TW202039969A - Pile foundation and construction method of pile foundation - Google Patents

Pile foundation and construction method of pile foundation Download PDF

Info

Publication number
TW202039969A
TW202039969A TW109112909A TW109112909A TW202039969A TW 202039969 A TW202039969 A TW 202039969A TW 109112909 A TW109112909 A TW 109112909A TW 109112909 A TW109112909 A TW 109112909A TW 202039969 A TW202039969 A TW 202039969A
Authority
TW
Taiwan
Prior art keywords
pile
ground
sand
ground improvement
peripheral surface
Prior art date
Application number
TW109112909A
Other languages
Chinese (zh)
Inventor
田邉成
Original Assignee
日商東電設計股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 日商東電設計股份有限公司 filed Critical 日商東電設計股份有限公司
Publication of TW202039969A publication Critical patent/TW202039969A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/16Foundations formed of separate piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/54Piles with prefabricated supports or anchoring parts; Anchoring piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Abstract

A pile foundation includes: a pile that supports a towering structure and that extends along a vertical direction, a pile top projecting further upward than the ground; and ground improvement body provided in the pile in a state where the pile is driven into the ground, at least a part of which is in close contact with the inner peripheral surface of the pile.

Description

樁基礎及樁基礎之施工方法Pile foundation and construction method of pile foundation

本公開係關於一種樁基礎及樁基礎之施工方法。The present disclosure relates to a pile foundation and a construction method of the pile foundation.

在日本特開2003-293938號公報中,公開了一種在空心單樁基礎上施工有風力發電裝置的結構。另一方面,日本特開昭57-161224號公報公開了一種基樁,藉由在鋼管樁下端的內周面夾持圓筒狀的混凝土,增大鋼管下端的端面面積。Japanese Patent Laid-Open No. 2003-293938 discloses a structure in which a wind power generation device is constructed on a hollow single pile foundation. On the other hand, Japanese Patent Application Laid-Open No. 57-161224 discloses a foundation pile in which cylindrical concrete is clamped on the inner peripheral surface of the lower end of the steel pipe pile to increase the end surface area of the lower end of the steel pipe.

但是,作為單樁基礎等樁基礎的施工方法,已知有藉由打擊將樁直接打入地盤的工法。藉由將樁打入地下,前端閉塞效果能夠增加支撐力,並能夠於短期內完成施工。然而,樁口徑較大時,則無法獲得足夠的前端閉塞效果,無法得到較大的支撐力。另一方面,如日本特開昭57-161224號公報所述,當樁的下端的端面面積增大時,樁難以打入地盤,而降低工作效率。However, as a construction method for pile foundations such as single pile foundations, there is known a construction method in which piles are directly driven into the ground by striking. By driving the pile into the ground, the front-end blocking effect can increase the supporting force, and the construction can be completed in a short time. However, when the pile diameter is large, a sufficient front end occlusion effect cannot be obtained, and a large supporting force cannot be obtained. On the other hand, as described in Japanese Patent Application Laid-Open No. 57-161224, when the area of the end face of the lower end of the pile increases, it is difficult for the pile to drive into the ground, which reduces work efficiency.

本公開係考慮上述事實,其目的在於提供一種能夠確保工作效率的同時,增加樁的支撐力的樁基礎及樁基礎之施工方法。The present disclosure takes the above facts into consideration, and its purpose is to provide a pile foundation and a construction method of pile foundation that can increase the supporting force of the pile while ensuring work efficiency.

第1態樣之樁基礎具有:樁,其沿垂直方向延伸以支撐塔狀構造物,並且所述樁的樁頭比地盤更向上方突出,而所述樁的下端開放;以及地盤改良體,其在所述樁打入地盤的狀態下設置於所述樁內,並且所述地盤改良體的至少一部分與所述樁的內周面緊貼。The pile foundation of the first aspect has: a pile extending in a vertical direction to support a tower-like structure, and the pile head of the pile protrudes upward than the ground, and the lower end of the pile is open; and a ground improvement body, It is installed in the pile with the pile driven into the ground, and at least a part of the ground improvement body is in close contact with the inner peripheral surface of the pile.

在第1態樣之樁基礎中,在樁被打入地盤的狀態下,樁內設有地盤改良體。而且,此地盤改良體的至少一部分與樁的內周面緊貼。由此,樁與地盤改良體緊貼的部分使樁的內周面的摩擦力提高,進一步能夠增大樁的支撐力。In the pile foundation of the first aspect, in the state where the pile is driven into the ground, a ground improvement body is provided in the pile. Moreover, at least a part of this ground improvement body is in close contact with the inner peripheral surface of the pile. Thereby, the part where the pile and the ground improvement body are in close contact improves the frictional force of the inner peripheral surface of the pile, and can further increase the supporting force of the pile.

此外,由於能夠增加支撐力而不增加樁自身的厚度,故能夠藉由打擊將樁打入地盤。In addition, since the supporting force can be increased without increasing the thickness of the pile itself, it is possible to drive the pile into the ground by striking.

第2態樣之樁基礎,係在第1態樣中,所述樁內有砂土侵入,所述地盤改良體設置在所述樁的內周面與砂土之間。The pile foundation of the second aspect is in the first aspect, in which sand and soil intrude into the pile, and the ground improvement body is arranged between the inner peripheral surface of the pile and the sand.

在第2態樣之樁基礎中,與將砂土整體作為地盤改良體的情況相比,藉由在樁的內周面與砂土之間設置地盤改良體,能夠縮短工期。In the pile foundation of the second aspect, compared to the case where the whole sand is used as the ground improvement, the construction period can be shortened by providing the ground improvement between the inner peripheral surface of the pile and the sand.

第3態樣之樁基礎,係在第2態樣中,在從軸向觀察所述樁的截面時,所述地盤改良體沿著所述樁的內周面間隔地設置於多處。The pile foundation of the third aspect is in the second aspect, and when the cross section of the pile is viewed from the axial direction, the ground improvement body is provided at a plurality of places along the inner circumferential surface of the pile.

在第3態樣之樁基礎中,與沿樁的內周面全周設有地盤改良體的情況相比,能夠縮短工期。In the pile foundation of the third aspect, the construction period can be shortened compared to the case where the ground improvement body is provided along the entire circumference of the inner peripheral surface of the pile.

第4態樣之樁基礎,係在第2態樣或第3態樣中,所述地盤改良體僅形成在進入所述樁內部的砂土中的軸向的一部分的砂土中。The pile foundation of the fourth aspect is in the second aspect or the third aspect, and the ground improvement body is formed only in a part of the sand in the axial direction of the sand entering the pile.

第5態樣之樁基礎,係在第1態樣中,在從軸向觀察所述樁的截面時,所述地盤改良體設置於所述樁內的整個區域。The pile foundation of the fifth aspect is the first aspect. When the cross section of the pile is viewed from the axial direction, the ground improvement body is installed in the entire area of the pile.

在第5態樣之樁基礎中,藉由地盤改良體能夠提高樁的內部整體的剛性。In the pile foundation of the fifth aspect, the entire inner rigidity of the pile can be improved by the ground improvement body.

第6態樣之樁基礎,係在第1態樣至第5態樣的任一態樣中,在所述樁頭附近的所述樁的內周面上,設有從上方支撐所述地盤改良體的支撐構件。The pile foundation of the sixth aspect is in any one of the first aspect to the fifth aspect, and the inner peripheral surface of the pile near the pile head is provided with supporting the ground from above Improved support member.

在第6態樣之樁基礎中,藉由支撐構件從上方支撐地盤改良體,故能夠使樁和地盤改良體更加緊貼地一體化。In the pile foundation of the sixth aspect, since the ground improvement body is supported from above by the supporting member, the pile and the ground improvement body can be integrated more closely.

第7態樣之樁基礎具有:樁,其沿垂直方向延伸以支撐塔狀構造物,並且所述樁的樁頭比地盤更向上方突出,所述樁的下端開放;以及支撐構件,其設置在所述樁頭附近的所述樁的內周面上,並從上方支撐進入所述樁的內部的至少一部分砂土。The pile foundation of the seventh aspect has: a pile that extends in a vertical direction to support a tower-shaped structure, and the pile head of the pile protrudes upward than the ground, and the lower end of the pile is open; and a supporting member, which is provided On the inner peripheral surface of the pile near the pile head, at least a part of the sand that has entered the inside of the pile is supported from above.

