CN110056015A - Concave reinforced anti-floating anchor rod waterproof node structure and construction method thereof - Google Patents
Concave reinforced anti-floating anchor rod waterproof node structure and construction method thereof Download PDFInfo
- Publication number
- CN110056015A CN110056015A CN201910197021.XA CN201910197021A CN110056015A CN 110056015 A CN110056015 A CN 110056015A CN 201910197021 A CN201910197021 A CN 201910197021A CN 110056015 A CN110056015 A CN 110056015A
- Authority
- CN
- China
- Prior art keywords
- concrete
- asphalt
- waterproof
- steel bar
- anchoring steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 38
- 238000007667 floating Methods 0.000 title claims abstract description 24
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 63
- 239000010959 steel Substances 0.000 claims abstract description 63
- 239000004567 concrete Substances 0.000 claims abstract description 58
- 239000010426 asphalt Substances 0.000 claims abstract description 55
- 238000004873 anchoring Methods 0.000 claims abstract description 44
- 239000012528 membrane Substances 0.000 claims abstract description 18
- 239000011241 protective layer Substances 0.000 claims abstract description 17
- 239000002674 ointment Substances 0.000 claims abstract description 16
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 15
- 239000000463 material Substances 0.000 claims abstract description 13
- 239000011248 coating agent Substances 0.000 claims abstract description 9
- 238000000576 coating method Methods 0.000 claims abstract description 9
- 239000010410 layer Substances 0.000 claims description 29
- 230000002787 reinforcement Effects 0.000 claims description 14
- 238000005452 bending Methods 0.000 claims description 7
- 239000004519 grease Substances 0.000 claims description 7
- 238000004140 cleaning Methods 0.000 claims description 6
- 229920000728 polyester Polymers 0.000 claims description 6
- 239000002199 base oil Substances 0.000 claims description 4
- 239000004568 cement Substances 0.000 claims description 4
- 239000000839 emulsion Substances 0.000 claims description 4
- 239000002689 soil Substances 0.000 claims description 4
- 238000004804 winding Methods 0.000 claims description 4
- 230000001680 brushing effect Effects 0.000 claims description 3
- 230000000694 effects Effects 0.000 abstract description 8
- 239000011435 rock Substances 0.000 abstract description 6
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 6
- 238000010586 diagram Methods 0.000 description 3
- 229910052742 iron Inorganic materials 0.000 description 3
- 239000004576 sand Substances 0.000 description 3
- 239000002002 slurry Substances 0.000 description 3
- 239000011449 brick Substances 0.000 description 2
- 239000011083 cement mortar Substances 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 239000004575 stone Substances 0.000 description 2
- 238000004078 waterproofing Methods 0.000 description 2
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000001934 delay Effects 0.000 description 1
- 230000003111 delayed effect Effects 0.000 description 1
- 239000000428 dust Substances 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 230000014509 gene expression Effects 0.000 description 1
- 239000012943 hotmelt Substances 0.000 description 1
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 239000003921 oil Substances 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000005096 rolling process Methods 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 239000002904 solvent Substances 0.000 description 1
- 230000037303 wrinkles Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
- E02D31/025—Draining membranes, sheets or fabric specially adapted therefor, e.g. with dimples
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/10—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
- E02D31/12—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure against upward hydraulic pressure
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/76—Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Road Paving Structures (AREA)
Abstract
本发明提供基础底板凹式防水加强型抗浮锚杆结构,包括自基岩、混凝土垫层、沥青卷材、混凝土防水保护层、锚杆锚固钢筋、注浆管、沥青嵌缝油膏、止水条以及钢筋临时支撑体系,所述混凝土垫层铺设在自基岩上端,所述沥青卷材通过防水涂料粘接在混凝土垫层上端,所述混凝土防水保护层铺设在沥青卷材上端,所述锚杆锚固钢筋下端依次穿过混凝土防水保护层、沥青卷材以及混凝土垫层,且插入自基岩内,该设计使用方便,通过将锚杆锚固钢筋伸出部进行折弯加工,节约钢材,降低材料成本以及施工时间,又利于绿色施工且防水效果好,同时本发明提供基础底板凹式防水加强型抗浮锚杆结构的施工方法。
The invention provides a concave waterproof and reinforced anti-floating anchor structure of a foundation floor, which includes a self-base rock, a concrete cushion, an asphalt coil, a concrete waterproof protective layer, an anchoring steel bar, a grouting pipe, an asphalt caulking ointment, and a stopper. A temporary support system for water strips and steel bars, the concrete cushion is laid on the upper end of the bedrock, the asphalt membrane is bonded to the upper end of the concrete cushion by the waterproof coating, and the concrete waterproof protective layer is laid on the upper end of the asphalt membrane, so The lower end of the bolt anchoring steel bar passes through the concrete waterproof protective layer, the asphalt coil material and the concrete cushion in sequence, and is inserted into the bedrock. This design is convenient to use. The material cost and construction time are reduced, green construction is facilitated, and the waterproof effect is good. At the same time, the invention provides a construction method of a concave waterproof and reinforced anti-floating anchor structure of a foundation floor.
