SU983275A1 - Arrangement for protecting preparatory workings - Google Patents

Arrangement for protecting preparatory workings Download PDF

Info

Publication number
SU983275A1
SU983275A1 SU813308858A SU3308858A SU983275A1 SU 983275 A1 SU983275 A1 SU 983275A1 SU 813308858 A SU813308858 A SU 813308858A SU 3308858 A SU3308858 A SU 3308858A SU 983275 A1 SU983275 A1 SU 983275A1
Authority
SU
USSR - Soviet Union
Prior art keywords
blocks
arrangement
preparatory workings
pedestals
block
Prior art date
Application number
SU813308858A
Other languages
Russian (ru)
Inventor
Николай Петрович Бажин
Леонид Когосович Нейман
Владимир Николаевич Рева
Олег Иванович Мельников
Вадим Васильевич Райский
Владимир Ефимович Кардаков
Original Assignee
Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Горной Геомеханики И Маркшейдерского Дела "Вними"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Горной Геомеханики И Маркшейдерского Дела "Вними" filed Critical Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Горной Геомеханики И Маркшейдерского Дела "Вними"
Priority to SU813308858A priority Critical patent/SU983275A1/en
Application granted granted Critical
Publication of SU983275A1 publication Critical patent/SU983275A1/en

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Description

гих материалов. Блок снабжен гибкой перемычкой 4, котора  предназначена дл  перекрыти  выреза блока,и представл ет собой, например, канат. Один конец каната жестко соединен с блоком в месте 5 со стороны отработанной части пласта и перекрывает вырез , а другой оборудован замком 6. Со стороны охран емой выработки 3 блок имеет монтажное кольцо 7. Дл  повышени  устойчивости тумб блоки в них собирают на стойке 8, при этом ,стойка входит в вырез блока. Стойка может быть дерев нной, металлической ( железобетонной и т.п. Ее оставл ют в Чилработанном пространстве при извлечении блоков и она служит дл  предохранени  кровли от обрушени  в процессе извлечени  блоков.gih materials. The block is provided with a flexible jumper 4, which is intended to overlap the cut-out of the block, and is, for example, a rope. One end of the rope is rigidly connected to the block in place 5 on the side of the spent part of the reservoir and overlaps the cutout, and the other is equipped with a lock 6. On the side of protected output 3, the block has a mounting ring 7. To increase the stability of the pedestals, the blocks in them are assembled on a rack 8, This, the rack is included in the cutout block. The rack can be made of wood, metal (reinforced concrete, etc. It is left in the Chilworked space when removing blocks and it serves to protect the roof from collapsing during the process of removing blocks.

Устройство работает следующим образом .The device works as follows.

В выработанном пространстве параллельно выработке 3 устанавливают стойки 8 и расклинивают их между почвой и кровлей пласта. Блоки 1соби рают в тумбы 2 на стойках 8 таким образом, чтоба вырез в блоках вместе со стойкой был обращен в выработанное пространство, а монтажное кольцо 7 в сторону выработки 3. Канатом 7 перекрывают вырез блока со стойкой и замком 6 закрепл ют ее на монтажном кольце 7. Перемычка 4 удерживает блок на стойке при монтаже и демонтаже его при наклонном залегании пластов. Под кровлей собранные из блоков тумбы расклинивают. Образованнеит из тумб 2 околс итрекова  полоса воспринимает вес-налегающих пород и предотвращает деформгщию охран емой выработки 3. При демоитсше устройства выбивают клинь  на тумбах и разгружают тумбы от горного да лени , передава  его на.стойки 8. Наблоках 1 освобождают канат 4 путем сн ти  замка б с монтажного кольца 7. После чего вытаскивают блоки вручную или с помощью лебедки в выработку 3 под защитой стоек 8. Извлеченные блоки перенос т на новое место и устанавливают аналогично. При этом стойки 8 выполн ют поддерживающую функцию, преп тству  обрушению пород кровли.In the developed space in parallel with the development of 3 set the rack 8 and wedged them between the soil and the roof of the reservoir. The blocks 1 are assembled into pedestals 2 on the uprights 8 in such a way that the cutout in the blocks together with the stand is turned into the worked out space, and the mounting ring 7 is towards the working side 3. Rope 7 covers the cutout of the block with the stand and the lock 6 fix it to the mounting ring 7. Jumper 4 holds the unit on the rack during installation and dismantling it when the layers are inclined. Under the roof, the blocks assembled from the blocks are wedged. Formed from the bollards 2 around the itrekova strip perceives weight-overlying rocks and prevents the deformed protected production 3. At the demo device, they knock the wedges on the pedestals and unload the pedestals from the mountain and laziness, transferring it to the pillars 8. Sublocks 1 release the rope 4 by removing lock b from the mounting ring 7. After that, the blocks are pulled out manually or by means of a winch into generation 3 under the protection of the pillars 8. The removed blocks are transferred to a new location and installed similarly. In this case, the pillars 8 perform a supporting function, preventing the collapse of the roof rocks.

