TH36630B - How to construct an elevated concrete floor using precast concrete slabs And the way to support temporarily elevated - Google Patents

How to construct an elevated concrete floor using precast concrete slabs And the way to support temporarily elevated

Info

Publication number
TH36630B
TH36630B TH101001388A TH0101001388A TH36630B TH 36630 B TH36630 B TH 36630B TH 101001388 A TH101001388 A TH 101001388A TH 0101001388 A TH0101001388 A TH 0101001388A TH 36630 B TH36630 B TH 36630B
Authority
TH
Thailand
Prior art keywords
reinforced concrete
support
elevated
aforementioned
concrete
Prior art date
Application number
TH101001388A
Other languages
Thai (th)
Other versions
TH49115A (en
Inventor
นาคาจิมา นายเคนอิจิ
อิชิดะ นายมิโนรุ
ทาเคอิ นายยูกิโอะ
Original Assignee
นางสาวปรับโยชน์ ศรีกิจจาภรณ์
นายจักรพรรดิ์ มงคลสิทธิ์
นายจักรพรรดิ์ มงคลสิทธิ์ นางสาวปรับโยชน์ ศรีกิจจาภรณ์ นายบุญมา เตชะวณิช นายต่อพงศ์ โทณะวณิก
นายต่อพงศ์ โทณะวณิก
นายบุญมา เตชะวณิช
Filing date
Publication date
Application filed by นางสาวปรับโยชน์ ศรีกิจจาภรณ์, นายจักรพรรดิ์ มงคลสิทธิ์, นายจักรพรรดิ์ มงคลสิทธิ์ นางสาวปรับโยชน์ ศรีกิจจาภรณ์ นายบุญมา เตชะวณิช นายต่อพงศ์ โทณะวณิก, นายต่อพงศ์ โทณะวณิก, นายบุญมา เตชะวณิช filed Critical นางสาวปรับโยชน์ ศรีกิจจาภรณ์
Publication of TH49115A publication Critical patent/TH49115A/en
Publication of TH36630B publication Critical patent/TH36630B/en

Links

Abstract

DC60 (18/03/56) วิธีการก่อสร้างพื้นคอนกรีตยกระดับ ซึ่งการก่อสร้างของโครงสร้างถาวรทั้งหมดบนชิ้นส่วน แนวดิ่งที่รองรับ ณ สถานที่ก่อสร้างสามารถถูกกระทำได้ทั้งหมดเหนือพื้นดินหรือเหนือพื้นชั้นล่าง โดยปราศจากการใช้ชิ้นส่วนค้ำยันหนึ่งใดถูกจัดให้มีขึ้นในการประดิษฐ์นี้ วิธีการก่อสร้างนี้ได้รับผล ด้วยการใช้ประโยชน์สี่ส่วนประกอบการประดิษฐ์ที่จัดให้มีขึ้นด้วยการประดิษฐ์นี้ สี่ส่วนประกอบ เหล่านี้ก็คือ วิถีทางรองรับยกระดับชั่วคราวที่มีชุดการก่อรูปรูเข้าถึงได้ แผ่นพื้นคอนกรีตเสริมแรงหล่อ สำเร็จ แบบหล่อช่องว่างเว้นระยะ และแบบผสมผสานของแท่งเสริมแรงพื้นคอนกรีต กระบวนการ ก่อสร้างรวมถึงการติดตั้งชิ้นส่วนแนวดิ่งรองรับ ซึ่งอาจจะเป็นเสาเข็มรองรับหรือเสารองรับ การติดตั้ง วิถีทางรองรับยกระดับชั่วคราว การติดตั้งแผ่นพื้นคอนกรีตเสริมแรงหล่อสำเร็จ การติดตั้งแบบหล่อ ช่องว่างเว้นระยะและการติดตั้งแบบผสมผสานของแท่งเสริมแรงพื้นคอนกรีต ตามด้วยการติดตั้งแบบ หล่อด้านข้าง การเทส่วนผสมคอนกรีตเหลว ช่วงเวลาการบ่มตัวของคอนกรีต และการถอดออก ส่วนประกอบที่ถอดออกได้ รวมทั้งการตบแต่งผิวหน้าพื้นคอนกรีตเพื่อทำให้การก่อสร้างสมบูรณ์ วิธีการก่อสร้างของการประดิษฐ์นี้ถูกพิสูจน์ให้เห็นว่า เป็นวิธีการที่ง่ายกว่ารวดเร็วกว่าคุณภาพดีกว่า และแพงน้อยกว่าวิธีการแบบสัญนิยมหนึ่งใดมันยังถูกพิสูจน์ให้เห็นอีกด้วยว่า สามารถใช้ประยุกต์ได้ กับสถานที่ซึ่งวิธีการแบบสัญนิยมที่มีอยู่ไม่สามารถประยุกต์ใช้ได้อย่างมีประสิทธิผล มีประสิทธิภาพ และอย่างประหยัด วิธีการก่อสร้างพื้นคอนกรีตยกระดับ ซึ่งการก่อสร้างของโครงสร้างถาวรทั้งหมดบนชิ้นส่วน แนวดิ่งที่รองรับ ณ สถานที่ก่อสร้างสามารถถูกกระทำได้ทั้งหมดเหนือพื้นดินหรือเหนือพื้นชั้นล่าง โดยปราศจากการใช้ชิ้นสวนค้ำยันหนึ่งใดถูกจัดให้มีขึ้นในการประดิษฐ์นี้ วิธีการก่อสร้างนี้ได้รับผล ด้วยการใช้ประโยชน์สี่ส่วนประกอบการประดิษฐ์ที่จัดให้มีขึ้นด้วยการประดิษฐ์นี้ สี่ส่วนประกอบ เหล่านี้ก็คือ เครื่องมือรองรับยกระดับชั่วคราวที่มีชุดจัดรูปแบบรูเข้าถึงได้ แผ่นพื้นคอนกรีตเสริมแรงหล่อ สำเร็จ แบบหล่อช่องว่างเว้นระยะ และแบบผสมผสานของแท่งเสริมแรงพื้นคอนกรีต กระบวนการ ก่อสร้างประกอบด้วย การติดตั้งชิ้นส่วนแนวดิ่งรองรับ ซึ่งอาจจะเป็นเสาเข็มรองรับหรือเสารองรับ การติดตั้ง วิถีทางรองรับยกระดับชั่วคราว การติดตั้งแผ่นพื้นคอนกรีตเสริมแรงหล่อสำเร็จ การติดตั้งแบบหล่อ ช่องว่างเว้นระยะและการติดตั้งแบบผสมผสานของแท่งเสริมแรงพื้นคอนกรีต ตามด้วยการติดตั้งแบบ หล่อด้านข้าง การเทส่วนผสมคอนกรีตเหลว ช่วงเวลาการบ่มตัวของคอนกรีต และการถอดออก ส่วนประกอบที่ถอดออกได้ รวมทั้งการตบแต่งผิวหน้าพื้นคอนกรีตเพื่อทำให้การก่อสร้างสมบูรณ์ วิธีการก่อสร้างของการประดิษฐ์นี้ถูกพิสูจน์ให้เห็นว่า เป็นวิธีการที่ง่ายกว่ารวดเร็วกว่าคุณภาพดีกว่า และแพงน้อยกว่าวิธีการแบบสัญนิยมหนึ่งใด มันยังถูกพิสูจน์ให้เห็นอีกด้วยว่า สามารถใช้ประยุกต์ได้ กับสถานที่ซึ่งวิธีการแบบสัญนิยมที่มีอยู่ไม่สามารถประยุกต์ใช้ได้อย่างมีประสิทธิผล มีประสิทธิภาพ และอย่างประหยัด DC60 (18/03/56) Construction method of elevated concrete floor. which the construction of all permanent structures on parts The vertical supports at the construction site can be