Description
技术领域technical field
本发明是基础底板凹式防水加强型抗浮锚杆结构及其施工方法,属于建筑施工设备领域。The invention relates to a foundation floor concave waterproof reinforced anti-floating anchor structure and a construction method thereof, belonging to the field of building construction equipment.
背景技术Background technique
现有技术中,传统临时支撑结构,施工时间长,延缓了施工时间,且增加了施工成本,施工难度大,防水效果差,所以急需基础底板凹式防水加强型抗浮锚杆结构来解决上述出现的问题。In the prior art, the traditional temporary support structure has a long construction time, which delays the construction time, increases the construction cost, is difficult to construct, and has poor waterproof effect. problem occurs.
发明内容SUMMARY OF THE INVENTION
针对现有技术存在的不足,本发明目的是提供基础底板凹式防水加强型抗浮锚杆结构及其施工方法,以解决上述背景技术中提出的问题,本发明使用方便,节约钢材,降低材料成本以及施工时间,又利于绿色施工且防水效果好。In view of the deficiencies in the prior art, the purpose of the present invention is to provide a concave waterproof reinforced anti-floating anchor rod structure of a foundation floor and a construction method thereof, so as to solve the problems raised in the above-mentioned background technology, the present invention is convenient to use, saves steel, and reduces material The cost and construction time are favorable for green construction and the waterproof effect is good.
为了实现上述目的,本发明是通过如下的技术方案来实现:基础底板凹式防水加强型抗浮锚杆结构,包括自基岩、混凝土垫层、沥青卷材、混凝土防水保护层、锚杆锚固钢筋、注浆管、沥青嵌缝油膏、止水条以及钢筋临时支撑体系,所述混凝土垫层铺设在自基岩上端,所述沥青卷材通过防水涂料粘接在混凝土垫层上端,所述混凝土防水保护层铺设在沥青卷材上端,所述锚杆锚固钢筋下端依次穿过混凝土防水保护层、沥青卷材以及混凝土垫层,且插入自基岩内,所述注浆管下端延伸至自基岩内,所述沥青嵌缝油膏固定在锚杆锚固钢筋环形侧面,所述止水条缠绕在锚杆锚固钢筋环形侧面,且设置在沥青嵌缝油膏下侧,所述钢筋临时支撑体系由抗浮锚杆锚固钢筋锚固钢筋和水平钢筋制作而成。In order to achieve the above purpose, the present invention is achieved through the following technical solutions: the concave waterproof reinforced anti-floating anchor structure of the base plate, including the self-base rock, the concrete cushion, the asphalt coil, the concrete waterproof protective layer, the anchor anchor Reinforcing bars, grouting pipes, asphalt caulking ointment, water stop strips and a temporary reinforcing steel bar support system, the concrete cushion is laid on the upper end of the self-base rock, and the asphalt coil is bonded to the upper end of the concrete cushion by the waterproof coating, so The concrete waterproof protective layer is laid on the upper end of the asphalt membrane, the lower end of the bolt anchoring steel bar passes through the concrete waterproof protective layer, the asphalt membrane and the concrete cushion in sequence, and is inserted into the bedrock, and the lower end of the grouting pipe extends to the self. In the bedrock, the asphalt caulking ointment is fixed on the annular side of the bolt anchored steel bar, the water stop strip is wrapped around the annular side of the bolt anchored steel bar, and is arranged on the lower side of the asphalt caulking ointment, and the steel bar temporarily supports the system It is made of anti-floating anchor anchor reinforcement and horizontal reinforcement.
