TWI765187B - A floor steel frame support device - Google Patents

A floor steel frame support device Download PDF

Info

Publication number
TWI765187B
TWI765187B TW108139236A TW108139236A TWI765187B TW I765187 B TWI765187 B TW I765187B TW 108139236 A TW108139236 A TW 108139236A TW 108139236 A TW108139236 A TW 108139236A TW I765187 B TWI765187 B TW I765187B
Authority
TW
Taiwan
Prior art keywords
steel
floor
steel beam
beams
fixing
Prior art date
Application number
TW108139236A
Other languages
Chinese (zh)
Other versions
TW202117148A (en
Inventor
黃建德
Original Assignee
黃建德
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 黃建德 filed Critical 黃建德
Priority to TW108139236A priority Critical patent/TWI765187B/en
Publication of TW202117148A publication Critical patent/TW202117148A/en
Application granted granted Critical
Publication of TWI765187B publication Critical patent/TWI765187B/en

Links

Images

Landscapes

  • Floor Finish (AREA)

Abstract

A floor steel frame support device for supporting floor. The floor steel frame support device comprises a plurality of support frames, a plurality of first steel beams, and a plurality of second steel beams. The first steel beam is mounted on the support frames. The first steel beam is arranged along a first direction at a first predetermined distance. The second steel beam is disposed on the first steel beam. The second steel beam is arranged along a second direction at a second predetermined distance. Thereby, it can simplify the connection of steel beams, improve the load capacity of raised floors, and save costs.

Description

一種地板鋼架支撐裝置 A floor steel frame support device

本發明涉及廠房建設之技術領域,尤其涉及一種地板鋼架支撐裝置。 The present invention relates to the technical field of plant construction, in particular to a floor steel frame supporting device.

高架地板是通過利用架高的方式設置在地面或是樓地板上,以使得高架地板的面板與地面之間會存在一定的空間,這些空間可以被用來佈設電線或者送風。因此,高架地板在市場中變得越來越受歡迎。 The raised floor is set on the ground or floor by means of elevation, so that there will be a certain space between the panel of the raised floor and the ground, and these spaces can be used for wiring or supplying air. As a result, raised floors are becoming more and more popular in the market.

但是傳統的高架地板在使用時,鋼樑為保證高架地板的承重強度,其銜接結構往往較為複雜,並且成本高。而且傳統的高架地板的承重強度也不高。 However, when the traditional raised floor is used, in order to ensure the load-bearing strength of the raised floor, the connection structure of the steel beam is often complicated and the cost is high. Moreover, the load-bearing strength of traditional raised floors is not high.

因此,本發明的主要目的在於提供一種地板鋼架支撐裝置,以解決上述問題。 Therefore, the main purpose of the present invention is to provide a floor steel frame supporting device to solve the above problems.

本發明之目的在於提供一種地板鋼架支撐裝置,藉由多層級鋼樑的設置,以使得高架地板可以簡化鋼樑銜接,提升高架地板的承重能力,並節約製造 成本。 The purpose of the present invention is to provide a floor steel frame support device, through the arrangement of multi-level steel beams, the raised floor can simplify the connection of the steel beams, improve the load-bearing capacity of the raised floor, and save manufacturing cost.

為達所述優點至少其中之一或其他優點,本發明的一實施例提出一種地板鋼架支撐裝置,用於支撐複數個地板,地板鋼架支撐裝置包括複數個支撐架、複數個第一鋼樑、複數個第二鋼樑以及複數個固定板。其中,支撐架設置於樓地板上,第一鋼樑架設於支撐架上,且第一鋼樑是以一第一預設距離為間隔沿著一第一方向排列,第二鋼樑設置於第一鋼樑上,且第二鋼樑是以一第二預設距離為間隔沿著一第二方向排列。該固定板以螺絲鎖固之方式將相鄰二該第一鋼樑固定連接,該固定板以螺絲之方式將相鄰二該第二鋼樑固定連接。 In order to achieve at least one of the above advantages or other advantages, an embodiment of the present invention provides a floor steel frame support device for supporting a plurality of floors. The floor steel frame support device includes a plurality of support frames, a plurality of first steel frames. beams, a plurality of second steel beams, and a plurality of fixing plates. Wherein, the support frame is arranged on the floor, the first steel beam is erected on the support frame, and the first steel beam is arranged along a first direction with a first predetermined distance as an interval, and the second steel beam is arranged on the first on a steel beam, and the second steel beams are arranged along a second direction with a second predetermined distance as an interval. The fixing plate fixedly connects the two adjacent first steel beams by means of screw locking, and the fixing plate fixedly connects the two adjacent second steel beams by means of screws.

其中該第一鋼樑與該第二鋼樑為H型鋼樑,該第一鋼樑使用螺絲鎖固方式固定於該支撐架上,該第二鋼樑的兩端處的底面使用螺絲鎖固方式固定於該第一鋼樑的頂面上,而形成一至少雙層鋼樑的疊加結構,以調整地板的高度。 The first steel beam and the second steel beam are H-shaped steel beams, the first steel beam is fixed on the support frame by means of screw locking, and the bottom surfaces of the two ends of the second steel beam are fixed by screws It is fixed on the top surface of the first steel beam to form a superimposed structure of at least two-layer steel beams, so as to adjust the height of the floor.

