SU905358A1 SU802983549A SU2983549A SU905358A1 SU 905358 A1 SU905358 A1 SU 905358A1 SU 802983549 A SU802983549 A SU 802983549A SU 2983549 A SU2983549 A SU 2983549A SU 905358 A1 SU905358 A1 SU 905358A1
Authority
SU
USSR - Soviet Union
Prior art keywords
layer
soil
alluvial
map
pulp
Prior art date
Application number
SU802983549A
Other languages
Russian (ru)
Inventor
Олег Васильевич Мерзляков
Давид Лазаревич Меламут
Ольга Степановна Лавроненко
Мосес Михайлович Саркисов
Хоммат Бабаевич Бабаев
Мая Васильевна Казимова
Original Assignee
Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Гидротехники И Мелиорации Им.А.Н.Костякова
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Гидротехники И Мелиорации Им.А.Н.Костякова filed Critical Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Гидротехники И Мелиорации Им.А.Н.Костякова
Priority to SU802983549A priority Critical patent/SU905358A1/en
Application granted granted Critical
Publication of SU905358A1 publication Critical patent/SU905358A1/en

Links

Landscapes

  • Revetment (AREA)

Description

1one

Изобретение относитс  к гидротехническому строительству, а именно к способам возведени  намывных сооружений , преимущественно плотин распластанного профил  с волноустойчивыми откосами.The invention relates to hydraulic engineering, in particular, to methods for erecting alluvial structures, mainly dams of a flattened profile with wave-resistant slopes.

Известен способ возведени  плотин обжатого профил  с креплением верхового откоса 1 .There is a method of erecting a dam of a crimped profile with the fastening of a raised slope 1.

Недостатком этого способа  вл етс  большой объем железобетонных работ и необходимость промышленной базы дл  изготовлени  железобетонных плит покрыти , а при намыве плотины из пылеватых и суглинистых грунтов дополнительно необходимо устраивать массивные упорные призмы из грави  дл  придани  устойчивости сооружению.The disadvantage of this method is a large amount of reinforced concrete work and the need for an industrial base for the manufacture of reinforced concrete slabs, and when the dam is leached out of silty and loamy soils, it is necessary to arrange massive thrust prisms of gravel to make the structure stable.

Наиболее близким техническим решением к предлагаемому  вл етс  способ возведени  намывных сооружений, закл;очаюи1ийс  в послойном намыве грунта на карты намыва с обвалованием 2.The closest technical solution to the present invention is a method for erecting alluvial structures, in the form of an alluvial layer-by-layer alluvium on damming maps 2.

Недостатком данного способа  вл етс  большой объем земл ных работ , а также не вполне обеспеченна  надежность сооружени .The disadvantage of this method is a large amount of earthworks, as well as the reliability of the structure that is not fully ensured.

Цель изобретени  - сокращение объ ома работ и повышение надежности сооружени .The purpose of the invention is to reduce the work volume and increase the reliability of the structure.

Поставленна  цель достигаетс  тем, что согласно способу обвалование со стороны верхового откоса выполн ют в The goal is achieved by the fact that according to the method, the embankment on the side of the upper slope is performed in

10 виде слоев гравийного материала с продольным валиком, после чего осуществл ют кольматацию каждого сло  посредством пропуска через него части потока пульпы намываемого сло  сооружеIS ни  .10 as layers of gravel material with a longitudinal roller, after which each layer is muddied by passing through it a portion of the pulp flow of the washable layer with a layer.

На фиг. 1 показана схема намыва сооружени ,план; на фиг. 2 - сечение А-А на фиг. 1; на фиг. 3 заполнение пор гравийного материала.FIG. Figure 1 shows the layout of the installation, plan; in fig. 2 is a section A-A in FIG. one; in fig. 3 filling the pores of gravel material.

МM

Способ осуществл етс  следующим образом.The method is carried out as follows.

