SU1590840A1 - Boiler house - Google Patents

Boiler house Download PDF

Info

Publication number
SU1590840A1
SU1590840A1 SU884494405A SU4494405A SU1590840A1 SU 1590840 A1 SU1590840 A1 SU 1590840A1 SU 884494405 A SU884494405 A SU 884494405A SU 4494405 A SU4494405 A SU 4494405A SU 1590840 A1 SU1590840 A1 SU 1590840A1
Authority
SU
USSR - Soviet Union
Prior art keywords
heater
economizer
air
inlet
water
Prior art date
Application number
SU884494405A
Other languages
Russian (ru)
Inventor
Leonid G Semenyuk
Andrej A Mikhajlov
Andrej L Gergalov
Yurij M Feshchenko
Original Assignee
Uk Otdel Vgni Pk I Vnipienergo
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Uk Otdel Vgni Pk I Vnipienergo filed Critical Uk Otdel Vgni Pk I Vnipienergo
Priority to SU884494405A priority Critical patent/SU1590840A1/en
Application granted granted Critical
Publication of SU1590840A1 publication Critical patent/SU1590840A1/en

Links

Landscapes

  • Air Supply (AREA)

Description

Изобретение относится к теплоэнергетике, в частности к котельным, работающим

2

на природном газе. Цель изобретения - повышение экономичности путем повышения эффективности подогрева воздуха и увеличения количества получаемого конденсата. Для этого в установку, включающую котел 4, снабженный контактными экономайзером (Э) 5 и воздухоподогревателем (В) 6, имеющими соответственно основную секцию 9 поверхностного подогревателя и водяную рубашку 13 входного патрубка, включены дополнительные секции (ДС) 14 и 15 поверхностного подогревателя, установленные соответственно под орошающими устройствами (ОУ) 8 В 6 и Э 5. Причем ДС 15, размещенная в Э 5, подключена на входе к поддону 7 В 6, а на выходе - к его ОУ 8, а ДС 14, размещенная в В 6, подключена на входе

1590840 А1

3

1590840

4

к поддону 7 Э 5, а на выходе - к входу водяной рубашки 13 В 6, При этом выход последней подключен к ОУ 8 Э 5, При таком выполнении вода оросительного контура В 6 нагреватется в ДС 15 поверхностного подогревателя Э 5, а вода оросительного контура Э 5 охлаждается в ДС 14 В 6. Это

позволяет производить увлажнение дутьевого воздуха только за счет упаривания воды оросительного контура В 6, подпитываемого водопроводной водой, а полученный из увлажненных продуктов сгорания в Э 5 конденсат направлять на подпитку в подводящую линию 2 котла 4. 1 ил.

Изобретение относится к теплоэнергетике, в частности к котельным, работающим на природном газе.

Целью изобретения является повышение экономичности путем повышения эф- Е фективности подогрева воздуха и увеличения количества получаемого конденсата.

На чертеже представлена схема котельной установки, 1

Котельная установка содержит сообщенный подводящей и отводящей линиями I и 2 с потребителем 3 тепла (тракт теплосети) котел 4, снабженный контактным экономайзером 5 и воздухоподогревателем 6, каждый 1 из которых содержит поддон 7 и орошающее устройство 8, причем под орошающим устройством 8 экономайзера 5 установлена основная секция 9 поверхностного подогревателя, подключенная к трубопрово- 2 дам 10 и 11 системы горячего водоснабжения, а воздухоподогреватель 6 снабжен входным патрубком 12 с водяной рубашкой 13.