在一实施例中,所述止水条为BW遇水膨胀止水条,缠绕高度大于100mm,并用水泥钉固定牢固。In one embodiment, the water-stop strip is a BW water-swellable water-stop strip, the winding height is greater than 100mm, and it is firmly fixed with cement nails.
在一实施例中,所述沥青卷材为4mm厚SBS聚酯胎 -25°Ⅱ型改性沥青卷材,且沥青卷材上端铺设卷材加强层。In one embodiment, the asphalt coil is a 4mm thick SBS polyester tire -25° type II modified asphalt coil, and the upper end of the asphalt coil is provided with a coil reinforcement layer.
一种基础底板凹式防水加强型抗浮锚杆结构的施工方法,包括:A construction method for a concave waterproof reinforced anti-floating anchor structure of a foundation floor, comprising:
基础垫层浇筑,锚杆锚固钢筋节点处混凝土预留;The foundation cushion is poured, and the concrete is reserved at the anchorage of the anchor rod;
垫层与锚杆锚固钢筋节点间土层清理;Cleaning the soil layer between the cushion layer and the anchor bolt anchoring steel bar nodes;
混凝土杯型槽施工;Concrete cup groove construction;
缠绕止水条并灌注沥青嵌缝油膏;Wind the waterstop and pour asphalt caulking ointment;
杯型槽顶部锚杆锚固钢筋节点处油膏密封;Grease seal at the top anchor rod anchoring steel bar nodes of the cup groove;
混凝土封闭杯型槽;Concrete closed cup groove;
涂刷水乳型SBS改性沥青防水涂料;Apply water-emulsion SBS modified bitumen waterproof coating;
基层清理,刷冷底子油;Basic cleaning, brushing cold base oil;
铺贴4mm厚SBS聚酯胎 -25°Ⅱ型改性沥青卷材防水层及沥青卷材加强层;Paving 4mm thick SBS polyester tire -25°Type II modified asphalt membrane waterproof layer and asphalt membrane reinforcement layer;
混凝土防水保护层施工;Construction of concrete waterproof protective layer;
对锚杆锚固钢筋锚固钢筋进行弯折;Bending the anchor rod anchoring steel bar;
绑扎钢筋临时支撑体系。Temporary support system for binding steel bars.
本发明的有益效果:本发明的基础底板凹式防水加强型抗浮锚杆结构,因添加了基岩、混凝土垫层、沥青卷材、混凝土防水保护层、锚杆锚固钢筋、注浆管、沥青嵌缝油膏、止水条以及钢筋临时支撑体系,该设计使用方便,通过将锚杆锚固钢筋伸出部进行折弯加工,节约钢材,降低材料成本以及施工时间,又利于绿色施工且防水效果好,解决了传统临时支撑结构,施工时间长,延缓了施工时间,且增加了施工成本,施工难度大,防水效果差的问题,本发明使用方便,节约钢材,降低材料成本以及施工时间,又利于绿色施工且防水效果好。Beneficial effects of the present invention: The concave waterproof and reinforced anti-floating anchor structure of the base plate of the present invention has the addition of bedrock, concrete cushion, asphalt coil, concrete waterproof protective layer, bolt anchoring steel bar, grouting pipe, Asphalt caulking ointment, water stop strips and temporary steel reinforcement system, the design is easy to use, by bending the extension part of the anchor rod anchoring steel bar, it saves steel, reduces material cost and construction time, and is conducive to green construction and waterproofing The effect is good, it solves the problems of traditional temporary support structure, long construction time, delayed construction time, increased construction cost, high construction difficulty and poor waterproof effect, the present invention is convenient to use, saves steel, reduces material cost and construction time, It is also conducive to green construction and has good waterproof effect.
