SU1463853A1 - Method of constructing temporary water bed for passing flood water over tip of unfinished structure - Google Patents

Method of constructing temporary water bed for passing flood water over tip of unfinished structure Download PDF

Info

Publication number
SU1463853A1
SU1463853A1 SU864130984A SU4130984A SU1463853A1 SU 1463853 A1 SU1463853 A1 SU 1463853A1 SU 864130984 A SU864130984 A SU 864130984A SU 4130984 A SU4130984 A SU 4130984A SU 1463853 A1 SU1463853 A1 SU 1463853A1
Authority
SU
USSR - Soviet Union
Prior art keywords
water
freezing
flood
slope
layer
Prior art date
Application number
SU864130984A
Other languages
Russian (ru)
Inventor
Василий Иванович Белан
Анатолий Афанасьевич Ленгин
Original Assignee
Сибирский филиал Всесоюзного научно-исследовательского института гидротехники им.Б.Е.Веденеева
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Сибирский филиал Всесоюзного научно-исследовательского института гидротехники им.Б.Е.Веденеева filed Critical Сибирский филиал Всесоюзного научно-исследовательского института гидротехники им.Б.Е.Веденеева
Priority to SU864130984A priority Critical patent/SU1463853A1/en
Application granted granted Critical
Publication of SU1463853A1 publication Critical patent/SU1463853A1/en

Links

Landscapes

  • Revetment (AREA)

Abstract

Изобр.етение относитс  к гидротехническому строительству. Цель изобретени  - упрощение технологии работ и снижение трудозатрат. При осуществлении способа строительства временного быстротока дл  пропуска паводка через гребень недостроенного сооружени  крепление низовйго откоса ведут в следующей последовательности. По мере возведени  сооружени  осуществл ют послойный пролив водой с последующим промораживанием наружной зоны каменной наброски. Укладывают на поверхности низовой призмы полимерные рукава, заполн емые водой. Укладку верхнего рукава производ т только после полного промораживани  воды в нижнем. Крепление полимерных рукавов на откосе осуществл ют посредством защемлени  их концов в объеме наружного сло  каменной наб- роски. Размеры зоны пролива водой определ ют расчетом. 2 ил.. . а (ЛThe image refers to hydraulic engineering. The purpose of the invention is to simplify the technology of work and reduce labor costs. When implementing a method for constructing a temporary rapid current for passing a flood through the ridge of an unfinished structure, the fastening of the lower slope is carried out in the following sequence. As the structure is erected, a layer-by-layer strait is carried out with water, followed by freezing of the outer zone of the rock layer. Polymer sleeves, filled with water, are placed on the surface of the lower prism. The upper hose is laid only after complete freezing of water in the lower one. The polymeric sleeves are fastened on the slope by pinching their ends in the bulk of the outer layer of the stone dust. The dimensions of the strait zone with water are determined by calculation. 2 il .. a (L

Description

Изобретение относитс  к гидротехническому строительству и может быть использовано в северных районах при пропуске паводков через недостроенные плотины, дамбы, перемычки и другие водонапорные сооружени .The invention relates to hydraulic construction and can be used in the northern regions when passing floods through unfinished dams, dams, lintels and other water-pressure structures.

Цель изобретени  - упрощение технологии работ и снижение трудозатрат.The purpose of the invention is to simplify the technology of work and reduce labor costs.

На фиг. 1 представлено возводимое сооружение, разрез; на фиг. 2 - узел I на фиг. 1.FIG. 1 shows the erected structure, section; in fig. 2 — node I in FIG. one.

