SU62185A1 - Tunnel tunneling method - Google Patents

Tunnel tunneling method

Info

Publication number
SU62185A1
SU62185A1 SU32889A SU302336A SU62185A1 SU 62185 A1 SU62185 A1 SU 62185A1 SU 32889 A SU32889 A SU 32889A SU 302336 A SU302336 A SU 302336A SU 62185 A1 SU62185 A1 SU 62185A1
Authority
SU
USSR - Soviet Union
Prior art keywords
jacks
lining
tunnel
section
knife
Prior art date
Application number
SU32889A
Other languages
Russian (ru)
Inventor
К.А. Романович
Original Assignee
К.А. Романович
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by К.А. Романович filed Critical К.А. Романович
Priority to SU32889A priority Critical patent/SU62185A1/en
Application granted granted Critical
Publication of SU62185A1 publication Critical patent/SU62185A1/en

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

Производство работ по осуществлению подземных соорул еиий водопроводных ,, канализационных, теплофикационных, газопроводных, транспортных и т- д. при пересечении их с железными дорогами, шоссе и т. п., нри проходке под здани ми и сооружени ми, всегда св зано с р дом осложнений. Проходка открытыми транше ми снижает скорость дв ижени  по пересекаемым транспортным пут м и нередко требует отвода транспортных путей или временной остановки движени . Кроме того, требуетс  крайн   осторожность, во избежание повреждени  пересекаемых подземных сооружений и вызываетс  необходимость исключительной тщательности и применени  т желых типов креплени , чтобы предохранить от повреждени  фундаменты блилсайших сооружений . Все указанные трудности уве.чичиваютс  но мере возраста11и  глубины заложени  осуществл емых нодземных сооружений (трубопроводов и пр.) и особенно при проход,ках в водоносных грунтах. Примен емые закрытые способы производства работ - тоннельные с последующей обделкой штольни или с помощью специальных механизмов-щитов ,  вл ютс  крайне сложными, трудоемкими и дорогосто щими .Implementation of the implementation of underground water supply structures, sewage, heating, gas, transportation and so on. When crossing them with railways, highways, etc., when sinking under buildings and structures, always connected with house of complications. Driving by open trenches reduces the speed of movement along intersected transport routes and often requires the withdrawal of transport routes or a temporary stopping of traffic. In addition, extreme care is required in order to avoid damage to the intersected underground structures and there is a need for exceptional care and the use of heavy types of fasteners to protect the foundations of the nearest structures from damage. All of these difficulties are heightened by the age of 11 and the depth of the foundation of the existing underground structures (pipelines, etc.), and especially when passing through water-bearing soils. The use of closed work methods — tunnels with subsequent lining of the adit or with the help of special shield mechanisms — are extremely complex, time consuming and expensive.

Известен способ проходки тоннелей или прокладк); труб, нри котором звень  тоннельной облицовки или труб проталкивают в грунт домкратами с одновременной разработкой грунта в забое. Этот 11звестнь й снособ примен етс  на практике только нри небольшой длине трубопроводов или тоннелей. При проходке труб и тоннелей бо.П) д.шны снособ также оказываетс  слишком с.ложным, так как иродавливание обдсл1ки нужно производить из р да последовательно располагаемых шахт с соответствующим оборудованием.There is a known method of tunneling or laying; pipes, in which the links of the tunnel lining or pipes are pushed into the ground by jacks while simultaneously developing the ground in the bottomhole. This famous technique is used in practice only for a small length of pipelines or tunnels. When pipes and tunnels are drilled, the boreholes are also too complicated, since the work must be done from a series of consistently located mines with the appropriate equipment.

Изобретение имеет целью исключнть недостатки этого способа и заключаетс  в том, что между отделы1ыл и участками облицовки устанавливают дополнительные домкраты, которые с.пужат дл  последовг.М 621852The invention aims to eliminate the disadvantages of this method and lies in the fact that additional jacks are installed between the sections of the rear and the cladding areas, which the village will require to follow. M 621852

тельного прота;1кива 1и  облицовки по част м и дают возможность уве,;1нчить длину проходки из одного места (рабочей шахты).1kiva 1i cladding in parts and make it possible to increase; 1nchit the length of penetration from one place (working mine).

