SU1506027A1 - Method of reinforcing hollow pile - Google Patents

Method of reinforcing hollow pile Download PDF

Info

Publication number
SU1506027A1
SU1506027A1 SU874294629A SU4294629A SU1506027A1 SU 1506027 A1 SU1506027 A1 SU 1506027A1 SU 874294629 A SU874294629 A SU 874294629A SU 4294629 A SU4294629 A SU 4294629A SU 1506027 A1 SU1506027 A1 SU 1506027A1
Authority
SU
USSR - Soviet Union
Prior art keywords
pile
plug
soil
cavity
bearing capacity
Prior art date
Application number
SU874294629A
Other languages
Russian (ru)
Inventor
Игорь Петрович Полишко
Айрат Хасанович Еникеев
Хаим Давыдович Гилинский
Мугин Кариевич Мударисов
Original Assignee
Научно-Исследовательский Институт Промышленного Строительства
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Научно-Исследовательский Институт Промышленного Строительства filed Critical Научно-Исследовательский Институт Промышленного Строительства
Priority to SU874294629A priority Critical patent/SU1506027A1/en
Application granted granted Critical
Publication of SU1506027A1 publication Critical patent/SU1506027A1/en

Links

Abstract

Изобретение относитс  к области строительства и может быть использовано при возведении фундаментов из полых круглых свай и свай-оболочек. Целью изобретени   вл етс  ускорение производства работ и повышение несущей способности сваи. Усиление сваи производ т следующим образом. Полую сваю 1 с открытым концом погружают в грунт. Если после испытаний вы снилось, что ее несуща  способность меньше проектной не более 15-20%, то в полости сваи образуют грунтовую пробку 2 высотой, равной 1-1,5 наружного диаметра сваи. При этом, если грунтова  пробка выше, то лишний грунт извлекают, если она ниже , то досыпают. Затем втрамбовывают грунт пробки 2 пуансоном 3, который погружают до уровн  нижнего торца сваи, создава  в грунтовой пробке 2 напр жени , превышающие предел прочности стенки сваи 1, вследствие чего образуетс  уширенна  п та, после чего полость сваи заполн ют гравийно-песчаной смесью, а затем бетонируют. 2 ил.The invention relates to the field of construction and can be used in the construction of foundations from hollow round piles and shells. The aim of the invention is to accelerate the production of works and increase the bearing capacity of the pile. The pile is reinforced as follows. Hollow pile 1 with an open end is immersed in the ground. If, after testing, you dreamed that its bearing capacity less than the design capacity is not more than 15-20%, then in the cavity of the pile they form a ground plug 2 with a height equal to 1-1.5 of the outer diameter of the pile. At the same time, if the soil plug is higher, then the extra soil is removed, if it is lower, then fill it up. Then, the soil of the plug 2 is poured in by the punch 3, which is submerged to the level of the bottom end of the pile, creating a voltage in the plug 2 that exceeds the tensile strength of the wall of the pile 1, resulting in a broadened heel, after which the pile cavity is filled with a gravel-sand mixture and then concrete. 2 Il.

Description

Изобретение относитс  к строительству и может быть использовано при возведении фундаментов из полых круглых свай и свай-оболочек.The invention relates to the construction and can be used in the construction of foundations of hollow round piles and shells.

Цель изобретени  - ускорение производства работ и повышение несущей способности сваи.The purpose of the invention is to accelerate the production of works and increase the bearing capacity of the pile.

На фиг. 1 изображена погруженна  пола  сва  с грунтовой пробкой и пуансоном , продольный разрез; на фиг. 2 - пола  сва  с уширенной п той.FIG. 1 shows a submerged pile with a ground plug and a punch, longitudinal section; in fig. 2 - floor of the pile with a broadened p.

Усиление сваи производ т следуюпшм образом.The pile reinforcement is produced in the following way.

Полую сваю 1 с открытым концом погружают любым известным способом. ЕслиHollow pile 1 with an open end is immersed in any known manner. If a

несуща  способность меньше проектной не пробки, втрамбовывание ее и заполнениеload bearing capacity is less than design not plug, tamping it and filling

Л(- Tfio 1 ОП / тг Q пг по ч / Лглс1 пп ТПРП п i irtiil а топ на ппклL (- Tfio 1 OP / tg Q pg for h / Lgls1 pp TPRP n i irtiil and top to PPL

более 15-20%, то в полости сван образуют грунтовую пробку 2 высотой, равной 1-1,5 наружного диаметра сваи. При этом, если грунтова  пробка вьппе, то . жшний грунт извлекают, если она меныпе, то досыпают .more than 15-20%, then in the cavity Svan form a ground plug 2 with a height equal to 1-1.5 of the outer diameter of the pile. At the same time, if the soil plug is high, then. The old soil is removed, if it is replaced, then it is poured.