在一些實施例中,第一方向垂直於第二方向。 In some embodiments, the first direction is perpendicular to the second direction.

在一些實施例中,地板鋼架支撐裝置還可包括複數個固定板,固定板是以螺絲鎖固的方式將相鄰二個第一鋼樑固定連接,固定板以螺絲鎖固之方式將相鄰二個第二鋼樑固定連接。 In some embodiments, the floor steel frame supporting device may further include a plurality of fixing plates, the fixing plates are fixedly connected to two adjacent first steel beams by means of screw locking, and the fixing plates are The adjacent two second steel beams are fixedly connected.

在一些實施例中,第一預設距離是第二預設距離之整數倍。 In some embodiments, the first predetermined distance is an integer multiple of the second predetermined distance.

在一些實施例中,第一鋼樑之截面高度小於第二鋼樑之截面高度,第一鋼樑之截面寬度大於第二鋼樑之截面寬度,第一鋼樑之厚度大於第二鋼樑之厚度。 In some embodiments, the cross-sectional height of the first steel beam is smaller than the cross-sectional height of the second steel beam, the cross-sectional width of the first steel beam is greater than the cross-sectional width of the second steel beam, and the thickness of the first steel beam is greater than that of the second steel beam. thickness.

在一些實施例中,支撐架還可包括支撐座,第一鋼樑是以螺絲鎖固的方式固定於支撐架頂端的支撐座上。 In some embodiments, the support frame may further include a support seat, and the first steel beam is fixed on the support seat at the top of the support frame by means of screw locking.

在一些實施例中,支撐架還可包括翼板、管體以及固定座,管體固定於固定座上,翼板設置於固定座上並抵住管體。 In some embodiments, the support frame may further include a wing plate, a tube body, and a fixing seat, the tube body is fixed on the fixing seat, and the wing plate is arranged on the fixing seat and abuts the tube body.

在一些實施例中,地板是以螺絲鎖固之方式固定於第二鋼樑上。 In some embodiments, the floor is fixed on the second steel beam by means of screw locking.

在一些實施例中,地板鋼架支撐裝置還可包括複數個固定件,間隔一個第二預設距離以黏貼的方式設置於第二鋼樑上,用以定位固定地板。 In some embodiments, the floor steel frame supporting device may further include a plurality of fixing members, which are disposed on the second steel beam by means of sticking at a second predetermined distance for positioning and fixing the floor.

在一些實施例中,固定件包括凸出結構,凸出結構透過地板底部的四個角落以定位固定地板。 In some embodiments, the fixing member includes protruding structures, and the protruding structures penetrate four corners of the bottom of the floor to locate and fix the floor.

因此,利用本發明所提供一種地板鋼架支撐裝置,藉由多層級鋼樑的設置,以使得高架地板可以簡化鋼樑銜接,提升高架地板的承重能力,進而節約製造成本,並可增加地板下方的空間,以放置較大之設備與較多之管線。 Therefore, by using the floor steel frame support device provided by the present invention, the raised floor can simplify the connection of the steel beams by the arrangement of the multi-level steel beams, improve the load-bearing capacity of the raised floor, thereby saving the manufacturing cost and increasing the number of lower floors under the floor. space to place larger equipment and more pipelines.

上述說明僅是本發明技術方案的概述,為了能夠更清楚瞭解本發明的技術手段,而可依照說明書的內容予以實施,並且為了讓本發明的上述和其他目的、 特徵和優點能夠更明顯易懂,以下特舉較佳實施例,並配合附圖,詳細說明如下。 The above description is only an overview of the technical solution of the present invention. In order to understand the technical means of the present invention more clearly, it can be implemented according to the content of the description, and in order to make the above and other purposes of the present invention, The features and advantages can be more obvious and easy to understand. The preferred embodiments are exemplified below, and the detailed description is as follows in conjunction with the accompanying drawings.