На фиг. 1 изображен продольный разрез тоннел  после проталкивани  трех участков облицовки; на фиг. 2, 3, 4 - три последовательных положени  домкратов ири продавливании двух частков облицовки; на фиг. 5 и 6 - два положени  домкратов, расположенных в промежуT (j4iK)ft камере.FIG. Figure 1 shows a longitudinal section of a tunnel after pushing through the three facing sections; in fig. 2, 3, 4 - three consecutive positions of the jacks and pressing for two parts of the facing; in fig. 5 and 6 are two positions of the jacks located in the span of the (j4iK) ft camera.

Изображенна  па чертеже примерна  установка дл  осуществлени  способа состоит в следующем.The exemplary installation shown in the drawing for implementing the method is as follows.

Передн   ножева  часть (ножевое звено) /, предназначаетс  дл  вырезани  породы по наружному габариту обделки (облицовки) тоннел  с ушпрением по все.му периметру. Ущирение должно уменьшать трение о породу проталкиваемой обделки (облицовки). Режуща  часть ножевого звена выполн етс  из стали. Тело ножевого звена может быть выполнено из металла, железобетона и дерева. Ножевое звено сопр гаетс  с первым звеном облицовки свободно горцами. Нри проходке в водоносных породах сопр жение уплотн етс  прокладкой (сальником). Нри однотипных проходках ножева  часть (ножевое звено) используетс мн огократно , т. е. оно  вл етс  инвентарным. Дл  корректирова , ни  возможных отклонений ножевого звена от заданного направлени , как в профиле, так и в плане проходки устанавливаетс  необходимое количество выравнивающих винтов или домкратов, закрепленных в те ,je ножевого звена и упирающихс  в торец первой секции облицовки тоинел .The front knife part (knife link) / is intended to cut the rock along the outer lining of the lining (tunnel) of the tunnel with a full perimeter. Enlargement should reduce the friction of the rock pushed lining (cladding). The cutting part of the blade is made of steel. The body of a knife link can be made of metal, reinforced concrete and wood. The knife link is mated to the first link of the cladding freely by the highlanders. When penetrating into aquifers, the junction is sealed with a gasket (stuffing box). In the case of similar penetrations, the knife part (knife unit) is used multiple times, i.e., it is an inventory. In order to correct the possible deviations of the knife link from the given direction, both in the profile and in the penetration plan, the necessary number of leveling screws or jacks fixed in those je of the knife link and abutted against the end of the first section of the liner are installed.

Облицовка изготовл етс  заранее в виде отдельных звеньев длиной 2-4 м. Ноперечпое сечение не ограничиваетс  ни размерами, ни формой. Наружна  поверхность звеньев должна быть строго выдержана по проекту и иметь гладкую поверхностьДл  проталкивани  звеньев служат гидравлические домкраты 7, устанавливаемые в рабочей камере (шахте) 2. Давление домкратов па звень  осуществл етс  через нажимное кольцо, имеющее опорные подущки дл  домкратов. Между нажимным кольцом и домкратом могут нставл тьс  нажимные трубы 8, дающие возможность увеличивать длину действи  домкратов. Гидравлические домкраты примен ютс  любою типа с об зательным устройством приспособлений дл  возврата штоков в исходное положение, а также дл  осуществлени  синхронности работы их. Дл  креплени  домкратов и строгой фиксации расположени  и направлени  осей домкратов должна быть применена рама креплени . Упор, наход щийс  за рамой креплени  домкратов, припимает на себ  горизонтальные усили  при проталкивании сооружени  li должен обеспечить неподвижность рамы. Обычно упором служит )да, на которую рама креплепи  домкратов может опиратьс  непосредственно или, при слабых породах, через подушку (железобетонную , бетонную, дерев нную и т. п.).The cladding is pre-fabricated as individual links with a length of 2-4 m. But the cross section is not limited by either size or shape. The outer surface of the links must be strictly maintained according to the project and have a smooth surface. Hydraulic jacks 7 installed in the working chamber (mine) 2 are used to push the links. The pressure of the jacks of the pa link is carried out through a pressure ring having support points for the jacks. Pressure pipes 8 may be inserted between the pressure ring and the jack, which make it possible to increase the length of the action of the jacks. Hydraulic jacks are used of any type with the obligatory device of devices for returning the rods to their initial position, as well as for synchronizing their operation. To fasten the jacks and strictly fix the location and direction of the axes of the jacks, the fastening frame should be used. The stop, which is located behind the jack fixing frame, takes horizontal forces upon pushing the structure and li must ensure the frame is fixed. Usually it serves as an emphasis) yes, on which the frame of the jacking-up of the jacks can rest directly or, with weak rocks, through a cushion (reinforced concrete, concrete, wood, etc.).