附图说明Description of drawings
通过阅读参照以下附图对非限制性实施例所作的详细描述,本发明的其它特征、目的和优点将会变得更明显:Other features, objects and advantages of the present invention will become more apparent by reading the detailed description of non-limiting embodiments with reference to the following drawings:
图1为本发明基础底板凹式防水加强型抗浮锚杆结构的结构示意图;Fig. 1 is the structural schematic diagram of the concave waterproof reinforced anti-floating anchor rod structure of the foundation base plate of the present invention;
图2为本发明基础底板凹式防水加强型抗浮锚杆结构中锚杆锚固钢筋与钢筋临时支撑体系的结构示意图;Fig. 2 is the structural schematic diagram of the bolt anchoring steel bar and the steel bar temporary support system in the concave waterproof reinforced anti-floating anchor structure of the foundation base plate of the present invention;
图3为本发明基础底板凹式防水加强型抗浮锚杆结构中锚杆锚固钢筋施工的剖面结构示意图3 is a schematic cross-sectional structural diagram of the construction of the anchor rod anchoring steel bar in the concave waterproof reinforced anti-floating anchor rod structure of the foundation floor of the present invention
图中:1-基岩、2-混凝土垫层、3-沥青卷材、4-混凝土防水保护层、5-锚杆锚固钢筋、6-注浆管、7-沥青嵌缝油膏、8-卷材加强层、9-止水条、10-钢筋临时支撑体系。In the picture: 1-bed rock, 2-concrete cushion, 3-asphalt membrane, 4-concrete waterproof protective layer, 5-anchor bolt anchoring steel bar, 6-grouting pipe, 7-asphalt caulking grease, 8- Coil reinforcement layer, 9-waterstop, 10-rebar temporary support system.
具体实施方式Detailed ways
在详细描述实施例之前,应该理解的是,本发明不限于本申请中下文或附图中所描述的详细结构或元件排布。本发明可为其它方式实现的实施例。而且,应当理解,本文所使用的措辞及术语仅仅用作描述用途,不应作限定性解释。本文所使用的“包括”、“包含”、“具有”等类似措辞意为包含其后所列出之事项、其等同物及其它附加事项。特别是,当描述“一个某元件”时,本发明并不限定该元件的数量为一个,也可以包括多个。Before the embodiments are described in detail, it is to be understood that the invention is not limited to the detailed structures or arrangements of elements described herein below or in the accompanying drawings. The invention may be embodied in other ways. Also, it is to be understood that the phraseology and terminology used herein is for the purpose of description and should not be interpreted as limiting. As used herein, "including", "including", "having" and similar expressions are meant to encompass the items listed thereafter, their equivalents, and other additional items. In particular, when "a certain element" is described, the present invention does not limit the number of the element to one, and may include a plurality of elements.