performed entirely above the ground or above the ground floor. without the use of any supporting parts being provided in this invention. This method of construction was effective. By utilizing the four fabrication components provided by this invention four components these are Temporary elevation support paths with accessible hole formation kits. Precast reinforced concrete slabs, spaced gap formwork. and a combination of concrete slab reinforcing bars. The construction process includes the installation of vertical supports. which may be supporting piles or supporting columns Installation of precast reinforced concrete slabs formwork installation Spaced gaps and combined installation of concrete slab reinforcement rods This was followed by the installation of side formwork, pouring the liquid concrete mix. Concrete curing time and removal Detachable components including finishing the concrete surface to complete the construction The construction method of this invention is proven to be It's an easier, faster, better quality method. and less expensive than any conventional method, it has also been proven that can be applied to places where existing conventional methods cannot be effectively applied. effective and economically How to build an elevated concrete floor which the construction of all permanent structures on parts The vertical supports at the construction site can be performed entirely above the ground or above the ground floor. without the use of any one of the prop pieces being provided in this invention. This method of construction was effective. By utilizing the four fabrication components provided by this invention four components these are Temporary elevating support with accessible hole pattern kit. Precast reinforced concrete slabs, spaced gap formwork. and a combination of concrete slab reinforcement bars. The construction process consists of Installation of vertical support parts which may be supporting piles or supporting columns Installation of precast reinforced concrete slabs formwork installation Spaced gaps and combined installation of concrete slab reinforcement rods This was followed by the installation of side formwork, pouring the liquid concrete mix. Concrete curing time and removal Detachable components including finishing the concrete surface to complete the construction The construction method of this invention is proven to be It's an easier, faster, better quality method. and less expensive than any conventional method. It has also been proven that can be applied to places where existing conventional methods cannot be effectively applied. effective and economically

Claims (9)

ข้อถือสิทธฺ์ (ทั้งหมด) ซึ่งจะไม่ปรากฏบนหน้าประกาศโฆษณา : 1. วิธีการก่อสร้างสำหรับพื้นคอนกรีตเสริมแรงยกระดับซึ่งรวมถึงขั้นตอนของ การติดตั้งชิ้นส่วนแนวดิ่งรองรับบนพื้นดินหรือต่ำกว่า, การติดตั้งวิถีทางรองรับยกระดับชั่วคราวรอบส่วนหัวของชิ้นส่วนแนวดิ่งรองรับดังกล่าว, การติดตั้งแผ่นพื้นคอนกรีตเสริมแรงหล่อสำเร็จบนวิถีทางรองรับยกระดับชั่วคราวดังกล่าวที่ มีช่องว่างเว้นระยะที่กำหนดไว้ล่วงหน้า, การติดตั้งแบบหล่องช่องว่างเว้นระยะเพื่อปิดช่องว่างเว้นระยะระหว่างวิถีทางรองรับยกระดับ ชั่วคราวดังกล่าวและระหว่างแผ่นพื้นคอนกรีตเสริมแรงหล่อสำเร็จดังกล่าว, โดยตรงที่ขอบนอกของ วิถีทางรองรับยกระดับชั่วคราวดังกล่าวและที่ผิวหน้าด้านล่างสุดของแผ่นพื้นคอนกรีตเสริมแรงหล่อ สำเร็จดังกล่าว, เช่นเดียวกันกับการติดตั้งแบบหล่อด้านข้างโดยตรงที่ด้านที่เปิดของแผ่นพื้นคอนกรีต เสริมแรงหล่อสำเร็จดังกล่าว, การวางแนวแท่งเสริมแรงคอนกรีตรอบส่วนหัวของชิ้นส่วนแนวดิ่งรองรับดังกล่าว, ไปตาม ช่องว่างเว้นระยะที่กำหนดไว้ล่วงหน้าดังกล่าวระหว่างแผ่นพื้นคอนกรีตเสริมแรงหล่อสำเร็จดังกล่าว, ตลอดทั้งผิวหน้าบนสุดที่ถูกล้อมรอบโดยแบบหล่อด้านข้างดังกล่าว, และบนพื้นที่เหนือหัวของ ชิ้นส่วนแนวดิ่งรองรับดังกล่าว, การเทคอนกรีตเหนือแท่งเสริมแรงคอนกรีตดังกล่าว เพื่อก่อรูปแผ่นพื้นคอนกรีตเสริมแรง, และ การถอดออกซึ่งส่วนประกอบถอดออกได้ทั้งหมด, ซึ่งรวมถึงวิถีทางรองรับยกระดับชั่วคราว ดังกล่าว, หลังพื้นคอนกรีตเสริมแรงดังกล่าวได้บ่มหรือได้ความแข็งแรงพอเพียง; ซึ่งมีลักษณะเฉพาะที่ว่า ชิ้นส่วนแนวดิ่งรองรับดังกล่าว ถูกติดตั้งอย่างถาวรที่ตำแหน่งมุมของแผ่นพื้นคอนกรีต เสริมแรงหล่อสำเร็จดังกล่าว เพื่อว่ามุมที่อยู่ติดกันของแผ่นพื้นคอนกรีตเสริมแรงหล่อสำเร็จดังกล่าว