在第7態樣的樁基礎中,在樁頭附近的樁的內周面上設有支撐構件,而此支撐構件從上方支撐進入樁內部的至少一部分的砂土。藉由如此設置支撐構件,在將樁打入地盤時,能夠利用支撐構件壓縮樁內的砂土,而能夠得到前端閉塞效果。In the pile foundation of the seventh aspect, a supporting member is provided on the inner circumferential surface of the pile near the pile head, and the supporting member supports at least a part of the sand that has entered the pile from above. By providing the supporting member in this way, when the pile is driven into the ground, the sand and soil in the pile can be compressed by the supporting member, and the front end blocking effect can be obtained.

第8態樣之樁基礎,係在第7態樣中,所述支撐構件是從所述樁的內周面向徑向內側延伸的環狀凸緣。In the eighth aspect of the pile foundation, in the seventh aspect, the supporting member is an annular flange extending radially inward from the inner circumferential surface of the pile.

在第8態樣的樁基礎中,能夠利用環形凸緣來壓縮樁內的砂土。此外,由於凸緣的上下空間連通,因此,在打入樁後,能夠將藥劑等投入砂土進行地盤改良。In the pile foundation of the eighth aspect, the annular flange can be used to compress the sand in the pile. In addition, since the upper and lower spaces of the flange are connected, it is possible to put medicines and the like into the sand and soil to improve the ground after the pile is driven.

第9態樣之樁基礎,係在第7態樣中,所述支撐構件是使所述樁頭的下端部閉塞的圓盤狀構件。In the ninth aspect of the pile foundation, in the seventh aspect, the support member is a disc-shaped member that closes the lower end of the pile head.

在第9態樣的樁基礎中,藉由圓盤狀構件能夠向樁內的砂土整體傳遞垂直力。In the pile foundation of the ninth aspect, the vertical force can be transmitted to the entire sand and soil in the pile by the disc-shaped member.

第10態樣之樁基礎,係在第7態樣至第9態樣的任一態樣中,在進入所述樁的內部的砂土和所述支撐構件之間填充有填充材料。The pile foundation of the tenth aspect is in any one of the seventh aspect to the ninth aspect, and a filling material is filled between the sand entering the pile and the supporting member.

在第10態樣的樁基礎中,藉由填充材料能夠使砂土和支撐構件一體化。In the pile foundation of the tenth aspect, the sand and the supporting member can be integrated with the filling material.

第11態樣之樁基礎,係在第1態樣至第10態樣的任一態樣中,地盤上設置有地板,所述地板固定在所述樁頭上,而使作用於所述樁上的力向地盤傳遞。The pile foundation of the eleventh aspect is attached to any one of the first aspect to the tenth aspect. A floor is provided on the ground, and the floor is fixed on the pile head so as to act on the pile The force is transmitted to the site.

在第11態樣的樁基礎中,即使有樁倒下方向的外力輸入的情況下,也能夠經由地板將此外力的至少一部分傳遞至地盤,而能夠確保樁對水平力之抵抗力。In the pile foundation of the eleventh aspect, even when an external force is input in the direction in which the pile falls, at least a part of the external force can be transmitted to the ground via the floor, and the resistance of the pile to the horizontal force can be ensured.

第12態樣之樁基礎,係在第1態樣至第11態樣的任一態樣中,所述塔狀構造物構成為風力發電裝置的腳部。The pile foundation of the twelfth aspect is in any one of the first aspect to the eleventh aspect, and the tower-shaped structure constitutes the foot of the wind power generator.

在第12態樣的樁基礎中,即使在因風力發電裝置等重物而向樁施加傾倒方向的力矩的情況下,也可以藉由增大樁的支撐力來抑制樁的翻倒。In the pile foundation of the twelfth aspect, even when a moment in the tilting direction is applied to the pile due to a heavy object such as a wind turbine, the pile can be prevented from falling over by increasing the supporting force of the pile.

第13態樣的樁基礎之施工方法具有以下步驟:將下端開放的樁打入地盤,使所述樁的樁頭向地盤上方突出;以及在進入所述樁的內部的砂土中,至少對所述樁的內周面附近的砂土進行地盤改良。The construction method of the pile foundation of the thirteenth aspect has the following steps: driving a pile with an open lower end into the ground so that the pile head of the pile protrudes above the ground; and in the sand entering the inside of the pile, at least The sandy soil near the inner peripheral surface of the pile is improved on the ground.

在第13態樣的樁基礎之施工方法中,藉由至少對樁的內周面附近的砂土進行地盤改良,能夠使此地盤改良體與樁的內周面緊貼。由此,能夠提高樁內周面的摩擦力,增大樁的支撐力。此外,與切削地盤後進行樁施工的方法相比,藉由將樁打入地盤,能夠確保工作效率。In the construction method of the pile foundation of the thirteenth aspect, by performing ground improvement on at least the sand near the inner peripheral surface of the pile, the ground improvement body can be brought into close contact with the inner peripheral surface of the pile. Thereby, the frictional force of the inner peripheral surface of the pile can be increased, and the supporting force of the pile can be increased. In addition, compared with the method of pile construction after cutting the ground, the work efficiency can be ensured by driving the pile into the ground.

如上所述,根據本公開的樁基礎及樁基礎之施工方法,能夠在確保工作效率的同時,提高樁的支撐力。As described above, according to the pile foundation and the construction method of the pile foundation of the present disclosure, it is possible to improve the supporting force of the pile while ensuring work efficiency.

>第1實施形態> 參照附圖對第1實施形態之樁基礎10進行說明。如圖1所示,本實施形態之樁基礎10為支撐風力發電裝置12的基礎。>First Embodiment> The pile foundation 10 of the first embodiment will be described with reference to the drawings. As shown in FIG. 1, the pile foundation 10 of this embodiment is a foundation supporting a wind power generator 12.

風力發電裝置12包括:腳部(塔)14,其作為塔狀構造物,從樁基礎10沿垂直方向延伸;以及設置在此腳部14的上端部的風車部16。另外,風車部16包括機艙18、輪轂20以及葉片22。The wind power generator 12 includes a foot (tower) 14 that is a tower-shaped structure extending from the pile foundation 10 in a vertical direction; and a windmill 16 provided at the upper end of the foot 14. In addition, the windmill part 16 includes a nacelle 18, a hub 20 and blades 22.

風力發電裝置12的腳部14的直徑朝上方逐漸變小,此腳部14的下端與樁基礎10連結。另外,構成風車部16的機艙18轉動自如地安裝在腳部14的上端部,在此機艙18的內部收容有未圖示的發電機和放大器。The diameter of the leg portion 14 of the wind turbine generator 12 gradually decreases upward, and the lower end of the leg portion 14 is connected to the pile foundation 10. In addition, a nacelle 18 constituting the windmill unit 16 is rotatably attached to the upper end of the leg portion 14, and a generator and an amplifier (not shown) are housed in the nacelle 18.

機艙18經由未圖示的轉子軸與輪轂20連結。而且,在輪轂20上安裝有作為多個旋轉翼的葉片22,在本實施形態中,作為一例,在輪轂20的周面上安裝有3片葉片22。The nacelle 18 is connected to the hub 20 via a rotor shaft (not shown). In addition, blades 22 as a plurality of rotating wings are attached to the hub 20. In this embodiment, as an example, three blades 22 are attached to the peripheral surface of the hub 20.

如上所述的風力發電裝置12的腳部14被樁基礎10支撐。在此,本實施形態之樁基礎10包括大致圓筒狀的樁24。The legs 14 of the wind power generator 12 as described above are supported by the pile foundation 10. Here, the pile foundation 10 of this embodiment includes a substantially cylindrical pile 24.

樁24係由鋼管所形成,以垂直方向為軸向延伸,設置在與風力發電裝置12的腳部14大致同軸上。另外,樁24除了設置在上部的樁頭24A之外,其他部分藉由打擊工法打入地盤26中。在此,在本實施形態中,由於是應用於海上的風力發電裝置12的樁基礎10,因此,樁24被打入海底,從地盤26打入樁24的樁直徑的4至6倍左右的深度。在本實施形態中,作為一例,使用樁直徑為5~9m的樁24,從地盤26打入至約30m的深度。The pile 24 is formed of a steel pipe, extends in a vertical direction as an axial direction, and is provided substantially coaxially with the leg 14 of the wind power generator 12. In addition, except for the pile head 24A provided on the upper part of the pile 24, the other parts are driven into the site 26 by the striking method. Here, in this embodiment, since it is the pile foundation 10 of the offshore wind power generator 12, the pile 24 is driven into the seabed, and the pile 24 is driven from the ground 26 to about 4 to 6 times the diameter of the pile 24 depth. In this embodiment, as an example, a pile 24 having a pile diameter of 5 to 9 m is used, and it is driven from the ground 26 to a depth of about 30 m.

