本發明係關於一種複合結構板(二),尤指一種得於鋼樑上方設置鋼板,並於鋼板成型前先與防水鋪面毯結合,並讓防水鋪面毯得設延伸部,於相鄰的鋼板互相結合後,再利用防水鋪面毯得設延伸部覆蓋於鋼板之部分範圍,即可將鋼板與之外表外部環境隔離,得以於屋頂或牆面產生絕佳的防水效果,符合綠色建築之結構創新者。The invention relates to a composite structural board (2), in particular to a steel plate which is arranged above the steel beam, and is combined with the waterproof paving blanket before the steel plate is formed, and the waterproof laying blanket is provided with an extension part in the adjacent steel plate. After combining with each other, the waterproof paving blanket can be used to cover the outer part of the steel plate with the extension part, so that the steel plate can be isolated from the external environment of the outer surface, so as to produce an excellent waterproof effect on the roof or the wall surface, which is in line with the structural innovation of the green building. By.
按習知複合鋼板,如台灣發明專利第I340194號「防火複合鋼板」,係包含上層鋼板及下層鋼板,當前述下層鋼板之結合部與前述上層鋼板之結合槽互相結合時,係以上層鋼板之結合槽先對應於下層鋼板之結合部,並壓迫上層鋼板,使下層鋼板之結合角部與上層鋼板之凹入部卡合,再利用前述固定架兩側之延伸部卡固前述上層鋼板之凹入部,即可將上層鋼板與下層鋼板充分結合;防火層,設於前述上層鋼板與下層鋼板之間,再於上、下層鋼板之間設有防火隔層,讓上層鋼板暴露於屋頂上表面,任憑風吹雨淋而鏽蝕,雖可以材質克服,但上層鋼板突出於屋頂,讓建築物之造型受到限制。According to the conventional composite steel plate, for example, Taiwan Patent No. I340194 "fireproof composite steel plate" includes an upper steel plate and a lower steel plate. When the joint portion of the lower steel plate and the joint groove of the upper steel plate are combined with each other, the upper steel plate is The coupling groove first corresponds to the joint portion of the lower steel plate, and presses the upper steel plate to engage the joint corner portion of the lower steel plate with the concave portion of the upper steel plate, and then fixes the concave portion of the upper steel plate by using the extension portions on both sides of the fixing frame The upper steel plate and the lower steel plate can be fully combined; the fireproof layer is disposed between the upper steel plate and the lower steel plate, and a fire barrier layer is disposed between the upper and lower steel plates to expose the upper steel plate to the upper surface of the roof. The wind is raining and rusting. Although it can be overcome by materials, the upper steel plate protrudes from the roof, which limits the shape of the building.
為此,本發明者,再就複合結構板之運用與建材設計製造經驗,並針對綠色建築之提升,加以研究,發明本案。To this end, the inventor has studied and manufactured the experience of the composite structural panel and the design and manufacture of the building materials, and researched and invented the case for the improvement of the green building.
本發明之目的,乃是在提供一種具備防火、耐燃,可回收再利用之複合結構板,以提昇綠色建材之安全性並兼顧環保要求。The object of the present invention is to provide a composite structural board which is provided with fireproof, flameproof and recyclable, in order to improve the safety of green building materials and to meet environmental protection requirements.
本發明之複合結構板(二),至少包含鋼板,係利用固定座以固設於鋼樑上方,並利用鋼板所設之平板部與結構部,且於鋼板之外表面與防水鋪面毯互相結合,於二相鄰鋼板互相結合時,得 利用防水鋪面毯之延伸部覆蓋於鋼板部分結構部,將鋼板之外表面與外部環境隔離,得以於屋頂或牆面產生絕佳的防水效果,且如於屋頂植栽綠色植物時,亦可防止植物的根部穿過防水鋪面毯與鋼板,提升綠色建築之效益、優點與結構創新性。The composite structural plate (2) of the present invention comprises at least a steel plate, which is fixed on the steel beam by a fixing seat, and uses the flat plate portion and the structural portion of the steel plate, and is combined with the waterproof tarpaulin on the outer surface of the steel plate. When the two adjacent steel plates are combined with each other, The extension of the waterproof blanket is used to cover the structural part of the steel plate to isolate the outer surface of the steel plate from the external environment, so as to provide excellent waterproof effect on the roof or the wall surface, and prevent the green plants on the roof. The roots of plants pass through waterproof paving blankets and steel plates to enhance the benefits, advantages and structural innovation of green buildings.
如此,為使 貴審查員可充份了解本發明,茲依附圖式解說如下:如圖1及2所示為鋼板之實施例一,本發明複合結構板(二)之鋼板與防水鋪面毯之結合,乃是於鋼板成型前,先將尚未成型之鋼板材料1與防水鋪面毯2先行以膠合材料貼合結合,且依據需求將鋼板材料1與防水鋪面毯2以不同之寬度結合,如本實施例一,於鋼板材料1與防水鋪面毯2之一端為齊平,另一端之防水鋪面毯2則伸出於鋼板材料1之外側寬度為W1。In this way, in order to enable the examiner to fully understand the present invention, the following is a schematic diagram of the following: FIG. 1 and FIG. 2 show the first embodiment of the steel plate, and the steel plate and waterproof tarpaulin of the composite structural plate (2) of the present invention. The combination is that before the steel sheet is formed, the unformed steel sheet material 1 and the waterproof paving blanket 2 are first bonded together by the bonding material, and the steel sheet material 1 and the waterproof paving blanket 2 are combined according to the requirements with different widths, such as In the first embodiment, the steel sheet material 1 is flush with one end of the waterproof blanket 2, and the waterproof blanket 2 at the other end protrudes from the outer side of the steel sheet material 1 to have a width W1.
