point-to-point inspection, and control system testing are mostly recorded manually, which is not only laborious, time-consuming, and error-prone. Once an error occurs, correction is more time-consuming. Furthermore, the current current method of site construction period management is that the person in charge of the project prepares a simple construction record sheet by manpower before the start of construction, which is an inefficient specification for equipment performance calculation, file archiving, and document production precision.

一般熟悉機電工程的業者,對系統與單機性能量測驗收的普遍看法,都認為紀錄項目繁多瑣碎,且變數很多,尤其是性能量測,單台設備出現問題,便將使整個進度延期,近一步討論更可發現普遍在量測結束回辦公室製作報告時,才發現錯誤需重新再行量測,因此對量測的時間管理並不樂觀;同樣地,綠建築工程也囊括有上述問題,當最後查驗時發現未能達設計方案之標準時,往往會大幅遲滯進度,大量的人力及時間資 源浪費,甚至容易有雙方或多方(如業主、施工方、查驗方)爭議、戶不認帳之問題產生。因此,如何有效建立一套可以節省人力、減少爭議與錯誤,有效控管進度、以及迅速有效地整合各流程項目,進而精準有效地控管工程品質,係綠建築與機電工程領域長久以來有待改善的重要課題。 Those who are familiar with electromechanical engineering generally agree on the performance measurement and acceptance of systems and stand-alone machines. They believe that there are many and trivial recording items and many variables, especially performance measurement. If a single device fails, the entire progress will be delayed. One step of discussion can be found that it is generally found that the error needs to be re-measured when the measurement is completed and returned to the office. Therefore, the time management of the measurement is not optimistic; similarly, the green building project also includes the above problems. In the final inspection, when it is found that the standard of the design scheme is not met, the progress will often be greatly delayed, a lot of manpower and time resources The source is wasted, and it is even easy for disputes between two or more parties (such as the owner, the construction party, and the inspector) to occur and the households not to accept the accounts. Therefore, how to effectively establish a set that can save manpower, reduce disputes and errors, effectively control the progress, and quickly and effectively integrate various process projects to accurately and effectively control the quality of the project is a long-term improvement in the field of green construction and electromechanical engineering. Important subject.

本創作主要目的係提供了一種綠建築工程查驗管理系統,藉由能依個案生成專屬查驗表單,以及方便攜帶並能透過網路同步且內建人性化操作介面之移動電子裝置,讓查驗人員能依查驗表單編列之項目輕鬆進行檢測,根據檢測數據現場進行運算,提供雙方核實查驗結果,進而精準有效的追蹤控管工程之進度與品質,及早發覺問題與改善,提高綠建築之工程與查驗之效率。 The main purpose of this creation is to provide a green building engineering inspection management system. By generating a dedicated inspection form on a case-by-case basis and a mobile electronic device that is easy to carry and can be synchronized through the network and has a built-in user-friendly operation interface, inspection personnel can The items listed in the inspection form can be easily tested, and the calculations can be performed on the spot based on the detection data to provide both parties to verify the inspection results, so as to accurately and effectively track the progress and quality of the control project, detect problems and improvements early, and improve the engineering and inspection of the green building. effectiveness.