Установка также снабжена дополнительными секциями 14 и 15 поверхностного подо- 2 гревателя, установленными под орошающими устройствами 8, соответственно воздухоподогревателя 6 и экономайзера 5, причем дополнительная секция 15 подогревателя, размещенная в экономайзере 5, 3 подключена на входе к поддону 7 воздухоподогревателя б, а на выходе - к его орошающему устройству 8, а дополнительная секция 14 подогревателя, размещенная в воздухоподогревателе 6, подключена на 3 входе к поддону 7 экономайзера 5, а на выходе - к входу водяной рубашки 13 входного патрубка 12 воздухоподогревателя б, при этом выход последней подключен к орошающему устройству 8 экономайзера 5. 2

. Поддон 7 экономайзера 5 соединен со сборником 16 конденсата, связанным через насос 17, деаэратор 18 и подпиточный насос 19 с подводящей линией 1 котла 4.

Подключение дополнительной секции ζ 15 поверхностного подогревателя, размещенной в экономайзере 5, к орошающему устройству 8 воздухоподогревателя и к его

поддону 7 осуществляется посредством линий 20, подключение поддона 7 экономайзера 5 к трубному пучку дополнительной секции 14 поверхностного подогревателя, установленной в воздухоподогревателе 6, посредством линии 21 с установленным на ней насосом 22, а подключение выхода водяной рубашки 13 входного патрубка 12 к орошающему устройству 8 экономайзера 5 посредством линии 23.

В установке также предусмотрены регулятор 24 расхода, связанный импульсными линиями с исполнительными органами 25, установленными на линиях 23 и 20, датчиком 26 температуры, размещенным в отводящей линии 2 котла 4, и. управляющим датчиком 27 температуры, установленным в поддоне 7 воздухоподогревателя 6. На линии 20 отвода воды из поддона установлен насос 28.

Установка работает следующим образом.

Уходящие газы котла 4, работающего на природном газе, поступают в контактный экономайзер 5 и нагревают воду, идущую по теплообменным пучкам основной и дополнительной секции 9 и 15 поверхностного подогревателя экономайзера 5. Избытки конденсата водяных паров, выделившихся из увлажненных дымовых газов в результа,те их глубокого охлаждения и имеющих температуру 55-60°, поступают через перелив в поддоне 7 экономайзера 5 в сборник 16 конденсата. Далее с помощью насоса 17 конденсат подается в деаэратор 18, откуда подпиточным насосом 19 направляется на подпитку в подводящую линию 1 котла 4,

Нагретая в теплообменном пучке основной секции 9 поверхностного подогревателя вода подается в трубопровод 11 системы горячего водоснабжения..

В теплообменном пучке дополнительной секции 15 поверхностного подогревателя нагревается вода оросительного контура воздухоподогревателя 6, которая затем по линии 20 подается на орошающее устройство 8 воздухоподогревателя 6. Стекая по наружной поверхности дополнительной

5

1590840

6

секции 14 подогревателя, вода при непосредственном контакте с нагреваемым дутьевым воздухом охлаждается и собирается в поддоне 7 воздухоподогревателя 6, Далее охлажденная вода по линии 20 насосом 28 подается снова в теплообменный пучок дополнительной секции 15 подогревателя.

В теплообменном пучке теплообменника дополнительной секции 14 подогревателя, установленной над орошающим устройством 8 воздухоподогревателя, охлаждается вода оросительного контура экономайзера 5, которая затем доохлаждается в водяной рубашке 13 и по линии 23 подается, на орошающее устройство 8 экономайзера 5. Стекая по наружной поверхности теплообменного пучка основной и дополнительной секции 9 и 15 подогревателя экономайзера 5, вода при непосредственном контакте с уходящими газами нагревается и собирается в поддоне 7 экономайзера 5. Далее нагретая вода по линии 21 насосом 22 подается снова в теплообменный пучок дополнительной секции 14 подогревателя, установленного в воздухоподогревателе 6.

Дутьевой воздух, поступающий в котел 4, нагревается и увлажняется при непосредственном контакте с теплой водой в контактном воздухоподогревателе 6.