之後,再以鋼板成型設備將已互相結合之鋼板材料1與防水鋪面毯2輪輾成型為鋼板3,且如圖3-6,得將鋼板3成型為各種形狀,但本發明並未限定於圖3-6之形狀。如此,於鋼板3成型時,得將防水鋪面毯2包覆於鋼板3之外表面全部,並因為防水鋪面毯2之寬度大於鋼板3,因此防水鋪面毯2乃於鋼板之一側設有適當長度的延伸部20。After that, the steel plate material 1 and the waterproof tarpaulin 2 rims which have been combined with each other are formed into the steel plate 3 by a steel plate forming apparatus, and as shown in FIG. 3-6, the steel plate 3 is formed into various shapes, but the invention is not limited thereto. Figure 3-6. Thus, when the steel sheet 3 is formed, the waterproof blanket 2 is covered on the outer surface of the steel sheet 3, and since the width of the waterproof blanket 2 is larger than that of the steel sheet 3, the waterproof blanket 2 is provided on one side of the steel sheet. Extension 20 of length.
前述防水鋪面毯2,係為由彈性的聚烯烴(polyolefines)與瀝青烴(ethylene copolymer bitumen)製成者,具有防水與抗UV破壞之優點,得利用前述防水鋪面毯2完全覆蓋於鋼板3外表面,得以將易生鏽之元件全部隱藏,避免受到風吹雨淋而鏽蝕。且如於屋頂植栽綠色植物時,亦可防止植物的根部穿過防水鋪面毯與鋼板,提升綠色建築之效益、優點與結構創新性。The waterproof mat blanket 2 is made of elastic polyolefins and ethylene copolymer bitumen, and has the advantages of waterproofing and anti-UV damage, and can be completely covered by the waterproof mat blanket 2 outside the steel plate 3 The surface can hide all the components that are easy to rust, and avoid being rusted by wind and rain. Moreover, if the green plants are planted on the roof, the roots of the plants can be prevented from passing through the waterproof paving carpet and the steel plate, thereby improving the benefits, advantages and structural innovation of the green building.
如圖7-12,為前述鋼板3之實施例一的施工運用例,本施工運用例一~五,其中圖7及8之施工運用例,至少包含: 鋼樑4,係被設置於最下方,得依據金屬建築之結構需求而為H型鋼樑或C型鋼樑或管狀鋼樑等均無不可。前述鋼樑4係作為金屬建築物之主要結構體。As shown in Fig. 7-12, the construction application example of the first embodiment of the steel plate 3, the construction application examples 1 to 5, wherein the construction application examples of Figs. 7 and 8 include at least: The steel beam 4 is placed at the bottom, and it is not necessary to be an H-shaped steel beam or a C-shaped steel beam or a tubular steel beam depending on the structural requirements of the metal building. The aforementioned steel beam 4 is the main structural body of the metal building.
固定座5,得為各種形狀,如圖7及8,為固定座5,下方兩側並形成小延伸面50,得以栓設元件51穿過前述小延伸面50以固設於前述鋼樑4之上方;或如圖9之運用例二之C型固定座5a一側並焊接一L型座52,並以L型座52焊接於前述鋼樑4之上方;或如圖10之運用例三之C型固定座5a一側並以栓設元件53固設一L型座52,並再以栓設元件51穿過L型座52以固設於前述鋼樑4之上方;或如圖11之運用例四之ㄇ型固定座5b兩側並以栓設元件53各自固設一L型座52,並再以栓設元件51穿過L型座52以固設於前述鋼樑4之上方;或如圖12之運用例五之環ㄇ型固定座5c,其環圍並形成小延伸面50,得以栓設元件51穿過前述小延伸面50以固設於前述鋼樑4之上方。The fixing base 5 has various shapes, as shown in FIGS. 7 and 8, is a fixing base 5, and the lower sides are formed with a small extending surface 50, so that the bolting member 51 passes through the small extending surface 50 to be fixed to the steel beam 4 Above or as shown in FIG. 9 on the side of the C-type fixing seat 5a of the second embodiment, and welding an L-shaped seat 52, and welding the L-shaped seat 52 above the steel beam 4; or as shown in FIG. One side of the C-shaped fixing base 5a is fixed with an L-shaped seat 52 by the bolting member 53, and then the bolting member 51 is passed through the L-shaped seat 52 to be fixed above the steel beam 4; or as shown in FIG. The L-shaped seat 52 is fixed to each of the two sides of the fixing base 5b of the fourth embodiment, and the bolting member 53 is inserted through the L-shaped seat 52 to be fixed above the steel beam 4. Or the ring-shaped fixing seat 5c of the fifth embodiment of FIG. 12, which surrounds and forms a small extending surface 50, so that the bolting member 51 passes through the small extending surface 50 to be fixed above the steel beam 4.
鋼板3,設平板部31,於平板部31兩側設結構部32a、32b,結構部32a、32b係為對稱結構,因此,乃於二結構部32a、32b之間形成適當的空間33。The steel plate 3 is provided with a flat plate portion 31, and structural portions 32a and 32b are provided on both sides of the flat plate portion 31. The structural portions 32a and 32b have a symmetrical structure. Therefore, an appropriate space 33 is formed between the two structural portions 32a and 32b.