為達成上述功效目的,本創作綠建築工程查驗管理系統主要採行之技術手段係包括有一伺服資料庫、一伺服主機及至少一移動電子裝置;該伺服資料庫其至少包含一綠建築設備資料庫及一專案資料庫,該綠建築設備資料庫用以存儲各式綠建築設備標準性能資料,該專案資料庫用以存儲複數專案之設計資料及查驗數據資料;該伺服主機係設有一用以提供管理操作之管理介面,且該管理介面連結該伺服資料庫並包含一用以管理使用者身分之人員管理模組及一專案管理模組,其中該專案管理模組係用以追蹤該各專案之查驗進度及管理該各專案之設計資料及查驗數據資料,且該專案管理模組於新進專案時能依該新進專案設計之工程設備比對該綠建築設備數據庫生成該新進專案預定查驗項目之查驗表單;該移動電 子裝置係能透過網際網路連結該伺服資料庫,包含一操作介面及一儲存單元,該操作介面連結該儲存單元,用以供使用者依身分登入與操作,該儲存單元包含有一綠建築設備資料庫及一專案查驗記錄,該綠建築設備資料庫係能從該伺服資料庫之綠建築設備資料庫更新資料,該專案查驗記錄係能從該專案資料庫取得新進專案之設計資料及查驗表單,供使用者透過操作介面依預定查驗項目記錄查驗數據資料,並透過網際網路將該查驗表單的數據資料同步回該伺服資料庫;其中,該操作介面包含一記錄存證模組及一性能檢核模組,該記錄存證模組用以供使用者依該查驗表單檢測該專案之設備並記錄查驗數據資料,該性能檢核模組用以拋轉運算查驗數據資料及比對該綠建築設備數據庫,綜合該專案設計資料判斷該設備之性能查驗結果,以供現場核實查驗數據資料。 In order to achieve the above purpose, the technical means adopted by the green building engineering inspection management system include a servo database, a servo host and at least one mobile electronic device; the servo database contains at least a green building equipment database And a project database, the green building equipment database is used to store various types of green building equipment standard performance data, the project database is used to store design data and inspection data of multiple projects; the server host is provided with a Management interface for management operations, and the management interface is linked to the server database and includes a personnel management module for managing user identities and a project management module, where the project management module is used to track the status of each project Check the progress and manage the design data and inspection data of each project, and the project management module can generate the inspection of the new inspection project according to the engineering equipment designed by the new project according to the engineering equipment design of the new project. Form; the mobile The sub-device can be connected to the server database through the Internet, and includes an operation interface and a storage unit. The operation interface is connected to the storage unit for users to log in and operate according to their identity. The storage unit includes a green construction equipment Database and a project inspection record, the green construction equipment database can update data from the green construction equipment database of the servo database, and the project inspection record can obtain the design data and inspection form of new projects from the project database , For users to record the inspection data according to the predetermined inspection items through the operation interface, and synchronize the data of the inspection form back to the server database through the Internet; wherein, the operation interface includes a record storage module and a performance Verification module, the record storage module is used for users to detect the equipment of the project according to the verification form and record the verification data, and the performance verification module is used to toss the calculation verification data and compare the green The construction equipment database integrates the project design data to judge the performance inspection results of the equipment for on-site verification of the inspection data.

藉此,管理者可透過管理平台登錄新進專案並自動生成查驗表單,提供外派之查驗員依查驗項目進行檢測,有助於減少須人為經驗判斷的資歷需求,適度培訓即可依排程作業,提升查驗效率;透過資料同步能即時追蹤專案工程及查驗之進度,現場數據運算能統一查驗品質,減少人為疏失及查驗後驗算可能發生的爭議,達到及早發覺問題並改善目標,係能有效控管綠建築工程品質、設備運行效率、簡化查驗流程之管理系統。 In this way, the manager can log in the new project through the management platform and automatically generate an inspection form to provide an inspector who is dispatched to perform inspection according to the inspection item, which helps reduce the qualification requirements that require human experience judgment. To improve the inspection efficiency; through data synchronization, the progress of project projects and inspections can be tracked in real time. On-site data calculation can unify the quality of inspections, reduce human error and possible disputes after the inspections, achieve early detection of problems and improve goals, which can be effectively controlled A management system that manages the quality of green building projects, equipment operating efficiency, and simplifies the inspection process.

依上述系統架構,其中該管理介面進一步包含有一查驗結果匯出模組,其係連結該綠建築設備資料庫及該專案資料庫,用以依操作將完成查驗之專案數據資料經拋轉運算及比對該綠建築設備數據庫,綜合該專案設計資料判斷並輸出該專案設備項目的性能查驗結果。 According to the above system architecture, the management interface further includes an inspection result export module, which is connected to the green construction equipment database and the project database, and is used to transfer the completed project data data to the operation according to the operation and Compare with the green construction equipment database, integrate the project design data to judge and output the performance inspection results of the project equipment project.

依上述系統架構,其中該管理介面可再進一步包含一綠建築 設備數據更新模組,用以供操作輸入更新之綠建築設備標準性能資料。 According to the above system architecture, the management interface may further include a green building The equipment data update module is used for the operation to input updated green building equipment standard performance data.