10:高架地板 10: Raised Floors

12:樓地板 12: Floor Floor

14:支撐架 14: Support frame

16:鋼樑 16: Steel beam

18:地板 18: Flooring

1402:翼板 1402: Flap

1404:管體 1404: Tube body

1406:固定座 1406: Fixed seat

1602:第一鋼樑 1602: First Steel Beam

1604:第二鋼樑 1604: Second steel beam

20:固定件 20: Fixtures

22:固定孔 22: Fixing hole

S1:第一預設距離 S1: The first preset distance

S2:第二預設距離 S2: The second preset distance

A:第一方向 A: The first direction

B:第二方向 B: The second direction

H1:第一鋼樑的截面高度 H1: Section height of the first steel beam

H2:第二鋼樑的截面高度 H2: Section height of the second steel beam

W1:第一鋼樑的截面寬度 W1: Section width of the first steel beam

W2:第二鋼樑的截面寬度 W2: Section width of the second steel beam

1601:支撐座 1601: Support seat

24:固定板 24: Fixed plate

2402:螺絲 2402: Screw

2002:凸出結構 2002: Projecting Structures

40:地板鋼架支撐裝置 40: Floor steel frame support device

T1:第一鋼樑的厚度 T1: Thickness of the first steel beam

T2:第二鋼樑的厚度 T2: Thickness of the second steel beam

所包括的附圖用來提供對本申請實施例的進一步的理解,其構成了說明書的一部分,用於例示本申請的實施方式,並與文字描述一起來闡釋本申請的原理。顯而易見地,下面描述中的附圖僅僅是本申請的一些實施例,對於本領域普通技術人員來講,在不付出創造性勞動性的前提下,還可以根據這些附圖獲得其他的附圖。在附圖中:圖1是本發明高架地板的結構示意圖;圖2是本發明高架地板的側面示意圖;圖3是本發明固定件一實施例的結構示意圖;圖4是本發明第一鋼樑與第二鋼樑的截面對比示意圖;圖5是本發明高架地板安裝有固定板的側面示意圖;圖6是本發明固定件另一實施例的結構示意圖;圖7是圖6的剖面示意圖;圖8是本發明高架地板另一實施例的示意圖;以及圖9是本發明高架地板另一實施例的示意圖。 The accompanying drawings, which are included to provide a further understanding of the embodiments of the present application, constitute a part of the specification, are used to illustrate the embodiments of the present application, and together with the written description, serve to explain the principles of the present application. Obviously, the drawings in the following description are only some embodiments of the present application, and for those of ordinary skill in the art, other drawings can also be obtained from these drawings without creative effort. In the accompanying drawings: FIG. 1 is a schematic structural diagram of a raised floor of the present invention; FIG. 2 is a schematic side view of a raised floor of the present invention; FIG. 3 is a schematic structural diagram of an embodiment of a fixture of the present invention; FIG. 4 is the first steel beam of the present invention. Fig. 5 is a schematic side view of a raised floor of the present invention with a fixing plate installed; Fig. 6 is a schematic structural diagram of another embodiment of a fixing member of the present invention; Fig. 7 is a schematic sectional view of Fig. 6; Fig. 8 is a schematic view of another embodiment of the raised floor of the present invention; and FIG. 9 is a schematic view of another embodiment of the raised floor of the present invention.

這裏所公開的具體結構和功能細節僅僅是代表性的,並且是用於描述本發明的示例性實施例 的目的。但是本發明可以通過許多替換形式來具體實現,並且不應當被解釋成僅僅受限於這裏所闡述的實施例。 Specific structural and functional details disclosed herein are merely representative and for purposes of describing exemplary embodiments of the present invention the goal of. However, the present invention may be embodied in many alternative forms and should not be construed as limited only to the embodiments set forth herein.

在本發明的描述中,需要理解的是,術語“中心”、“橫向”、“上”、“下”、“左”、“右”、“豎直”、“水準”、“頂”、“底”、“內”、“外”等指示的方位或位置關為基於附圖所示的方位或位置關係,僅是為了便於描述本發明和簡化描述,而不是指示或暗示所指的裝置或組件必須具有特定的方位、以特定的方位構造和操作,因此不能理解為對本發明的限制。此外,術語“第一”、“第二”僅用於描述目的,而不能理解為指示或暗示相對重要性或者隱含指明所指示的技術特徵的數量。由此,限定有“第一”、“第二”的特徵可以明示或者隱含地包括一個或者更多個該特徵。在本發明的描述中,除非另有說明,“多個”的含義是兩個或兩個以上。另外,術語“包括”及其任何變形,意圖在於覆蓋不排他的包含。 In the description of the present invention, it should be understood that the terms "center", "lateral", "top", "bottom", "left", "right", "vertical", "horizontal", "top", The orientations or positions indicated by "bottom", "inner", "outer", etc. are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying the indicated device. Or the components must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of the present invention. In addition, the terms "first" and "second" are only used for descriptive purposes, and should not be construed as indicating or implying relative importance or implying the number of indicated technical features. Thus, a feature defined as "first" or "second" may expressly or implicitly include one or more of that feature. In the description of the present invention, unless otherwise specified, "plurality" means two or more. Additionally, the term "comprising" and any variations thereof are intended to cover non-exclusive inclusion.

在本發明的描述中,需要說明的是,除非另有明確的規定和限定,術語“安裝”、“相連”、“連接”應做廣義理解,例如,可以是固定連接,也可以是可拆卸連接,或一體地連接;可以是機械連接,也可以是電連接;可以是直接相連,也可以通過中間媒介間接相連,可以是兩個組件內部的連通。對於本領域的普通技術人員而言,可以具體情況理解上述術語在本發明中的具體含義。 In the description of the present invention, it should be noted that the terms "installed", "connected" and "connected" should be understood in a broad sense, unless otherwise expressly specified and limited, for example, it may be a fixed connection or a detachable connection Connection, or integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, and it can be the internal communication between the two components. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood in specific situations.

這裏所使用的術語僅僅是為了描述具體 實施例而不意圖限制示例性實施例。除非上下文明確地另有所指,否則這裏所使用的單數形式“一個”、“一項”還意圖包括複數。還應當理解的是,這裏所使用的術語“包括”和/或“包含”規定所陳述的特徵、整數、步驟、操作、單元和/或組件的存在,而不排除存在或添加一個或更多其他特徵、整數、步驟、操作、單元、組件和/或其組合。 The terms used here are for the purpose of describing specific The examples are not intended to limit the exemplary embodiments. As used herein, the singular forms "a", "an" and "an" are intended to include the plural unless the context clearly dictates otherwise. It should also be understood that the terms "comprising" and/or "comprising" as used herein specify the presence of stated features, integers, steps, operations, units and/or components, but do not preclude the presence or addition of one or more Other features, integers, steps, operations, units, components and/or combinations thereof.

