Prior art keywords
excavation
construction method
foundation construction
foundation
soil
Prior art date
Application number
SU792717958A
Other languages
Russian (ru)
Inventor
Владимир Иванович Крутов
Рашид Рафикович Авазов
Виктор Львович Рафальзук
Original Assignee
Ордена Трудового Красного Знамени Научно-Исследовательский Институт Оснований И Подземных Сооружений Им.Н.М.Герсеванова
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ордена Трудового Красного Знамени Научно-Исследовательский Институт Оснований И Подземных Сооружений Им.Н.М.Герсеванова filed Critical Ордена Трудового Красного Знамени Научно-Исследовательский Институт Оснований И Подземных Сооружений Им.Н.М.Герсеванова
Priority to SU792717958A priority Critical patent/SU887735A1/en
Application granted granted Critical
Publication of SU887735A1 publication Critical patent/SU887735A1/en

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Description

Вытрамбовывание котлована под фундамент в песчаном или супесчаном грунте 1 производ т следующим образом.Punching out the foundation pit in sandy or sandy loam soil 1 is performed as follows.

На поверхности грунта 2 отсыпают слой глинистого грунта 3 с влажностью близкой к оптимальной и щебн  4, либо другого крупно зернистого материала (грави , песчано-гравийной смеси, крупного песка), трамбовкой 5 вытрамбовывают котлован 6. В процессе вытрамбовывани  котлована щебень погружаетс  в глинистый слой, щебенисто-глинистый слой выт гиваетс  вдоль стенок и создает щебенисто-глинистую оболочку 7, предотвращающую обрушени  стенок котлована. После вытрамбовывани  котлована на глубину 1,5-ЗА (h - суммарна  толщина щебенисто-глинистого сло ) в котлован 6 отсыпают поэтапно следующий слой глинистого грунта 3 и щебн  4 и производ т через них дальнейшее вытрамбовывание котлована 7 на заданную глубину Я.A layer of clayey soil 3 is filled with soil near the optimum and crushed stone 4, or another coarsely grained material (gravel, sand and gravel, coarse sand), tamping 5 extrudes the soil 6. The rubble-clay layer stretches along the walls and creates a rubble-clay shell 7, which prevents the walls of the excavation from collapsing. After the excavation of the excavation to a depth of 1.5-WA (h is the total thickness of the rubble-clay layer), the next excavation of the clay soil 3 and crushed rock 4 is gradually poured into the excavation 6 and the subsequent excavation of the excavation 7 is performed through them

При реализации описанного способа возведени  фундамента- обеспечиваетс  возможность вытрамбовывани  котлована в песчаных и супесчаных грунтах. По сравнению с изготовлением фундамента в отрываемом котловане обеспечиваетс  снижение объема земл ных работ в 2-3 раза за счет исключени  обратной засыпки котлована; полное исключение опалубочных работ при бетонировании фундаментов «враспор со стенками вытрамбованного котлована; повышение несущей способности фундамента за счет шлотнени  грунта под и вокруг котлована; снижение стоимости и трудоемкости изготовлени  фундамента в 1,5-2 раза.When implementing the described method of erecting a foundation, it is possible to wipe out a pit in sandy and sandy sandy soils. Compared with the manufacture of the foundation in a trench, which is torn off, the volume of earthworks is reduced by a factor of 2-3 by eliminating the backfilling of the excavation; complete elimination of formwork work during the concreting of foundations “with the walls of the compacted pit; increasing the bearing capacity of the foundation due to soil compaction under and around the pit; reducing the cost and complexity of manufacturing the foundation by 1.5-2 times.

Claims (2)

1.Божко А. Г. и др.. Опыт устройства фундаментов на просадочных грунтах в вытрамбованных котлованах. «Основани , фундаменты и механика грунтов, № 1, 1977, с. 5--7.1. Bozhko A. G., et al. Experience in foundations on subsiding soils in compressed trenches. “Foundations, foundations and soil mechanics, No. 1, 1977, p. 5--7. 2.Авторское свидетельство СССР № 699105, кл. Е 02D 27/32, 1977.2. USSR author's certificate number 699105, cl. E 02D 27/32, 1977. Фиг.11 Фuг.ZZG Фиг.ЪFIG.
SU792717958A 1979-01-25 1979-01-25 Foundation construction method SU887735A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU792717958A SU887735A1 (en) 1979-01-25 1979-01-25 Foundation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU792717958A SU887735A1 (en) 1979-01-25 1979-01-25 Foundation construction method

Publications (1)

Publication Number Publication Date
SU887735A1 true SU887735A1 (en) 1981-12-07

Family

ID=20807356

Family Applications (1)

Application Number Title Priority Date Filing Date
SU792717958A SU887735A1 (en) 1979-01-25 1979-01-25 Foundation construction method

Country Status (1)

Country Link
SU (1) SU887735A1 (en)

Similar Documents

Publication Publication Date Title
CN109594442A (en) Garden path construction technology
SU887735A1 (en) Foundation construction method
CN215052842U (en) Column hammer ramming method pore-forming reinforcement pile composite foundation structure
JP3702435B2 (en) How to build the foundation
SU1599481A1 (en) Method of erecting building foundation in heaving soil
RU2249082C1 (en) Method for erecting shallow and surface foundations in thawed ground located above underlying permafrost or rock grounds
SU885446A1 (en) Method of constructing pile foundation on sagging soil
SU1742423A1 (en) Method of erection of building foundation
SU1728382A1 (en) Foundation construction method
JP3099040B2 (en) Embankment culvert
CN108360532A (en) The construction method that Soft Deep Foundation Pit is gone along with sb. to guard him with SMW engineering method stake cantilevers
SU699105A1 (en) Foundation construction method
SU1694779A1 (en) Method for consolidating subsiding soil
SU887733A1 (en) Method of constructing a foundation
JPS6049734B2 (en) How to form a basement
SU829785A1 (en) Method of making pits in sandy soils
CN114086599B (en) Subway station weir building open cut method suitable for bay hydraulic reclamation operation area
SU1760018A1 (en) Method for erection of foundation
SU844692A1 (en) Foundation constructing method
SU1629415A1 (en) Method of erecting foundation for twin columns and walls
SU1763558A1 (en) Channel building method
JPH09268542A (en) Dam bank structure using cement mixing material and dam bank construction method
SU759647A1 (en) Method of preparing bed in compressible and loose soils
SU702114A1 (en) Method of making excavations in clayey soil
SU844693A1 (en) Pile foundation constructing method