如圖2A所示,樁24的上端及下端開放,利用打擊工法將樁24打入地盤26,使砂土S進入樁24的內部。此外,藉由將樁24打入地盤26,樁24內的砂土S的表面會位於地盤26的表面的下方。As shown in FIG. 2A, the upper end and the lower end of the pile 24 are open, and the pile 24 is driven into the ground 26 by the hammering method, so that the sand S enters the inside of the pile 24. In addition, by driving the pile 24 into the ground 26, the surface of the sand S in the pile 24 will be located below the surface of the ground 26.

在此,在樁24被打入地盤26的狀態下,樁24內設有地盤改良體28。如圖2B所示,地盤改良體28的至少一部分與樁24的內周面24B緊貼,本實施形態的地盤改良體28設置於樁24的內周面24B與砂土S之間。Here, in a state where the pile 24 is driven into the ground 26, a ground improvement body 28 is provided in the pile 24. As shown in FIG. 2B, at least a part of the ground improvement body 28 is in close contact with the inner peripheral surface 24B of the pile 24, and the ground improvement body 28 of this embodiment is provided between the inner peripheral surface 24B of the pile 24 and the sandy soil S.

(樁基礎之施工方法) 接下來,對本實施形態之樁基礎10之施工方法的一例進行說明。首先,利用打擊工法將樁24打入地盤26至預定深度。此時,採用使樁頭24A比地盤26更向上方突出的方式打入樁24。若採用此種打擊工法,則地盤26不限於砂土地盤或較鬆散的砂礫地盤,即使是軟岩也能夠進行樁24的施工(打入)。(Construction method of pile foundation) Next, an example of the construction method of the pile foundation 10 of this embodiment is demonstrated. First, the pile 24 is driven into the site 26 to a predetermined depth by using the striking method. At this time, the pile 24 is driven so that the pile head 24A protrudes more upward than the ground 26. If such a blow construction method is adopted, the site 26 is not limited to a sand ground or a relatively loose gravel site, and the pile 24 can be constructed (driving) even in soft rock.

接著,對進入樁24內部的砂土S中的在樁24的內周面24B附近的砂土S進行地盤改良。具體而言,在樁24的內周面24B或樁24的內部,沿鋼管的軸向形成多個注入孔,從樁24的上部向這些注入孔投入藥劑或水泥微粒等改良材料,藉由滲透注入而形成地盤改良體28。作為其他方法,也可從樁24的上部挖掘鉆孔,並透過攪拌翼或噴射等方式投入水泥等地盤改良材料,以形成地盤改良體28。以此方式進行樁基礎10的施工。Next, the sandy soil S near the inner peripheral surface 24B of the pile 24 among the sandy soil S entering the inside of the pile 24 is ground improvement. Specifically, in the inner peripheral surface 24B of the pile 24 or the inside of the pile 24, a plurality of injection holes are formed along the axial direction of the steel pipe, and improved materials such as chemicals or cement particles are injected into these injection holes from the upper part of the pile 24. The ground improvement body 28 is formed by injection. As another method, a drill hole may be excavated from the upper part of the pile 24, and a ground improvement material such as cement may be injected through a method such as mixing blades or spraying to form the ground improvement body 28. The construction of the pile foundation 10 is performed in this way.

(作用) 接下來,說明本實施形態之作用。(effect) Next, the function of this embodiment will be explained.

在本實施形態的樁基礎10中,地盤改良體28的至少一部分與樁24的內周面24B緊貼。藉此,在樁24與地盤改良體28緊貼部分的樁24的內周面24B的摩擦力提高。因此,能夠增大樁24的支撐力。In the pile foundation 10 of the present embodiment, at least a part of the ground improvement body 28 is in close contact with the inner peripheral surface 24B of the pile 24. Thereby, the frictional force of the inner peripheral surface 24B of the pile 24 in the part where the pile 24 and the ground improvement body 28 are in close contact is improved. Therefore, the supporting force of the pile 24 can be increased.

尤其是,若樁24的口徑為大口徑,則無法充分獲得前端閉塞效果,無法得到較大的支撐力,但藉由本實施形態的結構,能夠得到較大的支撐力。參照圖10所示樁的模式圖對此作用進行說明。In particular, if the diameter of the pile 24 is a large diameter, the front end blocking effect cannot be sufficiently obtained, and a large supporting force cannot be obtained. However, with the structure of this embodiment, a large supporting force can be obtained. This effect will be described with reference to the schematic diagram of the pile shown in FIG. 10.

圖10A顯示小口徑的樁100。樁100的徑例如為直徑1m。當利用打擊工法將樁100打入地盤26時,藉由前端阻塞效應而形成帶載荷的壓力影響圈。值得一提的是,樁100的周圍區域T是因樁100的打擊而受到攪亂的砂土。如此一來,樁100的表面可看到的截面積變大,而樁100的支撐力增大。Figure 10A shows a small diameter pile 100. The diameter of the pile 100 is, for example, 1 m in diameter. When the pile 100 is driven into the site 26 by the percussion method, a pressure influence circle with load is formed by the front end blocking effect. It is worth mentioning that the surrounding area T of the pile 100 is soil disturbed by the impact of the pile 100. As a result, the visible cross-sectional area of the surface of the pile 100 increases, and the supporting force of the pile 100 increases.

另一方面,圖10B顯示大口徑的樁102。樁102的徑例如為直徑5~9m。當利用打擊工法將樁102打入地盤26時,樁102的周圍區域T的砂土被攪亂的幅度主要取決於地盤。並且,樁102的徑向中心部分的砂土因遠離樁102的周面,而不會被攪亂。因此,會形成線載荷的壓力影響圈,與小口徑的樁100相比,無法指望前端閉塞效果帶來的支撐力增大。On the other hand, Fig. 10B shows a large-diameter pile 102. The diameter of the pile 102 is 5-9 m in diameter, for example. When the pile 102 is driven into the ground 26 by the percussion method, the extent to which the sand in the surrounding area T of the pile 102 is disturbed mainly depends on the ground. In addition, the sand and soil in the radial center portion of the pile 102 is far away from the peripheral surface of the pile 102 and will not be disturbed. Therefore, a pressure influence circle of linear load is formed, and compared with the small-diameter pile 100, it is impossible to expect an increase in the supporting force due to the occlusion effect of the front end.

如上所述,在圖10B所示的模式中,無法超過樁102的內周面的摩擦力而發揮前端閉塞效果,並且認為此前端閉塞效果與樁102的內周面的摩擦力大致相等。在此,將樁102的內周面的每單位面積的摩擦力設為τ、將樁102的內周面的半徑設為rin 、將侵入樁102的砂土的高度設為h,則總摩擦力F按以下的式(1)計算。As described above, in the mode shown in FIG. 10B, the frictional force of the inner peripheral surface of the pile 102 cannot be exceeded to exert the front-end blocking effect, and it is considered that this front-end blocking effect is substantially equal to the frictional force of the inner peripheral surface of the pile 102. Here, the friction force per unit area of the inner peripheral surface of the pile 102 is set to τ, the radius of the inner peripheral surface of the pile 102 is set to r in , and the height of the sand invading the pile 102 is set to h, then the total The frictional force F is calculated by the following formula (1).

(式1)

Figure 02_image001
・・・(1)(Formula 1)
Figure 02_image001
···(1)

另一方面,若將樁102的內周面的砂土的前端支撐力設為P,將每單位面積的支撐力設為pin ,則P與pin 具有下式(2)的關係。On the other hand, if the front end supporting force of the inner peripheral surface of the pile of sand to 102 P, the supporting force per unit area is set to p in, and P p in the relation having the formula (2).