Дл  осуществлени  предложенного способа служит промежуточ:1а  камера 3, выполн ема  из железа и располагаема  между двум  участками обделки. Передн   часть промежуточной камеры укреплена (надвинута) в последнем звене 4 переднего участка обделки. Задн   часть камеры укреплена (надвинута) в первом звене 5 заднего участка.In order to carry out the proposed method, an intermediary serves: 1a, chamber 3, made of iron and located between two areas of the lining. The front part of the intermediate chamber is reinforced (pulled over) in the last link 4 of the front section of the lining. The rear part of the camera is reinforced (pulled over) in the first link of the 5 rear section.

Промежуточна  камера собираетс  и устанавливаетс  в рабочей камере 2 после окончани  нродавливани  первого участка обделки, примыкающего к ножевой части. В промежуточной камере установлены гидравлические дом краты 6, которые подталкивают первый передний участок обделки вместе с звеном. Во врем  действи  домкратов в промежуточной камере домкраты рабочей камеры 2 н второй учаеток обделки 1геподвижны и елужат упором дл  домкратов промежуточной камеры.The intermediate chamber is assembled and installed in the working chamber 2 after termination of the first section of the lining adjacent to the knife portion. In the intermediate chamber, hydraulic crates 6 are installed, which push the first front section of the lining together with the link. During the action of the jacks in the intermediate chamber, the jacks of the working chamber 2 and the second section of the lining are 1 fixed and with a stop for the jacks of the intermediate chamber.

По окончании проталкивани  первого участка обделки на шаг домкратов 6 (фиг. 2 и 5) давление в них спуекаетс  открытием кранов; привод тс  в действие домкраты 7 в рабочей камере, проталкиваетс  второй участок обделки на шаг домкратов; тем самым штокк домкратов 6 в промежуточной камере станов тс  в исходное положение (фиг. 3 н 6); снова включаютс  домкраты 5 и т. д. Если будет не об.ходимо де:1ение проходки тоннел  способом проталкивани  больше чем на два участ а, то между каждым участком устанавливаетс  промежуточна  камера (фиг. 1); технОоЮгический процесс, описанный выше , дл  этого случа  неизменно повтор етс .Upon completion of pushing the first section of the lining onto the pitch of the jacks 6 (Fig. 2 and 5), the pressure in them closes the opening of the taps; jacks 7 are actuated in the working chamber, the second section of the lining is pushed onto the jacks pitch; thereby, the stock jacks 6 in the intermediate chamber become reset to their original position (Fig. 3 N 6); again jacks 5 and so on are turned on. If it is not necessary to: 1 penetrate the tunnel by pushing more than two sections, then an intermediate chamber is installed between each section (Fig. 1); The technological process described above is invariably repeated for this case.

Во врем  проталкивани  обделки производитс  разработка грунтн в забое (в ножевом звене).During pushing through the lining, mining is done in the face (in the knife section).

Практически следует доетигнуть такой скорости продвил ени  обделки , при которой имеюшимис  транспортными возможност ми порода будет убрана из еооружени  в отвал.Practically, it is necessary to reach such a speed of advancement of the lining, at which the transport capacity of the breed will be removed from the structure to the dump.

В зависимости от крепости породы, разработка ее ведете  с З1.1и иным зглом естественного откоса.Depending on the strength of the breed, you develop it with 11.1 and another zglom natural repose.

При наличии плывунов следует держать плывуны под давлением и породу выпускать через периодичееки открываемые окна закрытого ножевого звена.In the presence of quicksand, fluids should be kept under pressure and the rock should be released through the periodical openable windows of the closed knife link.