依上述系統架構,其中該綠建築設備標準性能資料可包含有BIM模型資料(Building Information Modeling)。 According to the above system architecture, the green building equipment standard performance data may include BIM model information (Building Information Modeling).

依上述系統架構,其中該記錄存證模組記錄之查驗數據資料至少包含檢測之數值記錄及存證之照片記錄。 According to the above system architecture, the verification data recorded by the record storage module at least includes the detected value record and the photo record of the record.

依上述系統架構,其中該各專案之設備項目至少包含泵浦葉輪、風車葉輪、盤管、冰水主機、儲冰主機、熱泵主機、熱回收主機或冷卻水塔其中之一或任意組合。 According to the above system architecture, the equipment items of each project include at least one or any combination of pump impeller, windmill impeller, coil, ice water host, ice storage host, heat pump host, heat recovery host or cooling water tower.

為使本創作之上述目的、特徵及功能作用獲致更具體的瞭解,茲舉本創作較佳之實施例並配合附圖說明如後: In order to gain a more specific understanding of the above purpose, features and functions of this creation, the preferred embodiments of this creation are described below with the accompanying drawings as follows:

1‧‧‧綠建築工程查驗管理系統 1‧‧‧ Green Building Engineering Inspection Management System

10‧‧‧伺服主機 10‧‧‧Servo host

11‧‧‧管理介面 11‧‧‧ Management interface

111‧‧‧人員管理模組 111‧‧‧Personnel Management Module

112‧‧‧專案管理模組 112‧‧‧Project management module

113‧‧‧查驗結果匯出模組 113‧‧‧Examination result export module

114‧‧‧綠建築設備數據更新模組 114‧‧‧ Green Construction Equipment Data Update Module

12‧‧‧伺服資料庫 12‧‧‧Servo database

121‧‧‧人員資料庫 121‧‧‧ personnel database

122‧‧‧專案資料庫 122‧‧‧ Project database

123‧‧‧綠建築設備資料庫 123‧‧‧ Green Construction Equipment Database

20‧‧‧移動電子裝置 20‧‧‧Mobile electronic device

21‧‧‧操作介面 21‧‧‧Operation interface

211‧‧‧記錄存證模組 211‧‧‧ record certificate module

212‧‧‧性能檢核模組 212‧‧‧Performance Inspection Module

22‧‧‧儲存單元 22‧‧‧Storage unit

221‧‧‧專案查驗記錄 221‧‧‧ Project inspection record

222‧‧‧綠建築設備資料庫 222‧‧‧ Green Construction Equipment Database

30‧‧‧網際網路 30‧‧‧Internet

第1圖係本創作實施例系統方塊示意圖。 Fig. 1 is a block diagram of the system of this creative embodiment.

第2圖係本創作實施例伺服主機之方塊示意圖。 FIG. 2 is a block diagram of the servo host in this creative embodiment.

第3圖係本創作實施例行動電子裝置之方塊示意圖。 FIG. 3 is a block diagram of a mobile electronic device of this creative embodiment.

第4圖係本創作實施例一操作介面之示意圖。 FIG. 4 is a schematic diagram of an operation interface of the first embodiment of the present creation.

第5圖係本創作實施例另一操作介面之示意圖。 FIG. 5 is a schematic diagram of another operation interface of this creative embodiment.

請參閱第1圖,可知本創作系統架構主要包括能透過網際網路30相互連結的伺服主機10、伺服資料庫12及移動電子裝置20等部分。 Please refer to FIG. 1, it can be seen that the architecture of the authoring system mainly includes a server host 10, a server database 12 and a mobile electronic device 20 that can be connected to each other through the Internet 30.