如此,如圖7,當二相鄰的鋼板3之結構部32a、32b互相結合前時,需先將第一鋼板3a之結構部32b以栓設元件34固設於前述固定座5之上方,再將第二鋼板3b之結構部32a與第一鋼板3a之結構部32b互相結合,利用前述第二鋼板3b之結構部32a包覆於第一鋼板3a之結構部32b外表面,並將位於第二鋼板3b之結構部32a末端所設前述防水鋪面毯2之延伸部20加熱滾壓貼合於第一鋼板3a外部之防水鋪面毯2上方,即可將第一鋼板3a顯露於屋頂上之末端部35包覆,將鋼板3之外表面與外部環境全部隔離,可組成防水、隔熱之屋頂或牆壁。Thus, as shown in FIG. 7, when the structural portions 32a, 32b of the two adjacent steel plates 3 are joined to each other, the structural portion 32b of the first steel plate 3a is first fixed to the fixing seat 5 by the plugging member 34. Further, the structural portion 32a of the second steel sheet 3b and the structural portion 32b of the first steel sheet 3a are joined to each other, and the structural portion 32a of the second steel sheet 3b is coated on the outer surface of the structural portion 32b of the first steel sheet 3a, and will be located at the The extension portion 20 of the waterproof blanket 2 provided at the end of the structural portion 32a of the second steel plate 3b is heated and rolled to fit over the waterproof blanket 2 outside the first steel plate 3a, so that the first steel plate 3a can be exposed on the end of the roof. The portion 35 is covered to completely isolate the outer surface of the steel sheet 3 from the external environment, and can form a waterproof or heat-insulated roof or wall.
如圖13所示,為本發明複合結構板(二)之鋼板實施例二,本實施例二係衍生自前述實施例一,前述鋼板與防水鋪面毯之結 合,乃是於鋼板型前,先以鋼板材料1與防水鋪面毯2先行結合,且依據需求將鋼板材料1與防水鋪面毯2以不同之寬度結合,如本實施例一,乃是於鋼板材料1之一端較防水鋪面毯2之同一端較寬,其寬度為W2,防水鋪面毯2之另一端則是較鋼板材料1之同一端為較寬,其寬度為W1。As shown in FIG. 13 , it is the second embodiment of the steel plate of the composite structural board ( 2 ) of the present invention, and the second embodiment is derived from the foregoing first embodiment, and the knot of the steel plate and the waterproof paving blanket is In the front of the steel plate type, the steel plate material 1 and the waterproof blanket 2 are first combined, and the steel plate material 1 and the waterproof blanket 2 are combined with different widths according to requirements, as in the first embodiment, the steel plate is One end of the material 1 is wider than the same end of the waterproof blanket 2, and its width is W2, and the other end of the waterproof blanket 2 is wider than the same end of the steel sheet material 1, and its width is W1.
之後,再以鋼板成型設備將已互相結合之鋼板材料1與防水鋪面毯2輪輾成型為鋼板3,如圖14及15,本發明得將鋼板3成型為各種形狀,但本發明並未限定於圖14及15之形狀。於鋼板3成型時,得於鋼板3之結構部32b外表面不為防水鋪面毯包覆,但於鋼板3之另一端則於將防水鋪面毯2形成適當長度的延伸部20。After that, the steel sheet material 1 and the waterproof tarpaulin 2 rims which have been combined with each other are formed into a steel sheet 3 by a steel plate forming apparatus. As shown in FIGS. 14 and 15, the steel sheet 3 is formed into various shapes, but the invention is not limited thereto. The shapes of Figures 14 and 15 are shown. When the steel sheet 3 is molded, the outer surface of the structural portion 32b of the steel sheet 3 is not covered with the waterproof blanket, but at the other end of the steel sheet 3, the waterproof mat 2 is formed with the extension portion 20 of an appropriate length.
如圖16及17,為前述鋼板3之實施例二的施工運用例,本施工運用例,至少包含:鋼樑4,係被設置於最下方,得依據金屬建築之結構需求而為H型鋼樑或C型鋼樑或管狀鋼樑等均無不可。前述鋼樑4係作為金屬建築物之主要結構體。16 and 17, the construction application example of the second embodiment of the steel plate 3, the construction application example includes at least: the steel beam 4 is disposed at the bottom, and is made into an H-shaped steel according to the structural requirements of the metal building. Beams or C-shaped steel beams or tubular steel beams are all indispensable. The aforementioned steel beam 4 is the main structural body of the metal building.
固定座5,得為各種形狀(可參圖7~12),本運用例以ㄇ型固定座介紹之,故而於ㄇ型固定座下方兩側並形成小延伸面50,得以栓設元件51穿過前述小延伸面50以固設於前述鋼樑4之上方。The fixing base 5 can be of various shapes (refer to Figs. 7~12). This application example is described by a cymbal type fixing seat. Therefore, a small extending surface 50 is formed on both sides of the cymbal type fixing seat, so that the tying member 51 can be worn. The small extension surface 50 is fixed to the upper side of the steel beam 4 .
鋼板3,設平板部31,於平板部31兩側設結構部32a、32b,結構部32a、32b係為對稱結構,因此,乃於二結構部32a、32b之間形成適當的空間33。The steel plate 3 is provided with a flat plate portion 31, and structural portions 32a and 32b are provided on both sides of the flat plate portion 31. The structural portions 32a and 32b have a symmetrical structure. Therefore, an appropriate space 33 is formed between the two structural portions 32a and 32b.