(式2)

Figure 02_image003
・・・(2)(Equation 2)
Figure 02_image003
···(2)

如上所述,當前端閉塞效果等於樁102的內周面的摩擦力時,前端支撐力P與總摩擦力F相等,因此,以下的式(3)成立。As described above, when the front end blocking effect is equal to the frictional force of the inner peripheral surface of the pile 102, the front end supporting force P is equal to the total frictional force F. Therefore, the following formula (3) holds.

(式3)

Figure 02_image005
・・・(3)(Equation 3)
Figure 02_image005
・・・(3)

由式(3)導出以下的式(4)。The following formula (4) is derived from the formula (3).

(式4)

Figure 02_image007
・・・(4)(Equation 4)
Figure 02_image007
・・・(4)

根據上述式(4)可知,樁102的內周面的每單位面積的支撐力pin 與樁102的內周面的半徑rin 成反比。即,樁102越是大口徑,前端的支撐力越小。Understood the above formula (4), the radius r of the inner circumferential surface of the per unit area of the inner peripheral surface 102 of the supporting force of the pile and the pile 102 p in the in inverse proportion. That is, the larger the diameter of the pile 102, the smaller the supporting force of the tip.

另一方面,根據式(4)可知,即使樁102為大口徑,藉由增大摩擦力τ,也能夠確保前端的支撐力。在此,在本實施形態中,如圖2A及圖2B所示,藉由使地盤改良體28與樁24的內周面24B緊貼,增大樁24的內周面24B的摩擦力。由此,即使在使用大口徑的樁24的情況下,也能夠增大樁24的支撐力。On the other hand, according to equation (4), even if the pile 102 has a large diameter, by increasing the friction force τ, the supporting force of the tip can be ensured. Here, in the present embodiment, as shown in FIGS. 2A and 2B, the frictional force of the inner peripheral surface 24B of the pile 24 is increased by bringing the ground improvement body 28 and the inner peripheral surface 24B of the pile 24 into close contact. Thereby, even in the case of using a large-diameter pile 24, the supporting force of the pile 24 can be increased.

此外,在本實施形態中,由於不加厚樁24自身的厚度而能夠增大支撐力,故能夠藉由打擊將樁24打入地盤26。即,無需在切削地盤26後才能進行樁的施工。因此,能夠在確保工作效率的同時,增大樁24的支撐力。尤其,在海上進行樁基礎10的施工時,如本實施形態所示,藉由利用地盤改良體28增加支撐力的結構,能夠使用小型的樁24,從而能夠降低運輸用船舶的規格。因此,可降低施工之成本。In addition, in this embodiment, since the thickness of the pile 24 itself is not thickened and the supporting force can be increased, the pile 24 can be driven into the ground 26 by a blow. That is, there is no need to perform pile construction after cutting the ground 26. Therefore, it is possible to increase the supporting force of the pile 24 while ensuring work efficiency. In particular, when the pile foundation 10 is constructed on the sea, as shown in the present embodiment, by using the structure in which the ground improving body 28 increases the supporting force, the small pile 24 can be used, and the specifications of the transportation ship can be reduced. Therefore, the cost of construction can be reduced.

進而,在本實施形態中,與將砂土S整體作為地盤改良體的情況相比,藉由在樁24的內周面24B與砂土S之間設置地盤改良體28,能夠縮短工期。Furthermore, in this embodiment, compared with the case where the whole sand S is used as a ground improvement body, by providing the ground improvement body 28 between the inner peripheral surface 24B of the pile 24 and the sand and soil S, the construction period can be shortened.

值得一提的是,在本實施形態中,如圖2B所示,在樁24的內周面24B上遍及全周設有地盤改良體28,但並不限定於此。例如,可採用圖3所示之變形例的結構。It is worth mentioning that, in the present embodiment, as shown in FIG. 2B, the ground improvement body 28 is provided on the inner peripheral surface 24B of the pile 24 throughout the entire circumference, but it is not limited to this. For example, the structure of the modified example shown in FIG. 3 may be adopted.

(變形例) 如圖3A所示,與本實施形態相同,構成本變形例的樁基礎30的樁24,除設置於上部的樁頭24A以外的部分,藉由打擊工法打入地盤26。(Modification) As shown in FIG. 3A, similar to the present embodiment, the pile 24 constituting the pile foundation 30 of this modification example is driven into the ground 26 by the hammering method except for the pile head 24A provided on the upper part.

在此,如圖3B所示,在樁24被打入地盤26的狀態下,樁24內設有地盤改良體28。地盤改良體28設置於樁24的內周面24B與砂土S之間。此外,從軸向觀察樁24的截面時,地盤改良體31沿樁24的內周面24B間隔地設置於多處,在本變形例中,沿內周面24B間隔地在五處設置有地盤改良體31。Here, as shown in FIG. 3B, in a state where the pile 24 is driven into the ground 26, a ground improvement body 28 is provided in the pile 24. The ground improvement body 28 is provided between the inner peripheral surface 24B of the pile 24 and the sand S. In addition, when the cross-section of the pile 24 is viewed from the axial direction, the ground improvement bodies 31 are provided at a plurality of intervals along the inner peripheral surface 24B of the pile 24. In this modification, grounds are provided at five places at intervals along the inner peripheral surface 24B. Improved body 31.

如上所述,在本變形例中,能夠在地盤改良體31與樁24的內周面24B緊貼的部分增大摩擦力。此外,與沿樁24的內周面24B在全周設置地盤改良體的情況相比,沿樁24的內周面24B間隔地在多處設置地盤改良體31,能夠縮短工期。As described above, in this modification, the frictional force can be increased in the portion where the ground improvement body 31 and the inner peripheral surface 24B of the pile 24 are in close contact. In addition, compared to the case where the ground improvement bodies are provided over the entire circumference along the inner peripheral surface 24B of the pile 24, the ground improvement bodies 31 are provided at intervals along the inner peripheral surface 24B of the pile 24, and the construction period can be shortened.

<第2實施形態> 接下來,參照圖4A及圖4B對第2實施形態之樁基礎32進行說明。值得一提的是,對於與第1實施形態相同的結構標註相同的符號,並適當省略說明。<The second embodiment> Next, the pile foundation 32 of the second embodiment will be described with reference to FIGS. 4A and 4B. It is worth mentioning that the same components as those in the first embodiment are given the same reference numerals, and descriptions are omitted as appropriate.

如圖4A所示,構成本實施形態之樁基礎32的樁24與第1實施形態相同。除樁頭24A外,樁24的其他部分藉由打擊工法打入地盤26。As shown in FIG. 4A, the pile 24 constituting the pile foundation 32 of the present embodiment is the same as that of the first embodiment. Except for the pile head 24A, the other parts of the pile 24 are driven into the site 26 by the strike method.

在此,樁24的內部設有地盤改良體33。地盤改良體33的至少一部分與樁24的內周面24B緊貼,並且從軸向觀察樁24的截面時,本實施形態的地盤改良體33設置於樁24內的整個區域。Here, a ground improvement body 33 is provided inside the pile 24. When at least a part of the ground improvement body 33 is in close contact with the inner peripheral surface 24B of the pile 24 and the cross section of the pile 24 is viewed from the axial direction, the ground improvement body 33 of this embodiment is installed in the entire area within the pile 24.

另外,在樁24的內周面24B上設置有凸緣34,其作為從上方支撐地盤改良體33的支撐構件的同時,將樁24的內部空間上下隔開。凸緣34由金屬製成,配置於樁頭24A附近,並藉由焊接等方式接合(固定)於樁24的內周面24B。In addition, a flange 34 is provided on the inner peripheral surface 24B of the pile 24 as a support member that supports the ground improvement body 33 from above, and partitions the inner space of the pile 24 up and down. The flange 34 is made of metal, is disposed near the pile head 24A, and is joined (fixed) to the inner peripheral surface 24B of the pile 24 by welding or the like.

此外,凸緣34從樁24的內周面24B向徑向內側延伸而形成為環狀,如圖4B所示,在凸緣34的徑向中央部分形成有大致圓形的開口34A。因此,地盤改良體33成為透過開口34A向樁頭24A側露出的結構。In addition, the flange 34 extends radially inward from the inner peripheral surface 24B of the pile 24 and is formed in a ring shape. As shown in FIG. 4B, a substantially circular opening 34A is formed in the radial center portion of the flange 34. Therefore, the ground improvement body 33 has a structure exposed to the pile head 24A side through the opening 34A.