該伺服資料庫12,可配合參閱第2圖,其中主要包含有一人員資料庫121、一專案資料庫122及一綠建築設備資料庫123。該人員資料庫121主要用來儲存使用者相關資料,使用者可分為管理人員及查驗人員,相關之資料包含如人員身分資料、對應之身分驗證帳號密碼、查驗人員派遣狀態、派遣記錄等的人員檔案資料。該綠建築設備資料庫123主要存儲有各式綠建築設備標準性能資料,諸如記錄了各種廠牌、款式的綠建築機電設對應的性能判斷項目及規範的標準性能參數,以供系統作為比對或運算判斷之依據。該專案資料庫122則係用來儲存專案的設計資料及查驗數據資料。 The servo database 12 can be coordinated with reference to FIG. 2, which mainly includes a personnel database 121, a project database 122 and a green construction equipment database 123. The personnel database 121 is mainly used to store user-related data. Users can be divided into management personnel and inspection personnel. Related data includes such as personnel identification data, corresponding identity verification account passwords, inspection personnel dispatch status, dispatch records, etc. Personnel file information. The green building equipment database 123 mainly stores various types of green building equipment standard performance data, such as recording the performance judgment items and standard standard performance parameters corresponding to various brands and styles of green building mechanical and electrical equipment for the system to compare Or the basis for operation judgment. The project database 122 is used to store project design data and inspection data.

該伺服主機10,其主要係有一管理介面11,用以提供管理人員經身分驗證後能登陸進行各種管理操作,該管理介面11至少設有一人員管理模組111、一專案管理模組112、一查驗結果匯出模組113及一綠建築設備數據更新模組114。其中,該人員管理模組111主要是連結該人員資料庫121,用以供管理人員對人員檔案資料進行查閱、更新或紀錄等之操作管理。該專案管理模組112係連結該專案資料庫122及該綠建築設備資料庫123,根據各專案的進度狀態分別提供有新進專案時表單生成、派遣查驗時追蹤查驗進度及數據管理等功能;其中,於新建專案時能依該專案設計之工程設備比對該綠建築設備數據庫123生成該專案預定查驗項目之查驗表單,儲存於該專案資料庫122,供派遣之查驗人員利用移動電子裝置20取得表單進行查驗,而在查驗過程中,管理人員可從該專案資料庫122查閱查驗中專案同步的記錄,以追蹤判斷查驗進度,以及管理該些專案的設計資料及查驗數據資料。 The server host 10 is mainly provided with a management interface 11 for providing management personnel who can log in to perform various management operations after identity verification. The management interface 11 is provided with at least a personnel management module 111, a project management module 112, a The inspection result export module 113 and a green construction equipment data update module 114. Among them, the personnel management module 111 is mainly connected to the personnel database 121 for the management personnel to perform operations management such as searching, updating or recording personnel file data. The project management module 112 is connected to the project database 122 and the green building equipment database 123, and provides functions such as form generation when entering a new project, tracking inspection progress during dispatch inspection, and data management according to the progress status of each project; , When the project is newly built, it can generate the inspection form of the scheduled inspection items of the project according to the engineering equipment design of the project compared to the green construction equipment database 123, which is stored in the project database 122 for the dispatched inspection personnel to obtain using the mobile electronic device 20 The form is inspected, and during the inspection process, the administrator can check the project synchronization records from the project database 122 to track and judge the inspection progress, and manage the design data and inspection data of these projects.

一般而言,綠建築專案的工程設備項目可為泵浦葉輪、風車葉輪、盤管、冰水主機、儲冰主機、熱泵主機、熱回收主機、冷卻水塔等等。 Generally speaking, the engineering equipment projects of the Green Building Project can be pump impeller, windmill impeller, coil, ice water host, ice storage host, heat pump host, heat recovery host, cooling water tower, etc.