如此,如圖16,當二相鄰的鋼板3之結構部32a、32b互相結合前時,需先將第一鋼板3a之結構部32b以栓設元件34固設於前述固定座5之上方,再將第二鋼板3b之結構部32a與第一鋼板3a之結構部32b互相結合,利用前述第二鋼板3b之結構部32a 包覆於第一鋼板3a之結構部32b外表面。Thus, as shown in FIG. 16, when the structural portions 32a, 32b of the two adjacent steel plates 3 are joined to each other, the structural portion 32b of the first steel plate 3a is first fixed to the fixing seat 5 by the plugging member 34. Further, the structural portion 32a of the second steel sheet 3b and the structural portion 32b of the first steel sheet 3a are joined to each other, and the structural portion 32a of the second steel sheet 3b is used. Covered on the outer surface of the structural portion 32b of the first steel sheet 3a.
且使得第二鋼板3b之結構部32a末端部35與第一鋼板3a之防水鋪面毯2之一端20接觸,並將位於第二鋼板3b之結構部32a末端所設前述防水鋪面毯2之延伸部20加熱滾壓貼合於第一鋼板3a外部之防水鋪面毯2上方,即可將第二鋼板3b顯露於屋頂上之末端部35包覆,將鋼板3之外表面與外部環境全部隔離,可組成防水、隔熱之屋頂或牆壁。And the end portion 35 of the structural portion 32a of the second steel plate 3b is brought into contact with one end 20 of the waterproof blanket 2 of the first steel plate 3a, and the extension portion of the waterproof blanket 2 is disposed at the end of the structural portion 32a of the second steel plate 3b. 20 heating and rolling is applied to the top of the waterproof blanket 2 outside the first steel plate 3a, so that the second steel plate 3b can be covered on the top end portion 35 of the roof, and the outer surface of the steel plate 3 is completely isolated from the external environment. A waterproof, insulated roof or wall.
如圖18所示,為本發明複合結構板(二)之鋼板實施例三,本實施例二係衍生自前述實施例一及二,前述鋼板與防水鋪面毯之結合,乃是於鋼板型前,先以鋼板材料1與防水鋪面毯2先行結合,且依據需求將鋼板材料1與防水鋪面毯2以不同之寬度結合,如本實施例一,乃是於鋼板材料1之一端較防水鋪面毯2之同一端較寬,其寬度為W2,防水鋪面毯2之另一端則是較鋼板材料1之同一端為較寬,其寬度為W1,且於W3之寬度範圍,防水鋪面毯2不與鋼板材料1貼合結合。As shown in FIG. 18, it is the third embodiment of the steel plate of the composite structural plate (2) of the present invention. The second embodiment is derived from the first embodiment and the second embodiment. The combination of the steel plate and the waterproof paving blanket is in front of the steel plate type. First, the steel plate material 1 and the waterproof paving blanket 2 are firstly combined, and the steel plate material 1 and the waterproof paving carpet 2 are combined with different widths according to requirements, as in the first embodiment, the waterproofing blanket is one end of the steel plate material 1. The same end of 2 is wider, the width is W2, and the other end of the waterproof blanket 2 is wider than the same end of the steel material 1, the width is W1, and within the width range of W3, the waterproof blanket 2 does not The steel sheet material 1 is bonded and bonded.
之後,再以鋼板成型設備將已互相結合之鋼板材料1與防水鋪面毯2輪輾成型為鋼板3,如圖19及20,或如圖21、22及23,本發明得將鋼板3成型為各種形狀,但本發明並未限定於圖19-23,或圖3-6之形狀。於鋼板3成型時,得於鋼板3之結構部32b外表面不為防水鋪面毯2包覆,但於鋼板3之另一端設不與之結合之防水鋪面毯2延伸部20a。Thereafter, the steel sheet material 1 and the waterproof tarpaulin 2 rims which have been combined with each other are formed into a steel sheet 3 by a steel plate forming apparatus, as shown in FIGS. 19 and 20, or as shown in FIGS. 21, 22 and 23, the present invention is formed by forming the steel sheet 3 into Various shapes, but the invention is not limited to the shapes of Figures 19-23, or Figures 3-6. When the steel sheet 3 is molded, the outer surface of the structural portion 32b of the steel sheet 3 is not covered with the waterproof blanket 2, but at the other end of the steel sheet 3, the waterproof blanket 2 extending portion 20a is not provided.
如圖24及25,及圖26及27,為前述鋼板3之實施例三的施工運用例,本施工運用例,至少包含:鋼樑4,係被設置於最下方,得依據金屬建築之結構需求而為H型鋼樑或C型鋼樑或管狀鋼樑等均無不可。前述鋼樑4係作為金屬建築物之主要結構體。24 and 25, and Figs. 26 and 27, are the construction application examples of the third embodiment of the steel sheet 3. The construction application example includes at least the steel beam 4, which is disposed at the bottom, and is based on the structure of the metal building. H-shaped steel beams or C-shaped steel beams or tubular steel beams are all indispensable for demand. The aforementioned steel beam 4 is the main structural body of the metal building.
