TWM501548U - Water quality management system for cooling water tower - Google Patents

Water quality management system for cooling water tower Download PDF

Info

Publication number
TWM501548U
TWM501548U TW104202254U TW104202254U TWM501548U TW M501548 U TWM501548 U TW M501548U TW 104202254 U TW104202254 U TW 104202254U TW 104202254 U TW104202254 U TW 104202254U TW M501548 U TWM501548 U TW M501548U
Authority
TW
Taiwan
Prior art keywords
water
tower
pipe
cooling
treated
Prior art date
Application number
TW104202254U
Other languages
Chinese (zh)
Inventor
Qiu-Ting Zeng
Original Assignee
Uni President Entpr Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Uni President Entpr Corp filed Critical Uni President Entpr Corp
Priority to TW104202254U priority Critical patent/TWM501548U/en
Publication of TWM501548U publication Critical patent/TWM501548U/en

Links

Landscapes

  • Separation Using Semi-Permeable Membranes (AREA)
  • Water Treatment By Electricity Or Magnetism (AREA)
  • Treatment Of Water By Ion Exchange (AREA)

Description

冷卻水塔水質管控系統Cooling tower water quality control system

本創作係一種冷卻水塔水質管控系統,尤指檢測並控制水的導電度的冷卻水塔水質管控系統。This creation is a water quality control system for cooling towers, especially the water quality control system for cooling towers that detects and controls the conductivity of water.

於供給冷卻用水的水處理作業中,待處理的水先注入一水塔內,該水塔與冷卻用水之設備間以管件連通,水塔內設置一水位感測器,其中,水塔內的水可通過管件供給需使用冷卻用水的設備,處理過後的水可用以殺菌機、冰水機等機械設備使用,且該水位感測器在檢測到水塔內的水位下降至一定程度後,注水件可將待處理的水再注入水塔內。In the water treatment operation for supplying cooling water, the water to be treated is first injected into a water tower, and the water tower is connected with the equipment for cooling water by a pipe, and a water level sensor is arranged in the water tower, wherein the water in the water tower can be supplied through the pipe. The equipment for cooling water needs to be used, and the treated water can be used by a mechanical device such as a sterilizer or an ice water machine, and the water level sensor can detect the water level in the water tower to a certain extent after the water level sensor detects that the water level in the water tower drops to a certain extent. The water is reinjected into the water tower.

然而,待處理的水含有礦物質,若待處理的水所含的礦物質含量過高時,廢水的排放量大,且相關設備易結構容易阻塞而降低使用壽命與效果,且需以人工進行排水、補水的水質管控作業,無效工時長。However, the water to be treated contains minerals. If the content of minerals contained in the water to be treated is too high, the discharge of the wastewater is large, and the related equipment is easy to block and the service life and effect are reduced, and it is required to be manually performed. Drainage and hydration water quality control operations, long working hours.

本創作之主要目的在於提供一種冷卻水塔水質管控系統,藉此改善需以人工進行排水、補水的水質管控作業,降低無效工時長的問題。The main purpose of this creation is to provide a water quality control system for cooling towers, thereby improving the water quality control operations that require manual drainage and hydration, and reducing the problem of ineffective working hours.

為達成前揭目的,本創作之冷卻水塔水質管控系統,包含有:   一控制單元;   一水塔,其包含一具有容置空間的本體,該本體內設置一導電度感測器,該導電度感測器電性連接該控制單元;   一注水件,其包含一注水管及一水位感測器,該注水管的開口面向該本體的容置空間,該水位感測器設於該本體內;   一出水管,其連通該水塔;   一排水管,其連通該水塔,且該排水管上設置一控制該排水管啟閉的電動閥,該電動閥電性連接該控制單元。In order to achieve the foregoing, the water cooling pipe control system of the present invention comprises: a control unit; a water tower, comprising a body having a receiving space, wherein the body is provided with a conductivity sensor, the conductivity sense The water level sensor is electrically connected to the control unit; a water injection member includes a water injection pipe and a water level sensor, the opening of the water injection pipe faces the accommodating space of the body, and the water level sensor is disposed in the body; An outlet pipe that communicates with the water tower; a drain pipe that communicates with the water tower, and an electric valve that controls opening and closing of the drain pipe is disposed on the drain pipe, and the electric valve is electrically connected to the control unit.