該查驗結果匯出模組113係連結該專案資料庫122及該綠建築設備資料庫123,供管理人員操從專案資料庫122取得專案資料,依其數據資料經拋轉運算及比對該綠建築設備數據庫,綜合該專案設計資料判斷並輸出該專案設備項目的性能查驗結果,進一步的,可依需求輸出為預期的執行報告或記錄數據等格式。該綠建築設備數據更新模組114其係連結該綠建築設備資料庫123,提供管理人員將新增的綠建築設備標準性能資料更新至該綠建築設備資料庫123,進者,該綠建築設備標準性能資料可包含有BIM模型資料(Building Information Modeling),操作人員可藉此快速匯入專案之BIM模型資料,可大量減少人力與物力,讓一般查驗人員能利用BIM模型資料,解決高專業能力需求之問題。 The verification result export module 113 is connected to the project database 122 and the green construction equipment database 123, for the management personnel to obtain project data from the project database 122, according to the data after tossing calculation and comparison of the green The construction equipment database integrates the project design data to judge and output the performance inspection results of the project equipment project. Further, it can be output as expected execution report or record data and other formats according to demand. The green building equipment data update module 114 is connected to the green building equipment database 123, and provides management personnel to update the new green building equipment standard performance data to the green building equipment database 123. Standard performance data can include BIM model data (Building Information Modeling), which allows operators to quickly import project BIM model data, which can greatly reduce manpower and material resources, allowing general inspectors to use BIM model data to solve high professional capabilities The problem of demand.

該移動電子裝置20,主要作為供查驗人員攜帶至施工現場的記錄儀器,透過網際網路30連結該伺服資料庫12,於本創作實施例中係採用具拍攝功能的平板電腦。該移動電子裝置20至少內建有一儲存單元22並可供執行一操作介面21,該操作介面21提供了方便查驗人員操作的人性化界面(如第4圖所示),查驗人員可於身分驗證登入後進行操作;該儲存單元22連結該操作介面21,並能透過網際網路30與該伺服資料庫12連線資料同步,至少提供存儲有一專案查驗記錄221及一綠建築設備資料庫222,該專案查驗記錄221係能從該專案資料庫12取得新進專案之設計資料及查驗表單,供查驗人員透過操作介面21依預定查驗項目記錄查驗數據資 料,再將該查驗表單的數據資料同步回該伺服資料庫12,而該綠建築設備資料庫222係能從該伺服資料庫12的綠建築設備資料庫123更新各式綠建築設備標準性能的資料。該操作介面21設有一記錄存證模組211及一性能檢核模組212,該記錄存證模組211係供查驗人員依查驗表單(如第4圖左側所示的查驗項目)檢測相應專案之設備並記錄查驗數據資料,於本實施例中,所記錄之查驗數據資料包含有檢測之數值記錄及用於存證的照片記錄(如第4圖所示);而該性能檢核模組212係能拋轉運算查驗數據資料及比對該綠建築設備數據庫222,綜合該專案設計資料判斷該設備之性能查驗結果,性能查驗結果可透過數據呈現或以圖表呈現,數據呈現概如第4圖所示之設計值、實測值提供比對,而圖表呈現概如第5圖所示,係以綠建築設備的標準性能曲線與實測之落點提供比對,以供現場雙方或多方核實查驗數據資料。 The mobile electronic device 20 is mainly used as a recording instrument for inspectors to bring to the construction site, and is connected to the servo database 12 through the Internet 30. In this creative embodiment, a tablet computer with a shooting function is used. The mobile electronic device 20 has at least a storage unit 22 built in and can be used to execute an operation interface 21, which provides a user-friendly interface (as shown in FIG. 4) for the inspection personnel to operate, and the inspection personnel can verify their identity Operate after logging in; the storage unit 22 connects to the operation interface 21, and can synchronize with the connection data of the server database 12 through the Internet 30, and at least provide a storage of a project inspection record 221 and a green construction equipment database 222, The project inspection record 221 can obtain the design data and inspection form of the new project from the project database 12 for the inspection personnel to record the inspection data according to the scheduled inspection items through the operation interface 21 Data, and then synchronize the data of the inspection form back to the servo database 12, and the green building equipment database 222 can update the standard performance of various green building equipment from the green building equipment database 123 of the servo database 12. data. The operation interface 21 is provided with a record storage module 211 and a performance verification module 212. The record storage module 211 is for inspection personnel to inspect the corresponding project according to the inspection form (the inspection items shown on the left side of Figure 4) Equipment and record inspection data, in this embodiment, the recorded inspection data includes the detected numerical records and photo records for certificate storage (as shown in Figure 4); and the performance verification module 212 is able to toss calculation data and compare with the green construction equipment database 222, synthesize the project design data to judge the performance inspection results of the equipment. The performance inspection results can be presented through data or graphs. The design value and measured value shown in the figure provide comparison, and the chart is presented as shown in Figure 5. The standard performance curve of the green construction equipment is compared with the measured drop point for the verification of the two or more parties on the site data.

