CN104695473A - Tree-root-shaped electric tower pile cluster - Google Patents
Tree-root-shaped electric tower pile cluster Download PDFInfo
- Publication number
- CN104695473A CN104695473A CN201310651189.6A CN201310651189A CN104695473A CN 104695473 A CN104695473 A CN 104695473A CN 201310651189 A CN201310651189 A CN 201310651189A CN 104695473 A CN104695473 A CN 104695473A
- Authority
- CN
- China
- Prior art keywords
- stake
- supporting
- supporting pile
- cluster
- tower
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 claims description 31
- 239000010959 steel Substances 0.000 claims description 31
- 239000004567 concrete Substances 0.000 claims description 23
- 239000011150 reinforced concrete Substances 0.000 abstract description 4
- 208000037656 Respiratory Sounds Diseases 0.000 description 9
- 230000003014 reinforcing effect Effects 0.000 description 7
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 6
- 230000000694 effects Effects 0.000 description 6
- 230000010349 pulsation Effects 0.000 description 6
- 238000010586 diagram Methods 0.000 description 5
- 238000010276 construction Methods 0.000 description 4
- 230000006835 compression Effects 0.000 description 3
- 238000007906 compression Methods 0.000 description 3
- 229910052742 iron Inorganic materials 0.000 description 3
- 238000009412 basement excavation Methods 0.000 description 2
- 230000006378 damage Effects 0.000 description 2
- 239000004575 stone Substances 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 230000002045 lasting effect Effects 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 238000010008 shearing Methods 0.000 description 1
- 239000000758 substrate Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Foundations (AREA)
Abstract
The invention discloses a tree-root-shaped electric tower pile cluster which comprises a bearing platform of an electric tower, a supporting pile cluster extends out from the bearing platform in the downward inclined direction or downward direction, the supporting pile cluster comprises supporting pile columns, the axis of each of the supporting pile columns is a curve, and each supporting pile column comprises a reinforced concrete column body and a rubber tube body. Due to the tree-root-shaped cluster structure, the comprehensive quantity of motion after the cluster is formed is very small although the quantity of motion of each supporting pile column is relatively large, the bearing platform is supported and tensioned in various directions, so that the bearing platform is still very stable under the action of turbulent wind, and no crack occurs.
Description
Technical field
The present invention relates to a kind of Reinforced Concrete Pole Tower stake clump of cast-in-site, be specifically related to a kind of tree root shape electric force pole tower stake clump.
Background technology
As the base configuration supporting steel tower king pile post, when supporting layer is relatively dark, as shown in Figure 1, squeeze into the relatively little pile body of multiple bore 50 in ground after, utilizing steel concrete to make the footing 51 connecting these pile body 50 tops, is (with reference to the following patent document 1 etc.) generally used by the mode that this footing 51 is connected with the king pile post 52 of steel tower.
Further, for the fixture construction of above-mentioned footing 51 and king pile post 52, roughly distinguish, there is the modes such as bolt fixed mode, anchor parts fixed form, base plate fixed form.Bolt fixed mode as shown in Figure 1, it is the mode utilizing many stone bolt 54 to be fixedly located at the substrate 53 on king pile post 52 bottom surface, above-mentioned anchor parts fixed form is as shown in Fig. 2 (A) ~ (C), by welding etc., installing plate 56 is fixedly installed on the bottom side face of the king pile post be embedded on footing 51, the fixed form that many places are set will be configured in around across paired angle steel 57 bolted joints of this installing plate about 56, above-mentioned base plate fixed form as shown in Figure 3, utilize the mode that the base plate 58 of the ring-type projecting outward in the bottom surface and/or outside that are embedded in the king pile post 52 in footing 51 etc. is fixed.On the other hand, the juncture at footing and stake top adopts mode as described below: as shown in Fig. 4 (A), utilizes the base plate juncture be fixed at base plates 59 such as the outside at the stake top in footing 51 of submerging ring-types projecting outward; Or as shown in Fig. 4 (B), the reinforcing bar juncture etc. that the many reinforcing bars 60 carrying out that traverse a top and footing 51 engage is set.