在此,對本實施形態的樁基礎32的施工方法的一例進行說明。首先,凸緣34與樁24的內周面24B接合。然後,利用打擊工法將具有凸緣34的樁24打入地盤26至預定深度。此時,樁頭24A向地盤26的上方突出。Here, an example of the construction method of the pile foundation 32 of this embodiment is demonstrated. First, the flange 34 is joined to the inner peripheral surface 24B of the pile 24. Then, the pile 24 with the flange 34 is driven into the site 26 to a predetermined depth by using the striking method. At this time, the pile head 24A protrudes above the ground 26.

接著,對進入樁24內部的砂土整體進行地盤改良,以形成地盤改良體33。以此方式進行樁基礎10的施工。Next, ground improvement is performed on the entire sandy soil that has entered the pile 24 to form a ground improvement body 33. The construction of the pile foundation 10 is performed in this way.

(作用) 接下來,說明本實施形態的作用。(effect) Next, the function of this embodiment will be explained.

在本實施形態的樁基礎32中,藉由設置在樁24內整個區域的地盤改良體33,能夠提高樁24內部整體的剛性。此外,由於地盤改良體33是由凸緣34從上方支撐,能夠使樁24和地盤改良體33更緊貼地一體化。In the pile foundation 32 of this embodiment, the rigidity of the whole inside of the pile 24 can be improved by the ground improvement body 33 provided in the whole area of the pile 24. In addition, since the ground improvement body 33 is supported from above by the flange 34, the pile 24 and the ground improvement body 33 can be integrated more closely.

此外,在本實施形態中,由於凸緣34形成為環狀,因此,能夠利用所述凸緣34壓縮樁24內的砂土。此外,由於凸緣34的上下空間連通,因此,在打入樁24後,能夠將藥劑等投入砂土進行地盤改良。其他作用與第1實施形態相同。In addition, in this embodiment, since the flange 34 is formed in a ring shape, the sand and soil in the pile 24 can be compressed by the flange 34. In addition, since the upper and lower spaces of the flange 34 communicate, after the pile 24 is driven, a chemical or the like can be put into sand and soil to improve the ground. The other functions are the same as in the first embodiment.

<第3實施形態> 其次,參照圖5A及圖5B對第3實施形態之樁基礎40進行說明。值得一提的是,對於與第1實施形態相同的結構標註相同的符號,並適當省略說明。<The third embodiment> Next, the pile foundation 40 of the third embodiment will be described with reference to FIGS. 5A and 5B. It is worth mentioning that the same components as those in the first embodiment are given the same reference numerals, and descriptions are omitted as appropriate.

如圖5A所示,構成本實施形態之樁基礎40的樁24與第1實施形態相同。而且,除了樁頭24A之外,樁24的其他部分藉由打擊工法打入地盤26。As shown in FIG. 5A, the pile 24 which comprises the pile foundation 40 of this embodiment is the same as that of 1st Embodiment. Moreover, except for the pile head 24A, the other parts of the pile 24 are driven into the site 26 by the striking method.

此外,在樁24被打入地盤26的狀態下,樁24內設有地盤改良體28。地盤改良體28設置於樁24的內周面24B與砂土S之間。In addition, in a state where the pile 24 is driven into the ground 26, a ground improvement body 28 is provided in the pile 24. The ground improvement body 28 is provided between the inner peripheral surface 24B of the pile 24 and the sand S.

在此,在本實施形態中,在樁24的樁頭24A上設置有地板42,地板42包括基座42A以及三角板42B。Here, in this embodiment, a floor 42 is provided on the pile head 24A of the pile 24, and the floor 42 includes a base 42A and a triangular plate 42B.

基座42A以樁24的軸向(垂直方向)為厚度方向而形成,並設置在地盤26上。另外,如圖5B所示,基座42A在俯視時呈與樁24同心狀的大致圓形。並且,在本實施形態中,作為一例,基座42A由鋼材形成,固定在樁頭24A的周面上。作為將基座42A固定在樁頭24A上的方法,除了焊接以外,也可以採用利用螺栓及螺母等進行機械緊固的方法。The base 42A is formed with the axial direction (vertical direction) of the pile 24 as the thickness direction, and is installed on the ground 26. In addition, as shown in FIG. 5B, the base 42A has a substantially circular shape concentric with the pile 24 in a plan view. In addition, in this embodiment, as an example, the base 42A is formed of steel material and is fixed to the peripheral surface of the pile head 24A. As a method of fixing the base 42A to the pile head 24A, in addition to welding, a method of mechanically tightening with bolts, nuts, or the like may be used.

在基座42A的上表面側設有多個三角板42B。沿樁24的周向等間隔地設有8個三角板42B。此外,如圖5A所示,各個三角板42B以沿樁24的方向和沿基座42A的方向呈直線部分的方式形成為大致三角形狀。A plurality of triangular plates 42B are provided on the upper surface side of the base 42A. Eight triangular plates 42B are provided at equal intervals along the circumferential direction of the pile 24. In addition, as shown in FIG. 5A, each triangular plate 42B is formed in a substantially triangular shape so as to form a linear portion in the direction of the pile 24 and the direction of the base 42A.

三角板42B的下端面沿著基座42A沿樁24的徑向上延伸,固定於基座42A的上表面。此外,三角板42B的位於樁24的中心側的側面沿樁頭24A在垂直方向上延伸,固定在上述樁頭24A上。作為將上述三角板42B固定在基座42A及樁頭24A上的方法,與基座42A相同,除了焊接以外,也可以採用利用螺栓及螺母等機械緊固的方法。The lower end surface of the triangular plate 42B extends along the base 42A in the radial direction of the pile 24 and is fixed to the upper surface of the base 42A. In addition, the side surface of the triangular plate 42B located on the center side of the pile 24 extends in the vertical direction along the pile head 24A, and is fixed to the aforementioned pile head 24A. As a method of fixing the above-mentioned triangular plate 42B to the base 42A and the pile head 24A, it is the same as the base 42A. In addition to welding, a mechanical fastening method such as bolts and nuts may also be used.

如上所述,地板42設置在地盤26上,並固定於樁頭24A。因此,作用於樁24的外力經由地板42向地盤26傳遞。As described above, the floor 42 is provided on the ground 26 and fixed to the pile head 24A. Therefore, the external force acting on the pile 24 is transmitted to the ground 26 via the floor 42.

(作用) 接下來,說明本實施形態的作用。(effect) Next, the function of this embodiment will be explained.

在本實施形態的樁基礎40中,即使在樁24倒下的方向有外力輸入的情況下,也能夠經由地板42將此外力的至少一部分傳遞至地盤26,而能夠確保樁24對水平力之抵抗力。此外,可以藉由地板42來抑制海底表面的沖刷。其他作用與第1實施形態相同。In the pile foundation 40 of the present embodiment, even when an external force is input in the direction in which the pile 24 falls, at least a part of the external force can be transmitted to the ground 26 via the floor 42, and the horizontal force of the pile 24 can be ensured. resistance. In addition, the floor 42 can suppress the erosion of the seabed surface. The other functions are the same as in the first embodiment.

<第4實施形態> 其次,參照圖6A及圖6B對第4實施形態之樁基礎50進行說明。值得一提的是,對於與第2實施形態相同的結構標註相同的符號,並適當省略說明。<The fourth embodiment> Next, the pile foundation 50 of the fourth embodiment will be described with reference to FIGS. 6A and 6B. It is worth mentioning that the same reference numerals are given to the same structures as in the second embodiment, and the descriptions are appropriately omitted.

如圖6A所示,相對於第2實施形態的結構,在本實施形態的樁基礎50中,安裝了在第3實施形態中說明的地板42。具體而言,樁24的內部設有地盤改良體33,在從軸向觀察樁24的截面時,此地盤改良體33設置於樁24內的整個區域。As shown in FIG. 6A, with respect to the structure of the second embodiment, in the pile foundation 50 of this embodiment, the floor 42 described in the third embodiment is installed. Specifically, a ground improvement body 33 is provided inside the pile 24, and this ground improvement body 33 is provided in the entire area of the pile 24 when the cross section of the pile 24 is viewed from the axial direction.

此外,樁24的內周面24B設有凸緣34。凸緣34配置於樁頭24A附近,藉由焊接等方式與樁24的內周面24B接合。In addition, the inner peripheral surface 24B of the pile 24 is provided with a flange 34. The flange 34 is arranged near the pile head 24A, and is joined to the inner peripheral surface 24B of the pile 24 by welding or the like.