สามารถถูกวางบนวิถีทางรองรับยกระดับชั่วคราวดังกล่าว ที่มีช่องว่างเว้นระยะที่กำหนดไว้ล่วงหน้า ดังกล่าว, และ แผ่นพื้นคอนกรีตเสริมแรงหล่อสำเร็จดังกล่าวจะรวมถึงแท่งยื่นเพื่อว่าเมื่อประกอบรวมเข้ากับ แท่งเสริมแรงคอนกรีตดังกล่าว ด้วยแผ่นพื้นคอนกรีตเสริมแรงหล่อสำเร็จดังกล่าวจะสามารถถูกใช้ ประโยชน์เป็นส่วนหนึ่งของโครงสร้างถาวรของพื้นคอนกรีตเสริมแรงยกระดับดังกล่าว, และ โครงสร้างถาวรดังกล่าว ของพื้นคอนกรีตเสริมแรงยกระดับดังกล่าวสามารถถ่ายโอนน้ำหนักทั้งหมด โดยตรงลงบนชิ้นสว่นแนวดิ่งรองรับดังกล่าวโดยไม่ใช้คานรองรับเพิ่มเติมใดๆ , หลังการถอดออกของ วิถีทางรองรับยกระดับชั่วคราวดังกล่าว 2. วิธีการก่อสร้างสำหรับพื้นคอนกรีตเสริมเเรงยกระดับตามข้อถือสิทธิข้อที่ 1 ซึ่งรวมต่อไป ถึงขั้นตอนของ การติดตั้งชุดการก่อรูปรูเข้าถึงได้บนวิถีทางรองรับยกระดับชั่วคราวดังกล่าว เพื่อก่อรูปรู เข้าถึงผ่านพื้นคอนกรีตเสริมเเรงดังกล่าว ซึ่งมีลักษณะเฉพาะที่ว่า ชุดการก่อรูปรูเข้าถึงได้ดังกล่าวที่ประกอบรวมเข้ากับวิถีทางรองรับยกระดับชั่วคราวดังกล่าว สามารถก่อรูปรูเข้าถึงจากผิวหน้าบนสุดขอวพื้นคอนกรีตเสริมเเรงดังกล่าวไปยังผิวหน้าด้านล่างสุด ของวิถีทางรองรับยกระดับชั่วคราวดังกล่าว เเละ การลดระดับของวิถีทางรองรับยกระดับชั่วคราวดังกล่าว ระหว่างกระบวนการถอดออก สามารถถูกกระทำอย่างสะดวกจากผิวหน้าบนสุดของพื้นคอนกรีตเสริมเเรงดังกล่าวผ่านรูเข้าถึง ดังกล่าว 3. วิธีการก่อสร้างสำหรับพื้นคอยนกรีตเสริมเเรงยกระดับตามข้อถือสิทธิข้อที่ 2 โดยที่เเต่ละ อันของชิ้นส่วนเเนวดิ่งรองรับดังกล่าวคือเสาเข็มรองรับที่มีรูปร่างภาคตัดขวางเป็นวงเเหวนที่ถูก ขับเคลื่อนในเเนวดิ่งลงไปในพื้นดิน เเละถูกตัดออกหรือถูกตั้งที่ระดับเเนวนอนที่กำหนดให้เหนือ พื้นดิน 4. วิธีการก่อสร้างสำหรับพื้นคอนกรีตเสริมเเรงยกระดับตามข้อถือสิทธิข้อที่ 3 โดยที่เเต่ละ อันของวิถีทางรองรับยกระดับชั่วคราวดังกล่าวรวมถึง ปลอกสวมรองรับถอดออกได้ที่มีรูเข้าถึงปลอกสวมใได้ที่ถูกติดตั้งที่ตำเเหน่งที่กำหนดให้รอบ ส่วนหัวของเสาเข็มรองรับดังกล่าว เเท่นรองรับถอดออกได้ที่มีรูเข้าถึงเเท่นรองรับได้ ประกอบอยู่รอบส่วนหัวของเสาเข็มรองรับ ดังกล่าวเเละนั่งบนด้านบนของปลอกสวมรองรับถอดออกได้ดังกล่าว เเละ ชุดเเขวนเเท่นรองรับที่เเขวนอยู่บนส่วนบนสุดของเสาเข็มรองรับดังกล่าวเเละจับยึดปลอก สวมรองรับถอดออกได้ดังกล่าว เเละเเท่นรองรับถอดออกได้ดังกล่าวผ่านรูเข้าถึงปลอกสวมได้ ดังกล่าวเเละรูเข้าถึงเเท่นรองรับได้ดังกล่าว 5. วิธีการก่อสร้างสำหรับพื้นคอนกรีตเสริมเเรงระดับตามข้อถือสิทธิข้อที่ 4 โดยที่ปลอก สวมรองรับถอดออกได้ดังกล่าว ประกอบรวด้วยสองชิ้นภาคตัดขวางรูปครึ่งวงเเหวนซึ่งประกอบ รวมเข้าเป็นปลอกสวมภาคตัดขวางรูปวงเเหวนโดยอาศัยสลักเกลียวเเละเเป้นเกลียวที่มีจำนวนหนึ่ง ของรูเข้าถึงปลอกสวมได้ ที่มีเส้นผ่าศูนย์กลางภายในเหมือนกันอย่างเป็นสำคัญกับของ เส้นผ่าศูนย์กลางภายนอกของเสาเข็มรองรับดังกล่าว เเละที่มีความกว้างที่เหมาะสมเพื่อว่า เมื่อ ประกอบรวมเข้ากับเเถบยางผิวยืดดังกล่าว ซึ่งประกอบในระหว่างผิวหน้าด้านในของปลอกสวมรองรับ ถอดออกได้ดังกล่าวเเละผิวหน้าด้านนอกของเสาเข็มรองรับดังกล่าว ปลอกสวมรองรับถอดออกได้ ดังกล่าวสามารถถูกติดตั้งอย่างเเน่นรอบเสาเข็มรองรับดังกล่าว เพื่อรองรับเเท่นรองรับถอดออกได้ ดังกล่าวด้วยปัจจัยความปลอดภัยที่เหมาะสม 6. วิธีการก่อสร้างสำหรับพื้นคอนกรีตเสริมเเรงยกระดับตามข้อถือสิทธิข้อที่ 5 โดยทีเเท่น รองรับถอดออกได้ดังกล่าวประกอบรวมด้วย สองชิ้นภาคตัดขวางรูปครึ่งวงเเหวนซึ่งประกอบรวมเข้า เป็นเเท่นรองรับภาคตัดขวางรูปวงเเหวนโดยอาศัยสลักเกลียวเเป้นเกลียวที่มีจำนวนหนึ่งของรู เข้าถึงเเท่นรองรับได้ที่สอดคล้องกับจำนวนหนึ่งของรูเข้าถึงปลอกสวมได้ เเละที่มีเส้นผ่าศูนย์กลาง ภายในใหญ่กว่าเส้นผ่าศูนย์กลางภายนอกของเสาเข็มรองรับดังกล่าวเล็กน้อยเพื่อประกอบพอดีรอบ เสาเข็มรองรับดังกล่าวอย่างสะดวก ที่มีเส้นผ่าศูนย์กลางภายนอกใหญ่พอเพียงสำหรับเเผ่นพื้น คอนกรีตเสริมเเรงหล่อสำเร็จดังกล่าวที่จะถูกวางบนนั้นอย่างเหมาะสม ที่มีจำนวนหนึ่งของรูรองรับ โดยรอบขอบนอกของมันเพื่อรองรับเเบบหล่อช่องว่างเว้นระยะดังกล่าว ที่มีบ่าต่ำกว่ารูปวงเเหวน รอบขอบในของมันที่รูเข้าถึงเเท่นรองรับได้ดังกล่าวตั้งอยู่ เเละที่จะถูกตั้งให้ต่ำกว่าส่วนบ่าบนสุดของ เสาเข็มรองรับดังกล่าวเพื่อที่จะก่อรูปส่วนหนึ่งของพื้นคอนกรีตเสริมเเรงดังกล่าวรอบส่วนหัวของ เสาเข็มรองรับดังกล่าวเพื่อคงเสาเข็มรองรับดังกล่าวให้อยู่กับที่อย่างมั่นคง 7. วิธีการก่อสร้างสำหรับพื้นคอนกรีตเสริมเเรงยกระดับตามข้อถือสิทธิข้อที่ 6 โดยที่ชุด เเขวนเเท่นรองรับดังกล่าวประกอบรวมด้วย กรอบเเขวนที่มีจำนวนหนึ่งของเเป้นเกลียวเเขวนเเละ จำนวนหนึ่งของสลักเกลียวเเขวนถอดออกได้ที่ทั้งคู่สอดคล้องกับจำนวนหนึ่งของรูเข้าถึงเเท่นรองรับ ได้ดังกล่าว ที่กรอบเเขวนดังกล่าวถูกวางอยู่บนนั้นเเละปิดครอบส่วนบนสุดของเสาเข็มรองรับ ดังกล่าวเเละสลักเกลียวเเขวนถอดออกได้ดังกล่าว ถูกขันสลักเกลียวเข้าสู่เเป้นเกลียวเเขวนดังกล่าว จากส่วนล่างสุดของปลอกสวมรองรับดังกล่าวผ่านรูเข้าถึงปลอกสวมได้ดังกล่าวเเละรูเข้าถึงเเท่น รองรับได้ดังกล่าวเพื่อยึดเเท่นรองรับถอดออกได้ดังกล่าว ให้อยู่กับที่เเละเเขวนปลอกสวมรองรับถอด ออกได้ดังกล่าวเเละเเท่นรองรับถอดออกได้ดังกล่าวบนส่วนบนสุดของเสาเข็มรองรับดังกล่าวเพื่อ ที่ว่าน้ำหนักชั่วคราวเเละถาวระซึ่งเกิดขึ้นระหว่างการก่อสร้างจะต้องถูกรองรับบนส่วนบนสุดของ เสาเข็มรองรับดังกล่าว 8. วิธีการก่อสร้างสำหรับพื้นคอนกรีตเสริมเเรงยกระดับตามข้อใดข้อหนึ่งของข้อถือสิทธิข้อ ที่ 1 ถึงข้อถือสิทธิข้อที่ 7 โดยที่เเต่ละอันของเเผ่นพื้นคอนกรีตเสริมเเรงหล่อสำเร็จดังกล่าว จะมีรูปร่าง เป็นรูปสามเหลี่ยมหรือสี่เหลี่ยมด้านขนานที่มีมุมตัดออก ซึ่งประกอบรวมด้วย จำนวนหนึ่งของเเท่นเสริมเเรงรูปตัว U กลับหัวยื่นออกที่ตั้งขึ้นจากผิวหน้าบนสุดของเเต่ละ อันของเเผ่นพื้นคอนกรีตเสริมเเรงหล่อสำเร็จดังกล่าว จำนนหนึ่งของเเท่งเสริมเเรงรูปตัว L ยื่นออกซึ่งยื่นออกไปตามด้านหนึ่งของเเต่ละอันของ เเผ่นพื้นคอนกรีตเสริมเเรงหล่อสำเร็จดังกล่าว เเละ จำนนวนหนึ่งของเเท่งสมอที่มีเเป้นเกลียวบนผิวหน้าด้านสุดใกล้ด้านหนึ่งของเเต่ละอัน ของเเผ่นพื้นคอนกรีตเสริมเเรงหล่อสำเร็จดังกล่าว 9. วิธีการก่อสร้างสำหรับพื้นคอนกรีตเสริมเเรงยกระดับตามข้อถือสิทธิข้อที่ 8 โดยที่เเต่ละ อันของเเบบหล่อช่วงว่างเว้นระยะดังกล่าว ประกอบรวมด้วยอย่างน้อยที่สุด สองชิ้นที่เหมือนกัยทุกประการของเเบบหล่อประกอบพอดีด้านข้างเเท่นรองรับเเต่ละอันที่มี จำนวนหนึ่งของเเท่งประกอบพอดีสำหรับประกอบพอดีเข้าไปในรูรองรับดังกล่าว รอบขอบนอกของ เเท่นรองรับถอดออกได้ดังกล่าวเพื่อปิดเเต่ละบริเวณด้านข้างเเท่นรองรับของช่องว่างเว้นระยะ ดังกล่าว ชิ้นเดียวของเเบบหล่อปิดบริเวณส่วนกลางสำหรับการปิดบริเวณที่เหลืออย่ของเเต่ละอันของ ช่องว่างเว้นระยะดังกล่าว เเละ สองชชิ้นของท่อรองรับที่มีสลักเกลียวเพื่อรองรับเเผ่นปิดบริเวณส่วนกลางดังกล่าว เช่นเดียวกันกับเเบบหล่อประกอบพอดีด้านข้างเเท่นรองรับดังกล่าว ด้วยวิถีการขันเเน่นสลักเกลียว ดังกล่าวเข้าไปในเเท่งสมอดังกล่าวที่มีเเป้นเกลียวบนผิวหน้าด้านล่างสุดใกล้ด้านหนึ่งของเเผ่นพื้น คอนกรีตเสริมเเรงหล่อสำเร็จดังกล่าว 1 0. วิธีการก่อสร้างสำหรับพื้นคอนกรีตเสริมเเรงยกระดับตามข้อถือสิทธิข้อที่ 8 หรือข้อถือ สิทธิข้อที่ 9 โดยที่เเท่งเสริมเเรงคอนกรีตดังกล่าวประกอบรวมด้วย จำนวนหนึ่งของเเท่งเสริมเเรงคล้ายกรงเเต่ละอันที่มีเเผ่นวงกลมที่ปลายด้านล่างสุดซึ่งอุด ภายในเเกนกลวงเเละครอบรอบส่วนหัวของเสาเข็มรองรับดังกล่าว ภายในบ่าต่ำกว่ารูปวงเเหวน ดังกล่าวของเเท่นรองรับถอดออกได้ดังกล่าวเพื่อจำกัดปริมาณของคอนกรีตดังกล่าวภายในเเกนกลาง ดังกล่าวเเละเพื่อคงส่วนหัวของเสาเข็มรองรับดังกล่าวให้อยู่กับที่อย่างมั่นคง จำนวนหนึ่งของเเท่งเสริมเเรงที่ถูกวางเหนือเเท่งเสริมเเรงรูปตัว L ยื่นออกดังกล่าวของเเผ่น พื้นคอนกรีตเสริมเเรงหล่อสำเร็จดังกล่าวไปตามช่องว่างเว้นระยะที่กำหนดไว้ล่วงหน้าดังกล่าว ระหว่างเเผ่นพื้นคอนกรีตเสริมเเรงหล่อสำเร็จดังกล่าวเเละคร่อมส่วนหัวของเสาเข็มรองรับจำนวน หนึ่งดังกล่าวเพื่อก่อรูปโครงสร้างคล้ายคานไปตามเเนวเส้นตรงซึ่งเชื่อมต่อส่วนหัวของเสาเข็มรองรับ จำนวนหนึ่งดังกล่าว จำนวนหนึ่งของเเท่งเสริมเเรงที่ถูกวางเหนือเเท่งเสริมเเรงรูตัว U กลับหัวยื่นออกดังกล่าว ของเเผ่นพื้นคอนกรีตเสริมเเรงหล่อสเร็จดังกล่าวตลอดทั้งพื้นระนาบของเเบบหล่อประกอบ (composite formwork) ซึ่งครอบเเท่นรองรับถอดออกได้จำนวนหนึ่งดังกล่าว เเผ่นพื้นคอนกรีต เสริมเเรงหล่อสำเร็จดังกล่าวเเละเเบบหล่อช่วงว่างเว้นระยะดังกล่าว เพื่อก่อรูปโครงสร้างคล้ายพื้น ระนาบบนพื้นระนาบดังกล่าวของเเบบหล่อประกอบ เเละ จำนวนหนึ่งของเเท่งเสริมเเรงเพิ่มเติมที่เพิ่มให้กับโครงสร้างคล้ายพื้ระนาบดังกล่าว เพื่อก่อ รูปโครงสร้างคล้ายหมวกครอบบนพื้นที่เหนือส่วนหัวของเสาเข็มรองรับจำนวนหนึ่งดังกล่าว 1Disclaimers (all) that will not appear on the advertisement page: 1. Construction methods for elevated reinforced concrete floors, including the steps of Installation of the support vertical part on the ground or below, installation of the temporary elevated support path around the head of the support vertical part, installation of the precast reinforced concrete slab on the support path. Such temporary elevation at There is a predefined gap spacing, installation of a spacing gap formwork to close the gap between the elevated support paths. And between such precast reinforced concrete slabs, directly at the outer edge of Such temporary elevation supports and at the bottom face of the cast reinforced concrete slabs. Such a finish, as well as the installation of side formwork directly on the open