Расход воды, подаваемой в орошающие устройства 8 по одной из линий 20 или 23, регулируют при· помощи исполнительных органов 25 регулятора 24 расхода, управляющий сигнал на который поступает от датчика 26 температуры сетевой воды в отводящей линии 2 котла 4. Например, при снижении нагрузки котла 4 уменьшают расход дутьевого воздуха и топлива, при этом снижается расход уходящих газов и температура воды в отводящей линии 2. Регулятор 24 расхода в этом случае уменьшает расход воды по линиям 20 и 23, предотвращая повышение температуры уходящих газов на выходе из экономайзера 5, при этом степень утилизации тепла уходящих газов не изменится.

При работе в зимних условиях в случае снижения температуры воды в поддоне 7

воздухоподогревателя 6 ниже 1-2°С датчик

27 температуры через регулятор 24 расхода

дает команду на исполнительный орган 25 иа

увеличение расхода воды через линию 20.

Предлагаемая схема котельной установки благодаря применению в воздухоподогревателе 6 дополнительной секции 14 подогревателя, включенного в оросительный контур экономайзера 5, позволяет повысить температуру нагрева и соответственно влагосодержание дутьевого воздуха, а наличие двух независимых оросительных контуров экономайзера 5 и воздухоподогревателя 6 при повышенном влагосодержании дутьевого воздуха увеличивает количество получаемого конденсата.

The invention relates to a power system, in particular to the boiler, working

2

on natural gas. The purpose of the invention is to increase efficiency by increasing the efficiency of heating the air and increasing the amount of condensate produced. To do this, the installation, including the boiler 4, equipped with contact economizer (E) 5 and air heater (B) 6, having respectively the main section 9 of the surface heater and the water jacket 13 of the inlet nozzle, includes additional sections (DS) 14 and 15 of the surface heater, installed respectively, under irrigation devices (OA) 8 V 6 and O 5. Moreover, DS 15, located in O 5, is connected at the inlet to the 7 V 6 pallet, and at the outlet - to its OS 8, and DS 14, located in B 6, connected at the entrance

1590840 A1

3

1590840

four

to the pallet 7 O 5, and at the exit - to the entrance of the water jacket 13 V 6, the output of the latter is connected to the OU 8 O 5, With this implementation, the water of the irrigation circuit B 6 will be heated in DS 15 of the surface heater E 5 and the water of the irrigation circuit A 5 is cooled in DS 14 V 6. It

allows you to humidify the blast air only due to the evaporation of water in the irrigation circuit B 6 fed by tap water, and the condensate obtained from the moistened products of combustion in E 5 to be fed to the feed line 2 of the boiler 4. 1 sludge.

The invention relates to a power system, in particular to boiler, running on natural gas.

The aim of the invention is to increase the efficiency by increasing the efficiency of heating the air and increasing the amount of condensate.

The drawing shows a diagram of the boiler plant, 1

The boiler plant contains a supply 4 and supply lines I and 2 with a heat consumer 3 (heat network path) boiler 4, equipped with a contact economizer 5 and an air heater 6, each 1 of which contains a sump 7 and irrigation device 8, and under the irrigator 8 economizer 5 is installed the main section 9 of the surface heater, connected to the pipelines 2 and 10 and 11 of the hot water supply system, and the air heater 6 is equipped with an inlet 12 with a water jacket 13.

The installation is also equipped with additional sections 14 and 15 of the surface heater heater 2 installed under the irrigation devices 8, respectively of the air heater 6 and economizer 5, and the additional heater section 15 placed in economizer 5, 3 is connected at the inlet to the pallet 7 of the air heater b, and the output to its irrigation device 8, and an additional section 14 of the heater placed in the air heater 6 is connected at the 3rd input to the sump 7 of economizer 5, and at the exit to the input of the water jacket 13 of the input steam cutting air heater 12 b, the output of the last device is connected to irrigate economiser 8 5. 2

. The economizer tray 5 7 is connected to a condensate collector 16 connected via a pump 17, a deaerator 18 and a makeup pump 19 with a supply line 1 of the boiler 4.

