SU1510453A1 - Method of erecting storring in mine working - Google Patents

Method of erecting storring in mine working Download PDF

Info

Publication number
SU1510453A1
SU1510453A1 SU874346442A SU4346442A SU1510453A1 SU 1510453 A1 SU1510453 A1 SU 1510453A1 SU 874346442 A SU874346442 A SU 874346442A SU 4346442 A SU4346442 A SU 4346442A SU 1510453 A1 SU1510453 A1 SU 1510453A1
Authority
SU
USSR - Soviet Union
Prior art keywords
rock
pieces
jumper
roof
erecting
Prior art date
Application number
SU874346442A
Other languages
Russian (ru)
Inventor
Ю.Я. Савельев
В.Н. Коваленко
Г.Л. Сергун
А.Г. Недельский
В.И. Степанов
А.П. Литвинов
Original Assignee
Предприятие П/Я Г-4938
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Предприятие П/Я Г-4938 filed Critical Предприятие П/Я Г-4938
Priority to SU874346442A priority Critical patent/SU1510453A1/en
Application granted granted Critical
Publication of SU1510453A1 publication Critical patent/SU1510453A1/en

Links

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Description

tt

(21)43Д6442/03(21) 43D6442 / 03

(22)21.12.87(22) 12/21/87

(А6) 07.06.92. Бюл. Ь 21(A6) 07.06.92. Bul Ь 21

(.72) Ю.Я.Савельев, В.П.Коваленко,(.72) J.Ya. Saveliev, V.P. Kovalenko,

Г-. Л.Сергуи, Л.Г.Недельский, В.И.Степдчюв и Л.П.ЛитвирювG- L.Sergui, L.G.Nedelsky, V.I.Stepdchyuv and L.P.Litviryuv

(55 Г-622.273.2 (088.8)(55 Г-622.273.2 (088.8)

(%) Льторское свидетельство СССР(%) Litor's certificate of the USSR

К° 977836, кл. Е 21 F 15/02, 1981.К ° 977836, cl. E 21 F 15/02, 1981.

Авторское свидетельство СССР f 1129384, кл. Е 21 F 15/00, 1983.USSR author's certificate f 1129384, cl. E 21 F 15/00, 1983.

(5) СПОСОБ ВОЗВЕДЕНИЯ В ГОРНОЙ ВЬСРЛБОТКЕ(5) METHOD FOR INCLUSION IN THE MOUNTAIN REMOVER

(57) Изобретение относитс  к горной пром-сти и пред1газиачеио /у1  изол ции горной выработки (ГВ) закладочного массива. Цель изобретени  - снижение(57) The invention relates to the mining industry and to the gas and gas isolation of the mine workings (HS). The purpose of the invention is to reduce

затрат на возведение перемычки (П) и увеличение ее прочности. В г ерекрьг- аемой ГВ 1 на месте возведени  П производ т отбойку пород кровли и боковых сторон ГВ 1. Путем подбора сочетани  шпуров и зар дов ВВ образ}утот в центре П каркас 7 из кр, п}1ых кусков породы. Из мелких кусков породы образуют изолир тоисий экран 8, которьп преп тствует проникновению закладочного массива 10 в тело П. Куски породы П скрепл ют между собой в жуишм BentecTBOM, которое помещают в шпуры в качестве забойки зар дов ВВ. Дл  осмотра папноты перекрыти  ГВ 1 в кровле 1 I допо.пнительно производ т взрыв зар дов ВВ при помои шпуровых зар дов 12. 1 з.п. ф-лы, 3 i-ui.the cost of building jumpers (P) and increase its strength. At the site of construction, GW 1, the roof rocks and side surfaces of GW 1 are blasted. By selecting a combination of bore-holes and charges, an explosive image} dams in the center P of frame 7 from cr, n} of the first pieces of rock. Isolation screen 8 is formed from small pieces of rock, which prevents the filling of array 10 into the body of P. The pieces of rock P are fastened together in Bentec TBM bombs, which are placed in boreholes as a blocker for explosives. To inspect the daddy's overlap of HW 1 in the roof of 1 I, an additional explosion of explosive charges is carried out with the help of a blast-hole charge of 12.1. files, 3 i-ui.