固定座5,得為各種形狀(可參圖7~12),本運用例以ㄇ 型固定座介紹之,故而於ㄇ型固定座下方兩側並形成小延伸面50,得以栓設元件51穿過前述小延伸面50以固設於前述鋼樑4之上方。或如圖26之塔型固定座,得以將該金字塔型固定座設置於前述鋼樑4之上方,以為鋼板3之設置。或如圖27之於塔型固定座之上方設上結合部54,以為鋼板之結構部包覆後,即可將固定坐與鋼板3結合成一體。The fixed seat 5 can be of various shapes (refer to Figures 7~12). The type of fixing seat is introduced, so that a small extending surface 50 is formed on both sides of the lower side of the cymbal type fixing seat, so that the tying member 51 passes through the small extending surface 50 to be fixed above the steel beam 4. Alternatively, the tower-shaped fixing base can be placed above the steel beam 4 as shown in Fig. 26 to provide the steel plate 3. Alternatively, as shown in Fig. 27, the joint portion 54 is provided above the tower-shaped fixing seat, so that the structural portion of the steel sheet is covered, and the fixed seat can be integrated with the steel plate 3.
鋼板3,設平板部31,於平板部31兩側設結構部32a、32b,結構部32a、32b係為對稱結構,因此,乃於二結構部32a、32b之間形成適當的空間33。The steel plate 3 is provided with a flat plate portion 31, and structural portions 32a and 32b are provided on both sides of the flat plate portion 31. The structural portions 32a and 32b have a symmetrical structure. Therefore, an appropriate space 33 is formed between the two structural portions 32a and 32b.
如此,如圖24,當前述二相鄰的鋼板3之結構部32a、32b互相結合前時,需先將第一鋼板3a之結構部32b與第二鋼板3b之結構部32a互相結合,利用前述第二鋼板3b之結構部32a包覆於第一鋼板3a之結構部32b外表面,再以栓設元件34將第一鋼板3a之結構部32b與第二鋼板3b之結構部32a固設於前述固定座5之上方。Thus, as shown in Fig. 24, when the structural portions 32a, 32b of the two adjacent steel sheets 3 are joined to each other, the structural portion 32b of the first steel sheet 3a and the structural portion 32a of the second steel sheet 3b are first joined to each other. The structural portion 32a of the second steel sheet 3b is coated on the outer surface of the structural portion 32b of the first steel sheet 3a, and the structural portion 32b of the first steel sheet 3a and the structural portion 32a of the second steel sheet 3b are fixed to the aforementioned portion by the plugging member 34. Above the mount 5.
且使得第二鋼板3b之結構部32a末端部35與第一鋼板3a之防水鋪面毯2之一端20接觸(如圖24及25),並將位於第二鋼板3b之防水鋪面毯2延伸部20a跨設於第二鋼板3b之結構部32a上方,並加熱滾壓貼合於第一鋼板3a外部的防水鋪面毯2之部分表面,即可將鋼板3之外表面與外部環境全部隔離,可組成防水、隔熱之屋頂或牆壁。And the end portion 35 of the structural portion 32a of the second steel plate 3b is brought into contact with one end 20 of the waterproof blanket 2 of the first steel plate 3a (as shown in Figs. 24 and 25), and the waterproof blanket 2 extension 20a of the second steel plate 3b is placed. The outer surface of the steel plate 3 is completely isolated from the external environment by arranging over the structural portion 32a of the second steel plate 3b and heating and rolling the surface of the waterproof blanket 2 attached to the outside of the first steel plate 3a. Waterproof, insulated roof or wall.
再如圖28及29,為前述鋼板實施例一-三之雙層鋼板之施工運用例,本施工運用例,至少包含:鋼樑4,係被設置於最下方,得依據金屬建築之結構需求而為H型鋼樑或C型鋼樑或管狀鋼樑等均無不可。前述鋼樑4係作為金屬建築物之主要結構體。Further, as shown in FIGS. 28 and 29, the construction example of the double-layer steel plate of the first embodiment of the steel plate is used. The construction application example includes at least the steel beam 4, which is disposed at the bottom, and is required according to the structural requirements of the metal building. The H-shaped steel beam or the C-shaped steel beam or the tubular steel beam are all indispensable. The aforementioned steel beam 4 is the main structural body of the metal building.
固定座5,得為各種形狀(可參圖7~12或圖26及27), 圖28之運用例以ㄇ型固定座介紹之,故而於ㄇ型固定座下方兩側並形成小延伸面50,得以栓設元件51穿過前述小延伸面50以固設於前述鋼樑4之上方,並位於下層鋼板6之結構部內。圖29則是以圖27之塔型固定座為解釋。The fixing seat 5 has various shapes (refer to Figures 7 to 12 or Figures 26 and 27). The application example of FIG. 28 is described by a 固定-type fixing seat. Therefore, a small extension surface 50 is formed on both sides of the yoke type fixing seat, so that the bolting member 51 passes through the small extension surface 50 to be fixed to the steel beam 4 Above, and located in the structural part of the lower steel plate 6. Figure 29 is an illustration of the tower type mount of Figure 27.
下層鋼板6(結構亦可如圖3-6),設平板部61,於平板部61兩側設結構部62a、62b,結構部62a、62b係為對稱結構,因此,乃於二結構部62a、62b之間形成適當的空間63。如圖28,係以下層鋼板6之平板部61鋪設於前述鋼樑4上方。The lower steel plate 6 (the structure may be as shown in FIG. 3-6) is provided with a flat plate portion 61, and structural portions 62a and 62b are provided on both sides of the flat plate portion 61. The structural portions 62a and 62b are symmetrical structures, and therefore, the second structural portion 62a A suitable space 63 is formed between 62b. As shown in Fig. 28, the flat plate portion 61 of the lower steel sheet 6 is laid over the steel beam 4.