The connection of an additional section ζ 15 of the surface heater placed in the economizer 5 to the irrigation device 8 of the air heater and to its

the pallet 7 is carried out via lines 20, the economizer 5 pallet 7 is connected to the tube bundle of the additional section 14 of the surface heater installed in the air heater 6 via line 21 with the pump 22 mounted on it, and the water jacket 13 outlet 13 of the inlet 12 is connected to the irrigator irrigator 8 of the economizer 5 via line 23.

The installation also provides for a flow controller 24 connected by impulse lines to executive units 25 installed on lines 23 and 20, a temperature sensor 26 placed in a discharge line 2 of boiler 4, and. temperature control sensor 27 installed in the pallet 7 of the air preheater 6. On the line 20 to drain water from the pallet, a pump 28 is installed.

The installation works as follows.

The exhaust gases of the boiler 4, working on natural gas, enter the contact economizer 5 and heat the water flowing through the heat exchange beams of the main and additional sections 9 and 15 of the surface economizer heater 5. Excessive condensate of water vapor released from humidified flue gases as a result of their deep cooling and having a temperature of 55-60 °, fed through the overflow in the pan 7 of economizer 5 in the collection of 16 condensate. Next, using the pump 17, the condensate is fed to the deaerator 18, from where the makeup pump 19 is sent to the feed to the supply line 1 of the boiler 4,

The water heated in the heat exchange beam of the main section 9 of the surface heater is supplied to the pipeline 11 of the hot water supply system.

In the heat exchange bundle of the additional section 15 of the surface heater, the water of the irrigation circuit of the heater 6 is heated, which is then fed via line 20 to the spray device 8 of the heater 6. Flowing over the outer surface of the additional heater

five

1590840

6

section 14 of the preheater, water is in direct contact with the heated blast air is cooled and collected in the sump 7 of the heater 6, Next, the cooled water through line 20 by pump 28 is fed again into the heat exchange bundle of the additional section 15 of the preheater.

In the heat exchange bundle of the heat exchanger of the additional heater section 14, installed above the irrigating device 8 of the heater, the water of the irrigator circuit of the economizer 5 is cooled, which is then cooled in the water jacket 13 and fed along the line 23 to the irrigating device 8 of the economizer 5. Flowing along the outer surface of the heat exchange beam is basic and an additional section 9 and 15 of the heater economizer 5, water in direct contact with the exhaust gases is heated and collected in the sump 7 economizer 5. Next agretaya water pump 21 via line 22 is fed back to the heat exchanger bundle of the auxiliary section 14 of the heater installed in the air preheater 6.

The blast air entering the boiler 4 is heated and humidified by direct contact with warm water in the contact air heater 6.

The flow rate of water supplied to the irrigation devices 8 via one of the lines 20 or 23 is controlled with the help of the executive bodies 25 of the flow controller 24, the control signal to which comes from the sensor 26 of the temperature of the network water in the discharge line 2 of the boiler 4. For example, when the load decreases boiler 4 reduces the flow rate of the blast air and fuel, while reducing the flue gas consumption and the temperature of the water in the exhaust line 2. The flow controller 24 in this case reduces the flow of water along lines 20 and 23, preventing the flue gas temperature from rising ode from economizer 5, while the degree of heat utilization of flue gases will not change.

During the work in winter conditions in case of decrease in temperature of water in the pallet 7

air heater 6 below 1-2 ° C sensor

27 temperature through flow controller 24

gives a command to the executive body 25 ia

increase in water flow through line 20.

The proposed scheme of the boiler plant, due to the use in the air heater 6 of an additional section 14 of the heater included in the irrigator circuit of economizer 5, allows to increase the heating temperature and, accordingly, moisture content of the blast air, and the presence of two independent irrigation circuits of economizer 5 and air heater 6 with increased moisture content of the blast air increases the amount of received condensate.