Claims (2)

Участок дл  намывй С .х1руж иил VT.T биваетс  нд карты намывл 1 fivti M -/г i90 ройс1ва обваловани  2 со стороны низового откоса, поперечных валиков 3 из грунта тела сооружени . Намыв осуществл етс  послойно (0,3-0|5 м. Перед началом намыва каждого сло  отсыпают слой гравийного материала k с продольным валиком 5 из этого же материала, служащим обвалованием со стороны верхового откоса. Ширина отсыпаемого сло  м, что формирует по откосу необходимую дл  волноустойчивости толщину гравийного покрыти  в пределах 0,8-1,0 м при заложении верхового откоса 15-20. Пульпу подают на карту намыва из распределительного пульпопровода 6. В процессе намыва сбросной колодец 7 периодически закрывают с целью пропуска части потока пульпы по слою гравийног.о материала дл  заполнени  его пор глинис тыми и пылеватыми частицами. Направление потока пульпы показано стрелками 8, а заполнение пор - стрелками 9 Осветленна  вода перепускаетс  через смежную карту в сбросной колодец. Пос ле кольматации гравийного материала намыв грунта переключают на смежную карту, где работы осуществл ютс  в той же последовательности. Использование изобретени  позвол т намывать плотины распластанного рофил  с более крутым верховым откоом , что значительно сокращает объм земл ных работ, стоимость строиельства и повышает надежность сооруени . Формула изобретени  Способ возведени  намывных сооружений , заключающийс  в послойном намыве грунта на карты намыва с обвалованием , отличающийс  тем, что, с целью сокращени  объема работ и повьшени  надежности сооружени , обвалование со стороны верхового откоса выполн ют в виде слоев гравийного материала с продольным валиком , после чего осуществл ют кольматацию каждого сло  посредством пропуска через него части потока пульпы намываемого сло  сооружени . Источники информации, прин тые во внимание при экспертизе 1.Авторское свидетельство СССР (f 101579, кл. Е 02 В 7/06, 1953. The site for Alluvial S .x1irug or VT.T is beaten with a map of alluvial 1 fivti M - / g i90 Roycavan embankment 2 from the lower slope, the transverse ridges 3 from the soil of the building's body. The alluvium is carried out in layers (0.3-0 | 5 m.) Before the beginning of the inoculation of each layer, pour a layer of gravel material k with a longitudinal roller 5 of the same material, serving as a roll on the side of the upper slope. The width of the bed that is filled for wave resistance, the thickness of the gravel cover is within 0.8-1.0 m when laying the upper slope 15-20. The pulp is fed to the flush map from the distribution slurry pipe 6. During the washout process, the discharge well 7 is periodically closed in order to pass a part of the slurry flow about a layer of gravel material for filling its pores with clay and dust particles. The direction of flow of the pulp is shown by arrows 8 and filling of the pores with arrows 9 Clarified water flows through the adjacent map into the waste well. After soil has been smoothed, the soil is transferred to the adjacent map where the works are carried out in the same sequence. The use of the invention allows to wash up dams of sprawled rofil with steeper upflow, which significantly reduces the volume of earthworks, the cost l construction and increases the reliability of construction. The invention of the method of erection of alluvial structures, consisting in layer-by-layer alluvium of soil on maps of reclamation with dumping, characterized in that, in order to reduce the amount of work and increase the reliability of the structure, the embankment on the side of the upper slope is made in the form of layers of gravel material with a longitudinal roller after by which each layer is clogged by passing through it a portion of the pulp flow of the washed layer of the structure. Sources of information taken into account in the examination 1. The author's certificate of the USSR (f 101579, class E 02 B 7/06, 1953. 2.Авторское свидетельство СССР № 319669, кл. Е 02 В 7/06, 1971 . I nintii . .11. .1 . . . 41 .-4 ..au-.u ч .У ;.; {У .. .-.-чх-с .. .-..... :,;.. .. ...-.T- i Л.ч t.4...i ... z-j-j; y. tt .. .- Ul.l2. USSR author's certificate number 319669, cl. E 02 B 7/06, 1971. I nintii. .eleven. .one . . . 41.-4 ..au-.u h.;; {U ...-.-Chh-s..-.....:,; .. .. ...-. T- i L.ch t.4 ... i ... z-j-j; y. tt .. .- Ul.l . .. Э I I TTi г I т т -I. .. E I I TTi g I t t -I О О СУОГо О OO O SUOG O O i 6g5 jK«b bp:b.o«a:o.bi-V «. «. ,« ..i 6g5 jK "b bp: b.o" a: o.bi-V ". ". , ".. b i4Dioi o№ 5t aL v t .. . . Г . , «b i4Dioi o№ 5t aL v t ... . G. , " мл « . / I . t i «T .., , tml. " / I. t i "T ..,, t §A;. vMV.: - л .: ;.:-i ч . §A ;. vMV .: - l.:;.: - i h. .Л t ....l.X. Ik . . , Л. л ..L t .... l.X. Ik. . , L. l. i&5:o; v vv:.-. V V .-. ,: . : .-ч ;.A/::V -.: :njV....V.i & 5: o; v vv: .-. V v .-. ,: :.-h; .A / :: V - .:: njV .... V. СГОО&Г SSO & T .-....-.- .«...-....-.-. “.. /z.J/z.J
SU802983549A 1980-09-08 1980-09-08 Method of erecting earth-fill structures SU905358A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU802983549A SU905358A1 (en) 1980-09-08 1980-09-08 Method of erecting earth-fill structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU802983549A SU905358A1 (en) 1980-09-08 1980-09-08 Method of erecting earth-fill structures