實際應用時,綠建築業主於工程完成後提出查驗要求,管理人員可透過管理介面11建立新專案,專案管理模組112即根據專案設計之工程設備與綠建築設備數據庫123比對,生成此專案專屬的查驗表單;隨後,查驗人員即可利用移動電子裝置20取得該查驗表單,至該綠建築專案的施工現場進行查驗,透過操作介面21陳列該查驗表單預定的查驗項目,逐一對相應的綠建築設備進行檢測,透過記錄存證模組211記錄檢測之數值並拍攝檢測之設備、環境或檢測過程之存證照片,於各設備預定的查驗項目檢測完成後,可利用性能檢核模組212直接運算出該設備之性能查驗結果,供現場的業主或工程人員核實,確認檢測之正確性。待所有查驗項目完成後,即可透過網際網路30或移動至有網際網路30之環境下,將此專 案的查驗數據資料同步回傳至該專案資料庫122,之後管理人員即可利用查驗結果匯出模組113來匯出查驗結果或製成查驗報告,迅速且準確地完成綠建築查驗之流程。 In actual application, the owner of the green building puts forward inspection requirements after the project is completed. The management personnel can create a new project through the management interface 11. The project management module 112 compares the engineering equipment designed according to the project with the green building equipment database 123 to generate this project Exclusive inspection form; then, the inspector can use the mobile electronic device 20 to obtain the inspection form, go to the construction site of the green building project for inspection, and display the predetermined inspection items of the inspection form through the operation interface 21, one by one corresponding green Testing of construction equipment, record the value of the test through the record storage module 211 and take a photo of the test equipment, environment or test process. After the inspection of the predetermined inspection items of each equipment is completed, the performance verification module 212 can be used Calculate the performance inspection result of the equipment directly for verification by the owner or engineer on site to confirm the correctness of the inspection. After all the inspection items are completed, you can use Internet 30 or move to an environment with Internet 30 The inspection data of the case is synchronously returned to the project database 122, and then the management personnel can use the inspection result export module 113 to export the inspection result or make an inspection report, and complete the green building inspection process quickly and accurately.

綜合以上所述,本創作確能提升綠建築工程查驗之效率,減少進度遲滯與爭議,且能降低專業人力之需求,提高查驗作業之便利性,確保查驗品質,實為一具新穎性及進步性之創作,爰依法提出專利申請;惟上述說明之內容,僅為本創作之較佳實施例說明,舉凡依本創作之技術手段與範疇所延伸之變化、修飾、改變或等效置換者,皆應落入本創作之專利申請範圍內。 Based on the above, this creation can indeed improve the efficiency of green building engineering inspection, reduce progress lag and disputes, and reduce the demand for professional manpower, improve the convenience of inspection operations, and ensure the quality of inspection. It is a novelty and progress. For a creative creation, a patent application is filed in accordance with the law; however, the above description is only for the description of the preferred embodiment of this creation, and any change, modification, alteration, or equivalent replacement of the extension of the technical means and scope of this creation, All should fall within the scope of the patent application for this creation.

1‧‧‧綠建築工程查驗管理系統 1‧‧‧ Green Building Engineering Inspection Management System

10‧‧‧伺服主機 10‧‧‧Servo host

12‧‧‧伺服資料庫 12‧‧‧Servo database

20‧‧‧移動電子裝置 20‧‧‧Mobile electronic device

30‧‧‧網際網路 30‧‧‧Internet

Claims (6)