請參閱圖1、圖2和圖3,圖1是本發明高架地板10的結構示意圖,圖2是本發明高架地板10的側面示意圖,圖3是本發明固定件20一實施例的結構示意圖。為達所述優點至少其中之一或其他優點,本發明的一實施例提供一種高架地板10,用以架設於樓地板12。地板鋼架支撐裝置40用於高架地板10中,以支撐複數個地板18。 1, FIG. 2 and FIG. 3, FIG. 1 is a schematic structural diagram of the raised floor 10 of the present invention, FIG. 2 is a schematic side view of the raised floor 10 of the present invention, and FIG. To achieve at least one of the aforementioned advantages or other advantages, an embodiment of the present invention provides a raised floor 10 for erecting on the floor 12 . The floor steel frame support device 40 is used in the raised floor 10 to support a plurality of floors 18 .

結合圖2參閱圖1可見,地板鋼架支撐裝置40包括複數個支撐架14、複數個鋼樑16、複數個地板18以及複數個固定件20。進一步看,鋼樑16包括複數個第一鋼樑1602以及複數個第二鋼樑1604,支撐架14包括翼板1402、管體1404、固定座1406以及支撐座1601,每個固定件20具有多個固定孔22。 Referring to FIG. 1 in conjunction with FIG. 2 , the floor steel frame supporting device 40 includes a plurality of support frames 14 , a plurality of steel beams 16 , a plurality of floors 18 and a plurality of fixing members 20 . Looking further, the steel beam 16 includes a plurality of first steel beams 1602 and a plurality of second steel beams 1604, the support frame 14 includes a wing plate 1402, a pipe body 1404, a fixing seat 1406 and a supporting seat 1601, and each fixing member 20 has a plurality of 22 fixing holes.

在本實施例中,四個支撐架14是設置於樓地板12上以起支撐作用,兩個第一鋼樑1602以一第一預設距離S1為間隔沿著一第一方向A架設於支撐架14的支撐座1601上,五個第二鋼樑1604以一第二預設距離S2為間隔沿著一第二方向B排列於第一鋼樑1602上。第一鋼 樑1602使用螺絲2402以鎖固之方式固定於支撐座1601上,第二鋼樑1604使用螺絲2402以鎖固之方式固定於第一鋼樑1602上。固定件20以第二預設距離S2為間隔設置於第二鋼樑1604上,每個地板18之四個腳落位置固定於固定件20上,這些固定件20的設置位置是對應於地板18的角落位置。請同時參照圖3所示,各個固定件20具有多個固定孔22並以黏膠方式黏在第二鋼樑1604上,地板18可透過固定孔22以螺絲鎖固的方式固定於固定件20。藉由此種地板18通過固定件20固定於第二鋼樑1604上、第二鋼樑1604架設於第一鋼樑1602上、第一鋼樑1602架設於支撐架14上的設置方式,可以調整高架地板10的高度,簡化橫向鋼樑與縱向鋼樑間的連接結構,並可增強高架地板10的整體承重能力。每個支撐架14的固定座1406上皆固定有四個翼板1402與管體1404,翼板1402抵住管體1404以加強支撐架14的支撐能力。 In the present embodiment, four support frames 14 are disposed on the floor 12 for support, and two first steel beams 1602 are erected on the supports along a first direction A with a first predetermined distance S1 as an interval On the support base 1601 of the frame 14, five second steel beams 1604 are arranged on the first steel beam 1602 along a second direction B with a second predetermined distance S2 as an interval. first steel The beam 1602 is fastened to the support base 1601 by means of screws 2402, and the second steel beam 1604 is fastened to the first steel beam 1602 by means of screws 2402. The fixing members 20 are arranged on the second steel beam 1604 at intervals of a second predetermined distance S2, and the four foot positions of each floor 18 are fixed on the fixing members 20, and the installation positions of these fixing members 20 are corresponding to the floor 18. corner position. Please refer to FIG. 3 at the same time, each fixing member 20 has a plurality of fixing holes 22 and is adhered to the second steel beam 1604 by means of adhesive, and the floor 18 can be fixed to the fixing member 20 by means of screw locking through the fixing holes 22 . With the arrangement that the floor 18 is fixed on the second steel beam 1604 through the fixing member 20 , the second steel beam 1604 is erected on the first steel beam 1602 , and the first steel beam 1602 is erected on the support frame 14 , the adjustment can be made. The height of the raised floor 10 simplifies the connection structure between the transverse steel beams and the longitudinal steel beams, and can enhance the overall load-bearing capacity of the raised floor 10 . Four wings 1402 and a pipe body 1404 are fixed on the fixing base 1406 of each support frame 14 , and the wings 1402 abut the pipe body 1404 to enhance the supporting capacity of the support frame 14 .