Устройство дл  охраны подготовительных выработок позвол ет расширить область применени  тумб дл  охраны выработок на услови х наклонного залегани  пластов при бесцеликовой технологии их отработки и дает возможность использовани  тумб на пластах большой мощности за счет повышени  устойчивости тумб при воспри тии горного давлени  оThe device for the protection of preparatory workings makes it possible to expand the field of application of pedestals for the protection of workings on the conditions of inclined bedding of layers with the purposeless technology of their working out and allows the use of pedestals on high-powered formations by increasing the stability of pedestals when perceiving rock pressure

Кроме того, достигаетс  снижение затрат на крепежные материгиш благодар  частичному повторному использованию блоков гумб, которое осуществл етс  применением каната с замком и монтажного кольца.In addition, a reduction in the cost of fixing materials is achieved due to partial reuse of gumba blocks, which is carried out using a lock cable and mounting ring.

Claims (2)

1. Указани  по рациональному расположению , охране и поддержанию горных выработок на угольных шахтах СССР. Л., изд-во ВАИМИ, 1978, с. 68, табл. 22.1. Instructions on the rational location, protection and maintenance of mine workings in the coal mines of the USSR. L., publishing house VAIMI, 1978, p. 68, tab. 22 2. Сборник трудов ЮахтНИУИ Технологи  и техника струговой выемки антрацитов. Вып. 18, Юахты, 1977, с. б (прототип J.2. Collection of works YuahtNIUI Technologists and technology of anthracite plow excavation. Issue 18, Yuahty, 1977, p. b (prototype J.
SU813308858A 1981-05-25 1981-05-25 Arrangement for protecting preparatory workings SU983275A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU813308858A SU983275A1 (en) 1981-05-25 1981-05-25 Arrangement for protecting preparatory workings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU813308858A SU983275A1 (en) 1981-05-25 1981-05-25 Arrangement for protecting preparatory workings

Publications (1)

Publication Number Publication Date
SU983275A1 true SU983275A1 (en) 1982-12-23

Family

ID=20965931

Family Applications (1)

Application Number Title Priority Date Filing Date
SU813308858A SU983275A1 (en) 1981-05-25 1981-05-25 Arrangement for protecting preparatory workings

Country Status (1)

Country Link
SU (1) SU983275A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2472933C1 (en) * 2011-07-28 2013-01-20 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Санкт-Петербургский государственный горный университет" Pedestal for supporting reusable development workings

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2472933C1 (en) * 2011-07-28 2013-01-20 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Санкт-Петербургский государственный горный университет" Pedestal for supporting reusable development workings

Similar Documents

Publication Publication Date Title
US10662771B2 (en) Drill and blast method and apparatus for the same
SU983275A1 (en) Arrangement for protecting preparatory workings
JPS62153499A (en) Formwork assembling and overhauling device
JP3407208B2 (en) Construction method and apparatus for sheet pile for preventing collapse of ground behind TBM machine
CN217300587U (en) Disposal structure of karst cave on tunnel arch top
SU1490302A1 (en) Partition for preventing outburst of coal, muck and gas
CN212429273U (en) Drainage structure for mining construction project
RU2068957C1 (en) Device for charging of flooded holes with non-waterproof explosive
SU496366A1 (en) Bottom furnace
CN218716917U (en) Coal mining roof supporting structure
SU1239347A1 (en) Method of supporting and filling-up voids beyond the support of a mine working being restored
CN212582590U (en) Slope protection network for hydraulic engineering
SU1040167A1 (en) Method of supporting working
GB1500221A (en) Process for securing support frames in underground galleries
SU1679036A1 (en) Method for supporting conjunction of longwall and working sections
GB2223044A (en) Setting mine roof arches
SU1032189A1 (en) Frame roof support for mine working
SU1550153A1 (en) Tubing lining for inclined shafts
SU576427A1 (en) Method of mounting cave-in pipeline
SU699190A1 (en) Descending roof support blade section
JPH0512392Y2 (en)
SU891940A1 (en) Mine shaft falsework
RU2190100C2 (en) Blast-proof stopping
SU848653A1 (en) Tunnelling shield
SU1010279A1 (en) Method of maintaining matching of excavated space with preparatory working