Каменно-набросна  плотина выполнена с противофильтрационным элементом 1, низовой призмой 2, отдельнос- т ми 3 на низовом откосе и полимер- ными рукавами 4, заполненными льдoмThe stone dam is made with an anti-filtration element 1, a bottom prism 2, separate 3 on the lower slope and polymeric sleeves 4 filled with ice

В зимний период времени на грунтовом сооружении проливают водой на- .ружную зону, склон призмы 2 из ка-, менной наброски, пролив водой можно вести как на стро щемс , так и на построенном сооружении. Ширина пролива L определ етс  климатическими услови ми района, расчетным временем паводка и размерами самого сооружени . Высота проливаемого за одан раз сло  также зависит от размеров и кон- Фигурации сооружени  и температуры наружного воздуха во врем  производства работ. Основное внимание при производстве работ по созданию льдо- грунтового сло  на поверхности низо4 О)In the winter period of time on the soil structure they pour water into the outer zone, the slope of the prism 2 from the Kamennaya draft, the spill with water can be conducted both on the site and on the constructed structure. The width of the strait L is determined by the climatic conditions of the region, the estimated flood time and the size of the structure itself. The height of the layer that is poured at one time also depends on the size and configuration of the structure and the outside air temperature during production. The main focus in the construction of an ice-ground layer on the surface of the low 4 O)

СО СХ)CO CX)

елate

0000

вой призмы удел етс  выполнению условий полного промораживани  указанной зоны и наличию нарулшой зоны выступающих из льдогрунтового массива отдельностей 3. По мере подъема промороженной зоны по склону сооружени  укладывают полимерные рукава 4, например , из полиэтилена. Рулон двухслойной полиэтиленовой пленки раскатывают вдоль откоса сооружени . Один конец рулона или заранее заваривают, или зав зывают непосредственно на объектеt Р.аскатанный рулон заполн ют водой,, след  за обжатием полимерной пленкой выступак цик из льдогрунтового массива отдельностей. После того, как вода, заполн юща  рукав, замерзнет , укладывают следующий, обеспечиспедиально подготовленные траншеи и т.д.).The prism is given to the fulfillment of the conditions of complete freezing of the specified zone and the presence of a broken zone of the detachments 3 protruding from the ice-ground massif. A roll of two-layer polyethylene film is rolled along the side of the structure. One end of the coil is either brewed in advance or tied directly onto the object. The rolled up roll is filled with water, followed by compression of the protrusion loop from the ice-ground mass of the detachment by the polymer film. After the water filling the sleeve has frozen, the next one is laid, providing the internally prepared trenches, etc.).

Claims (1)

g Формулаизобретениg Formula of the invention Способ строительства временного быстротока дл  пропуска паводка че рез гребень недостроенного сооружеThe method of construction of a temporary speed for the passage of flood through the crest of an unfinished construction 10 ни , включающий крепление низового откоса, отличающийс  т что, с целью упрощени  технологии работ и снижени  трудозатрат, в зи ний период времени при отрицательн10, including the fixing of the lower slope, which differs, in order to simplify the technology of work and reduce labor costs, for a period of time with a negative 15 температурах воздуха по мере возве дени  сооружени  осуществл ют посл ный пролив водой с последукицим про мораживанием наружной зоны каменно наброски и укладывают на поверхнос15 temperatures of the air as the building is erected carry out a continuous spill with water, followed by freezing of the outer zone of the stone sketches and are placed on the surface ва  при этом перекрытие стыков нижне- 20 низовой призмы полимерные рукава.At the same time, the overlap of the joints of the lower- 20 lower prism is polymeric sleeves. спедиально подготовленные траншеи и т.д.).spedially prepared trenches, etc.). Формулаизобретени Invention Formula Способ строительства временного быстротока дл  пропуска паводка через гребень недостроенного сооружени , включающий крепление низового откоса, отличающийс  тем, что, с целью упрощени  технологии работ и снижени  трудозатрат, в зимний период времени при отрицательныхThe method of constructing a temporary rapid current for passing the flood through the crest of an unfinished structure, including mounting the lower slope, characterized in that, in order to simplify the work technology and reduce labor costs, during the winter period of time with negative температурах воздуха по мере возведени  сооружени  осуществл ют послойный пролив водой с последукицим промораживанием наружной зоны каменной наброски и укладывают на поверхностиas the erection of the structure, the air temperatures are stratified by water, followed by freezing of the outer zone of the rock layer and laid on the surface го сло  верхним,on the top, Омоноличивание создаваемого покрыти  и его крепление с сооружением осуществл ютс  по предлагаемому способу без выполнени  каких-либо специальных меропри тий (установка анкеров , закапывание части покрыти  вThe monolithing of the created coating and its fastening with the construction are carried out according to the proposed method without performing any special measures (installation of anchors, burying part of the coating in Рт.1Hom.1 заполн емые водой, причем укладку верхнего рукава производ .т после полного промораживани  вода в нижнем, а крепление полимерных рукавов на 25 откосе осуществл ют посредством защемлени  их концов в объеме наружного сло  каменной наброски.filled with water, the laying of the upper hose being made after the complete freezing of water in the lower one, and the fixing of the polymer sleeves on the 25th slope is carried out by pinching their ends in the volume of the outer layer of the stone outline. Pus.2Pus.2
SU864130984A 1986-10-08 1986-10-08 Method of constructing temporary water bed for passing flood water over tip of unfinished structure SU1463853A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU864130984A SU1463853A1 (en) 1986-10-08 1986-10-08 Method of constructing temporary water bed for passing flood water over tip of unfinished structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU864130984A SU1463853A1 (en) 1986-10-08 1986-10-08 Method of constructing temporary water bed for passing flood water over tip of unfinished structure