On the other hand, in order to the simplification of optimized integration structure, in following patent document 2, propose a kind of iron tower foundation structure, the rotation press-in steel pipe pile 70 lower end with the excavation blade larger than pile body diameter is along inclined direction pressed into and is arranged at the end, ground, the upper end rotating press-in steel pipe pile 70 is fastened on the bottom of steel tower foot 71 and forms, the rotation that along inclined direction arranges at the bottom of ground press-in steel pipe pile 70 and the steel tower foot 71 extended upward linearly.
Patent document: Unexamined Patent 9-3882 publication.
Patent document: JP 2003-166254 publication.
The patent that application number is 200580029551.X provides a kind of base configuration of steel tower, this patent is thought, in the basis of power supply steel tower, as shown in Figure 5, conduct oneself with dignity with steel tower, compared with impact that electric wire is conducted oneself with dignity, be subject to the impact of the wind loads such as the laying tension of electric wire, typhoon or monsoon more consumingly.Consequently, compared with the whole compression loads produced with other factors, turning torque becomes large, in the steel tower foot of therefore downwind side, effect has compression load, and in the steel tower foot of side of being in the wind effect have be about as much as compression load (pressing-in force) 70% drawing load (pulling capacity).Further, due to the couple that above-mentioned pressing-in force and pulling capacity produce, effect has moment of deflection, and effect has horizontal force.Therefore, at basis (footing) place in support iron column foot portion, as shown in Figure 6, if on the fixed part of king pile post 52 and footing 51, footing is excessively shallow, then can produce the shear fissure 61 of the taper centered by the base portion of king pile post 52, cause the destruction of fixed part.Further, as shown in Figure 7, at pile body 50 too when the outward flange of footing 51, the shear fissure 62 of isolating crackle shape may be produced from fixed part to outside, produce the destruction of fixed part.Further, when footing is crossed thin, as shown in the drawing, the problems such as the shear fissure 61 of the taper sometimes produced centered by pile body 50 are had.Therefore this patent proposes a kind of base configuration of steel tower; as shown in Figure 8, being be arranged at many piles body that bore is relatively little in base configuration form in ground, changing into as possibility by making the small-scale on basis; can the engineering time be shortened, reduce excavation amount, reduce concreting amount etc.In the base configuration of the steel tower that the many piles body 1 squeezed in ground is engaged by concrete body 3 with the king pile post 2 of steel tower, concrete body 3 is built by concrete 6 in the steel pipe 5 along the vertical direction at internal face with the shearing resistance flange 4 that multistage is fixedly installed along the circumferential direction and the structure made, the top of the many piles body 1 squeezed in described ground is engaged in the lower side of concrete body 3, and, multistage base plate 7 is provided with on outside the bottom of steel tower king pile post 2, the king pile post part (K) being provided with this base plate 7 is embedded in concrete body 3.
Occur the reason of crackle for power tower foundation cushion cap (this patent becomes concrete body), this patent thinks that, because pulling force causes, such explanation is not comprehensive.Because power tower is before construction, the load of its cushion cap is all through calculating, can resist maximum wind velocity.And the actual wind speed occurred is no greater than most value during design.In this case still there is crackle in cushion cap, just can not think it is only that the pulling force having wind speed to cause causes crackle.The reason of crackle is caused to be due to wind, namely the flowing of air.Because the fringe conditions of air flowing is complicated, wind is not Uniform Flow in fact, but with the flowing of sometimes fast and sometimes slow form, it is pulsation that concrete manifestation goes out wind speed.And record and the wind speed observed are moment wind speed or mean wind speed, only have Continuous Observation anemometer or watch the record of automatic anemobiagraph, could find that wind is all pulsation, this pulsation that yes under the consistent prerequisite of wind direction, the power be namely applied on electric wire and power tower is the pulsation that a lasting direction superposes within a period of time, its concrete manifestation form is the active force of power tower to basis is exactly except pulling force and pressure, has also superposed a vibration force.Because the cushion cap of design can both renitency and pulling force, if so cause the vibration force of advocating of cushion cap crackle, and this patent only address only the problem of pressure and pulling force, does not solve the problem of vibration force.
