SU742525A1 - Method of erecting a stone-earth dam - Google Patents

Method of erecting a stone-earth dam Download PDF

Info

Publication number
SU742525A1
SU742525A1 SU762351635A SU2351635A SU742525A1 SU 742525 A1 SU742525 A1 SU 742525A1 SU 762351635 A SU762351635 A SU 762351635A SU 2351635 A SU2351635 A SU 2351635A SU 742525 A1 SU742525 A1 SU 742525A1
Authority
SU
USSR - Soviet Union
Prior art keywords
dam
stone
erecting
transition zone
dumping
Prior art date
Application number
SU762351635A
Other languages
Russian (ru)
Inventor
Игорь Константинович Лавриненко
Иван Ефимович Саратов
Илья Никонорович Соловьев
Григорий Павлович Давидянц
Шаймуран Зиятдинович Касенов
Мамедали Аббасали Рагимов
Original Assignee
Харьковский Отдел Водного Хозяйства Промпредприятий Всесоюзного Научно- Исследовательского Института Водоснабжения,Канализации,Гидротехнических Сооружений И Инженерной Гидрогеологии "Водгео"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Харьковский Отдел Водного Хозяйства Промпредприятий Всесоюзного Научно- Исследовательского Института Водоснабжения,Канализации,Гидротехнических Сооружений И Инженерной Гидрогеологии "Водгео" filed Critical Харьковский Отдел Водного Хозяйства Промпредприятий Всесоюзного Научно- Исследовательского Института Водоснабжения,Канализации,Гидротехнических Сооружений И Инженерной Гидрогеологии "Водгео"
Priority to SU762351635A priority Critical patent/SU742525A1/en
Application granted granted Critical
Publication of SU742525A1 publication Critical patent/SU742525A1/en

Links

Landscapes

  • Revetment (AREA)

Description

Изобретение относитс  к гидротехническому строительству и может быть применено при возведении плотин хвостохранилищ горно-обогатительных комбинатов. Известен способ возведени  каменно-земл ных плотин путем послойной отсыпки упор ной призмы с устройством переходной зоны и экрана 1. Недостатком известного способа  вл етс  необходимость в разработке и сортировке грунтов дл  переходных зон, что увеличивает стоимость строительства плотины. Цель изобретени  - снижение стоимости возведени  плотины. Это достигаетс  тем, что упорную призму плотины отсыпают на полную высоту с образованием надгребневого конуса, который затем сдвигают слоем на верховой откос дл  образовани  переходной зоны. На фиг. 1 дан разрез по створу плотины в момент ее отсыпки; на фиг. 2 - изображена плотина, поперечный разрез. Способ возведени  плотины осуществл етс  следующим образом. Упорную призму плотины 1 отсыпают пионерным способом с отметки 2, превыщающей отметки гребн  3 плотины, с образованием надгребневого конуса 4. При этом за счет различи  сил трени  происходит фракционирование отсыпаемого материала по крупности так, что в верхней надгребневой части конуса отсыпки откладываютс  более мелкие частицы. После заверщени  отсыпки упорной призмы плотины (с надгребневым конусом) по всей длине надгребневой конус 4 сдвигают слоем на верховой откос дл  образовани  переходной зоны 5. Экран 6 плотины сооружаетс  в процессе эксплуатации хвостохранилища за счет намыва придамбового пл жа из хвостов с постепенным подъемом горизонтов воды в прудке хвостохранилища. Применение изобретени  позвол ет снизить стоимость возведени  каменно-земл ной плотины за счет отказа от разработки специальных карьеров и сортировки материалов дл  переходной зоны плотины, а также за счет отсутстви  необходимости искусственного уплотнени  упорной призмы плотины , так как она в период строительства уплотн етс  за счет дополнительного давлени  от надгребневого конуса. Эффективность изобретени  повыщаетс  при возведении каменно-земл ных плотинThe invention relates to hydraulic construction and can be applied in the construction of dams of tailings of mining and processing plants. There is a method of erection of stone-earth dams by layering the prism with a device of the transition zone and screen 1. A disadvantage of the known method is the need to develop and sort the soils for the transition zones, which increases the cost of building the dam. The purpose of the invention is to reduce the cost of construction of the dam. This is achieved by placing the thrust prism of the dam to its full height with the formation of a ridge cone, which is then shifted by a layer on the upper slope to form a transition zone. FIG. 1 is a section along the dam at the moment of its dumping; in fig. 2 - the dam, cross section is represented. The method of erection of the dam is as follows. The prism of the dam 1 is poured from the mark 2 above the ridge 3 of the dam to form the ridge cone 4. At the same time, due to the difference in frictional forces, the fractionated material is fractionated so that smaller particles are deposited in the upper ridge of the dumping cone. After the dumping of the stop dam prism (with a ridge cone) is completed, the entire length of the ridge cone 4 is shifted by a layer on the uphill slope to form a transition zone 5. The dam screen 6 is constructed during the operation of the tailings pond due to the washing of the dam platform from the tailings with the gradual rise of water horizons pond tailing. The application of the invention allows to reduce the cost of building a stone-earth dam by refraining from developing special quarries and sorting materials for the transition zone of the dam, as well as due to the absence of the need to artificially seal the stop prism of the dam, since it is compacted during construction. overhead cone pressure. The effectiveness of the invention increases with the erection of stone-earth dams.