слcl

Изобретение относитс  к горной промышленности и может быть использовано гфи подземной разработке месторождени  полезных ископаемых.The invention relates to the mining industry and can be used for underground mining of mineral deposits.

Цель изобретени  - снижение затрат на возведение перемычки и увеличение ее прочности, а также осуществление контрол  за полнотой перекрыти  выработки .The purpose of the invention is to reduce the cost of building a jumper and increase its strength, as well as monitoring the completeness of production overlap.

На фиг.1 изображена схема вьфабот- ки с oбypeнны и шпурами до взрывани  зар дов BR, на фиг. 2 - сечение А-А на фиг.1 (после взрывани  зар дов ВВ), на фиг.З - сечение Б-Б на фиг.2.Fig. 1 shows a diagram of machining operations with boreholes and boreholes prior to blasting of charges BR; fig. 2 - section A-A in FIG. 1 (after detonation of explosive charges); in FIG. 3 — section BB in FIG. 2.

Из перекрываемой выработки 1 создают шпуровые зар ды 2 регулируемогоFrom the overlapped production 1 create a drilled charge 2 adjustable

соударени  в боках 3 и кровле 4 выработки 1, а также лтуровые зар ды 5 и 6, взрываемые соответственно дл  образовани  каркас:а 7 из крупных кусков породы и изолир пощего экрана 8 из мелких кусков. Образующиес  при в.зрыва- НИИ зар дов ВВ боковые вьг)лаГ)Отки 9 служат дл  распора тела перемычки и повышени  сопротивлени  закладочному массиву 10. Дл  обеспечени  дл  осмотра перемычки со стороны кровли 11 осушествл ют взрыв зар дов ,ВВ с помощью пш ровых 12.collisions in sides 3 and roof 4 of excavation 1, as well as altar charges 5 and 6, exploded, respectively, to form a skeleton: 7 of large pieces of rock and an isolation screen of 8 of small pieces. The side bridges formed by the explosives of explosives of explosives 9 serve to expand the body of the jumper and increase the resistance of the backfill array 10. To ensure that the jumper from the roof side 11 is inspected, an explosive charge exploded by explosives 12 .

Возведение перемычки взрывом производ т следуюгим образом.The erection of the jumper by explosion is carried out as follows.

слcl

оabout

сл ы r ss

, 3 .-13.-1

Ип перекрынаемой выработки 1 в ее боках 3 н кровле 4 бур т шпуры с зар дами 2, обеспечиваюп9 ми соударение встречных потоков отбиваемой массы. Дл  укладки каркаса 7 вначале п боках 3 вьгработки и ее кровле 4 взрывлгот ишуровые зар ды 2.The overlap of the output 1 in its sides 3 on the roof 4 is a hole of bore-holes with charges 2, providing a collision of the opposing flows of fighting mass. To lay the skeleton 7 at the beginning in the sides 3 of the working and its roof 4 explosives ishuric charges 2.

П(1учение крупной кусковатости достигаетс  соударением мини 1альньгх объемов горной массы при взрыве на один интервал замедлени  по одному iimypy в боках и кровле выработки. Рассто ние, на котором обеспечиваетс  полное соударение кусков горной массы, рассчитываетс  по формулеP (1 the study of coarse lumpiness is achieved by the impact of mini-lumpy volumes of rock mass in an explosion by one slowdown interval by one iimypy in the sides and roof of the excavation. The distance on which the full impact of the rock mass pieces is ensured is calculated by the formula

L 0,6V.L 0.6V.

где I, Vwhere i, v

ИAND

gg

рассто ние, м начальна  скорость движени  куска отбиваемой горной массы , м/с,distance, m is the initial velocity of the piece of felled rock mass, m / s,

высота каркаса, м, ускорение свободного падени  м/с2 .frame height, m, acceleration of free fall m / s2.