隔絕層7,得由玻璃(二氧化矽)經由高溫自體發泡製成之發泡玻璃或稱氣泡玻璃或稱矽晶化礦纖板(Cellular Glass);或岩棉;或矽酸鈣板;或美耐板;或水泥板;或氧化鎂板等具備防火、隔音;隔熱之材料為之。如圖28,得將隔絕層7鋪設於前述下層鋼板6之二結構部62a、62b所形成的空間63中。The insulating layer 7 is made of glass (cerium oxide) foamed glass or so-called bubble glass or cellular glass (Cellular Glass); or rock wool; or calcium silicate board Or high-grade board; or cement board; or magnesium oxide board, etc., which has fireproofing and soundproofing; As shown in Fig. 28, the insulating layer 7 is laid in the space 63 formed by the two structural portions 62a, 62b of the lower steel sheet 6.
架高座8,如圖28及圖29,設第一結合部80,得與前述下層鋼板6之結構部62a結合,前述架高座8設第二結合部81,得與鋼板3之結構部32b結合,如圖28,得以栓設元件82自鋼板3之一結構部32b、架高座8之第二結合部81及第一結合部80、下層鋼板6之一結構部與固定座5(固定座之結構可參圖8-12)一起栓設結合。或如圖29,則是以鋼板3之結構部包覆於架高座8之第二結合部81,即可將鋼板3與架高座8結合成一體。As shown in FIGS. 28 and 29, the upper seat portion 8 is provided with a first joint portion 80 which is coupled to the structural portion 62a of the lower steel sheet 6, and the upper seat portion 8 is provided with a second joint portion 81 which is combined with the structural portion 32b of the steel sheet 3. As shown in FIG. 28, the component 82 is bolted from one structural portion 32b of the steel plate 3, the second joint portion 81 of the elevated seat 8, and the first joint portion 80, one of the lower steel plates 6, and the fixed seat 5 (the fixed seat) The structure can be combined with Figure 8-12). Alternatively, as shown in Fig. 29, the steel plate 3 and the elevated base 8 can be integrally joined by covering the second joint portion 81 of the elevated seat 8 with the structural portion of the steel plate 3.
鋼板3,設平板部31,於平板部31兩側設結構部32a、32b,結構部32a、32b係為對稱結構,因此,乃於二結構部32a、32b之間形成適當的空間33。The steel plate 3 is provided with a flat plate portion 31, and structural portions 32a and 32b are provided on both sides of the flat plate portion 31. The structural portions 32a and 32b have a symmetrical structure. Therefore, an appropriate space 33 is formed between the two structural portions 32a and 32b.
如此,當位於最外層之相鄰鋼板3之結構部32a、32b互相結合前時,需先將第一鋼板3a之結構部32b以栓設元件34固設於前述固定座5之上方,再將第二鋼板3b之結構部32a與第一鋼板3a之結構部32b互相結合,利用前述第二鋼板3b之結構部32a包覆於第一鋼板3a之結構部32b外表面,並將位於第二鋼板3b之 結構部32a末端所設前述防水鋪面毯2之延伸部20加熱滾壓貼合於第一鋼板3a外部之防水鋪面毯2上方,即可將第一鋼板3a顯露於屋頂上之末端部35包覆,將鋼板3之外表面與外部環境全部隔離,可組成防水、隔熱之屋頂或牆壁。Therefore, when the structural portions 32a and 32b of the adjacent outer steel sheets 3 are joined to each other, the structural portion 32b of the first steel plate 3a is first fixed to the upper portion of the fixing base 5 by the plugging member 34, and then The structural portion 32a of the second steel plate 3b and the structural portion 32b of the first steel plate 3a are joined to each other, and the structural portion 32a of the second steel plate 3b is coated on the outer surface of the structural portion 32b of the first steel plate 3a, and is placed on the second steel plate. 3b The extending portion 20 of the waterproof blanket 2 provided at the end of the structural portion 32a is heated and rolled to fit over the waterproof blanket 2 outside the first steel plate 3a, so that the first steel plate 3a is exposed on the roof end portion 35. The outer surface of the steel plate 3 is completely isolated from the external environment to form a waterproof or insulated roof or wall.
如此,即可於金屬建築所採用之鋼板預先以非金屬材質之防水鋪面毯2結合,以保護建築物之屋頂,並阻絕熱源進入建築物之內部,讓建築物之於屋頂產生絕佳的防水、隔熱效果,且如於屋頂植栽綠色植物時,亦可防止植物的根部穿過防水鋪面毯與鋼板,提升綠色建築之效益、優點與結構創新性,並得以提升金屬建築物之安全,為本案之組成。In this way, the steel plate used in the metal building can be combined with the non-metal waterproof paving blanket 2 to protect the roof of the building and prevent the heat source from entering the interior of the building, so that the building is excellent in waterproofing on the roof. Insulation effect, and when planting green plants on the roof, it can also prevent the roots of plants from passing through the waterproof paving blanket and steel plate, improving the efficiency, advantages and structural innovation of the green building, and improving the safety of the metal building. The composition of this case.
