- 238000009415 formwork Methods 0.000 title claims abstract description 11
- 239000002184 metal Substances 0.000 claims abstract description 9
- 235000014101 wine Nutrition 0.000 claims 1
- 229910000831 Steel Inorganic materials 0.000 abstract description 2
- 238000005065 mining Methods 0.000 abstract description 2
- 239000010959 steel Substances 0.000 abstract description 2
- 230000003245 working effect Effects 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 1
- 210000000078 claw Anatomy 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/102—Removable shuttering; Bearing or supporting devices therefor
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
Изобретение относитс к области горного дела и м.б.использовано дл креплени выработок. Цель - повышение эффективности тампонажных работ путем улучшени герметичности щита-опалубки. Последний состоит из арок крепи (АК) 1 и установленных по периметру АК 1 металлических зат жек 2 из листовой стали. Кажда АК 1 имеет кронштейны (К) 3, выполненные по форме верхн ка, и К 4, выполненные по форме стоек. Каждый К 3 и К 4 имеет отверсти под зажимные винты 7 и захваты 5. При монтаже щита-опалубки на АК 1 навешивают К 3 и 4 с помощью захватов 5 и хомутов 6. Зат жки 2 устанавливают на внутренние полки спецпрофил АК 1 и зажимают винтами 7. Между собой зат жки 2 соедин ют внахлест с помощью зажимных фиксаторов и пазов. После монтажа щита производ т тампонажные работы. 3 ил.The invention relates to the field of mining and may be used to fasten openings. The goal is to increase the efficiency of grouting works by improving the tightness of the formwork shield. The latter consists of arches lining (AK) 1 and installed around the perimeter of AK 1 metal zatzhek 2 of sheet steel. Each AK 1 has brackets (K) 3, made in the form of a top, and K 4, made in the form of racks. Each K 3 and K 4 has holes for clamping screws 7 and clamps 5. When mounting the formwork shield on AK 1, K 3 and 4 are hung with clamps 5 and clamps 6. Zatki 2 install the AK 1 special profile on internal shelves and clamp them with screws 7. Interconnected tightening 2 overlap with clamping clamps and grooves. After mounting the shield, the cementing works are performed. 3 il.
Description
сриг.1srig.1
Изобретение относитс к горному делу, а именно к креплению горных выработок.The invention relates to mining, namely to the fastening of mine workings.
Целью изобретени вл етс повышение эффективности тампонажных работ путем улучшени герметичности ш,ита-опалубки.The aim of the invention is to increase the efficiency of grouting operations by improving the airtightness of the w, formwork.
На фиг. 1 изображен щит-опалубка, поперечный разрез; на фиг. 2 - разрез А-А на фиг. 1; на фиг. 3 - ш,ит-опалубка, продольный разрез.FIG. 1 shows a formwork panel, a cross-section; in fig. 2 shows section A-A in FIG. one; in fig. 3 - w, IT formwork, longitudinal section.
Щит-опалубка состоит из рам арочной крепи 1 и отдельных металлических зат жек 2 из листовой стали. Кажда рама снабжена кронштейнами 3, выполненными по форме верхн ка, и кронштейнами 4, выполненные по форме стойки арочной крепи. Каждый кронштейн крепитс захватами 5 к раме крени 1. В качестве захватов могут использоватьс имеюшиес на раме хомуты б дл соединени верхн ка и стойки. На кронштейнах 3 и 4 имеютс зажимные винты 7 дл прижати металлических зат жек к внутренней полке спецпрофил . Зат жки соедин ютс между собой внахлестку с помощью зажимных фиксаторов 8 и пазов 9. В качестве временной крепи дл ограждени горных выработок служит металлическа сетка 10.The formwork panel consists of arch support frames 1 and separate metal caps 2 of sheet steel. Each frame is provided with brackets 3, made in the form of a top, and brackets 4, made in the form of an arch support. Each bracket is secured by the claws 5 to the frame of the heel 1. As the clamps, the clamps b used on the frame can be used to connect the top and the stand. Brackets 3 and 4 have clamping screws 7 to press the metal fasteners to the inside shelf of the special profile. The puffs are overlapped with the help of clamping fixtures 8 and grooves 9. Metal mesh 10 serves as a temporary support for fencing of mine workings.