По мере перекрыти  каркаса при взрьгое зар дов 6 и создани  экрана 8 объеь отбиваемой горной массы увеличиваетс , а при более высоком уровне энергии соудар юи1ихс  потоков достигаетс  мелкое дробление. После взрывов всех зар дов 6 формируетс  тело , перемычки, которое распираетс  в боковые вьфаботют 9 дл  повышени  ее у стойчивости при напоре закладочного массива 10. Исход  из этих требований , составл ютс  паспорта на отбойк горной массы в боках и кротзле выработки с конструкцией зар да, где в качестве забойки используетс  в жущее вещество, которое в процессе отбойки по мере взрывани  зар дов 2 и расплавл етс , обволакива  куски горной массы и обеспечива  их скрепление . Необходимый объем горной массы дл  формировани  тела перемычки достигаетс  глубиной бурени  шпуров илAs the carcass overlaps, when the charge 6 is ejected and the screen 8 is created, the volume of the rock mass recovered increases, and at a higher level of energy from the impact of their flow, fine crushing is achieved. After the explosions of all charges 6, a body is formed, jumpers that are distributed to the side 9 to increase its stability at the head of the backfill array 10. Based on these requirements, passports for mining of the rock mass are made in the sides and tilted with the design of charge, where as a tamping agent, a holding substance is used, which in the process of blasting as charges 2 explode and melts, enveloping the pieces of rock mass and ensuring their bonding. The required volume of rock mass to form the body of the jumper is achieved by drilling depth of bore holes or

3A

З величением количества иптуровых зар дов 2,в боках 3-й кровле 4 выработ- , ки 1. После завершени  формировани  ,With the magnitude of the number of lateral charges 2, in the sides of the 3rd roof 4, the output is 1. After completion of the formation,

перемычки в кровле 4 выработки 1 бур т наклонные шпуры, которые после взрыва шпуровых зар дов 12 обеспечивают доступ дл  осмотра за полнотой перекрыти  вьфаботки 1. Если объемjumpers in the roof 4 of the production 1 drill t inclined bore-holes, which, after the blast of blast-hole charges 12, provide access for inspection for completing the overlap of the working 1. If the volume

горной массы, уложенный в тело перемычки , недостаточен и не достигаетс  необходимый распор, то дополнительно обуривают шпуры в кровле выработки и взрывают.When the rock mass is laid in the body of the lintel, is insufficient and the required thrust is not reached, the holes in the roof of the excavation are additionally drilled and blown up.

После проведени  дополнительного взрывани  контроль за качеством формировани  перемычки осуществл ют аналогично описанному.After additional blasting, the quality of formation of the jumper is monitored as described.

Claims (2)

1. Способ возведени  перемычки в горной вьфаботке, включающий отбойку при помощи буровзрывных работ пород кровли вьфаботки и образование из1. The method of erection of the jumper in the mountain working, which includes blasting through the drilling and blasting of roof rocks and the formation of них насыпной перемычки, скрепление, кусков породы перемычки между собой в жущим веществом, отличаю- щ и и с   тем, что, с целью снижени  затрат на возведение перемычки и увеличени  ее прочности, одновременно с отбойкой пород кровли производ т отбойку пород боковых сторон выработки с образованием в центре перемычки каркаса из крупных кусков породы, аthese bulk bridges, bonding, pieces of rock bridges between themselves in a binder, are also distinguished by the fact that, in order to reduce the cost of erecting the bar and increase its strength, simultaneously with the breaking of roof rocks, the formation in the center of the frame lintel of large pieces of rock, and 5five по кра м - изолирующего экрана из мелких кусков, а скрепление кусков породы между собой производ т путем размещени  в жущего вещества в шпурах в качестве забойки зар дов ВВ.. f. along the edges of an insulating screen made of small pieces, and the binding of pieces of rock between them is done by placing a binder in the hole in the hole as the blockage of explosives .. f. 2. Способ по п. 1, отличающийс  тем, что, с целью осуществлени  контрол  за полнотой перекрыти  выработки, после возведени  перемычки производ т дополнительное взрывание зар дов ВВ в кровле выработки с направлением отбойки горной массы на перемычку и образованием доступа дл  осмотра ее сверху.2. The method according to claim 1, characterized in that, in order to monitor the completeness of production overlap, after erecting the jumper, additional explosive charges are exploded in the roof of the excavation with the direction of rock mass breaking down on the jumper and forming an access to inspect it from above. Г-ГГТГГГТ GGGGTGGT Ч И 1 I 1.ИТ H AND 1 I 1.IT /I/ I /I/ I 555555 .2.2 Фие.ЗFi.Z
SU874346442A 1987-12-21 1987-12-21 Method of erecting storring in mine working SU1510453A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU874346442A SU1510453A1 (en) 1987-12-21 1987-12-21 Method of erecting storring in mine working