Pole and tower foundation generally adopts chassis, chuck, cable quadrant, i.e. " three dishes "." three dishes " forms with reinforced concrete prefabricated usually, and natural stone also can be adopted to make.Similar to power tower foundation, shaft tower, under the effect of pulsation wind-force, except under tension and pressure, also receives a vibration force.Because the pole and tower foundation of initial design can renitency and pulling force, if so cause pole and tower foundation to occur the vibration force of advocating of crackle.
Summary of the invention
To the active force of electric wire and shaft tower, shaft tower being shaken to occur the technical problem of crackle in order to solve fluctuating wind speed, the invention provides a kind of tree root shape electric power
shaft towerstake clump.
Technical scheme of the present invention is as follows:
A kind of tree root shape electric force pole tower stake clump, it comprises the cushion cap of electric force pole tower; Cushion cap stretches out supporting pile clump obliquely or downwards.Supporting pile clump is made up of multiple supporting stake, and the axis of supporting stake is curve, and every root supporting stake comprises steel concrete cylinder and the external rubber body of reinforced concrete post.The thick 10-20mm of rubber body, steel concrete cylinder diameter is 50-100mm.
The supporting pile clump of the plexi structure of this tree root, although the amount that each root supporting stake can move is larger, after Cheng Cong, integrated motion amount is very little, make cushion cap be subject to support and the tension in each direction, be still very firm under larger pulsation wind-force, there is no the appearance of crackle.
Accompanying drawing explanation
Fig. 1 represents the base configuration of existing steel tower, and (A) is longitdinal cross-section diagram, and (B) is view in transverse section;
Fig. 2 is the anchor parts fixed form representing king pile post 52, and (A) is footing longitdinal cross-section diagram, and (B) is the top view of anchor parts, and (C) is the lateral view of anchor parts;
Fig. 3 represents the base plate fixed form of king pile post 52, and (A) is longitdinal cross-section diagram, and (B) is view in transverse section;
Fig. 4 (A) is the figure of the base plate fixed form representing pile body 50, and (B) is the figure representing reinforcing bar fixed form;
Fig. 5 is the state diagram of wind load to the External Force Acting that iron tower foundation produces;
Fig. 6 is the figure of the failure mode (one) representing footing;
Fig. 7 is the figure of the failure mode (its two) representing footing;
Fig. 8 represents the base configuration of the steel tower of patent 200580029551.X first embodiment, and (A) is longitdinal cross-section diagram, and (B) is view in transverse section;
Fig. 9 is the structural representation of shaft tower tree root shape electric force pole tower stake clump;
Figure 10 is the structural representation of each supporting stake.
Figure 11 is the structural representation of supporting stake in construction.
Detailed description of the invention
A kind of tree root shape electric force pole tower stake clump, as shown in Figure 9, it comprises the cushion cap 105 of electric force pole tower; Cushion cap 105 stretches out supporting pile clump obliquely or downwards.Supporting pile clump is made up of multiple supporting stake 106.
The axis of supporting stake 106 is curves, and as shown in Figure 10, every root supporting stake 106 comprises the rubber body 102 outside steel concrete cylinder 101 and steel concrete cylinder 101.Rubber body 102 wall thickness 10-20mm, steel concrete cylinder 101 diameter is 50-100mm.
With reference to figure 9 and Figure 11, the construction method of tree root shape electric force pole tower stake clump of the present invention is:
1.. in electric force pole tower cushion cap foundation ditch, in earth 103, get multiple curved slot with poling orientation drill obliquely or downwards;
2. rubber body 102 is enclosed within reinforcing bar 103;
3.. rubber body 102 and reinforcing bar 103 are inserted each curved slot;
4.. concrete is filled with in the gap between rubber body 102 and reinforcing bar 103;
5.. after concrete setting, form supporting stake 106.
After concrete setting, reinforcing bar 103 and concrete form steel concrete cylinder 101 in rubber body 102.