此外,在樁24的樁頭24A上設有地板42,構成地板42的基座42A及三角板42B固定於樁頭24A。In addition, a floor 42 is provided on the pile head 24A of the pile 24, and a base 42A and a triangular plate 42B constituting the floor 42 are fixed to the pile head 24A.

(作用) 接下來,說明本實施形態的作用。(effect) Next, the function of this embodiment will be explained.

在本實施形態的樁基礎50中,和第3實施形態相同,即使在樁24倒下的方向有外力輸入的情況下,也能夠經由地板42將此外力的至少一部分傳遞至地盤26,而能夠確保樁24對水平力之抵抗力。其他作用與第1實施形態相同。In the pile foundation 50 of the present embodiment, as in the third embodiment, even when an external force is input in the direction in which the pile 24 falls, at least a part of the external force can be transmitted to the ground 26 via the floor 42. Ensure the resistance of the pile 24 to horizontal forces. The other functions are the same as in the first embodiment.

<第5實施形態> 其次,參照圖7A及圖7B對第5實施形態之樁基礎60進行說明。值得一提的是,對於與第1實施形態相同的結構標註相同的符號,並適當省略說明。<The fifth embodiment> Next, the pile foundation 60 of the fifth embodiment will be described with reference to FIGS. 7A and 7B. It is worth mentioning that the same components as those in the first embodiment are given the same reference numerals, and descriptions are omitted as appropriate.

如圖7A所示,構成本實施形態的樁基礎70的樁24與第1實施形態相同。而且,除了樁頭24A之外,樁24的其他部分藉由打擊工法打入地盤26。As shown in FIG. 7A, the pile 24 which comprises the pile foundation 70 of this embodiment is the same as that of 1st Embodiment. Moreover, except for the pile head 24A, the other parts of the pile 24 are driven into the site 26 by the striking method.

在此,在樁24的內周面24B上設置有圓盤狀構件62,其作為從上方支撐砂土S的支撐構件的同時,將樁24的內部空間上下隔開。圓盤狀構件62配置於樁頭24A附近,圓盤狀構件62的周緣部藉由焊接等方式接合(固定)於樁24的內周面24B。Here, a disc-shaped member 62 is provided on the inner peripheral surface 24B of the pile 24 as a support member that supports the sand and soil S from above while partitioning the inner space of the pile 24 up and down. The disc-shaped member 62 is arranged near the pile head 24A, and the peripheral edge portion of the disc-shaped member 62 is joined (fixed) to the inner peripheral surface 24B of the pile 24 by welding or the like.

此外,在進入樁24內部的砂土S與圓盤狀構件62之間填充有填充材料64。作為填充材料64,例如可以使用砂漿、混凝土、纖維強化混凝土、石膏、水泥漿及纖維強化樹脂等。並且,藉由填充材料64使砂土S與圓盤狀構件62一體化。In addition, a filling material 64 is filled between the sand S entering the inside of the pile 24 and the disc-shaped member 62. As the filler 64, for example, mortar, concrete, fiber reinforced concrete, gypsum, cement slurry, fiber reinforced resin, etc. can be used. In addition, the sand S and the disc-shaped member 62 are integrated by the filler 64.

(作用) 接下來,說明本實施形態的作用。(effect) Next, the function of this embodiment will be explained.

在本實施形態的樁基礎60中,在樁頭24A附近的樁24的內周面24B設有圓盤狀構件62,而此圓盤狀構件62從上方支撐進入樁24內部的砂土S。藉由如此設置圓盤狀構件62,在將樁24打入地盤26時,能夠利用圓盤狀構件62壓縮樁24內的砂土S,能夠得到前端閉塞效果。In the pile foundation 60 of this embodiment, a disc-shaped member 62 is provided on the inner peripheral surface 24B of the pile 24 near the pile head 24A, and this disc-shaped member 62 supports the sand and soil S entering the pile 24 from above. By providing the disc-shaped member 62 in this way, when the pile 24 is driven into the ground 26, the sand and soil S in the pile 24 can be compressed by the disc-shaped member 62, and the front end blocking effect can be obtained.

尤其,在本實施形態中,由於能夠藉由圓盤狀構件62向樁24內的砂土S整體傳遞垂直力,因此,能夠增大樁24的支撐力。In particular, in this embodiment, since the disk-shaped member 62 can transmit the vertical force to the entire sand and soil S in the pile 24, the supporting force of the pile 24 can be increased.

此外,在本實施形態中,砂土S與圓盤狀構件62藉由填充材料64一體化。由此,與未設置填充材料64的結構相比,無需對樁24內的砂土S進行地盤改良,即能夠增大樁24的支撐力。In addition, in this embodiment, the sand S and the disc-shaped member 62 are integrated by the filler 64. Thereby, compared with the structure in which the filler 64 is not provided, it is not necessary to perform ground improvement on the sand and soil S in the pile 24, that is, the supporting force of the pile 24 can be increased.

以上,對第1至第5實施形態及變形例進行了說明,但在不脫離本公開之要旨的範圍內,當能以各種態樣實施。例如,也可以採用將上述實施形態分別組合的結構。即,也可以將圖4A及圖4B所示的第2實施形態的凸緣34固定在圖2A及圖2B所示的第1實施形態的樁基礎10上。另外,在第2實施形態的凸緣34和地盤改良體33之間,也可以設置圖7A所示的第5實施形態的填充材料64。The first to fifth embodiments and modification examples have been described above, but they can be implemented in various ways within the scope not departing from the gist of the present disclosure. For example, it is also possible to adopt a configuration in which the above-mentioned embodiments are combined separately. That is, the flange 34 of the second embodiment shown in FIGS. 4A and 4B may be fixed to the pile foundation 10 of the first embodiment shown in FIGS. 2A and 2B. In addition, between the flange 34 of the second embodiment and the floor improvement body 33, the filler 64 of the fifth embodiment shown in FIG. 7A may be provided.

另外,在上述第2實施形態及第4實施形態中,在樁24的內周面24B設置金屬製的凸緣34,但並不限定於此。例如,可設置混凝土製的凸緣。在此情況下,可在將樁24打入地盤26後灌注凸緣。此外,亦可在將水泥漿等的填充材料填充在凸緣與砂土或地盤改良體之間。In addition, in the second embodiment and the fourth embodiment described above, the metal flange 34 is provided on the inner peripheral surface 24B of the pile 24, but it is not limited to this. For example, a concrete flange can be provided. In this case, the flange can be poured after the pile 24 is driven into the ground 26. In addition, a filler such as cement slurry may be filled between the flange and the sand or the ground improvement.

此外,在上述實施形態中,樁24由鋼管形成,但樁24的材質並無特別限定,也可以由其他材質來形成樁。例如,可使用木造的木樁或混凝土造的混凝土樁。此外,也可以使用由這些材質組合而成的樁。In addition, in the above-described embodiment, the pile 24 is formed of a steel pipe, but the material of the pile 24 is not particularly limited, and the pile may be formed of other materials. For example, wood piles or concrete piles made of concrete can be used. In addition, piles formed by combining these materials can also be used.

再者,在上述實施形態中,是以用來支撐風力發電裝置12的腳部14的樁基礎作為塔狀構造物進行說明,但不限於此。即,可應用於支撐其他塔狀構造物的樁基礎,亦可應用於支撐鐵塔等的塔狀構造物的樁基礎。在此情況下,可將多個樁打入地盤以支撐鐵塔等的塔狀構造物。In addition, in the above-mentioned embodiment, the pile foundation for supporting the leg part 14 of the wind power generator 12 was demonstrated as a tower-shaped structure, but it is not limited to this. That is, it can be applied to pile foundations supporting other tower-shaped structures, and can also be applied to pile foundations supporting tower-shaped structures such as iron towers. In this case, multiple piles can be driven into the site to support tower-like structures such as iron towers.

此外,在上述第1實施形態中,如圖2所示,相對於進入樁24內部的砂土S,在軸向的整個區域形成地盤改良體28,但不限於此。例如,可採用圖8及圖9所示的結構。In addition, in the above-mentioned first embodiment, as shown in FIG. 2, the ground improvement body 28 is formed in the entire axial direction with respect to the sand and soil S entering the inside of the pile 24, but it is not limited to this. For example, the structure shown in FIG. 8 and FIG. 9 may be adopted.