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU874346442A SU1510453A1 (en) 1987-12-21 1987-12-21 Method of erecting storring in mine working

Publications (1)

Publication Number Publication Date
SU1510453A1 true SU1510453A1 (en) 1992-06-07

Family

ID=21343453

Family Applications (1)

Application Number Title Priority Date Filing Date
SU874346442A SU1510453A1 (en) 1987-12-21 1987-12-21 Method of erecting storring in mine working

Country Status (1)

Country Link
SU (1) SU1510453A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EA014007B1 (en) * 2008-10-24 2010-08-30 Открытое Акционерное Общество "Белгорхимпром" (Оао "Белгорхимпром") Method of damp proof bulkhead erection in underground working
RU2459087C1 (en) * 2010-12-29 2012-08-20 Государственное образовательное учреждение высшего профессионального образования "Санкт-Петербургский государственный горный институт имени Г.В. Плеханова (технический университет)" Method for isolation of emergency area of underground working

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EA014007B1 (en) * 2008-10-24 2010-08-30 Открытое Акционерное Общество "Белгорхимпром" (Оао "Белгорхимпром") Method of damp proof bulkhead erection in underground working
RU2459087C1 (en) * 2010-12-29 2012-08-20 Государственное образовательное учреждение высшего профессионального образования "Санкт-Петербургский государственный горный институт имени Г.В. Плеханова (технический университет)" Method for isolation of emergency area of underground working

Similar Documents

Publication Publication Date Title
CN102967191A (en) Blasting method for treatment of gob
CN104596375A (en) Fully mechanized excavation construction method for rock roadway
CN105021096A (en) Five-segment-type millisecond electric detonator secondary blasting construction method applied to blasting of high-gas large-section tunnel
CN111780633B (en) Step-type rapid excavation method for IV-V-level surrounding rock lower step of double-track tunnel
Tatiya Civil excavations and tunnelling: A practical guide
CN115183639B (en) Three-face upper-breaking single-roadway down-cutting blasting construction method for roof-cutting retained roadway
CA1259854A (en) Smooth wall blasting in rock
US4069760A (en) Method for driving a shaft with shaped charges
US4135450A (en) Method of underground mining
CN111457804B (en) Method for blasting IV-grade massive crushed rock with disordered development and wide fracture surface
CN212154765U (en) Deep hole pre-splitting structure for fully mechanized mining face waste rock area
SU1510453A1 (en) Method of erecting storring in mine working
CN112923821A (en) Drilling and blasting tunneling method for reducing and fixing rock resistance
CN114935290B (en) Pre-splitting blasting method for cutting single roadway and cutting deep hole on two sides of top-cutting retained roadway
Gupta Emerging explosives and initiation devices for increased safety, reliability, and performance for excavation in weak rocks, mining and close to surface structures
Reddy et al. Influence of stemming material on performance of blasting
SU1116177A1 (en) Method of driving a mine working in rock body with gas-dynamic hazard
SU1634784A1 (en) Method for sealing off mine workings
RU2078211C1 (en) Method of mining thick steep coal seams
SU1555502A2 (en) Method of relieving a mine working from strain
SU1303719A1 (en) Method of controlling hard roof
SU1689643A1 (en) Method for prevention of rock bursts
RU2203419C2 (en) Process of underground development of thick ore deposits
SU901535A1 (en) Method for driving mine shafts
Ouchterlony Some recent research and developments in Swedish tunnel blasting