SU985289A1 - Method of open-cast mining of gently sloping and sloping mineral deposit - Google Patents
Method of open-cast mining of gently sloping and sloping mineral deposit Download PDFInfo
- Publication number
- SU985289A1 SU985289A1 SU813243065A SU3243065A SU985289A1 SU 985289 A1 SU985289 A1 SU 985289A1 SU 813243065 A SU813243065 A SU 813243065A SU 3243065 A SU3243065 A SU 3243065A SU 985289 A1 SU985289 A1 SU 985289A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- stage
- sloping
- open
- rock
- mining
- Prior art date
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Description
Изобретение относитс к горной V промьл ленности и может быть использовано при открытой разработке наклонных и КРУтопадающих залежей полезных ископаемых.The invention relates to the mining of the V industry and can be used in the open-pit development of inclined and deep-falling mineral deposits.
Известен способ открытой разработки наклонных и крутопадакхцих залежей полезных ископаемых, включающий разработку вскрыши и полезного ископаемого в направлении падени залежи, с внешним отвалообразованием при углах наклона борта в лежачем боку месторождени , рассчитанных дл полной проектной глубины карьера tl 3Однако известный способ характеризуетс увеличенным объемом вскрыши в конечных контурах карьера и большими территори м, зан тыми внешними отвалами.There is a method of opencast development of sloping and steeply mineral deposits, including the development of overburden and mineral in the direction of a fall of a deposit, with external dumping at a side tilt angle in the recumbent side of the field calculated for the full design depth of the open-pit mine tl 3 the contours of the quarry and large areas occupied by external dumps.
Известен также способ открытой разработки наклонных и крутопадаюцих залежей полезных ископаемых, включающий отработку карьера продольными заходками с внешним отаалообразованием в -первой очереди и поперечными заходкгили с внутреннигл отвалообразованием во второй очереди t2.There is also known a method for the open development of inclined and steep deposits of minerals, which includes mining the pit with longitudinal treads with external oval formation in the first order and transverse treads with internal dumping in the second stage t2.
Однако данный способ неэффективен при глубине разработки более ISO м, резко снижаетс производительностьHowever, this method is inefficient at a depth of development of more than ISO m, the performance decreases sharply
оборудовани из-за стесненных условий работы, сложности водоотлива, транспорта и др.,equipment due to constrained working conditions, difficulty in draining, transportation, etc.,
Цель изобретени - сокращение затрат на вскрьлиные работы во второй очереди путем увеличени предельного угла откоса бортов.The purpose of the invention is to reduce the costs of vskrilinnye work in the second stage by increasing the marginal angle of slope of the sides.
Поставленна цепь достигаетс тем, The delivered chain is achieved by
to что fe способе открытой разработки на,клонных и крутопадающих залежей«полезных ископаемых, включающем отработку карьера продольными зaxoдkaми с внешним отвсшообразованием в первой to what fe method of opencast mining, clone and steeply dipping deposits of minerals, including the mining of the quarry by longitudinal tools with external formation in the first
IS очереди и поперечными заходками с внутренним отвалообразованием во второй очереди, на дне карьера первой .очереди отсыпают из пород вскрыши распорную призму, а при выемке второй IS queues and transverse windings with internal dumping in the second turn, at the bottom of the first open-pit mine, spread the prism from the overburden rocks, and during the second excavation
20 очереди породы распорной призмы перемещают рпереди фронта горных работ по мере о1гработки карьера.Twenty queues of the rock of the prism are moved to the front of the mining front as the quarry is mined.
Одновременно с отработкой второй очереди карьера внешние отвалы первой Simultaneously with the development of the second stage of the pit, the external dumps of the first
25 очереди перемещают во внутренние отвалы .25 queues are moved to internal dumps.
На г.1 представлена схема предлагаемого cnocoQa на фиг.2 - разрез А-А на г.1) на фиг.З --разрез Б-Б ; D.1 shows the scheme of the proposed cnocoQa in Fig. 2 - section A-A in d. 1) in Fig. 3 is a section BB;
30 на фиг.2.30 in FIG.
Способ осуществл етс следующим образом.The method is carried out as follows.
Вначале разработку вскрыши и полезного ископаемого ведут продольными заходками до уровн горизонта 1 с вывозкой вскрышных пород на посто н- 5 нае или временные внешние отвалы. При необходикюсти увеличени устойчивости борта на ослабленных участках, на дне карьера первой очереди отсыпают распорную призму 2 дл создани О условий зажима потенциальной призме возможного обрушени в ее верхней части, ограниченной поверхностью 3. Угол наклона борта 4 до горизонта 1 определ ют известными методами с нор-}5 мативным коэффициентом запаса, в за-висимости от литологического состава пород. Затем вскрышные работы и разработку полезного ископаемого 5 ведут поперечными заходками б q транспорти-2о рованием пород вскрыши на внутренний отвал 7, причем нижнюю часть отвала формируют из более крепких пор&д, благодар чему откос отвала приобретает выпуклый профиль 8. в обычных 25 услови х, когда нет необходимости в распорной призме 2, скольз щие съезды устраивают толь1со ниже горизонта 1. С горизонта 1 до поверхности доставка полезного ископаемого осуществл етс ,Q с использованием выработанного прост-) ранства карьера первой очереди.Initially, the development of overburden and minerals is carried out by longitudinal stopping to horizon level 1 with removal of overburden at constant 5 or temporary external dumps. If necessary, increasing the stability of the bead in the weakened areas, place the prism 2 at the bottom of the open pit to create conditions for clamping the potential prism of possible breaking in its upper part bounded by surface 3. The angle of the bead 4 to horizon 1 is determined by known methods } 5 by the coefficient of safety, depending on the lithological composition of rocks. Then, the overburden operations and the development of mineral 5 are transversely driven by q q transportation of overburden rock to the internal blade 7, and the bottom of the blade is formed from stronger pores & d, thanks to which the blade slope acquires a convex profile 8. Under the usual 25 conditions when there is no need for the extension prism 2, sliding exits are arranged only below horizon 1. From horizon 1 to the surface, the mineral is delivered, Q using the developed space of the first stage.