Монтаж щита-опалубки в выработке производитс следующим образом.The installation of the formwork panel in the excavation is carried out as follows.
На раму арочной крепи навешивают кронштейны 3 и 4 с помощью захватов 5 иBrackets 3 and 4 are hung on the frame of the arch support with the help of clamps 5 and
хомутов 6. Металлические зат жки 2 устанавливают на внутреннюю полку спецпрофил и зажимают винтами 7, при этом фиксаторы 8 установлены в положении, обеспечивающем соединение зат жек между собой внахлестку. Поворотом фиксаторов 8 обеспечивают прижатие зат жек друг к другу. Затем производ т тампонажные работы. Металлическа сетка 10 дополнительно выполн ет функцию армирующего элемента. Демонтаж щита-опалубки производитс в обратной последовательности.clamps 6. Metal fasteners 2 are installed on the internal shelf of a special profile and clamped with screws 7, while the clamps 8 are installed in a position that allows the connection of the plugs to each other overlapped. By turning the clips 8, they are pressed against each other. Then, grouting works are performed. The metal mesh 10 further functions as a reinforcing member. The dismantling of the formwork panel is carried out in reverse order.
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU874248627A SU1472684A1 (en) | 1987-05-19 | 1987-05-19 | Formwork shield |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU874248627A SU1472684A1 (en) | 1987-05-19 | 1987-05-19 | Formwork shield |
Publications (1)
Publication Number | Publication Date |
---|---|
SU1472684A1 true SU1472684A1 (en) | 1989-04-15 |
Family
ID=21305681
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
SU874248627A SU1472684A1 (en) | 1987-05-19 | 1987-05-19 | Formwork shield |
Country Status (1)
Country | Link |
---|---|
SU (1) | SU1472684A1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108035735A (en) * | 2017-11-30 | 2018-05-15 | 中国冶集团有限公司 | A kind of tunnel double-lining reinforcing bar accurate positioning device and method |
-
1987
- 1987-05-19 SU SU874248627A patent/SU1472684A1/en active
Non-Patent Citations (1)
Title |
---|
Авторское свидетельство СССР № 619665, кл. Е 21 D 11/10, 1970. Заславский Ю. 3. и др. Инъекционное упрочнение горных пород. М.: Недра, 1984 с. 169. * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108035735A (en) * | 2017-11-30 | 2018-05-15 | 中国冶集团有限公司 | A kind of tunnel double-lining reinforcing bar accurate positioning device and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3874131A (en) | Building construction | |
FR2323838A1 (en) | Concrete building wall cladding - has panel fixed in position by supports consisting of bent strips embedded in panels and provided with holes for nails | |
SU1472684A1 (en) | Formwork shield | |
KR102702425B1 (en) | Ceiling frame support device for arcade roof installation | |
JP2001317015A (en) | Decorative-sheet mounting device | |
SU1161709A1 (en) | Trapezoidal mixed support | |
RU94023248A (en) | Formwork panel | |
SU875067A1 (en) | Ferroconcrete trapezoidal roof support | |
SU1053760A3 (en) | Method and device for installation of yielding arch mining roof support | |
CN209723331U (en) | A kind of type unitized curtain wall | |
CN217500733U (en) | Copper art texture strip furred ceiling installing the system | |
SU844772A1 (en) | Inter-frame tie of roof support | |
SU1186748A1 (en) | Device for fastening profiled sheets | |
SU1142638A1 (en) | Mine working roof support | |
SU1283409A1 (en) | Method of supporting adjoining workings with roof bolts | |
JPH08296304A (en) | Simple roof | |
SU901543A1 (en) | Yelding unit for | |
SU1507980A1 (en) | Mine working support | |
SU855217A1 (en) | Rigid-connection assembly of elements of special-section arch roof support | |
SU1675566A1 (en) | Trapezoidal support | |
SU1218127A1 (en) | Metal framework-type support | |
JP2618343B2 (en) | Temporary covering device | |
SU1392245A1 (en) | Metal arch support | |
SU1057646A1 (en) | Versions of arrangement for securing wall panel to column | |
SU1196467A1 (en) | Enclosure panel |