上述中,該冷卻水塔水質管控系統的注水件可將待處理的水,經由該注水管注入該本體的容置空間,以及該導電度感測器可感測水塔中待處理的水的導電度,若導電度超過設定值,表示水中的礦物質含量過高,該控制單元控制該電動閥開啟,讓待處理的水經由該排水管排出,待該導電度感測器感測到水的導電度低於設定值,該控制單元控制該電動閥關閉,讓待處理的水不會經由該排水管排出,而是經由該出水管流至需使用冷卻水之設備中進行處理作業,有效控制水質,改善需以人工進行排水、補水的水質控制作業,並改善無效工時長的問題。In the above, the water injection part of the water quality control system of the cooling tower can inject the water to be treated into the accommodating space of the body via the water injection pipe, and the conductivity sensor can sense the conductivity of the water to be treated in the water tower. If the conductivity exceeds the set value, indicating that the mineral content in the water is too high, the control unit controls the electric valve to open, and the water to be treated is discharged through the drain pipe, and the conductivity sensor senses the conductivity of the water. If the degree is lower than the set value, the control unit controls the electric valve to be closed, so that the water to be treated is not discharged through the drain pipe, but flows through the outlet pipe to the equipment that needs to use the cooling water to effectively control the water quality. Improve the water quality control operations that require manual drainage and hydration, and improve the problem of long working hours.

請參閱圖1,為本創作冷卻水塔水質管控系統之一種較佳實施例,其包含一控制單元10、一水塔20、一注水件30、一出水管40及一排水管50。Referring to FIG. 1 , a preferred embodiment of the water quality control system for the cooling tower is provided. The control unit 10 includes a control unit 10 , a water tower 20 , a water injection unit 30 , an outlet pipe 40 , and a drain pipe 50 .

該水塔20包含一具有容置空間22的本體21,該本體21內設置一導電度感測器23,該導電度感測器23電性連接該控制單元10。The water tower 20 includes a body 21 having an accommodating space 22, and a conductivity sensor 23 is disposed in the body 21, and the conductivity sensor 23 is electrically connected to the control unit 10.

該注水件30包含一注水管31及一水位感測器32,該注水管31的開口面向該本體21的容置空間22,該水位感測器32設於該本體21內,其中,該水位感測器32為一浮球。The water injection member 30 includes a water injection pipe 31 and a water level sensor 32. The opening of the water injection pipe 31 faces the accommodating space 22 of the body 21. The water level sensor 32 is disposed in the body 21, wherein the water level is The sensor 32 is a float.

該出水管40一端連通該水塔20,另一端連通一逆滲透處理裝置,以及該出水管40上設有一控制該出水管40啟閉的控制閥,該控制閥可電性連接該控制單元10。The outlet pipe 40 is connected to the water tower 20 at one end, and the reverse osmosis treatment device is connected to the other end, and the outlet pipe 40 is provided with a control valve for controlling the opening and closing of the outlet pipe 40, and the control valve is electrically connected to the control unit 10.

該排水管50一端連通該水塔20,以及該排水管50上設置一控制該排水管50啟閉的電動閥51,該電動閥51電性連接該控制單元10,且該排水管50上進一步可設置手動閥52,其中,該電動閥51為一電動碟閥。One end of the drain pipe 50 is connected to the water tower 20, and an electric valve 51 for controlling the opening and closing of the drain pipe 50 is disposed on the drain pipe 50. The electric valve 51 is electrically connected to the control unit 10, and the drain pipe 50 is further A manual valve 52 is provided, wherein the electric valve 51 is an electric disc valve.

請參閱圖2所示,待處理的水60經由該注水件30的注水管31注入該水塔20的容置空間22,該導電度感測器23可感測待處理的水60的導電度,導電度的數值在設定值以下,表示待處理的水60的礦物質含量在設定範圍內,該電動閥51關閉該排水管50,待處理的水60可順利通過該出水管40而提供相關設備使用。Referring to FIG. 2 , the water to be treated 60 is injected into the accommodating space 22 of the water tower 20 via the water injection pipe 31 of the water injection member 30 , and the conductivity sensor 23 can sense the conductivity of the water 60 to be treated. The value of the conductivity is below the set value, indicating that the mineral content of the water 60 to be treated is within the set range, the electric valve 51 closes the drain pipe 50, and the water 60 to be treated can smoothly pass the water outlet pipe 40 to provide related equipment. use.