Because steel concrete cylinder 101 overcoat has rubber body 102, during each supporting stake 106 of the vibration passing of power tower base institute wind-engaging, be laid to the supporting stake 106 of plexi structure, just as the root system of large tree, support from each direction and tension cushion cap 105, the mix of activities amount of cushion cap 105 is cancelled out each other, and firm quarters at ground, the appearance of Crack prevention.
Claims (3)
1. a tree root shape electric force pole tower stake clump, it comprises the cushion cap (105) of electric force pole tower; It is characterized in that: described cushion cap (105) stretches out supporting pile clump obliquely or downwards, supporting pile clump is made up of supporting stake (106).
2. tree root shape electric force pole tower stake clump as claimed in claim 1, it is characterized in that: the axis of described supporting stake (106) is curve, every root supporting stake (106) comprises steel concrete cylinder (101) and steel concrete cylinder (101) rubber body (102) outward.
3. tree root shape electric force pole tower stake clump as claimed in claim 2, is characterized in that: described rubber body (102) wall thickness 10-20mm; Described steel concrete cylinder (101) diameter is 50-100mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310651189.6A CN104695473A (en) | 2013-12-08 | 2013-12-08 | Tree-root-shaped electric tower pile cluster |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310651189.6A CN104695473A (en) | 2013-12-08 | 2013-12-08 | Tree-root-shaped electric tower pile cluster |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104695473A true CN104695473A (en) | 2015-06-10 |
Family
ID=53342988
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310651189.6A Pending CN104695473A (en) | 2013-12-08 | 2013-12-08 | Tree-root-shaped electric tower pile cluster |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104695473A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105201005A (en) * | 2015-10-16 | 2015-12-30 | 青岛新世纪太阳能科技有限公司 | Root pile |
-
2013
- 2013-12-08 CN CN201310651189.6A patent/CN104695473A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105201005A (en) * | 2015-10-16 | 2015-12-30 | 青岛新世纪太阳能科技有限公司 | Root pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204456167U (en) | Prestress anchoraging blower foundation | |
CN103114604B (en) | Prestressed concrete tubular type wind generating set foundation | |
CN203939288U (en) | Anti-wind net structure | |
CN203034464U (en) | Truss type foundation pit supporting structure | |
CN102162258B (en) | Concrete-filled steel tubular high-pile tower footing structure of tower crane and construction method thereof | |
CN105155572A (en) | Cast-in-place pre-stressed anchor cable draught fan foundation system and construction method thereof | |
CN110616733A (en) | Integral reinforcing device and method for foundation and component of power transmission tower | |
CN203625918U (en) | Anchor cable type wind driven generator base structure | |
CN204139197U (en) | Bottom enlarging prestress anchoring pile wind energy conversion system basis | |
CN105604086B (en) | Fan foundation structure | |
CN104963355A (en) | Classification anchoring type draught fan rock anchor rod assembly | |
CN201232193Y (en) | Wind motor tower foundation anchor pile structure on rock foundation | |
CN104110353B (en) | Antidumping blower foundation ring structure and construction method thereof | |
CN103015414A (en) | Precast concrete post grouting pile and grouting process | |
CN105569067A (en) | Foundation structure applicable to pre-stressed rock anchor rod fan base and construction method of foundation structure | |
CN202017214U (en) | Power pole tower base for frozen soil foundation | |
CN202247927U (en) | Barrel-shaped foundation with occlusive piles | |
CN104695468A (en) | Construction method of flat sphere-shaped electric power tower foundation | |
CN106592622A (en) | Annular concrete based wind-driven generator foundation structure with vertical prestress | |
CN104695473A (en) | Tree-root-shaped electric tower pile cluster | |
CN104695427A (en) | Construction method of bionic power tower | |
CN203361182U (en) | Unequal-length bottom-expanded rock anchor pile of power transmission pole tower | |
CN202989911U (en) | Post-grouting pile of precast concrete | |
CN104695428A (en) | Construction method of tree-root-shaped power pole tower pile cluster | |
CN104695467A (en) | Construction method of tree-root-shaped power pole tower pile cluster |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20150610 |