side of the slab. To reinforce the precast, the concrete reinforcement rod is aligned around the head of the vertical support, along the pre-defined gap between the precast reinforced concrete slabs, throughout. The top surface is surrounded by the aforementioned lateral formwork, and on the area above the head of the The vertical support, pouring concrete over the concrete reinforcement bar. To form reinforced concrete slabs, and the removal of all removable components, including such temporary elevated supports, after such reinforced concrete floors cured or obtained sufficient strength; Which has the characteristics that Vertical parts support such Being permanently installed at the corner location of the concrete slab Reinforcing such a successful casting So that the adjacent corners of the precast reinforced concrete slabs are Can be placed on such temporary elevated support path The pre-determined distance gaps, and the precast reinforced concrete slabs will include protrusions so that when assembled with Such concrete reinforcement rods With such precast reinforced concrete slabs can be used. Useful as part of the permanent structure of such elevated reinforced concrete floors, and such permanent structures. Of the reinforced concrete floor.Such elevations are able to transfer the entire weight Directly onto such vertical support parts without using any additional support beams, after removal of the 2. Construction method for elevated reinforced concrete floor according to claim No. 1, which includes the steps of Installation of the accessible hole formation on the above temporary elevated support path. To form a hole Access through the above reinforced concrete floor Which has the characteristics that The aforementioned accessible hole formation, which is integrated into the aforementioned temporary elevated support path. Able to form holes from the top surface of the reinforced concrete floor to the bottom surface. Of such temporary elevated support pathways and reduction of such temporary elevated support pathways During the removal process It can be conveniently operated from the top surface of the reinforced concrete floor through the aforementioned access holes. 3. Construction methods for reinforced concrete floors are elevated according to claim No. 2, where each One of the aforementioned supporting parts is a support pile with a recursive cross-sectional shape. Driven in the ground They were cut off or set at the level specified above the ground. 4. Construction methods for elevated reinforced concrete floors in accordance with claim No. 3, where each of each of the elevated supporting paths. Such provisional levels include Removable cover with holes to access the collars installed at the allotted position around. The head of such support piles Removable supports with holes accessible to support Assembled around the head of the supporting piles They are seated on top of the said detachable support sleeves and a set of supports that are circled on the top of the support piles and clamped to the casing. Wearing such removable supports And the removable supports are through holes accessible to the sleeve. 5. Construction methods for reinforced concrete floors in accordance with claim No. 4, where the sleeves can be removed as mentioned. Consists of two halves of a recursive cross-section, which comprise It is incorporated into a reticular cross-section sleeve using a number of bolts and threads. Of hole to access the sleeve Whose internal diameter is the same as that of Outside diameter of such support piles And at the appropriate width so that when assembled with the rubber band Which is assembled during the inner surface of the sleeve These are detachable and the outer surface of the supporting piles. Removable support collar They can be installed firmly around the support piles. To support removable supports 6. The construction method for the reinforced concrete floor is elevated in accordance with claim No. 5, where the aforementioned removable supports are included. Two halves of a reverted cross-section, assembled into It is a support for the loop-shaped cross-section