再參閱圖3所示,該導電度感測器23感測待處理的水60的導電度數值在設定值以上時,表示待處理的水60的礦物質含量超過設定範圍,即礦物質的含量過高,則關閉該出水管40,且該控制單元10控制該電動閥51開啟該排水管50,水塔20中待處理的水60經由該排水管50排出,待導電度感測器23待處理的水60的導電度數值降至設定值以下時,該控制單元10控制該電動閥51關閉該排水管50,使該排水管50停止排放水塔20中待處理的水60,並讓待處理的水60可經由該出水管40而流入需冷卻水之設備。Referring to FIG. 3 again, the conductivity sensor 23 senses that the conductivity value of the water 60 to be treated is above a set value, indicating that the mineral content of the water 60 to be treated exceeds a set range, that is, the content of the mineral. If the temperature is too high, the water outlet pipe 40 is closed, and the control unit 10 controls the electric valve 51 to open the drain pipe 50, and the water 60 to be treated in the water tower 20 is discharged through the drain pipe 50, and the conductivity sensor 23 is to be processed. When the conductivity value of the water 60 falls below a set value, the control unit 10 controls the electric valve 51 to close the drain pipe 50, so that the drain pipe 50 stops the water 60 to be treated in the discharge water tower 20, and allows the water to be treated. Water 60 can flow into the apparatus requiring cooling water via the outlet pipe 40.

上述中,該水位感測器32可感測水塔20中待處理的水60的水位下降時,並讓待處理的水60經由該注水管31補充至該水塔20的容置空間22中。In the above, the water level sensor 32 can sense that the water level of the water 60 to be treated in the water tower 20 drops, and the water 60 to be treated is replenished into the accommodating space 22 of the water tower 20 via the water injection pipe 31.

綜上所述,該冷卻水塔水質管控系統的導電度感測器23可感測水塔20中待處理的水60的導電度,依據導電度的數值控制待處理的水60經由該排水管50排出,或者經由該出水管40進入需冷卻水之設備進行處理作業,該冷卻水塔水質管控系統可有效管控進入該需冷卻水之設備的水60的礦物質含量,改善需以人工進行排水、補水的水質管控作業,進而改善無效工時長的問題。In summary, the conductivity sensor 23 of the cooling tower water quality control system can sense the conductivity of the water 60 to be treated in the water tower 20, and control the water 60 to be treated to be discharged through the drain 50 according to the value of the conductivity. Or through the outlet pipe 40 to enter the equipment requiring cooling water for processing, the cooling tower water quality control system can effectively control the mineral content of the water 60 entering the equipment to be cooled, and improve the drainage and hydration by manual Water quality control operations, thereby improving the problem of long working hours.

10‧‧‧控制單元
20‧‧‧水塔
21‧‧‧本體
22‧‧‧容置空間
23‧‧‧導電度感測器
30‧‧‧注水件
31‧‧‧注水管
32‧‧‧水位感測器
40‧‧‧出水管
50‧‧‧排水管
51‧‧‧電動閥
52‧‧‧手動閥
60‧‧‧待處理的水
10‧‧‧Control unit
20‧‧‧Water Tower
21‧‧‧ body
22‧‧‧ accommodating space
23‧‧‧Conductivity sensor
30‧‧‧Water injection parts
31‧‧‧Water injection pipe
32‧‧‧Water level sensor
40‧‧‧Outlet
50‧‧‧Drainage pipe
51‧‧‧Electric valve
52‧‧‧Manual valve
60‧‧‧Water to be treated

圖1:為本創作冷卻水塔水質管控系統之一較佳實施例之平面示意圖。 圖2:為本創作冷卻水塔水質管控系統之一較佳實施例之一使用狀態示意圖。 圖3:為本創作冷卻水塔水質管控系統之一較佳實施例之另一使用狀態示意圖。Figure 1 is a plan view showing a preferred embodiment of the water quality control system for the cooling tower. Figure 2 is a schematic view showing the state of use of one of the preferred embodiments of the water quality control system for the cooling tower. Fig. 3 is a schematic view showing another use state of a preferred embodiment of the water quality control system for the cooling tower.