一種綠建築工程查驗管理系統,包括:一伺服資料庫,其至少包含一綠建築設備資料庫及一專案資料庫,該綠建築設備資料庫用以存儲各式綠建築設備標準性能資料,該專案資料庫用以存儲複數專案之設計資料及查驗數據資料;一伺服主機,其設有一用以提供管理操作之管理介面,該管理介面連結該伺服資料庫,且至少包含:一人員管理模組,用以管理使用者身分;一專案管理模組,用以追蹤該各專案之查驗進度及管理該各專案之設計資料及查驗數據資料,且該專案管理模組於新進專案時能依該新進專案設計之工程設備比對該綠建築設備數據庫生成該新進專案預定查驗項目之查驗表單;至少一移動電子裝置,其係能透過網際網路連結該伺服資料庫,包含一操作介面及一儲存單元,該操作介面連結該儲存單元,用以供使用者依身分登入與操作,該儲存單元包含有一綠建築設備資料庫及一專案查驗記錄,該綠建築設備資料庫係能從該伺服資料庫之綠建築設備資料庫更新資料,該專案查驗記錄係能從該專案資料庫取得新進專案之設計資料及查驗表單,供使用者透過操作介面依預定查驗項目記錄查驗數據資料,並透過網際網路將該查驗表單的數據資料同步回該伺服資料庫;其中,該操作介面包含一記錄存證模組及一性能檢核模組,該記錄存證模組用以供使用者依該查驗表單檢測該專案之設備並記錄查驗數據資料,該性能檢核模組用以拋轉運算查驗數據資料及比對該綠建築設備數據庫,綜合該專案設計資料判斷該設備之性能查驗結果, 以供現場核實查驗數據資料。 A green construction engineering inspection management system includes: a servo database, which includes at least a green construction equipment database and a project database. The green construction equipment database is used to store various types of green construction equipment standard performance data. The database is used to store the design data and inspection data of the plural project; a servo host, which is provided with a management interface for providing management operations, the management interface is connected to the server database, and at least includes: a personnel management module, Used to manage user identities; a project management module to track the inspection progress of each project and manage the design data and inspection data of each project, and the project management module can follow the new project when it is newly entered The designed engineering equipment compares the green construction equipment database to generate the inspection form of the new project's scheduled inspection items; at least one mobile electronic device, which can connect to the servo database via the Internet, includes an operation interface and a storage unit, The operation interface is connected to the storage unit for users to log in and operate according to their identity. The storage unit includes a green construction equipment database and a project inspection record. The green construction equipment database can be accessed from the green Update data of the construction equipment database. The project inspection record can obtain the design data and inspection form of the new project from the project database for the user to record the inspection data according to the predetermined inspection items through the operation interface, and use the Internet to save the inspection data. The data of the verification form is synchronized back to the server database; wherein, the operation interface includes a record storage module and a performance verification module. The record storage module is used for the user to detect the project according to the verification form Equipment and record the inspection data, the performance check module is used to turn over the operation inspection data and compare with the green building equipment database, synthesize the project design data to judge the performance inspection results of the equipment, For on-site verification and inspection data. 如申請專利範圍第1項所述之綠建築工程查驗管理系統,其中該管理介面進一步包含一查驗結果匯出模組,其連結該綠建築設備資料庫及該專案資料庫,用以依操作將完成查驗之專案數據資料經拋轉運算及比對該綠建築設備數據庫,綜合該專案設計資料判斷並輸出該專案設備項目的性能查驗結果。 The green building engineering inspection management system as described in item 1 of the patent application scope, wherein the management interface further includes an inspection result export module, which connects the green building equipment database and the project database to The project data of the completed inspection is tossed and compared with the green construction equipment database, and the design data of the project is integrated to determine and output the performance inspection results of the project equipment project. 如申請專利範圍第1項所述之綠建築工程查驗管理系統,其中該管理介面進一步包含一綠建築設備數據更新模組,用以供操作輸入更新之綠建築設備標準性能資料。 The green building engineering inspection management system as described in item 1 of the patent application scope, wherein the management interface further includes a green building equipment data update module for the operation to input updated green building equipment standard performance data. 如申請專利範圍第3項所述之綠建築工程查驗管理系統,其中該綠建築設備標準性能資料可包含有BIM模型資料(Building Information Modeling)。 For example, the green building engineering inspection management system as described in item 3 of the patent application scope, wherein the standard performance data of the green building equipment may include BIM model data (Building Information Modeling). 如申請專利範圍第1項所述之綠建築工程查驗管理系統,其中該記錄存證模組記錄之查驗數據資料至少包含檢測之數值記錄及存證之照片記錄。 The green building engineering inspection management system as described in item 1 of the patent application scope, wherein the inspection data recorded by the record storage module at least includes the detected numerical record and the photo record of the storage certificate. 如申請專利範圍第1項所述之綠建築工程查驗管理系統,其中該各專案之設備項目至少包含泵浦葉輪、風車葉輪、盤管、冰水主機、儲冰主機、熱泵主機、熱回收主機或冷卻水塔其中之一或任意組合。 The green building engineering inspection management system as described in item 1 of the patent scope, wherein the equipment items of each project include at least pump impeller, windmill impeller, coil, ice water host, ice storage host, heat pump host, heat recovery host Or one or any combination of cooling water towers.
TW108207710U 2019-06-18 2019-06-18 Green building engineering inspection management system TWM593625U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW108207710U TWM593625U (en) 2019-06-18 2019-06-18 Green building engineering inspection management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW108207710U TWM593625U (en) 2019-06-18 2019-06-18 Green building engineering inspection management system