by using a threaded bolt with a certain number of holes. Accessibility support that corresponds to a certain number of holes for access to the sleeve And the diameter The inside is slightly larger than the outside diameter of the aforementioned support piles to fit around. Such support piles are convenient. With a large outside diameter just enough for the floor Such precast reinforced concrete will be properly placed on it. With a certain number of support holes Surrounding the perimeter of it to support the casting of the gap, ignoring the distance. With the shoulders below the reverted loop Around its inner perimeter where the aforementioned support holes are located. And to be set lower than the top of the shoulder The pile supports to form part of the reinforced concrete floor around the head of the Such support piles are used to maintain the aforementioned supporting piles in place. 7. Construction methods for elevated reinforced concrete floors in accordance with claim No. 6, whereby the aforementioned supporting piles are included. with A spiral frame containing a certain number of threads and A certain number of detachable bolts, both of which correspond to a certain number of such support holes, are placed on such a frame, and cover the top of the support piles. The said bolts and the removable part. It was screwed into the thread. From the bottom of the sleeve through the holes for access to the sleeve and through the holes for you to Such supports can be attached to the above removable supports. To stay in place and take off the support sleeve Such detachable supports on the top of the piles to It is said that the temporary and heavy weights that arise during construction must be supported on the top of the 8. Construction method for the reinforced concrete floor to be elevated according to any of the Clause 1 to Clause 7, where each piece of reinforced concrete floor Such precast formations have the shape of a triangle or a parallelogram with angles cut out. Which includes A number of upside-down U-shaped reinforcements stand up from the top surface of each individual. Of the precast reinforced concrete floor One surrender of an L-shaped extension rod protruding along one side of each of the These finished cast reinforced concrete slabs and a small number of anchor rods with threads on the front end near one side of each. 9. The construction method for the reinforced concrete slab to be upgraded according to claim No. 8, where each part of the concrete foundry during such period Including at least Two identical pieces of cast iron fit each side, but each one has A certain number of ribs to fit into the aforementioned support holes around the perimeter of the aforementioned removable supports to cover each side area to support the gap. The moldings cover the central area for covering the remaining areas of each one. The gap ignores the aforementioned and two pieces of support tube with bolts to support the center cover. The same is true for the casting of the lateral assembly and supports it. With the way of tightening the bolts It goes into the anchors with a thread on the bottom surface near one side of the floor. Precast reinforced concrete 1 0. Construction methods for elevated reinforced concrete floors in accordance with Clause 8 or Clause 9, whereby the said reinforced concrete reinforcement is included. A number of cage-like reinforcements, each with a circle at the bottom end that fill. Within the Nok Luan, the drama is baked around the head of the piles. The inside of the shoulder is lower than the reverted loop. As mentioned above, the aforementioned removable supports to limit the amount of such concrete within the center. And to maintain the head of the support pile in place A certain number of pillars are placed over the aforementioned L-shaped reinforcement of the wall. The precast reinforced concrete floor follows the predetermined gap. During the process of the precast reinforced concrete slab and straddled the head of the supporting piles. One of them to form a beam-like structure along a straight line connecting the head of the support pile. A