10‧‧‧控制單元 10‧‧‧Control unit

20‧‧‧水塔 20‧‧‧Water Tower

21‧‧‧本體 21‧‧‧ body

22‧‧‧容置空間 22‧‧‧ accommodating space

23‧‧‧導電度感測器 23‧‧‧Conductivity sensor

30‧‧‧注水件 30‧‧‧Water injection parts

31‧‧‧注水管 31‧‧‧Water injection pipe

32‧‧‧水位感測器 32‧‧‧Water level sensor

40‧‧‧出水管 40‧‧‧Outlet

50‧‧‧排水管 50‧‧‧Drainage pipe

51‧‧‧電動閥 51‧‧‧Electric valve

52‧‧‧手動閥 52‧‧‧Manual valve

60‧‧‧待處理的水 60‧‧‧Water to be treated

Claims (3)

一種冷卻水塔水質管控系統,其包含: 一控制單元; 一水塔,其包含一具有容置空間的本體,該本體內設置一導電度感測器,該導電度感測器電性連接該控制單元; 一注水件,其包含一注水管及一水位感測器,該注水管的開口面向該本體的容置空間,該水位感測器設於該本體內; 一出水管,其連通該水塔; 一排水管,其連通該水塔,且該排水管上設置一控制該排水管啟閉的電動閥,該電動閥電性連接該控制單元。A cooling water tower water quality control system comprising: a control unit; a water tower comprising a body having an accommodating space, wherein a conductivity sensor is disposed in the body, and the conductivity sensor is electrically connected to the control unit a water injection component comprising a water injection pipe and a water level sensor, the opening of the water injection pipe facing the accommodating space of the body, the water level sensor being disposed in the body; and an outlet pipe connecting the water tower; A drain pipe is connected to the water tower, and an electric valve for controlling opening and closing of the drain pipe is disposed on the drain pipe, and the electric valve is electrically connected to the control unit. 如請求項1所述之冷卻水塔水質管控系統,其中,該水位感測器為一浮球。The cooling tower water quality control system according to claim 1, wherein the water level sensor is a floating ball. 如請求項1所述之冷卻水塔水質管控系統,其中,該電動閥為一電動碟閥。The cooling tower water quality control system according to claim 1, wherein the electric valve is an electric disc valve.
TW104202254U 2015-02-12 2015-02-12 Water quality management system for cooling water tower TWM501548U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW104202254U TWM501548U (en) 2015-02-12 2015-02-12 Water quality management system for cooling water tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW104202254U TWM501548U (en) 2015-02-12 2015-02-12 Water quality management system for cooling water tower

Publications (1)

Publication Number Publication Date
TWM501548U true TWM501548U (en) 2015-05-21

Family

ID=53723287

Family Applications (1)

Application Number Title Priority Date Filing Date
TW104202254U TWM501548U (en) 2015-02-12 2015-02-12 Water quality management system for cooling water tower

Country Status (1)

Country Link
TW (1) TWM501548U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115492224A (en) * 2022-11-17 2022-12-20 四川坤睿泽智慧科技有限公司 Automatic inspection system and inspection method for pressure drainage

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115492224A (en) * 2022-11-17 2022-12-20 四川坤睿泽智慧科技有限公司 Automatic inspection system and inspection method for pressure drainage
CN115492224B (en) * 2022-11-17 2023-03-07 四川坤睿泽智慧科技有限公司 Automatic inspection system and inspection method for pressure drainage

Similar Documents

Publication Publication Date Title
WO2016010135A1 (en) Flue gas desulfurization apparatus and method of operating same
JP2016095999A5 (en)
TWM501548U (en) Water quality management system for cooling water tower
CN106288094B (en) Heat exchange cooling water system and control method
JP2008190731A (en) Cooling water supply and discharge structure of cooling tower and cooling water supply and discharge structure of cooling tower group using it
ATE467727T1 (en) DEVICE FOR SECURING HYDRANTS BY LOCKING THE SLIDE OF A SLIDE VALVE
CN103874390B (en) liquid injection device
CN103912041A (en) Automatic water tap closing structure
CN204285735U (en) A kind of data center precision air conditioner humidification gravity flow water supply installation
CN103542141B (en) A kind of making method of ball check valve
KR102201813B1 (en) Water purifying apparatus
KR20140004962U (en) Atomatic water supply for stall
CN103808099A (en) Automatic water replenishing device of cooling water supplying system
CN201864629U (en) Household water softener
CN204922210U (en) Take heating device's valve
CN109681400A (en) It is pumped in a kind of pipe with cooling device
US20170370615A1 (en) Apparatus and method for rapid drain of water heater
WO2018159300A1 (en) Cooling tower system
CN106641399A (en) Water faucet
RU2016106997A (en) The method of maintaining the level of heated electrolyte bath, working under current
CN206299875U (en) A kind of tap
JP6440033B2 (en) Water heater
KR101651359B1 (en) Preventing formation of scale and temperature control device
CN204531435U (en) Temperature Controlling of Mass Concrete system
JP2014173825A (en) Hot water supply device

Legal Events

Date Code Title Description
MM4K Annulment or lapse of a utility model due to non-payment of fees