進一步說明,在本實施例中,第一預設距離S1是240cm,第二預設距離S2是60cm,第二預設距離S2與地板18之寬度相同,第一預設距離S1是地板18寬度之四倍,第一預設距離S1大於第二預設距離S2並且第一預設距離S1是第二預設距離S2的四倍。 Further description, in this embodiment, the first preset distance S1 is 240cm, the second preset distance S2 is 60cm, the second preset distance S2 is the same as the width of the floor 18 , and the first preset distance S1 is the width of the floor 18 Four times, the first preset distance S1 is greater than the second preset distance S2 and the first preset distance S1 is four times the second preset distance S2.

進一步說明,在本實施例中,第一方向A是與第二方向B在水平面是相互垂直。不過本案亦不限於此,第一方向A與第二方向B可以是任意一方向,只要這兩個方向在同一個水平面即可。 To further illustrate, in this embodiment, the first direction A and the second direction B are perpendicular to each other in the horizontal plane. However, the present case is not limited to this, and the first direction A and the second direction B may be any direction, as long as the two directions are on the same horizontal plane.

進一步說明,在本實施例中,固定件20是以黏貼之方式固定於第二鋼樑1602上。不過本案亦不限於此,也可以是螺絲鎖固方式、焊接方式等。 To further illustrate, in this embodiment, the fixing member 20 is fixed on the second steel beam 1602 by sticking. However, this case is not limited to this, and it can also be a screw locking method, a welding method, and the like.

進一步說明,在本實施例中,因為第一預設距離S1大於第二預設距離S2,第一鋼樑1602的抗彎強度須大於第二鋼樑1604的抗彎強度,以便在壓彎第二鋼樑1604的時候,第一鋼樑1602仍可以起到有效的保護作用。不過本案亦不限於此,第二鋼樑1604的抗彎強度亦可以大於或等於第一鋼樑1602的抗彎強度。在一實施例中,可依據第一預設距離S1與第二預設距離S2選定具有適當抗彎強度的第一鋼樑1602與第二鋼樑1604,以維持整體結構強度。 To further illustrate, in this embodiment, because the first preset distance S1 is greater than the second preset distance S2, the flexural strength of the first steel beam 1602 must be greater than the flexural strength of the second steel beam 1604, so that the When there are two steel beams 1604, the first steel beam 1602 can still play an effective protective role. However, the present case is not limited thereto, and the flexural strength of the second steel beam 1604 may also be greater than or equal to the flexural strength of the first steel beam 1602 . In one embodiment, the first steel beam 1602 and the second steel beam 1604 with appropriate flexural strength can be selected according to the first predetermined distance S1 and the second predetermined distance S2 to maintain the overall structural strength.

請參閱圖4,圖4是本發明第一鋼樑1602與第二鋼樑1604的截面對比示意圖。圖4示例中可見,第一鋼樑1602的截面高度H1小於第二鋼樑1604的截面高度H2,第一鋼樑1602的截面寬度W1大於第二鋼樑1604的截面寬度W2,第一鋼樑1602的厚度T1大於第二鋼樑1604的厚度T2。因第一鋼樑1602分佈的密度較第二鋼樑1604分佈的密度為小,第一鋼樑1602單位面積須承載較大之重量,故須較大之抗彎強度,所以第一鋼樑1602之截面寬度W1與厚度T1須較大。 Please refer to FIG. 4 . FIG. 4 is a schematic cross-sectional comparison of the first steel beam 1602 and the second steel beam 1604 of the present invention. In the example shown in FIG. 4 , the section height H1 of the first steel beam 1602 is smaller than the section height H2 of the second steel beam 1604 , the section width W1 of the first steel beam 1602 is greater than the section width W2 of the second steel beam 1604 , and the first steel beam 1604 Thickness T1 of 1602 is greater than thickness T2 of second steel beam 1604 . Because the distribution density of the first steel beam 1602 is smaller than that of the second steel beam 1604, the first steel beam 1602 has to carry a larger weight per unit area, so it needs a larger flexural strength, so the first steel beam 1602 The cross-sectional width W1 and thickness T1 must be larger.

請參閱圖5,圖5是本發明高架地板10安裝有固定板24的側面示意圖。如圖5所示,使用一個固定板24用螺絲2402將相鄰二個的第一鋼樑1602固定連接,使 用一個固定板24用螺絲2402將相鄰二個第二鋼樑1604固定連接,固定板24用於加強相鄰二個第一鋼樑1602的連接和相鄰二個第二鋼樑1604的連接,第一鋼樑1602使用螺絲2402以鎖固方式固定於支撐架14頂端之支撐座1601上,第二鋼樑1604使用螺絲2402以鎖固方式固定於第一鋼樑1602上,以提升高架地板10的整體穩定性。不過本案亦不限於此,固定板24亦可以分別使用焊接的方式將相鄰二個的第一鋼樑1602固定連接及相鄰二個的第二鋼樑1604固定連接。 Please refer to FIG. 5 , which is a schematic side view of the raised floor 10 of the present invention with the fixing plate 24 installed. As shown in FIG. 5, a fixing plate 24 is used to fix the two adjacent first steel beams 1602 with screws 2402, so that the A fixing plate 24 is used to fix and connect two adjacent second steel beams 1604 with screws 2402. The fixing plate 24 is used to strengthen the connection between the two adjacent first steel beams 1602 and the connection between the adjacent two second steel beams 1604. , the first steel beam 1602 is fixed on the support base 1601 at the top of the support frame 14 by means of screws 2402, and the second steel beam 1604 is fixed on the first steel beam 1602 by means of screws 2402, so as to raise the raised floor 10 overall stability. However, the present case is not limited to this, and the fixing plate 24 can also be used to fixedly connect two adjacent first steel beams 1602 and two adjacent second steel beams 1604 by welding.