number of such A certain number of support towers are placed above the upside-down U-hole reinforcement. Of such precast reinforced concrete slabs throughout the plane of the composite formwork covering a number of such removable supports. Floor concrete Supplementing such successful casting and casting during the vacancy period To form a floor-like structure The above planes of the foundry consist of a number of additional support plates added to such planar structures to form a hood-like structure on the area above the head of a number of supporting piles. Such 1 1. วิธีการก่อสร้างสำหรับพื้นคอนกรีตเสริมเเรงยกระดับตามข้อใดข้อหนึ่งของข้อถือสิทธิ ข้อที่ 7 ถึงข้อถือสิทธิข้อที่ 10 โดยที่เเต่ละอันของชุดการก่อรูปรูเข้าถึงได้ดังกล่าวประกอบรวมด้วย จำนวนหนึ่งของท่อบางก่อรูปรูเข้าถึงคอนกรีตได้ที่สอดคล้องกับจำนวนหนึ่งของสลัก เกลียวเเขวนถอดออกได้ดังกล่าว ที่ประกอบพอดีในเเนวดิ่งรอบปลายที่โผล่ออกของสลักเกลียวเเขวน ถอดออกได้ดังกล่าวเเละยืนอยู่บนเเป้นเกลียวเเขวนดังกล่าว ที่มีปลายบนสุดกำหนดไว้สูงกว่าระดับที่ กำหนดไว้ล่วงหน้าของพื้นคอนกรีตเสริมเเรงดังกล่าว เเละ จำนวนหนึ่งของเเท่งสอดใส่ถอดออกได้ที่สอดคล้องกับจำนวนหนึ่งของท่อบางก่อรูปรู เข้าถึงคอนกรีตได้ดังกล่าว ที่ถูกสอดเข้าสู่ท่อบางการก่อรูปรูเข้าถึงคอนกรีตได้ดังกล่าว 11. Construction methods for reinforced concrete floors to be elevated in accordance with any one of Clause 7 to Clause 10, where each of the aforementioned accessible hole formation set includes: with A certain number of thin pipes form concrete access holes that correspond to a certain number of bolts. The screw thread is removable. That fit in a plunger around the protruding end of the screw bolt Removed it and stood on the thread. With the top end set higher than the level A predetermined number of such reinforced concrete slabs and a certain number of removable inserts corresponding to a certain number of holes form holes. Access to such concrete That is inserted into some pipes, forming a hole to access the concrete as such 1 2. วิธีการก่อสร้างสำหรับพื้นคอนกรีตเสริมเเรงยกระดับตามข้อถือสิทธิข้อที่ 11 โดยที่การ เทของการคอนกรีตดังกล่าวเพื่อก่อรูปพื้นคอนกรีตเสริมเเรงเหนือเเท่งเสริมเเรงคอนกรีตดังกล่าว ที่ถูก ติดตั้งบนพื้นระนาบดังกล่าว ของเเบบหล่อประกอบจะถูกทำให้สูงระดับทีกำหนดไว้ล่วงหน้าของ พื้นคอนกรีตเสริมเเรงดังกล่าว ซึ่งจะต่ำกว่าปลายบนสุดของท่อบางก่อรูปรูเข้าถึงคอนกรีตได้ ดังกล่าวของชุดการก่อรูปรูเข้าถึงได้ดังกล่าว 12. Construction method for elevated reinforced concrete floor in accordance with claim No. 11, where the pouring of the said concrete to form the reinforced concrete floor above the said reinforcement site. On the ground such a plane The assembled castings are made to a predetermined level of Reinforced concrete floor Which is lower than the top end of some pipes, forming holes accessible to concrete As mentioned of the aforementioned hole formation set 1. 3. วิธีการก่อสร้างสำหรับพื้นคอนกรีตเสริมเเรงยกระดับตามข้อถือสิทธิข้อที่ 12 โดยที่สลัก เกลียวเเขวนถอดออกได้ดังกล่าว ของชุดเเขวนเเท่นรองรับดังกล่าวเเละเเท่งสอดใส่ถอดออกได้ ดังกล่าวของชุดการก่อรูปรูเข้าถึงได้ดังกล่าว จะถูกถอดออกเพื่อก่อรูปรูเข้าถึงผ่านท่อบางการก่อรูปรู เข้าถึงได้คอนกรีตดังกล่าว ผ่านรูเข้าถึงเเท่นรองรับได้ดังกล่าวเเละยังผ่านรูเข้าถึงปลอกสวมได้ ดังกล่าว 13. Construction methods for elevated reinforced concrete floors in accordance with claim 12, whereby the bolts are removable. Of the aforementioned support kits and a removable implant As mentioned of the aforementioned hole formation set Is removed to form a hole through some pipes. Access to such concrete Through the holes for access to the aforementioned supports and also through the holes to access the sleeve 4. วิธีการก่อสร้างสำหรับพื้นคอนกรีตเสริมเเรงยกระดับตามข้อถือสิทธิข้อที่ 13 โดยที่เเท่น รองรับถอดออกได้จำนนหนึ่งดังกล่าวสามารถถูกลดระดับโดยการใช้เครืองมือการถอด ออกจาก ผิวหน้าบนสุดของพื้นคอนกรีตเสริมเเรงดังกล่าวหลังจากช่วงเวลาการบ่มตัวของมัน ผ่านรูเข้าถึง ดังกล่าว 14. Construction methods for elevated reinforced concrete floors in accordance with claim 13, where one such removable support can be lowered by means of a removal tool from the top surface. The end of the reinforced concrete floor after its curing period. Through the aforementioned access holes 1 5. วิถีทางรองรับยกระดับชั่วคราวดังที่ใช้ในวิธีการก่อสร้าง สำหรับพื้นคอนกรีตเสริมเเรง ยกระดับตามข้อใดข้อหนึ่งของข้อถือสิทธิข้อที่ 4 ถึงข้อถือสิทธิข้อที่ 7 15.Transiently elevated supports, as used in the construction method. For reinforced concrete floors Raise the level according to any of the Claims No. 4 to Claim No. 7 1. 