Предмет изобретени Subject invention

Claims (2)

1.Споеоб проходки тоннелей при номошл вдавливани  и прота.лкп;5ани  в грунт тоннельной облицовки домкратами, с одновременной разработкой грунта в забое, отл ич а ю ш; и и с   тем, что, с целью увеличени  возможной длины проходки из одного места между отдельныЛП1 участками облицовки устанавливают дополнительные домкраты, служащие дл  носледовательного проталкивани  тоннельной облицовки но част м.1. Soloing tunnels with the nominal indentation and prota.klkp; 5ani into the soil of the tunnel lining with jacks, with the simultaneous development of the soil in the bottomhole, deviating w; and with the fact that, in order to increase the possible length of penetration from one place between the separate LP1 facing sections, additional jacks are installed, which are used for the successive pushing of the tunnel facing into parts. 2.Устройство дл  осуществлени  способа по п. 1, отличающеес  тем, что между проталкиваемыми участками облицовки установлены тонр остенные камеры, служащие дл  установки в них домкратов.2. A device for carrying out the method according to claim 1, characterized in that between the pushed portions of the cladding are installed toner left-side chambers, which are used to install jacks in them. - 3 -№ 6-185- 3 - № 6-185
SU32889A 1940-05-04 1940-05-04 Tunnel tunneling method SU62185A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU32889A SU62185A1 (en) 1940-05-04 1940-05-04 Tunnel tunneling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU32889A SU62185A1 (en) 1940-05-04 1940-05-04 Tunnel tunneling method

Publications (1)

Publication Number Publication Date
SU62185A1 true SU62185A1 (en) 1941-11-30

Family

ID=48243417

Family Applications (1)

Application Number Title Priority Date Filing Date
SU32889A SU62185A1 (en) 1940-05-04 1940-05-04 Tunnel tunneling method

Country Status (1)

Country Link
SU (1) SU62185A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011065863A1 (en) * 2009-11-30 2011-06-03 Golubushin Sergey Vladimirovich Multisection concrete product and method for the assembly, transportation and trenchless installation thereof
RU2710832C1 (en) * 2019-07-15 2020-01-14 Артем Владимирович Дудко Tunnel and method of its construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011065863A1 (en) * 2009-11-30 2011-06-03 Golubushin Sergey Vladimirovich Multisection concrete product and method for the assembly, transportation and trenchless installation thereof
RU2710832C1 (en) * 2019-07-15 2020-01-14 Артем Владимирович Дудко Tunnel and method of its construction

Similar Documents

Publication Publication Date Title
KR101834847B1 (en) Echo-environmental construction method of tunnel portal area using mini pipe-roof
CN110219654A (en) The leading construction method of mud stone multiple-arch tunnel side pilot tunnel
CN106049532A (en) Supporting and retaining device for open excavation construction of comprehensive pipe gallery and construction method thereof
CN109339800A (en) A kind of Rapid Construction of Tunnels method in the connected section of bridge tunnel
SU62185A1 (en) Tunnel tunneling method
Moriya Special shield tunnelling methods in Japan
US4280732A (en) Method and apparatus for mining
CN87100318B (en) Secretly digging method with predisposed roof
CN111577331A (en) Construction method of expressway steep-dip phyllite IV-V-level surrounding rock tunnel
CN205839799U (en) A kind of pipe gallery open-cut props up blocking means
Katuwal et al. Challenges associated with the construction of vertical and inclined shafts in the Himalayan Region
GB1403033A (en) Tunnelling method
Clarke et al. The threat of abandoned mines on the stability of urban areas
Osborne Rehabilitation of the Wellington Caves phosphate mine: implications for Cainozoic stratigraphy
Abramson et al. Predicted and actual risks in construction of the Mercer Street Tunnel
JPS6145036B2 (en)
SU639995A1 (en) Method of shoring slopes
SU1122828A1 (en) Method of combination mining of seam deposits
Hughes et al. The River Aire slope failure at the St. Aidans Extension Opencast Coal Site, West Yorkshire, United Kingdom
Vashisht Methodology of cavity treatment by umbrella roofing in corrosive shear mass in Head Race Tunnel of Hydro Power Project in Himalayan region
Donovan Jacobs 3 Some tunnel failures and what they have taught
Saikat et al. Innovative rock support under flowing water conditions in underground caverns
RU2167300C1 (en) Method of tunneling in soft grounds
Matchett et al. Excavation through saturated decomposed granite by multiple headings with vacuum drainage
Iftimie et al. Microtunnelling, Romanian experience.