и отходов горно-обогатительного производст а, так как при этом используютс  без предварительной обработки отходы горнорудного производства, а также те же механизмы и транспорт, которыми ведутс  горные работы (вскрытие котлованов и складирование грунта вскрыши).and waste from the mining and processing industry, since it uses the waste from the mining industry without prior treatment, as well as the same mechanisms and transport that is used for mining (opening of the pits and storing the soil overburden).

Claims (1)

Формула изобретени Invention Formula Способ возведени  каменно-земл ной плотины путем отсыпки упорной призмы с устройством переходной зоны и экрана, отличающийс  тем, что, с целью снижени  стоимости плотины, упорную призму плотины отсыпают на полную высоту с образованием надгребневого конуса, который затем слоем сдвигают на верховой откос дл  образовани  переходной зоны.The method of erecting a stone-earth dam by dumping a stop prism with a transition zone and screen, characterized in that, to reduce the cost of the dam, the stop prism of the dam is poured to full height with the formation of a ridge cone, which is then shifted by a layer on the top slope to form transition zone. Источники информации, прин тые во внимание при экспертизе 1. Эрнстов В. С. Производство гидротехнических работ. М., Энерги , 1970, с. 141 - 142.Sources of information taken into account in the examination 1. Ernstov V. S. The production of hydraulic engineering works. M., Energie, 1970, p. 141 - 142. f J 4 Направление пионеркой отсыпки f J 4 Direction pioneer dumping
SU762351635A 1976-04-26 1976-04-26 Method of erecting a stone-earth dam SU742525A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU762351635A SU742525A1 (en) 1976-04-26 1976-04-26 Method of erecting a stone-earth dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU762351635A SU742525A1 (en) 1976-04-26 1976-04-26 Method of erecting a stone-earth dam

Publications (1)

Publication Number Publication Date
SU742525A1 true SU742525A1 (en) 1980-06-25

Family

ID=20658363

Family Applications (1)

Application Number Title Priority Date Filing Date
SU762351635A SU742525A1 (en) 1976-04-26 1976-04-26 Method of erecting a stone-earth dam

Country Status (1)

Country Link
SU (1) SU742525A1 (en)

Similar Documents

Publication Publication Date Title
ES442290A1 (en) Pile splicing apparatus and method
SU742525A1 (en) Method of erecting a stone-earth dam
SU926288A1 (en) Method for hydraulically deposing muck in stock-piles and tail storage facilities
US2947418A (en) Phosphate process
Cranstone The Archaeology of Washing Floors: Problems, Potentials, and Priorities
SU1346725A1 (en) Method of damping closure channel
WO1989007493A1 (en) Refuse dump for temporary or permanent disposal of hazardous waste and process for installing refuse dumps
SU945434A1 (en) Restoring the surface areas of abandoned open pits and caving-in zones
SU1255676A1 (en) Method of construcing an earth-and-stone dam
SU1509531A1 (en) Method of mining ore bodies in layers with filling-up
RU2088760C1 (en) Method for recultivation of slopes in opencast mining of mineral deposits
RU2039151C1 (en) Washed-up hydraulic structure
SU899950A1 (en) Method of forming internal dumps
ES8305877A1 (en) Mining excavating process using the bord and pillar method.
SU812922A1 (en) Method of consolidating slopes
SU821908A1 (en) Method of erecting dam
SU726253A1 (en) Method of forming waste rock dumps
SU905467A1 (en) Method of working unstable ores
SU1668670A1 (en) Method for mining inclined ore bodies
SU1691457A1 (en) Method for building anti-filtration screen of hydraulic-fill structure
RU2026992C1 (en) Method for dump formation and treatment
SU1055698A1 (en) Method for stockpiling watel-soluble salt wastes in outdoor storage facilities
SU1705476A1 (en) Method for consolidating canal banks
SU1270332A1 (en) Method of forming salt dumps
SU1460343A1 (en) Method of erecting a strip of hardening materials for mine working protection