Затем втрамбовывают грунт пробки 2 пуансоно.м 3. закрываюп им нижний торец сваи. Погружение пуансона 3 производ т до уровн  нижнего торца сваи 1, создаполости сваи твердеющим материалом, отличающийс  тем, что, с целью ускорени  производства работ и повышени  несущей способности сваи, грунтовую пробку образуют высотой 1,0-1,5 наружного диаметра 20 сваи, а при втрамбовывании создают в грунтовой пробке напр жени , превыщаю- щпе предел прочности стенки сваи, причем втрамбовывание производ т до уровн  нижнего торца сваи.Then ram the ground plugs 2 punch. M 3. close them to the lower end of the pile. The plunger 3 is immersed to the level of the bottom end of the pile 1, the pile is hardened with hardening material, characterized in that, in order to accelerate the work and increase the pile carrying capacity, the soil plug is formed with a height of 1.0-1.5 outer diameter 20 piles, during tamping, a voltage is generated in a ground plug that exceeds the stiffness of the pile wall, and the tamping is performed to the level of the lower end of the pile.

ва  в грунтовой пробке напр жени , превышающие предел прочности стенки сваи 1, вследствие чего образуетс  уширенна  п та 4, наличие которой приводит к увеличению площади поперечного сечени  сваи а значит к повышению ее несуш,ей способности .The voltage in the ground plug exceeds the ultimate strength of the wall of the pile 1, as a result of which a broadened 4 is formed, the presence of which leads to an increase in the cross-sectional area of the pile and, therefore, increases its thickness and its capacity.

После усилиени  сваи 1, полость сваи заполн ют гравийно-песчаной смесью, а затем бетонируют.After reinforcement of the pile 1, the pile cavity is filled with a gravel-sand mixture, and then concreted.

Claims (1)

Формула изобретени Invention Formula Способ усилени  полой сваи, включающий образование в полости сваи грунтовойThe method of strengthening the hollow pile, including the formation in the cavity of the pile soil пп ТПРП п i irtiil а топ на ппклpp TPRP p i irtiil and top on PPL полости сваи твердеющим материалом, отличающийс  тем, что, с целью ускорени  производства работ и повышени  несущей способности сваи, грунтовую пробку образуют высотой 1,0-1,5 наружного диаметра сваи, а при втрамбовывании создают в грунтовой пробке напр жени , превыщаю- щпе предел прочности стенки сваи, причем втрамбовывание производ т до уровн  нижнего торца сваи.the cavity of the pile hardening material, characterized in that, in order to accelerate the work and increase the bearing capacity of the pile, the soil plug is formed with a height of 1.0-1.5 outer diameter of the pile, and when embedded the pressure is created in the dirt plug, exceeding the limit strength of the pile wall, and tamping is performed to the level of the bottom end of the pile. аг.2ag.2 X X
SU874294629A 1987-08-05 1987-08-05 Method of reinforcing hollow pile SU1506027A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU874294629A SU1506027A1 (en) 1987-08-05 1987-08-05 Method of reinforcing hollow pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU874294629A SU1506027A1 (en) 1987-08-05 1987-08-05 Method of reinforcing hollow pile

Publications (1)

Publication Number Publication Date
SU1506027A1 true SU1506027A1 (en) 1989-09-07

Family

ID=21323392

Family Applications (1)

Application Number Title Priority Date Filing Date
SU874294629A SU1506027A1 (en) 1987-08-05 1987-08-05 Method of reinforcing hollow pile

Country Status (1)

Country Link
SU (1) SU1506027A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5145284A (en) * 1990-02-23 1992-09-08 Exxon Production Research Company Method for increasing the end-bearing capacity of open-ended piles

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Авторское свидетельство СССР № 50098, кл. Е 02 D 5/38. Авторское свидетельство СССР № 1021715, кл. Е 02 D 7/00, 1981. *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5145284A (en) * 1990-02-23 1992-09-08 Exxon Production Research Company Method for increasing the end-bearing capacity of open-ended piles

Similar Documents

Publication Publication Date Title
US3779025A (en) Pile installation
EP0170503B1 (en) Ground treatment
US4571124A (en) Method of forming cast-in-place concrete pile
US3540225A (en) Construction pile and a method of producing same in situ
CN106192999A (en) The construction method of uplift pile
CN113653032A (en) Construction method of uplift carrier pile
US3916635A (en) Piling and method of installation
SU1506027A1 (en) Method of reinforcing hollow pile
CN105926621A (en) Construction method for static pressure carrier pile
US3429129A (en) Method for producing foundations for columns and the like
EP0519575B1 (en) Method of making a foundation pile
GB2064625A (en) Method of Hole Forming for Miniature Piles
SU1677180A1 (en) Method of manufacturing reinforced cast-in-place pile
CN208136910U (en) A kind of built pile
RU2082851C1 (en) Precast pile
KR960003748B1 (en) Working method of concrete pile or sand pile for a soft-soil foundation
JP4479099B2 (en) Building foundation construction method
CN216999672U (en) Based on cast in situ reinforced concrete I shape stake
GB2289494A (en) Improvements in or relating to foundations
RU2139974C1 (en) Cast-in-place pile
CN219886789U (en) Precast pile with pile end and bearing platform in wedge-shaped connection
CN216339480U (en) Bearing pile with high bearing capacity for building foundation
GB2064627A (en) Method of Piling
CN110952524B (en) Waste tire thin-wall hollow pile for treating soft foundation and construction method thereof
CN207419437U (en) Building waste recycles pile