SU1559185A1 - Method of supporting mine workings - Google Patents

Method of supporting mine workings Download PDF

Info

Publication number
SU1559185A1
SU1559185A1 SU884365048A SU4365048A SU1559185A1 SU 1559185 A1 SU1559185 A1 SU 1559185A1 SU 884365048 A SU884365048 A SU 884365048A SU 4365048 A SU4365048 A SU 4365048A SU 1559185 A1 SU1559185 A1 SU 1559185A1
Authority
SU
USSR - Soviet Union
Prior art keywords
wells
anchors
corners
walls
section
Prior art date
Application number
SU884365048A
Other languages
Russian (ru)
Inventor
Леонид Иннокентьевич Сосновский
Андрей Леонидович Егоров
Эльвира Михайловна Сосновская
Елена Леонидовна Зайцева
Original Assignee
Иркутский государственный научно-исследовательский институт редких и цветных металлов
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Иркутский государственный научно-исследовательский институт редких и цветных металлов filed Critical Иркутский государственный научно-исследовательский институт редких и цветных металлов
Priority to SU884365048A priority Critical patent/SU1559185A1/en
Application granted granted Critical
Publication of SU1559185A1 publication Critical patent/SU1559185A1/en

Links

Abstract

Изобретение относитс  к горнодобывающей промышленности. Цель изобретени  - снижение затрат на крепление выработки (В) и повышение эффективности креплени . Дл  этого при проведении горной В 1 перед установкой анкеров 2 определ ют расположение вокруг В 1 зоны 3 максимальных напр жений горных пород. Затем по геологическому разрезу в поперечном сечении В 1 определ ют расположение систем пересекающихс  трещин I и II. Эти системы трещин образуют структурные блоки пород. После этого бур т центральные скважины в кровле, а боковые - в углах и стенках В 1 в направлении действи  максимальных напр жений. Центральные скважины размещают параллельно диагонал м структурных блоков, а в углах и стенках - перпендикул рно одной из систем пересекающихс  трещин. Рассто ние между скважинами по длине В 1 выбирают равным 0,8-1 м. Анкеры 2 имеют длину 0,5-0,6 ширины В 1 по почве. Концы анкеров 2 должны располагатьс  за зоной 3 максимальных напр жений. 1 ил.The invention relates to the mining industry. The purpose of the invention is to reduce the cost of fixing production (B) and increase the efficiency of mounting. To do this, when conducting mountain In 1, before installing the anchors 2, the location around Zone 1 of the maximum stress of the rocks is determined. Then, the location of the intersecting fracture systems I and II is determined from the geological section in cross section B 1. These fracture systems form structural rock blocks. After that, the central wells are drilled in the roof, and the side wells are in the corners and walls B 1 in the direction of the maximum stresses. The central wells are placed parallel to the diagonal of the structural blocks, and in the corners and walls - perpendicular to one of the intersecting fracture systems. The distance between the wells along the length B 1 is chosen equal to 0.8-1 m. Anchors 2 have a length of 0.5-0.6 width B 1 over the soil. The ends of the anchors 2 must be located beyond the zone of maximum 3 stresses. 1 il.

Description

Изобретение относится к горнодобывающей промышленности, а именно к способам крепления горных выработок в условиях повышенного горного давле- $ ния при подземной разработке месторождений полезных ископаемых.The invention relates to the mining industry, and in particular, to methods for securing mine workings under conditions of increased mountain pressure during underground mining of mineral deposits.

Целью изобретения является снижение затрат на крепление выработки и повышение эффективности крепления, ^дThe aim of the invention is to reduce the cost of fixing the workings and increasing the efficiency of fastening, ^ d

На чертеже изображена схема крепления горной выработки предлагаемым способом.The drawing shows a diagram of the fastening of the mining of the proposed method.

На схеме -показаны горная выработка 1, анкеры 2, зона 3 напряжений горных 15 пород вокруг выработки, сетка 4 систем пересекающихся трещин.The diagram shows the mine working 1, anchors 2, zone 3 of rock stress 15 rocks around the working, a grid of 4 systems of intersecting cracks.

Способ осуществляется .следующим образом.The method is carried out as follows.