如圖8A所示,在樁基礎70中,在樁24被打入地盤26的狀態下,樁24內設有地盤改良體28。在此,地盤改良體28僅形成於進入樁24內部的砂土S中的軸向的一部分砂土中。此外,如圖8B所示,地盤改良體28設置於樁24的內周面24B與砂土S之間。As shown in FIG. 8A, in the pile foundation 70, in a state where the pile 24 is driven into the ground 26, a ground improvement body 28 is provided in the pile 24. Here, the ground improvement body 28 is formed only in a part of the sand in the axial direction in the sand S entering the inside of the pile 24. Moreover, as shown in FIG. 8B, the ground improvement body 28 is provided between the inner peripheral surface 24B of the pile 24 and the sand soil S.

此外,在圖9A所示樁基礎80中,樁24內設有地盤改良體31,所述地盤改良體31僅形成於進入樁24內部的砂土S中的軸向的一部分砂土中。此外,如圖9B所示,在從軸向觀察樁24的截面時,地盤改良體31沿樁24的內周面24B間隔地設置於多處,在本變形例中,沿內周面24B間隔地在五處設置有地盤改良體31。In addition, in the pile foundation 80 shown in FIG. 9A, a ground improvement body 31 is provided in the pile 24, and the ground improvement body 31 is formed only in a part of the sand in the axial direction of the sand S entering the inside of the pile 24. In addition, as shown in FIG. 9B, when the cross-section of the pile 24 is viewed from the axial direction, the ground improvement bodies 31 are provided at a plurality of intervals along the inner peripheral surface 24B of the pile 24. In this modification, they are spaced apart along the inner peripheral surface 24B. Ground improvement bodies 31 are provided at five locations.

10:樁基礎 12:風力發電裝置 14:腳部(塔狀構造物) 24:樁 24A:樁頭 24B:內周面 26:地盤 28:地盤改良體 30:樁基礎 31:地盤改良體 32:樁基礎 33:地盤改良體 34:凸緣(支撐構件) 40:樁基礎 42:地板 50:樁基礎 60:樁基礎 62:圓盤狀構件(支撐構件) 64:填充材料 70:樁基礎 80:樁基礎 100:樁 102:樁 S:砂土10: pile foundation 12: Wind power plant 14: Feet (tower-shaped structure) 24: pile 24A: pile head 24B: inner peripheral surface 26: Site 28: Site Improvement 30: pile foundation 31: Site Improvement 32: pile foundation 33: Site Improvement 34: Flange (support member) 40: pile foundation 42: Floor 50: pile foundation 60: pile foundation 62: Disc-shaped member (support member) 64: filling material 70: pile foundation 80: pile foundation 100: pile 102: pile S: Sand

圖1係揭示應用第1實施形態之樁基礎的風力發電裝置的整體示意圖。 圖2A係第1實施形態之樁基礎的立面截面圖。 圖2B係揭示沿圖2A的2B-2B線切斷之狀態的截面圖。 圖3A係第1實施形態之變形例之樁基礎的立面截面圖。 圖3B係揭示沿圖3A的3B-3B線切斷之狀態的截面圖。 圖4A係第2實施形態之樁基礎的立面截面圖。 圖4B係揭示沿圖4A的4B-4B線切斷之狀態的截面圖。 圖5A係第3實施形態之樁基礎的立面截面圖。 圖5B係揭示沿圖5A的5B-5B線切斷之狀態的截面圖。 圖6A係第4實施形態之樁基礎的立面截面圖。 圖6B係揭示沿圖6A的6B-6B線切斷之狀態的截面圖。 圖7A係第5實施形態之樁基礎的立面截面圖。 圖7B係揭示沿圖7A的7B-7B線切斷之狀態的截面圖。 圖8A係第1實施形態之其他例之樁基礎的立面截面圖。 圖8B係揭示沿圖8A的8B-8B線切斷之狀態的截面圖。 圖9A係第1實施形態之其他例之樁基礎的立面截面圖。 圖9B係揭示沿圖9A的9B-9B線切斷之狀態的截面圖。 圖10A係揭示樁前端的壓力影響圈的示意圖,其中顯示小直徑樁的壓力影響圈。 圖10B係揭示樁前端的壓力影響圈的示意圖,其中顯示大直徑樁的壓力影響圈。Fig. 1 is an overall schematic diagram showing a wind power generation device applying the pile foundation of the first embodiment. Figure 2A is an elevational cross-sectional view of the pile foundation of the first embodiment. Fig. 2B is a cross-sectional view showing a state cut along the line 2B-2B of Fig. 2A. Fig. 3A is a vertical cross-sectional view of a pile foundation of a modification of the first embodiment. Fig. 3B is a cross-sectional view showing a state cut along the line 3B-3B of Fig. 3A. Fig. 4A is a vertical sectional view of the pile foundation of the second embodiment. Fig. 4B is a cross-sectional view showing a state cut along the line 4B-4B of Fig. 4A. Fig. 5A is an elevation sectional view of the pile foundation of the third embodiment. Fig. 5B is a cross-sectional view showing a state cut along the line 5B-5B of Fig. 5A. Fig. 6A is an elevation sectional view of the pile foundation of the fourth embodiment. Fig. 6B is a cross-sectional view showing a state cut along the line 6B-6B of Fig. 6A. Fig. 7A is a vertical sectional view of the pile foundation of the fifth embodiment. Fig. 7B is a cross-sectional view showing a state cut along the line 7B-7B of Fig. 7A. Fig. 8A is an elevation sectional view of a pile foundation of another example of the first embodiment. Fig. 8B is a cross-sectional view showing a state cut along the line 8B-8B of Fig. 8A. Fig. 9A is a vertical sectional view of a pile foundation of another example of the first embodiment. Fig. 9B is a cross-sectional view showing the state cut along the line 9B-9B of Fig. 9A. Figure 10A is a schematic diagram showing the pressure influence circle at the front end of the pile, which shows the pressure influence circle of the small diameter pile. Figure 10B is a schematic diagram showing the pressure influence circle at the front end of the pile, which shows the pressure influence circle of the large-diameter pile.

無。no.

10:樁基礎 10: pile foundation

24:樁 24: pile

24A:樁頭 24A: pile head

26:地盤 26: Site

28:地盤改良體 28: Site Improvement

Claims (13)

