SU71070A1 - The method of shifting cranes at the height of the building of the building - Google Patents

The method of shifting cranes at the height of the building of the building

Info

Publication number
SU71070A1
SU71070A1 SU67-46A SU351973A SU71070A1 SU 71070 A1 SU71070 A1 SU 71070A1 SU 351973 A SU351973 A SU 351973A SU 71070 A1 SU71070 A1 SU 71070A1
Authority
SU
USSR - Soviet Union
Prior art keywords
building
crane
height
cranes
shifting
Prior art date
Application number
SU67-46A
Other languages
Russian (ru)
Inventor
М.С. Будников
Original Assignee
М.С. Будников
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by М.С. Будников filed Critical М.С. Будников
Priority to SU67-46A priority Critical patent/SU71070A1/en
Application granted granted Critical
Publication of SU71070A1 publication Critical patent/SU71070A1/en

Links

Description

Предлагаемое изобретение касаетс  способа перестановки крана по высоте стро щегос  здани  с использованием в качестве опоры дл  рамы крана балок, монтируемых на возводимых стенах.The present invention relates to a method for rearranging a crane along the height of a building with the use of beams mounted on erected walls as a support for a crane frame.

Отличительной особенностью изобретени   вл етс  применение домкратов , у которых один из подвижных относительно друг друга элементов укрепл ют на раме крана, а другой при подъеме крана на следующую опору опирают на верхний обрез возводимых стен.A distinctive feature of the invention is the use of jacks, in which one of the moving elements relative to each other is fixed on the crane frame, and the other, when lifting the crane to the next support, is supported on the upper edge of the erected walls.

На чертеже схематически изображен вид крана сбоку.The drawing schematically shows a side view of the crane.

Кран состоит из рамы 7, опорной базы, двух стрел - грузовой 2 и противовесной 3, стрелового полиспаста 4, грузового троса 5, лебедки 6 и поворотного круга 7. Рама крана вращаетс  на неподвижном поворотном кругу 7 на роликах, смонтированных в кронштейнах 8.The crane consists of a frame 7, a support base, two arrows - cargo 2 and counterweight 3, jib polyspast 4, cargo cable 5, winch 6 and turntable 7. The frame of the crane rotates on a fixed turntable 7 on rollers mounted in brackets 8.

Поддерживающа  конструкци  состоит из стоек 9, св занных между собой насадками 70, несущими на себе поворотный круг 7. Нижние концы стоек 9 опираютс  на опорные бруски 77, уложенные в сквозные отверсти  кладки лестничной клетки. Подъемным устройством, выполненным в виде четырехвинтовых домкратов, приводимых в движение вручную, кран переставл ют вверх к схваткам поддерживающей конструкции , на которых устроена рабоча  площадка 74.The supporting structure consists of racks 9, interconnected by nozzles 70, bearing a turning circle 7. The lower ends of the racks 9 are supported on support bars 77, laid in the through-holes of the laying of the staircase. A lifting device, made in the form of four-screw jacks, set in motion manually, the crane is moved upwards to the fights of the supporting structure, on which the working platform 74 is arranged.

Первоначально кран собирают после устройства цокол  и изол ционного сло . Стойки 9 опираютс  на бруски 72, уложенные непосредственно на цоколь. Гайки 73 занимают при этом самое нижнее положение . Промежуток между цоколем и опорными башмаками 75 и 76 винтов 72 закладываетс  кирпичом, оставл   при этом гнезда дл  опорных брусков 77. В таком положении кран работает на монтаже конструкции первого этажа.Initially, the crane is assembled after the device is equipped with a base and an insulating layer. The posts 9 rest on the bars 72 laid directly on the base. Nuts 73 occupy the lowest position. The gap between the plinth and the support shoes 75 and 76 of the screws 72 is laid with bricks, while leaving the sockets for the supporting bars 77. In this position, the crane works on mounting the first floor structure.

Дл  перестановки крана на следующую , более высокую позицию ввод тс  в действие все домкраты, которые, опира сь на верхний обрез возведенных стен, поднимают кран. После чего (П1 стади ) под стойки 9 закладывают опорные бруски 77,To relocate the crane to the next, higher position, all the jacks are activated, which, resting on the upper edge of the erected walls, raise the crane. Then (P1 stage) under the rack 9 lay the supporting bars 77,

247247

а винты 12, враща  их в обратном направлении, став т в верхнее положение и т, д.and the screws 12, rotating them in the opposite direction, are set to the upper position and t, e.

Предмет изобретени Subject invention

Способ перестановки крана по высоте стро щегос  здани  с использованием в качестве опоры дл  рамыThe method of moving the crane along the height of the building with the use of a frame as a support

крана балок, монтируемых на возводимых стенах, отличающийс   применением домкратов, у которых один из подвижных относительно друг друга элементов укрепл ют на раме крана, а другой при подъеме крана на следующую опору, опирают на верхний обрез возводимых стен..Crane beams mounted on erected walls, characterized by the use of jacks, in which one of the movable relative to each other elements are fixed on the frame of the crane, and the other when lifting the crane on the next support, lean on the upper edge of the built walls.

SU67-46A 1946-12-31 1946-12-31 The method of shifting cranes at the height of the building of the building SU71070A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU67-46A SU71070A1 (en) 1946-12-31 1946-12-31 The method of shifting cranes at the height of the building of the building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU67-46A SU71070A1 (en) 1946-12-31 1946-12-31 The method of shifting cranes at the height of the building of the building

Publications (1)

Publication Number Publication Date
SU71070A1 true SU71070A1 (en) 1947-11-30

Family

ID=52472018

Family Applications (1)

Application Number Title Priority Date Filing Date
SU67-46A SU71070A1 (en) 1946-12-31 1946-12-31 The method of shifting cranes at the height of the building of the building

Country Status (1)

Country Link
SU (1) SU71070A1 (en)

Similar Documents

Publication Publication Date Title
JP5688493B2 (en) Compound lifting stage
ES448543A1 (en) Climbing scaffolding assemblies with associated shuttering
SU71070A1 (en) The method of shifting cranes at the height of the building of the building
US3468514A (en) Lifting assembly for lift-slab-type building construction
JP2009196802A (en) Conveying system and conveying method
JP3142819B2 (en) How to build a roof frame
JPH092780A (en) Jib-type traveling crane provided with jack up device
SU95163A1 (en) Construction crane
US3127998A (en) Elevator and trailer support structure
SU1308674A1 (en) Load-hoisting arrangement
CN212954139U (en) Belt type single-arm light elevator
SU477228A1 (en) Device for the construction of high-rise structures
KR960031743A (en) Progressive ascent expansion floor unit on mobile work floor
SU73863A1 (en) Lifting device
JPH0240076Y2 (en)
SU343549A1 (en) Self-lifting crane
SU94019A1 (en) Construction crane
JP3802617B2 (en) Moving scaffold
SU724667A1 (en) Form for concrete-coating of walls
US1666451A (en) Stack shaper
SU69530A1 (en) Device for stepped lifting loads with a jack
SU914480A1 (en) Hoisting device for construction of industrial buildings
JP2021017777A (en) Work floor construction equipment for elevator parking equipment
SU417591A1 (en)
SU31104A1 (en) Device crane supports for construction cranes