При проведении горной выработки 1 20 перед установкой анкеров 2 определяют расположение вокруг выработки зоны 3 максимальных напряжений горных пород. Затем по геологическому разрезу в поперечном сечении выработ- 25 ки 1 определяют расположение систем пересекающихся трещин I и II, образующих структурные блоки пород. После этого бурят в направлении действия максимальных напряжений скважины, jg из которых^центральные скважины размещают в кровле параллельно диагоналям структурных блоков, а в углах и стенках выработки 1 - перпендикулярно одной из систем пересекающихся трещин. Расстояние между скважи нами по длине выработки 1 в зависимости от степени трещиноватости закрепляемого участка пород выбирают равным 0,8-1,0 м. В скважины устанавливают анкеры 2 длиной 0,5-0,6 ширины выработки 1 по почве с таким расчетом, чтобы конец анкера 2 располагался за зоной 3 максимальных напряжений. При такой длине анкер 2 обычно пересекает до 15-45 структурных блоков.When conducting mining 1 20 before installing the anchors 2 determine the location around the mining zone 3 of the maximum stress of rocks. Then, according to the geological section in the cross section of the mine 1, the location of the systems of intersecting cracks I and II, forming the structural blocks of the rocks, is determined. After that, they drill in the direction of the action of the maximum well stresses, jg of which ^ central wells are placed in the roof parallel to the diagonals of the structural blocks, and in the corners and walls of the mine 1 - perpendicularly to one of the intersecting fracture systems. The distance between the wells along the length of the excavation 1, depending on the degree of fracturing of the fixed rock section, is chosen equal to 0.8-1.0 m. Anchors 2 are installed in the wells 0.5-0.6 widths of the excavation width 1 on the soil so that the end of anchor 2 was located beyond zone 3 of the maximum stress. With this length, anchor 2 usually crosses up to 15-45 structural blocks.

Claims (1)

Формула изобретенияClaim Способ крепления горных выработок, включающий определение расположения вокруг выработки зоны максимальных напряжений горных пород, бурение центральных скважин в кровле и боковых скважин <в углах и стенках выработки в направлении действия максимальных напряжений и установку в скважинах анкеров, отличающийся тем, что, с целью снижения затрат на крепление выработки и повышения эффективности крепления, предварительно по геологическому разрезу в поперечном сечении выработки определяют расположение систем пересекающихся трещин, образующих структурные блоки пород, при этом при бурении центральные скважины размещают в кровле параллельно диагоналям структурных блоков, а в углах и стенках - перпендикулярно одной из систем пересекающихся трещин.A method of securing mine workings, including determining the location around the working area of the maximum stress of rocks, drilling central wells in the roof and side wells <in the corners and walls of the working in the direction of maximum stress and installing anchors in the wells, characterized in that, in order to reduce costs to fix the workings and increase the efficiency of fastening, first, according to the geological section in the cross section of the workout, the location of the systems of intersecting cracks is determined, forming their structural blocks of rocks, while during drilling the central wells are placed in the roof parallel to the diagonals of the structural blocks, and in the corners and walls perpendicular to one of the systems of intersecting fractures.
SU884365048A 1988-01-13 1988-01-13 Method of supporting mine workings SU1559185A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU884365048A SU1559185A1 (en) 1988-01-13 1988-01-13 Method of supporting mine workings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU884365048A SU1559185A1 (en) 1988-01-13 1988-01-13 Method of supporting mine workings

Publications (1)

Publication Number Publication Date
SU1559185A1 true SU1559185A1 (en) 1990-04-23

Family

ID=21350280

Family Applications (1)

Application Number Title Priority Date Filing Date
SU884365048A SU1559185A1 (en) 1988-01-13 1988-01-13 Method of supporting mine workings

Country Status (1)

Country Link
SU (1) SU1559185A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Авторское свидетельство СССР № 1286784, кл. Е 21 D 20/00, 1985. Авторское свидетельство СССР № 1208260, кл. Е 21 D 20/00, 1984. *

Similar Documents

Publication Publication Date Title
SU1559185A1 (en) Method of supporting mine workings
RU2215150C1 (en) Method of supporting of underground mine workings with combined support
RU2128773C1 (en) Method for supporting mining workings with loose roof rock by anchor support
SU1652592A1 (en) Method for supporting mine workings
SU1002594A1 (en) Method of advanced supporting of mine working with anchors
SU1761874A1 (en) Method of reinforcing slopes
SU1276816A1 (en) Method of constructing a tunnel
SU1544985A1 (en) Method of supporting mine workings
SU875080A1 (en) Method of securing vaulted roof of mine workings
SU1504349A1 (en) Method of supporting underground working
RU1781436C (en) Process of securing of soil pillar between parallel tunnels
RU2400631C1 (en) Method for reinforcement of mines
SU901552A1 (en) Anchor roof support mounting method
SU1523675A1 (en) Method of supportting mine workings
SU1476145A1 (en) Method of consolidating the roof of stope
SU1265352A1 (en) Method of driving mine workings
SU1401142A1 (en) Method of eliminating sudden surges of water to working face of a working being driven
SU1615377A1 (en) Thrust roof bolt
CN113464146A (en) Integral pre-supporting method for upper-plate crushed ore body long anchor cable
SU1138508A1 (en) Method of erecting a framework roof support in front of working-face
RU97100403A (en) METHOD FOR STRENGTHENING BREEDS WITH BARS IN MINING
SU1442664A1 (en) Method of consolidating parent rock
SU1567789A1 (en) Method of securing mine working
SU1687791A1 (en) A method anchoring mining drifts
SU1328535A1 (en) Method of protecting mine working