結合圖1和圖2請參閱圖6和圖7,圖6是本發明固定件20另一實施例的結構示意圖,圖7是圖6的剖面示意圖。結合圖7參閱圖6,可清楚地看到,在本實施例中,固定件20還包括複數個凸出結構2002,凸出結構2002是以榫卯連接的方式設置於固定件20中,每個凸出結構2002內具有一固定孔22,地板18可透過固定孔22以螺絲鎖固的方式固定於固定件20上,凸出結構2002透過地板18底部之四個角落以定位固定地板18,且固定件20上可再使用墊片方式調整地板18之水平狀態,亦可避免地板18直接碰撞第二鋼樑1604,從而對第二鋼樑1604造成損傷。 Referring to FIGS. 6 and 7 in conjunction with FIGS. 1 and 2 , FIG. 6 is a schematic structural diagram of another embodiment of the fixing member 20 of the present invention, and FIG. 7 is a schematic cross-sectional view of FIG. 6 . Referring to FIG. 6 in conjunction with FIG. 7 , it can be clearly seen that, in this embodiment, the fixing member 20 further includes a plurality of protruding structures 2002 , and the protruding structures 2002 are arranged in the fixing member 20 in a tenon-and-mortise manner. Each protruding structure 2002 has a fixing hole 22 in it. The floor 18 can be fixed on the fixing member 20 by means of screw locking through the fixing hole 22. In addition, the fixing member 20 can be used to adjust the horizontal state of the floor 18 by using a shim, which can also prevent the floor 18 from directly colliding with the second steel beam 1604 , thereby causing damage to the second steel beam 1604 .

進一步說明,支撐架14的高度是可以根據需要進行調整的。若是所需搭設的高架地板10高度過高,單純的提高支撐架14高度會降低高架地板10的承重能力,可通過在第二鋼樑1604上繼續疊加第三鋼樑16、第 四鋼樑16等鋼樑16在保證高度的基礎上,保持高架地板10的承重能力。 Further, the height of the support frame 14 can be adjusted as required. If the height of the raised floor 10 to be erected is too high, simply increasing the height of the support frame 14 will reduce the load-bearing capacity of the raised floor 10 . The steel beams 16 such as the four steel beams 16 maintain the load-bearing capacity of the raised floor 10 on the basis of ensuring the height.

進一步說明,上述地板18與固定件20、兩個第二鋼樑1604間、兩個第一鋼樑1602間及第一鋼樑1602與支撐架14之間的連接方式皆為螺絲鎖固,不過亦不限於此,也可以是榫卯連接、焊接等,只要達到固定效果的連接方式都應在本發明的保護範圍之內。 Further description, the connection between the floor 18 and the fixing member 20, the two second steel beams 1604, the two first steel beams 1602, and the connection between the first steel beam 1602 and the support frame 14 are all screw locking, but It is not limited to this, and can also be mortise-and-mortise connection, welding, etc., as long as the connection method that achieves the fixing effect should be within the protection scope of the present invention.

請參閱圖8,圖8是本發明高架地板10另一實施例的示意圖。如圖8所示,高架地板10可鋪設32個地板18,以4×8的方式排列,相鄰二個第一鋼樑1602透過一個固定板24以螺絲鎖固的方式連接。固定件20焊接於第二鋼樑1604上,用以支撐地板18。第一鋼樑1602與第二鋼樑1604相互垂直。 Please refer to FIG. 8 , which is a schematic diagram of another embodiment of the raised floor 10 of the present invention. As shown in FIG. 8 , the raised floor 10 can be laid with 32 floors 18 arranged in a 4×8 manner, and two adjacent first steel beams 1602 are connected by a fixing plate 24 in a screw-locking manner. The fixing member 20 is welded to the second steel beam 1604 for supporting the floor 18 . The first steel beam 1602 and the second steel beam 1604 are perpendicular to each other.

請參閱圖9,圖9是本發明高架地板10另一實施例的示意圖。如圖9所示,高架地板10可鋪設32個地板18,以4×8的方式排列,三支第一鋼樑1602架設於支撐架14的支撐座1601上,十支第二鋼樑1604架設於這些第一鋼樑1602上。相鄰二個第二鋼樑1604透過一個固定板24以螺絲鎖固的方式連接。固定件20焊接於第二鋼樑1604上,用以支撐地板18。第一鋼樑1602與第二鋼樑1604相互垂直。 Please refer to FIG. 9 , which is a schematic diagram of another embodiment of the raised floor 10 of the present invention. As shown in FIG. 9 , the raised floor 10 can be laid with 32 floors 18 arranged in a 4×8 manner. Three first steel beams 1602 are erected on the support bases 1601 of the support frame 14 , and ten second steel beams 1604 are erected. on these first steel beams 1602. The two adjacent second steel beams 1604 are connected through a fixing plate 24 in a screw-locking manner. The fixing member 20 is welded to the second steel beam 1604 for supporting the floor 18 . The first steel beam 1602 and the second steel beam 1604 are perpendicular to each other.