一種樁基礎,其具有: 樁,其沿垂直方向延伸以支撐塔狀構造物,並且所述樁的樁頭比地盤更向上方突出,而所述樁的下端開放;以及 地盤改良體,其在所述樁打入地盤的狀態下設置於所述樁內,並且所述地盤改良體的至少一部分與所述樁的內周面緊貼。A pile foundation having: A pile that extends in a vertical direction to support a tower-shaped structure, and the pile head of the pile protrudes upward than the ground, and the lower end of the pile is open; and A ground improvement body is provided in the pile in a state where the pile is driven into the ground, and at least a part of the ground improvement body is in close contact with the inner peripheral surface of the pile. 如請求項1所述之樁基礎,其中,所述樁內有砂土侵入,所述地盤改良體設置在所述樁的內周面與砂土之間。The pile foundation according to claim 1, wherein the pile has sand and soil intrusion, and the ground improvement body is provided between the inner peripheral surface of the pile and the sand. 如請求項2所述之樁基礎,其中,在從軸向觀察所述樁的截面時,所述地盤改良體沿著所述樁的內周面間隔地設置於多處。The pile foundation according to claim 2, wherein, when the cross section of the pile is viewed from the axial direction, the ground improvement body is provided at a plurality of places along the inner circumferential surface of the pile. 如請求項2或請求項3所述之樁基礎,其中,所述地盤改良體僅形成在進入所述樁內部的砂土中的軸向的一部分的砂土中。The pile foundation according to claim 2 or claim 3, wherein the ground improvement body is formed only in a part of the sand in the axial direction of the sand entering the pile. 如請求項1所述之樁基礎,其中,在從軸向觀察所述樁的截面時,所述地盤改良體設置於所述樁內的整個區域。The pile foundation according to claim 1, wherein, when the cross section of the pile is viewed from the axial direction, the ground improvement body is provided in the entire area within the pile. 如請求項1至請求項3之任一項所述之樁基礎,其中,在所述樁頭附近的所述樁的內周面上,設有從上方支撐所述地盤改良體的支撐構件。The pile foundation according to any one of claims 1 to 3, wherein a support member that supports the ground improvement from above is provided on the inner peripheral surface of the pile near the pile head. 一種樁基礎,其具有: 樁,其沿垂直方向延伸以支撐塔狀構造物,並且所述樁的樁頭比地盤更向上方突出,所述樁的下端開放;以及 支撐構件,其設置在所述樁頭附近的所述樁的內周面上,並從上方支撐進入所述樁的內部的至少一部分砂土。A pile foundation having: A pile that extends in the vertical direction to support a tower-like structure, and the pile head of the pile protrudes upward than the ground, and the lower end of the pile is open; and a support member that is provided near the pile head On the inner peripheral surface of the pile, at least a part of the sand which enters the inside of the pile is supported from above. 如請求項7所述之樁基礎,其中,所述支撐構件是從所述樁的內周面向徑向內側延伸的環狀凸緣。The pile foundation according to claim 7, wherein the supporting member is an annular flange extending radially inward from the inner circumferential surface of the pile. 如請求項7所述之樁基礎,其中,所述支撐構件是使所述樁頭的下端部閉塞的圓盤狀構件。The pile foundation according to claim 7, wherein the supporting member is a disc-shaped member that closes the lower end of the pile head. 如請求項7至請求項9之任一項所述之樁基礎,其中,在進入所述樁的內部的砂土和所述支撐構件之間填充有填充材料。The pile foundation according to any one of claim 7 to claim 9, wherein a filling material is filled between the sand and soil entering the inside of the pile and the supporting member. 如請求項1至請求項3之任一項所述之樁基礎,其中,地盤上設置有地板,所述地板固定在所述樁頭上,而使作用於所述樁上的力向地盤傳遞。The pile foundation according to any one of claim 1 to claim 3, wherein a floor is provided on the ground, and the floor is fixed on the pile head so that the force acting on the pile is transmitted to the ground. 如請求項1至請求項3之任一項所述之樁基礎,其中,所述塔狀構造物構成為風力發電裝置的腳部。The pile foundation according to any one of claims 1 to 3, wherein the tower structure is configured as a foot of a wind power generator. 一種樁基礎之施工方法,具有以下步驟: 將下端開放的樁打入地盤,使所述樁的樁頭向地盤上方突出;以及 在進入所述樁的內部的砂土中,至少對所述樁的內周面附近的砂土進行地盤改良。A construction method of pile foundation has the following steps: Drive a pile with an open lower end into the site so that the pile head of the pile protrudes above the site; and Among the sand that has entered the inside of the pile, at least the sand near the inner peripheral surface of the pile is ground improvement.
TW109112909A 2019-04-23 2020-04-17 Pile foundation and construction method of pile foundation TW202039969A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2019-082270 2019-04-23
JP2019082270A JP2020180436A (en) 2019-04-23 2019-04-23 Pile foundation and construction method of pile foundation

Publications (1)

Publication Number Publication Date
TW202039969A true TW202039969A (en) 2020-11-01

Family

ID=72942063

Family Applications (1)

Application Number Title Priority Date Filing Date
TW109112909A TW202039969A (en) 2019-04-23 2020-04-17 Pile foundation and construction method of pile foundation

Country Status (4)

Country Link
US (1) US20220205210A1 (en)
JP (1) JP2020180436A (en)
TW (1) TW202039969A (en)
WO (1) WO2020218093A1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11203400B1 (en) * 2021-06-17 2021-12-21 General Technologies Corp. Support system having shaped pile-anchor foundations and a method of forming same
GB2622415A (en) * 2022-09-15 2024-03-20 Equinor Energy As Pile structure for an offshore wind turbine and methods of installing the same

Family Cites Families (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3022634A (en) * 1960-06-22 1962-02-27 Raymond Int Inc Methods for driving pile shells at submerged locations
JPS58110716A (en) * 1981-12-24 1983-07-01 Enoki Toshio Burying method of pile
FR2610652B1 (en) * 1987-02-09 1991-09-06 Soletanche METHOD FOR REINFORCING A TUBULAR BATTERY PILE, PIE OBTAINED BY THIS PROCESS, DEVICE FOR IMPLEMENTING THE PROCESS
JPH0617579B2 (en) * 1987-09-18 1994-03-09 日本鋼管株式会社 Soil cement composite pile
KR940004906B1 (en) * 1987-10-05 1994-06-04 가와사끼세이떼쓰 가부시끼가이샤 Hollow steel pile, manufacturing method and pipe driving method
US5145284A (en) * 1990-02-23 1992-09-08 Exxon Production Research Company Method for increasing the end-bearing capacity of open-ended piles
GB9107672D0 (en) * 1991-04-11 1991-05-29 Roxbury Ltd Improvements in or relating to piles
US5951207A (en) * 1997-03-26 1999-09-14 Chevron U.S.A. Inc. Installation of a foundation pile in a subsurface soil
JPH1171754A (en) * 1997-08-28 1999-03-16 Nkk Corp Pile execution method and equipment therefor
JP3518308B2 (en) * 1998-01-27 2004-04-12 株式会社大林組 Basic structure of cylindrical tower structure
JP2001064958A (en) * 1999-08-26 2001-03-13 Toyo Constr Co Ltd Foundation constructing method
JP2001164582A (en) * 1999-12-06 2001-06-19 Takenaka Komuten Co Ltd Foundation construction for ultra-high tower and construction method therefor
JP4575061B2 (en) * 2004-07-23 2010-11-04 第一建設機工株式会社 Construction method for offshore wind power generation facilities
JP4664636B2 (en) * 2004-09-16 2011-04-06 株式会社竹中土木 Monopile foundation construction method
CN101778757B (en) * 2008-08-28 2013-06-12 三菱重工业株式会社 Construction method and construction rig of floating wind turbine generator
US9816246B2 (en) * 2010-01-19 2017-11-14 University Of Washington Through Its Center For Commercialization Pile with sound abatement for vibratory installations
JP5649755B1 (en) * 2014-06-13 2015-01-07 有限会社坂井家起こし Steel pipe pile structure
EP3178996B1 (en) * 2015-12-09 2018-02-14 innogy SE Pile for an offshore monopile foundation
JP6627906B2 (en) * 2017-03-31 2020-01-08 Jfeスチール株式会社 Reinforcement method of existing steel pipe pile foundation

Also Published As

Publication number Publication date
JP2020180436A (en) 2020-11-05
US20220205210A1 (en) 2022-06-30
WO2020218093A1 (en) 2020-10-29

Similar Documents

Publication Publication Date Title
US9068318B1 (en) Rotary drive tip system for installation of piles or other foundation members into the ground
AU2013214147B2 (en) Foundation structure of an offshore plant, in particular an offshore wind turbine, which foundation structure is to be installed at a low noise level, and installation method therefor
TWI807091B (en) Pile foundation and construction method of pile foundation
TW202039969A (en) Pile foundation and construction method of pile foundation
CA2682816A1 (en) Spiral steel pile
US20220195686A1 (en) Anchoring Element
TW202012747A (en) Plie foundation
JP3230883U (en) Combined single pile foundation structure for offshore wind power generation
JP5464510B2 (en) Submarine foundation for offshore structures and construction method thereof
EP3103924A1 (en) Monopile foundation for an offshore tower structure
KR101624897B1 (en) A foundation pile
JP5471381B2 (en) Filling reinforcement method
CN212294728U (en) Pile foundation structure is revolved to jacket
JP5962728B2 (en) Steel pipe pile
JP2004218215A (en) Foundation pile and tip shoe of foundation pile
KR200364617Y1 (en) Bearing power increase apparatus of plant file
JP2020066875A (en) Foundation pile, foundation structure, structural body, and installation method of foundation pile
JP3754419B2 (en) Steel pipe pile
KR20230139102A (en) Underground anchor pile for a solar panel and the construction structure
JPH0565714A (en) Steel tubular pile
JP2017155448A (en) Construction method of pile foundation
CN111364490A (en) High pile cap foundation based on driven and rotated piles and construction method thereof
JP2002105953A (en) Screwing steel pipe pile
CN104695473A (en) Tree-root-shaped electric tower pile cluster
CN110700251A (en) Spiral pile and construction method thereof