1‧‧‧鋼板材料1‧‧‧Steel material
W1‧‧‧寬度W1‧‧‧Width
W2‧‧‧寬度W2‧‧‧Width
W3‧‧‧寬度W3‧‧‧Width
2‧‧‧防水鋪面毯2‧‧‧Waterproofing blanket
20‧‧‧延伸部20‧‧‧Extension
20a‧‧‧延伸部20a‧‧‧Extension
3‧‧‧鋼板3‧‧‧ steel plate
31‧‧‧平板部31‧‧‧ Flat section
32a、32b‧‧‧結構部32a, 32b‧‧‧Structural Department
33‧‧‧空間33‧‧‧ Space
3a‧‧‧第一鋼板3a‧‧‧First steel plate
34‧‧‧栓設元件34‧‧‧Equipment components
3b‧‧‧第二鋼板3b‧‧‧second steel plate
35‧‧‧末端部35‧‧‧End
4‧‧‧鋼樑4‧‧‧ steel beam
5‧‧‧固定座5‧‧‧ Fixed seat
50‧‧‧小延伸面50‧‧‧Small extension
51‧‧‧栓設元件51‧‧‧Equipment components
5a‧‧‧C型固定座5a‧‧‧C type holder
52‧‧‧L型座52‧‧‧L seat
53‧‧‧栓設元件53‧‧‧Equipment components
54‧‧‧上結合部54‧‧‧Upper joint
5b‧‧‧ㄇ型固定座5b‧‧‧ㄇ-type holder
5c‧‧‧環ㄇ型固定座5c‧‧‧ring type fixing seat
6‧‧‧下層鋼板6‧‧‧Under steel plate
61‧‧‧平板部61‧‧‧ Flat section
62a、62b‧‧‧結構部62a, 62b‧‧‧Structural Department
63‧‧‧空間63‧‧‧ Space
7‧‧‧隔絕層7‧‧‧Insulation
8‧‧‧架高座8‧‧‧High seat
80‧‧‧第一結合部80‧‧‧ first joint
81‧‧‧第二結合部81‧‧‧Second junction
82‧‧‧栓設元件82‧‧‧Equipment components
圖1為本發明鋼板材料與防水鋪面毯結合加工圖。1 is a combined processing diagram of a steel sheet material and a waterproof paving blanket of the present invention.
圖2為本發明鋼板材料與防水鋪面毯結合剖視圖。Figure 2 is a cross-sectional view showing the combination of the steel sheet material of the present invention and the waterproof blanket.
圖3為本發明鋼板實施例(一)之第一種鋼板視圖。Figure 3 is a view of a first steel sheet of the steel sheet embodiment (I) of the present invention.
圖4為本發明鋼板實施例(一)之第二種鋼板視圖。Figure 4 is a view of a second steel sheet of the steel sheet embodiment (I) of the present invention.
圖5為本發明鋼板實施例(一)之第三種鋼板視圖。Fig. 5 is a view showing a third steel sheet of the steel sheet embodiment (I) of the present invention.
圖6為本發明鋼板實施例(一)之第四種鋼板視圖。Fig. 6 is a view showing a fourth steel sheet of the steel sheet embodiment (I) of the present invention.
圖7為本發明鋼板實施例(一)之第一種施工運用例圖。Fig. 7 is a view showing an example of the first construction operation of the steel sheet embodiment (I) of the present invention.
圖8為本發明鋼板實施例(一)之第一種施工運用例圖。Fig. 8 is a view showing an example of the first construction operation of the steel sheet embodiment (I) of the present invention.
圖9為本發明鋼板實施例(一)之第二種施工運用例圖。Fig. 9 is a view showing an example of the second construction operation of the steel sheet embodiment (I) of the present invention.
圖10為本發明鋼板實施例(一)之第三種施工運用例圖。Fig. 10 is a view showing an example of the third construction operation of the steel sheet embodiment (I) of the present invention.
圖11為本發明鋼板實施例(一)之第四種施工運用例圖。Figure 11 is a view showing a fourth example of construction operation of the steel sheet embodiment (I) of the present invention.
圖12為本發明鋼板實施例(一)之第五種施工運用例圖。Fig. 12 is a view showing a fifth example of construction operation of the steel sheet embodiment (I) of the present invention.
圖13為本發明鋼板材料與防水鋪面毯結合剖視圖。Figure 13 is a cross-sectional view showing the combination of the steel sheet material and the waterproof blanket of the present invention.
圖14為本發明鋼板實施例(二)之第一種鋼板視圖。Figure 14 is a view of a first steel sheet of the steel sheet embodiment (II) of the present invention.
圖15為本發明鋼板實施例(二)之第二種鋼板視圖。Figure 15 is a view of a second steel sheet of the embodiment (2) of the steel sheet of the present invention.
圖16為本發明鋼板實施例(二)之施工運用例圖。Fig. 16 is a view showing an example of construction operation of the steel sheet embodiment (2) of the present invention.
圖17為本發明鋼板實施例(二)之施工運用例圖。Fig. 17 is a view showing an example of construction operation of the steel sheet embodiment (2) of the present invention.
圖18為本發明鋼板材料與防水鋪面毯結合剖視圖。Figure 18 is a cross-sectional view showing the combination of the steel sheet material and the waterproof blanket of the present invention.
圖19為本發明鋼板實施例(三)之第一種鋼板視圖。Figure 19 is a view of a first steel sheet of the embodiment (3) of the steel sheet of the present invention.
圖20為本發明鋼板實施例(三)之第二種鋼板視圖。Figure 20 is a view of a second steel sheet of the embodiment (3) of the steel sheet of the present invention.
圖21為本發明鋼板實施例(三)之第三種鋼板視圖。Figure 21 is a view showing a third steel sheet of the embodiment (3) of the steel sheet of the present invention.
圖22為本發明鋼板實施例(三)之第四種鋼板視圖。Figure 22 is a view of a fourth steel sheet of the embodiment (3) of the steel sheet of the present invention.
圖23為本發明鋼板實施例(三)之第五種鋼板視圖。Figure 23 is a view showing a fifth steel sheet of the embodiment (3) of the steel sheet of the present invention.