綜上述,本發明所提供之地板鋼架支撐裝置40,用以支撐複數個地板18,藉由多層級鋼樑16的設置,以使得高架地板10可以簡化鋼樑16銜接,提升高架 地板10的承重能力,並可增加地板18下方的空間,以放置較大之設備與較多之管線。 To sum up, the floor steel frame support device 40 provided by the present invention is used to support a plurality of floors 18 , and the raised floor 10 can simplify the connection of the steel beams 16 through the arrangement of the multi-level steel beams 16 , so that the elevated floor can be raised. The load-bearing capacity of the floor 10 can be increased, and the space below the floor 18 can be increased to accommodate larger equipment and more pipelines.

上述僅為本案較佳之實施例而已,並不對本案進行任何限制。任何所屬技術領域的技術人員,在不脫離本案的技術手段的範圍內,對本案揭露的技術手段和技術內容做任何形式的等同替換或修改等變動,均屬未脫離本案的技術手段的內容,仍屬於本案的保護範圍之內。 The above are only preferred embodiments of this case, and do not impose any limitations on this case. Any person skilled in the technical field who makes any form of equivalent replacement or modification to the technical means and technical content disclosed in this case, within the scope of the technical means of this case, does not deviate from the content of the technical means of this case. still falls within the scope of protection of this case.

10:高架地板 10: Raised Floors

12:樓地板 12: Floor Floor

14:支撐架 14: Support frame

16:鋼樑 16: Steel beam

18:地板 18: Flooring

1402:翼板 1402: Flap

1404:管體 1404: Tube body

1406:固定座 1406: Fixed seat

1602:第一鋼樑 1602: First Steel Beam

1604:第二鋼樑 1604: Second steel beam

20:固定件 20: Fixtures

22:固定孔 22: Fixing hole

S1:第一預設距離 S1: The first preset distance

S2:第二預設距離 S2: The second preset distance

B:第二方向 B: The second direction

A:第一方向 A: The first direction

1601:支撐座 1601: Support seat

40:地板鋼架支撐裝置 40: Floor steel frame support device

Claims (8)

一種地板鋼架支撐裝置,用於支撐複數地板,該地板鋼架支撐裝置包括:複數個支撐架;複數個第一鋼樑,設置於該些支撐架上;複數個第二鋼樑,該些第二鋼樑設置於該些第一鋼樑上,該些第一鋼樑是以一第一預設距離為間隔沿著一第一方向排列,該些第二鋼樑是以一第二預設距離為間隔沿著一第二方向排列;以及複數個固定板,該固定板以螺絲鎖固之方式將相鄰二該第一鋼樑固定連接,該固定板以螺絲之方式將相鄰二該第二鋼樑固定連接,其中該第一鋼樑與該第二鋼樑為H型鋼樑,該第一預設距離大於該第二預設距離S2,該第二鋼樑的抗彎強度小於該第一鋼樑,該第一鋼樑使用螺絲鎖固方式固定於該支撐架上,該第二鋼樑的兩端處的底面使用螺絲鎖固方式固定於該第一鋼樑的頂面上,以調整地板的高度。 A floor steel frame support device is used to support a plurality of floors, the floor steel frame support device comprises: a plurality of support frames; a plurality of first steel beams, arranged on the support frames; a plurality of second steel beams, the The second steel beams are disposed on the first steel beams, the first steel beams are arranged along a first direction with a first predetermined distance as an interval, and the second steel beams are arranged at a second predetermined distance The distance is set as an interval and arranged along a second direction; and a plurality of fixing plates are fixedly connected to the adjacent two first steel beams by means of screw locking, and the fixing plates are used to screw the adjacent two The second steel beam is fixedly connected, wherein the first steel beam and the second steel beam are H-shaped steel beams, the first preset distance is greater than the second preset distance S2, and the bending strength of the second steel beam Smaller than the first steel beam, the first steel beam is fixed on the support frame by means of screw locking, and the bottom surfaces at both ends of the second steel beam are fixed on the top surface of the first steel beam by means of screw locking to adjust the height of the floor. 如申請專利範圍第1項所述的地板鋼架支撐裝置,其中,該第一方向垂直於該第二方向。 The floor steel frame supporting device according to claim 1, wherein the first direction is perpendicular to the second direction. 如申請專利範圍第1項所述的地板鋼架支撐裝置,其中,該第一預設距離是該第二預設距離之整數倍。 The floor steel frame supporting device according to claim 1, wherein the first predetermined distance is an integer multiple of the second predetermined distance. 如申請專利範圍第1項所述的地板鋼架支撐裝置,其中,該支撐架包括一支撐座,該第一鋼樑以螺絲鎖固之方式固定於該支撐架頂端之支撐座上。 The floor steel frame supporting device according to claim 1, wherein the supporting frame comprises a supporting seat, and the first steel beam is fixed on the supporting seat at the top of the supporting frame by means of screw locking. 如申請專利範圍第1項所述的地板鋼架支撐裝置,其中,該支撐架更包括一翼板、一管體以及一固定座,該管體固定於該固定座,該翼板設置於該固定座並抵住該管體。 The floor steel frame supporting device as described in claim 1, wherein the supporting frame further comprises a wing plate, a tube body and a fixing seat, the tube body is fixed on the fixing seat, and the wing plate is arranged on the fixing seat seat and against the tube body. 如申請專利範圍第1項所述的地板鋼架支撐裝置,其中,該些地板是以螺絲鎖固之方式固定於該些第二鋼樑上。 The floor steel frame supporting device according to claim 1, wherein the floors are fixed on the second steel beams by means of screw locking. 如申請專利範圍第6項所述的地板鋼架支撐裝置,更包括複數個固定件,該些固定件間隔該第二預設距離以黏貼之方式設置於該些第二鋼樑上,以定位固定該些地板。 The floor steel frame supporting device as described in item 6 of the scope of the patent application further comprises a plurality of fixing pieces, and the fixing pieces are disposed on the second steel beams by sticking at the second predetermined distance for positioning Fix the floors. 如申請專利範圍第7項所述的地板鋼架支撐裝置,其中,該固定件包括一凸出結構,該凸出結構透過該地板底部之角落以定位固定該地板。 The floor steel frame supporting device as claimed in claim 7, wherein the fixing member comprises a protruding structure, and the protruding structure penetrates the corner of the bottom of the floor to position and fix the floor.
TW108139236A 2019-10-30 2019-10-30 A floor steel frame support device TWI765187B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW108139236A TWI765187B (en) 2019-10-30 2019-10-30 A floor steel frame support device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW108139236A TWI765187B (en) 2019-10-30 2019-10-30 A floor steel frame support device