Publications (1)

Publication Number Publication Date
SU1463853A1 true SU1463853A1 (en) 1989-03-07

Family

ID=21261586

Family Applications (1)

Application Number Title Priority Date Filing Date
SU864130984A SU1463853A1 (en) 1986-10-08 1986-10-08 Method of constructing temporary water bed for passing flood water over tip of unfinished structure

Country Status (1)

Country Link
SU (1) SU1463853A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114687361A (en) * 2021-12-09 2022-07-01 中国铁建大桥工程局集团有限公司 Construction method for preventing landslide of side slope at inlet of flood discharge tunnel

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Розанов Н.Н. Плотины из грунтовых материалов. - М.: Стройиздат, 1983, с. 218. Артюхина Т.е. Водопропускные грунтовые сооружени . Обзорна информаци , М., 1981, с. 56. *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114687361A (en) * 2021-12-09 2022-07-01 中国铁建大桥工程局集团有限公司 Construction method for preventing landslide of side slope at inlet of flood discharge tunnel
CN114687361B (en) * 2021-12-09 2024-05-03 中国铁建大桥工程局集团有限公司 Construction method for flood discharge tunnel entrance side slope anti-slip slope

Similar Documents

Publication Publication Date Title
JPS6263712A (en) Dam structure and its construction
CN109488371B (en) Waterproof system of full-enclosed waterproof station and dynamic setting and quantity-limiting drainage method
CN110438938B (en) River bank structure for constructing sponge city
CN110056015A (en) Concave reinforced anti-floating anchor rod waterproof node structure and construction method thereof
CN208982109U (en) A kind of tunnel structure with antiseepage drain function
CN114703770A (en) Box culvert construction process
CN105040707B (en) Combine the construction method of close pile deep foundation pit support building enclosure
SU1463853A1 (en) Method of constructing temporary water bed for passing flood water over tip of unfinished structure
CN110295630A (en) The late poured band structure of multilayer constraint antiseep
KR100335849B1 (en) A Construction Method of Side Ditch
JPH03206212A (en) Construction method of earth support in tubular pile and tubular pile
CN208136919U (en) Netting safeguard structure between a kind of foundation pit pile
CN216787233U (en) Basement bottom plate post-cast strip in building engineering
CN206956791U (en) A kind of new-old concrete interface waterproof sealing structure
JPH026887B2 (en)
KR200167841Y1 (en) A structure of side ditch for using film layer
CN215406197U (en) Water-resistant plate post-cast strip structure
CN214497605U (en) Waterproof structure of basement bottom plate post-cast strip
RU2267577C2 (en) Impervious member head arranged in crest area
SU1073365A1 (en) Method of erecting dams of earth materials
JPS602261Y2 (en) Water stop plate made of metal plate
SU1687722A1 (en) Canal
SU1710659A1 (en) Earth solidification method
FR2512092A1 (en) Trellis using prefabricated beams - is made up of series of interconnected, mutually perpendicular long and short beams
SU1717893A1 (en) Method for laying pipelines in trench on wear soils