Publications (1)

Publication Number Publication Date
SU905358A1 true SU905358A1 (en) 1982-02-15

Family

ID=20918319

Family Applications (1)

Application Number Title Priority Date Filing Date
SU802983549A SU905358A1 (en) 1980-09-08 1980-09-08 Method of erecting earth-fill structures

Country Status (1)

Country Link
SU (1) SU905358A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113186879A (en) * 2021-05-25 2021-07-30 中水北方勘测设计研究有限责任公司 Template-free roller compacted concrete dam rapid construction method capable of simplifying concrete temperature control

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113186879A (en) * 2021-05-25 2021-07-30 中水北方勘测设计研究有限责任公司 Template-free roller compacted concrete dam rapid construction method capable of simplifying concrete temperature control

Similar Documents

Publication Publication Date Title
Brown et al. Design of riprap revetment
SU905358A1 (en) Method of erecting earth-fill structures
CN105839653B (en) A kind of immersed tube tunnel rebuilds the construction method of seepage prevention of cofferdam system
CN214940031U (en) Unilateral formwork retaining wall drainage structure suitable for heightening and reinforcing old roads and river levees
RU2742145C1 (en) Alluvial hydraulic structure
Sheppard et al. The Usk scheme for the water supply of Swansea
CN112458811A (en) Roadbed widening structure and roadbed widening method
SU1758141A1 (en) Method of erecting pressure dam on weak flooded foundation
CN214832441U (en) Underwater throwing-filling type isolation dam
CN217758549U (en) Prefabricated cast-in-place concrete toe wall that combines
CN218843272U (en) Tailing pond area and dam body intercommunication type drainage system
CN217055164U (en) Water conservancy structures reinforced structure is worn under rich water sand bed shield constructs
CN114990959B (en) Waste T-beam recycling road drainage ditch and construction method
CN217869797U (en) Road structure permeates water with water drainage tank
JPS6183711A (en) Method of preventing liquefaction of ground
CN219710364U (en) Pit-in-pit dewatering system in foundation pit
SU983176A1 (en) Method of hydraulic filling of dams of local materials
SU1155663A1 (en) Method of constructing a tail pond
SU866034A1 (en) Hydraulic-fill hydraulic engineering structure
SU1565946A1 (en) Method of erecting pressure structure from local materials
JPH09268542A (en) Dam bank structure using cement mixing material and dam bank construction method
SU1368373A1 (en) Method of hydraulic filling of earth structure
SU960436A1 (en) Method and apparatus for earth-filling narrow-profile structures
SU1141148A2 (en) Method of constructing hydraulically filled structures of local materials
SU1740672A1 (en) Ore storage for hydraulic production