Publications (2)

Publication Number Publication Date
TW202117148A TW202117148A (en) 2021-05-01
TWI765187B true TWI765187B (en) 2022-05-21

Family

ID=77020650

Family Applications (1)

Application Number Title Priority Date Filing Date
TW108139236A TWI765187B (en) 2019-10-30 2019-10-30 A floor steel frame support device

Country Status (1)

Country Link
TW (1) TWI765187B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2470449Y (en) * 2001-02-28 2002-01-09 上海惠亚铝合金制品有限公司 Steel-beam combination structure of elevated floor-board
TW478536U (en) * 2001-02-23 2002-03-01 Jian-De Huang Positioning structure for steel beam of raised floor
CN2509281Y (en) * 2001-09-26 2002-09-04 上海惠亚铝合金制品有限公司 Adjustable bearing structure for overhead floors
US20100011680A1 (en) * 2008-07-16 2010-01-21 Oki Semiconductor Co., Ltd. Aseismatic reinforcing structure of double flooring and aseismatic reinforcing method of double flooring
TWM592891U (en) * 2019-10-30 2020-04-01 黃建德 A floor steel frame support device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW478536U (en) * 2001-02-23 2002-03-01 Jian-De Huang Positioning structure for steel beam of raised floor
CN2470449Y (en) * 2001-02-28 2002-01-09 上海惠亚铝合金制品有限公司 Steel-beam combination structure of elevated floor-board
CN2509281Y (en) * 2001-09-26 2002-09-04 上海惠亚铝合金制品有限公司 Adjustable bearing structure for overhead floors
US20100011680A1 (en) * 2008-07-16 2010-01-21 Oki Semiconductor Co., Ltd. Aseismatic reinforcing structure of double flooring and aseismatic reinforcing method of double flooring
TWM592891U (en) * 2019-10-30 2020-04-01 黃建德 A floor steel frame support device

Also Published As

Publication number Publication date
TW202117148A (en) 2021-05-01

Similar Documents

Publication Publication Date Title
TWM592891U (en) A floor steel frame support device
US8850770B2 (en) Structurally integrated accessible floor system
US9273464B2 (en) Structurally integrated accessible floor system
US7975443B2 (en) Precast prestress raised access floor construction
TWI765187B (en) A floor steel frame support device
EP2430252B1 (en) Structurally integrated accessible floor system
TWI807127B (en) A floor steel frame support device
JP5341687B2 (en) Free access floor mount
TWM599334U (en) Floor steel frame support device
TWI785323B (en) Floor steel frame support device
TWI748412B (en) Floor steel frame support device
JP2005207031A (en) Construction method of double floor
JP5290049B2 (en) Free access floor mount
TWI735363B (en) Floor steel frame support device
TWI744770B (en) Supporting structure
JP5042811B2 (en) Free access floor mount
TWI818771B (en) Raised floor support structure and raised floor for edge finishing thereof
CN220978669U (en) Reinforced floor structure for dust-free workshop
JP2009161914A (en) Pedestal for free access floor
TWM609839U (en) Floor steel frame support device
KR102564234B1 (en) Support structure for supporting lower frame modular raised floor panel and system including same
JP7316176B2 (en) unit building
KR102419135B1 (en) Support for prefabricated water tank
KR101975475B1 (en) flooring system
JP5079489B2 (en) Free access floor mount