圖24為本發明鋼板實施例(三)之施工運用例一。Fig. 24 is a first embodiment of construction operation of the steel plate embodiment (3) of the present invention.
圖25為本發明鋼板實施例(三)之施工運用例一之完成圖。Fig. 25 is a completed view of the construction operation example 1 of the embodiment (3) of the steel sheet of the present invention.
圖26為本發明鋼板實施例(三)之施工運用例二。Fig. 26 is a second application example 2 of the steel plate embodiment (3) of the present invention.
圖27為本發明鋼板實施例(三)之施工運用例三。Fig. 27 is a third structural application example of the steel plate embodiment (3) of the present invention.
圖28為本發明鋼板實施例(一)~(三)之雙層鋼板施工運用例圖。Fig. 28 is a view showing an example of construction of a double-layer steel plate according to the embodiment (1) to (3) of the steel sheet of the present invention.
圖29為本發明鋼板實施例(三)之雙層鋼板施工運用例圖。Fig. 29 is a view showing an example of construction work of a double-layer steel plate according to the third embodiment of the steel sheet of the present invention.
2‧‧‧防水鋪面毯2‧‧‧Waterproofing blanket
20‧‧‧延伸部20‧‧‧Extension
3‧‧‧鋼板3‧‧‧ steel plate
32a、32b‧‧‧結構部32a, 32b‧‧‧Structural Department
3a‧‧‧第一鋼板3a‧‧‧First steel plate
34‧‧‧栓設元件34‧‧‧Equipment components
3b‧‧‧第二鋼板3b‧‧‧second steel plate
35‧‧‧末端部35‧‧‧End
4‧‧‧鋼樑4‧‧‧ steel beam
5‧‧‧固定座5‧‧‧ Fixed seat
50‧‧‧小延伸面50‧‧‧Small extension
51‧‧‧栓設元件51‧‧‧Equipment components
Claims (18)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
TW101121268A TWI499708B (en) | 2012-06-14 | 2012-06-14 | Complex plate |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
TW101121268A TWI499708B (en) | 2012-06-14 | 2012-06-14 | Complex plate |
Publications (2)
Publication Number | Publication Date |
---|---|
TW201350656A TW201350656A (en) | 2013-12-16 |
TWI499708B true TWI499708B (en) | 2015-09-11 |
Family
ID=50157898
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
TW101121268A TWI499708B (en) | 2012-06-14 | 2012-06-14 | Complex plate |
Country Status (1)
Country | Link |
---|---|
TW (1) | TWI499708B (en) |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
TW201041742A (en) * | 2009-02-13 | 2010-12-01 | Fukuvi Chem Ind Co | Moisture permeable water proof sheet for building material |
TW201116409A (en) * | 2009-09-30 | 2011-05-16 | Grace W R & Co | Waterproofing membrane |
-
2012
- 2012-06-14 TW TW101121268A patent/TWI499708B/en not_active IP Right Cessation
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
TW201041742A (en) * | 2009-02-13 | 2010-12-01 | Fukuvi Chem Ind Co | Moisture permeable water proof sheet for building material |
TW201116409A (en) * | 2009-09-30 | 2011-05-16 | Grace W R & Co | Waterproofing membrane |
Also Published As
Publication number | Publication date |
---|---|
TW201350656A (en) | 2013-12-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101469641B1 (en) | Self-adhesive type composite waterproofing sheet and waterproof method using the same | |
WO2014052248A3 (en) | Composite insulated plywood, insulated plywood concrete form and method of curing concrete using same | |
CN204326582U (en) | A kind of container-combination formula house | |
KR102261398B1 (en) | manufacturing method of Complex waterproofing layer | |
KR20090110034A (en) | Butylene Rubber Waterproof Sheet, Complex Waterproof Constructing Method Using the Same and Waterproof Structure | |
TWI499708B (en) | Complex plate | |
KR101351378B1 (en) | Waterproof insulator | |
KR100702921B1 (en) | Method for Constructing Waterproof Sheet Using Dual Waterproof Sheet and Waterproof Structure | |
KR101448205B1 (en) | Noise insulation of building structures protruding joints art panel | |
CN204728515U (en) | A kind of outer-wall crack-resisting anti-leakage structure | |
KR101614749B1 (en) | Protection sheet of waterproof layer and constructing method using the same | |
KR101780988B1 (en) | Waterproofing method of building wall | |
KR101465453B1 (en) | Structure for avoiding water of a building | |
CN205100442U (en) | Wood constructs local -style dwelling houses roofing structure | |
CN203569713U (en) | Buckling type external wall insulation plate | |
TWI482898B (en) | Complex steel plate | |
CN201982883U (en) | Polyurethane heat insulation joint for steel pipe protect | |
KR101101165B1 (en) | Wet outer insulation structure for heat insulation and waterproof | |
CN205712519U (en) | Subsiding crack heat-preserving node structure | |
CN103665977A (en) | Waterproof thermal-insulating coating for exterior wall of a building | |
CN201671242U (en) | Sealed arched corrugated steel roof | |
CN203795613U (en) | Roof sheathing and wallboard connection bridge cutoff structure | |
CN204850264U (en) | Roofing structure | |
CN104196130B (en) | A kind of waterproof construction of water scenery glass lighting ceiling and preparation method thereof | |
RU104211U1 (en) | THREE-LAYERED OUTDOOR WALL PANEL |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
MM4A | Annulment or lapse of patent due to non-payment of fees |