6. เเผ่นพื้นคอนกรีตเสริมเเรงหล่อสำเร็จดังที่ใช้ในวิธีการก่อสร้างสำหรับพื้นคอนกรีต เสริมเเรงยกระดับตามข้อถือสิทธิข้อที่ 8 16. Precast concrete reinforced concrete floor as used in the construction method for concrete floor. Enhance and upgrade according to claim No. 8 1 7. เเบบหล่อช่องว่างเว้นระยะดังที่ใช้วิธีการก่อสร้างสำหรับพื้นคอนกรีตเสริมเเรง ยกระดับตามข้อถือสิทธิข้อที่ 9 . 17. Ee casting gap, spacing, as used in the construction method for reinforced concrete floor Raise the level according to claim No. 9. 1 8. เเท่งเสริมเเรงคอนกรีตดังที่ใช้ในวิธีการก่อสร้างสำหรับพื้คอนกรัตเสริมเเรงยกระดับ ตามข้อถือสิทธิข้อที่ 10 18. Reinforcing concrete as used in the construction method for elevated reinforced concrete floors. According to the claim No. 10 1 9. ชุดการก่อรูปรูเข้าถึงได้ดังที่ใช้ในวิธีการก่อสร้างสำหรับพื้นคอนกรีตเสริมเเรงยกระดับ ตามข้อถือสิทธิข้อที่ 119. Reachable hole formation as used in the construction method for raised reinforced concrete floors. According to claim No. 11
TH101001388A 2001-04-10 How to construct an elevated concrete floor using precast concrete slabs And the way to support temporarily elevated TH36630B (en)

Publications (2)

Publication Number Publication Date
TH49115A TH49115A (en) 2002-01-24
TH36630B true TH36630B (en) 2013-08-16

Family

ID=

Similar Documents

Publication Publication Date Title
US10428542B1 (en) Method of constructing an in-ground swimming pool and related form system
CN107605177A (en) The construction method of efficient precast floor slab and its independent support frame
JP2002256573A (en) Existing foundation reinforced steel tower foundation and its construction method
CN204571288U (en) Floor slab preformed hole mould
JP4738886B2 (en) Equipment foundation
KR20160125753A (en) L-shaped perimeter gutter construction method using mechanized equipment and this excellent receiving section for field applied to the production of concrete L-shaped perimeter gutter construction mechanization
KR100659606B1 (en) Rebar Reinforcement spacer
KR102186470B1 (en) Dowel Bar steel form
KR101140884B1 (en) Gangform device constructed for wall and constructing method this using
KR101091600B1 (en) Sidewall PC formwork and construction method using the same
CN207405882U (en) A kind of steel bar positioning frame
JPH0657956A (en) Construction of concrete structure
KR100674080B1 (en) Bridge pier installation method
TH36630B (en) How to construct an elevated concrete floor using precast concrete slabs And the way to support temporarily elevated
TH49115A (en) How to construct an elevated concrete floor using precast concrete slabs And the way to support temporarily elevated
KR100361047B1 (en) Construction mold
JPS6410837A (en) Box pulling basket retaining mold of iron pillar fixing part in s building
JP2004124641A (en) Outer form for tunnel entrance, and construction method of tunnel entrance using the same
CN102224307B (en) Hanger system for cementitious building units
KR101310090B1 (en) Independent type water supplying apparatus for swimming pool and floor construction method using thereof
JP3481986B2 (en) Precast concrete foundation slab and method of constructing concrete foundation floor
KR100296744B1 (en) Mold installation of cement concrete building using horizontal mold rest and execution method
CN106760487A (en) A kind of cast-in-place concrete exterior wall crack resistence Slate hanging construction method
JP2938386B2 (en) Construction method of formwork for residential foundation
JP2022161709A (en) A precast concrete foundation material for forming a mat foundation, a molding apparatus for molding such a precast concrete foundation material, a method for molding the above precast concrete foundation material using such a molding apparatus, and a mat foundation using the above precast concrete foundation material how to form