Claims (1)

Формула изобретенияClaim Котельная установка, содержащая котел, сообщенный подводящей и отводящей линиями с потребителем тепла и снабженный контактнымиэкономайзероми воздухоподогревателем, каждый из которых содержит поддон и орошающее устройство, причем под орошающим устройством экономайзера установлена основная секция поверхностного подогревателя, подключенная к системе горячего водоснабжения, а воздухоподогреватель снабжен входным патрубком с водяной рубашкой, отличающаяся тем, что, с целью повышения экономичности путем повышения эффективности подогрева воздуха и увеличения количества получаемого конденсата, установка снабжена дополнительными секциями поверхностного подогревателя, установленными соответственно под орошающими устройствами воздухоподогревателя и экономайзера, причем дополнительная секция подогревателя, размещенная в экономайзере, подключена на входе к поддону воздухоподогревателя, а на выходе - к его орошающему устройству, а дополнительная секция подогревателя, размещенная в воздухоподогревателе, подключена на входе к поддону экономайзера, а на выходе - к входу водяной рубашки входного патрубка воздухоподогревателя, при этом выход последней подключен коро"шающему устройству экономайзера .A boiler plant containing a boiler, connected to the supply and discharge lines with a heat consumer and equipped with economic and air heaters, each of which contains a drain pan and irrigation device, the main section of the surface heater connected to the hot water supply system installed under the economizer irrigation device and equipped with an inlet with a water jacket, characterized in that, in order to increase efficiency by increasing the efficiency of heating The unit is equipped with additional surface heater sections installed respectively under the irrigating devices of the air heater and economizer, and the additional section of the heater placed in the economizer is connected at the inlet to the pallet of the air heater, and at the outlet to its irrigating device, and an additional heater section located in the air heater is connected at the inlet to the economizer pan and at the outlet to the inlet the water jacket of the inlet pipe of the air preheater, while the output of the latter is connected to the booster of the economizer.
SU884494405A 1988-10-13 1988-10-13 Boiler house SU1590840A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU884494405A SU1590840A1 (en) 1988-10-13 1988-10-13 Boiler house

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU884494405A SU1590840A1 (en) 1988-10-13 1988-10-13 Boiler house

Publications (1)

Publication Number Publication Date
SU1590840A1 true SU1590840A1 (en) 1990-09-07

Family

ID=21404298

Family Applications (1)

Application Number Title Priority Date Filing Date
SU884494405A SU1590840A1 (en) 1988-10-13 1988-10-13 Boiler house

Country Status (1)

Country Link
SU (1) SU1590840A1 (en)

Similar Documents

Publication Publication Date Title
CN102269401A (en) Low-temperature flue gas waste heat recovery utilization method
AU651315B2 (en) Waste heat recovery apparatus
SU1590840A1 (en) Boiler house
SU909413A1 (en) Boiler unit
SU1239447A2 (en) Device for flue gas waste recovery
SU1158824A1 (en) System for preparing and feeding masout to burners
SU1573296A2 (en) Boiler unit
SU1163085A2 (en) Boiler unit
SU1262191A2 (en) Boiler set
SU684005A1 (en) Deaerator
SU1652745A1 (en) Boiler installations
SU1121537A1 (en) Boiler unit
SU1469190A1 (en) Power-and-heat generating system
SU717513A1 (en) Central heating turbine condenser cooling system
CN206897100U (en) A kind of vapor recovery system of desulfurization fume
SU1188449A1 (en) Boiler installation
SU669067A1 (en) Central-heating steam-turbine plant
SU757754A1 (en) Steam power plant
SU798412A1 (en) Additional water preparation system
SU1212110A1 (en) Method of operation of heat-supply turbine plant
SU1132101A2 (en) Make-up water preparation system
SU877222A1 (en) Steam-water heat exchanger
RU2064145C1 (en) Condensing plant
SU1059229A1 (en) Power plant
SU802723A1 (en) Heat supply system