Publications (1)

Publication Number Publication Date
TWM593625U true TWM593625U (en) 2020-04-11

Family

ID=71133525

Family Applications (1)

Application Number Title Priority Date Filing Date
TW108207710U TWM593625U (en) 2019-06-18 2019-06-18 Green building engineering inspection management system

Country Status (1)

Country Link
TW (1) TWM593625U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111539691A (en) * 2020-04-28 2020-08-14 江苏劲驰电力工程有限公司 Intelligent design comprehensive service system for power distribution engineering and use method
TWI703519B (en) * 2019-06-18 2020-09-01 冠呈能源環控有限公司 Green building engineering mechanical and electrical equipment performance inspection management system
TWI764470B (en) * 2020-07-17 2022-05-11 群光電能科技股份有限公司 Integrated intelligent building management system and management method for the same

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI703519B (en) * 2019-06-18 2020-09-01 冠呈能源環控有限公司 Green building engineering mechanical and electrical equipment performance inspection management system
CN111539691A (en) * 2020-04-28 2020-08-14 江苏劲驰电力工程有限公司 Intelligent design comprehensive service system for power distribution engineering and use method
TWI764470B (en) * 2020-07-17 2022-05-11 群光電能科技股份有限公司 Integrated intelligent building management system and management method for the same

Similar Documents

Publication Publication Date Title
CN114493213A (en) Carbon emission data acquisition and processing method based on Internet of things
TWM593625U (en) Green building engineering inspection management system
US11176028B2 (en) System, method and storage device for CIM/E model standard compliance test
CN109784758B (en) Engineering quality supervision early warning system and method based on BIM model
CN104008510A (en) Power grid project quality control method
CN106484716A (en) Organizational structure method of adjustment and system
CN103942726A (en) Intelligent inspection method for condition evaluation work of power grid equipment
CN116257926B (en) BIM-based Internet of things data binding method, device, equipment and storage medium
CN107507649A (en) A kind of full-automatic test system and its method suitable for solid state hard disc
CN106997524A (en) A kind of cold rolled automobile sheet product design and development system
CN111768172A (en) Engineering safety supervision traceability system based on block chain
CN116228163B (en) Four-electrical engineering intelligent handover method based on BIM platform
TWI703519B (en) Green building engineering mechanical and electrical equipment performance inspection management system
CN107908697A (en) The automatic acquiring method and device of host batch processing job result
CN112734348B (en) Green building engineering electromechanical device performance inspection management system
CN117033206A (en) Test management method and device based on clinical research software research and development process
WO2017063555A1 (en) Automatic system repair method and apparatus based on automatic exercise
CN105868065A (en) SmartRack whole cabinet hot plug component test method
CN111190073B (en) Power grid wide area measurement interaction and search service system
TWI502342B (en) Method and system for automatic synchronization of dual - track test
Gao Research on implementation of software test management
CN115660019B (en) Tool data supervision system and method based on cloud computing platform
TWI769764B (en) Computer assisted system, method, and user equipment for performing building inspection task
CN101894217A (en) Standard consistency testing system and testing method thereof
CN115879730A (en) Power plant equipment defect management system and method based on work order as main line