Дл того, чтобы меньше обнажать нерабочий борт 9 в лежачем боку месторождени , разработку ведут высокими уступами 10 (например 20 м), а ширину рабочих площадок. 11 принимёиот минимально необходимой, особенно на нижних горизонтах. При этом рабочий борт будет иметь крутой угол наклона или выпуклый профиль.40In order to less strip the non-working side 9 in the recumbent side of the field, the development is carried out with high ledges 10 (for example, 20 m) and the width of the working sites. 11 accepts minimum required, especially in the lower horizons. In this case, the working side will have a steep angle or a convex profile.
Угол наклона борта второй очереди карьера рассчитывают при значении коэффициента устойчивости, равном 1 по избыточным характеристикам пород. В зависимости от этих характеристик 45The angle of inclination of the second turn of the pit is calculated at a value of the stability coefficient equal to 1 according to the excess characteristics of the rocks. Depending on these characteristics 45
борт в целом может иметь выпуклый или плоский профиль.the board as a whole may have a convex or flat profile.
Преимущества предлагаемого способа заключаютс в том, что увеличением угла наклона нерабочего борта в лежачем боку месторождени на несколько градусов (в среднем на 5-6), сокращают объем вскрыши в предельных контурах карьера и сохран ют территорию, примыкающую к борту карьера, сокращаютс площади под внешние отвалы, ускор етс подача восстановленных земель землепользователю.The advantages of the proposed method are that by increasing the angle of inclination of the non-working side in the recumbent side of the field by several degrees (an average of 5-6), reduce the amount of overburden in the marginal contours of the quarry and preserve the area adjacent to the pit wall, reduce the area under external landfills, the delivery of the restored land to the land user is accelerated.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU813243065A SU985289A1 (en) | 1981-02-02 | 1981-02-02 | Method of open-cast mining of gently sloping and sloping mineral deposit |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU813243065A SU985289A1 (en) | 1981-02-02 | 1981-02-02 | Method of open-cast mining of gently sloping and sloping mineral deposit |
Publications (1)
Publication Number | Publication Date |
---|---|
SU985289A1 true SU985289A1 (en) | 1982-12-30 |
Family
ID=20941265
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
SU813243065A SU985289A1 (en) | 1981-02-02 | 1981-02-02 | Method of open-cast mining of gently sloping and sloping mineral deposit |
Country Status (1)
Country | Link |
---|---|
SU (1) | SU985289A1 (en) |
-
1981
- 1981-02-02 SU SU813243065A patent/SU985289A1/en active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
SU985289A1 (en) | Method of open-cast mining of gently sloping and sloping mineral deposit | |
SU960438A1 (en) | Method of strip mining of horizontal and gently-sloping beds of minerals | |
RU2700855C1 (en) | Method for formation of external dump overburden during trenching | |
SU1305346A1 (en) | Method of dumping on inclined bed | |
SU1323716A1 (en) | Method of remining mineral deposits | |
SU992739A1 (en) | Method of strip mining of minerals | |
SU1700236A1 (en) | Method of combined development scheme for mineral deposits | |
RU2013550C1 (en) | Method for open-pit mining of steeply dipping mineral deposits | |
RU1836561C (en) | A method for opencast mining of steeply falling mineral resource deposits | |
RU1812312C (en) | Process of strip mining of steeply dipping and inclined deposits | |
RU2290510C1 (en) | Open underground method for extracting formations of mineral resources | |
RU2139429C1 (en) | Method for opencast mining of flat and sloping deposits of minerals | |
SU1154468A1 (en) | Method of strip mining of sloping beds of mineral fields | |
SU953211A1 (en) | Method of open-cast mining of adjoining horizontal and gently-sloping seams of minerals | |
SU960437A1 (en) | Method of strip mining of horizontal and gently-sloping beds of minerals | |
RU2011827C1 (en) | Method for opencast mining of gently sloping and inclined mineral deposits | |
RU2124128C1 (en) | Method for opencast development of deposits | |
SU1761954A1 (en) | Method of open mining of steep-dipping mineral deposits | |
SU1721241A1 (en) | Method of dumping in working of useful mineral deposits | |
RU2213224C1 (en) | Method of opencast mining of mineral deposits | |
RU2208163C1 (en) | Method of formation of opencast nonmining flank in argillaceous rocks | |
RU2054549C1 (en) | Method for opencast mining of inclined and steeply dipping deposits | |
SU1735585A1 (en) | Open-pit mining method for steep and inclined deposits | |
SU1008450A1 (en) | Method for open-pit working of gently sloping mineral deposits | |
SU1023085A1 (en) | Method of stripping and working deposits in contour-adjoining gones of open mine |