请参阅图1-图3,本发明提供一种技术方案:基础底板凹式防水加强型抗浮锚杆结构,包括自基岩1、混凝土垫层2、沥青卷材3、混凝土防水保护层4、锚杆锚固钢筋5、注浆管6、沥青嵌缝油膏7、止水条9以及钢筋临时支撑体系10,混凝土垫层2铺设在自基岩1上端,沥青卷材3通过防水涂料粘接在混凝土垫层2上端,混凝土防水保护层4铺设在沥青卷材3上端,锚杆锚固钢筋5下端依次穿过混凝土防水保护层4、沥青卷材3以及混凝土垫层2,且插入自基岩1内,注浆管6下端延伸至自基岩1内,沥青嵌缝油膏7固定在锚杆锚固钢筋5环形侧面,止水条9缠绕在锚杆锚固钢筋5环形侧面,且设置在沥青嵌缝油膏7下侧,钢筋临时支撑体系10捆扎在锚杆锚固钢筋5上,把浇筑垫层部位松动的土与石子及杂物清理干净,清理完后泼水使基层土表层湿润,浇筑混凝土垫层2时,做好控制线,保证混凝土层厚度不应小于100mm,在抗浮锚杆锚固钢筋5节点处用普通页岩砖进行围挡,围挡直径为500mm,防止垫层混凝土流入围挡内,混凝土垫层2浇筑完毕后,将抗浮锚杆锚固钢筋5处围挡的页岩砖进行清理,清理完砖后,对垫层与锚杆锚固钢筋5节点间砂土层及锚杆锚固钢筋5上的浆体进行剃凿,剃凿尺寸为上口500mm,下口200mm,高度为400mm,剃凿完后,将垫层上部砂石及时清理干净,锚杆锚固钢筋5节点处砂石及浆体按照要求清理完毕后,将预先加工好的铁皮杯型槽模具,沿锚杆锚固钢筋5顶部钢筋套入锚杆锚固钢筋5节点处,用C15混凝土将铁皮杯型槽模具外侧与砂石间缝隙填实,待混凝土达到强度后,取出模具,铁皮杯型槽模具取出后,用水泥砂浆将杯型槽内部不平处进行收光,检查杯型槽底部是否找平,将BW遇水膨胀止水条9紧密的缠绕与抗浮锚杆锚固钢筋5上,缠绕高度大于100mm,最后用水泥钉固定住止水条9,当抗浮锚杆锚固钢筋5节点处BW遇水膨胀止水条9缠绕完后,应立即将建筑防水沥青嵌缝油膏7灌注于BW遇水膨胀止水条9与锚杆锚固钢筋5之间,灌注建筑防水沥青嵌缝油膏7时,必须将BW遇水膨胀止水条9内灌注密实,不得留有缝隙,第一遍建筑防水沥青嵌缝油膏7灌注完成10分钟后,再进行二遍沥青嵌缝油膏7灌注,保证BW遇水膨胀止水条9与锚杆锚固钢筋5之间的密实性,施工杯型槽顶部锚杆锚固钢筋5节点处用油膏进行密封,油膏密封高度为100mm,待抗浮锚杆锚固钢筋5节点处防水施工完毕后,应立即采用C15混凝土对杯型槽进行封闭,杯型槽混凝土封闭完毕后,应立即用混凝土原浆对杯型槽上口进行收光,凝土收光完后,进行涂刷水乳型SBS改性沥青防水涂料,涂刷水乳型SBS改性沥青防水涂料时,以抗浮锚杆锚固钢筋5为中心,半径大于550mm范围内涂刷,涂刷厚度为1.5mm厚,在基层清理前,应做好隐检验收,基层若高低不平或凹坑较大时,用1:2.5水泥砂浆抹平,基层与管道等相连接的阴角、其他阴阳角等转角处应抹成均匀一致,平整光滑的圆角,圆弧半径不得小于50mm,阴阳角、管根等复杂部位必须特别仔细认真清理,若有油污、铁锈等,应以砂纸、钢丝刷、溶剂等予以清除干净,必须将突出基层表面的异物,起砂和砂浆疙瘩等铲除,用高压空气将尘土杂物等清扫干净,待基层含水率在9%以下时,涂刷基层处理剂冷底子油两道,涂刷应均匀,不露底,等干燥4小时以上至不粘脚后方可进行下道工序,对于阴阳角、施工缝等部位在铺贴卷材之前,先做补强处理,粘贴必须牢固,阴阳角部位用附加卷材粘牢,转角处增加卷材防水层一层,每边≥250mm,铺贴时将卷材自然松铺且无皱折即可,不拉紧,以免影响附加层的质量,火焰的喷嘴距离卷材的间距控制适中,幅宽内加热均匀,以卷材表面熔融至光亮黑色为度,不过分加热卷材,卷材表面热熔后,施工人员应立即滚铺卷材,滚铺时应排除卷材下面的空气,使之平展并粘贴牢固,卷材按100mm进行互相搭接,满足防水规范要求,铺贴卷材时,做到平整顺直,搭接尺寸准确,不扭曲,铺贴锚杆锚固钢筋5处防水卷材时,应将卷材剪一直线豁口,并在锚杆锚固钢筋5四周剪出小三角豁口进行热熔铺贴,卷材层铺贴完后,再在卷材上部增加卷材加强层8,最后浇筑50mm厚C20细石混凝土保护层,浇筑混凝土时,且勿损坏卷材防水层平面,利用各种防水材料的特性,按照先后顺序先在已施工好的混凝土杯型槽内的锚杆锚固钢筋5上缠绕BW遇水膨胀止水条9,并灌注建筑沥青嵌缝油膏7,用混凝土封闭杯型槽并在混凝土表面涂刷水乳型SBS防水涂料,最后大面积铺贴4mm厚防水卷材,将各种防水材料重叠施工,使各种防水材料的特性在施工中达到最佳,避免了抗浮锚杆锚固钢筋5与节点处的混凝土由于毛细孔道现象的发生发展而出现渗漏现象,保证锚杆锚固钢筋5节点处防水达到内外结合、相互补充的效果,从而使锚杆锚固钢筋5节点防水质量符合施工规范要求,最后通过便携式液压弯曲机对锚杆锚固钢筋5进行弯折,弯折角度为90°,且使锚杆锚固钢筋5之间夹角在120°,然后在锚杆锚固钢筋5弯折后的水平部绑扎直径C12或者C14的钢筋杆7,且沿着一个方向布置,以部分主筋充当临时支撑水平结构,组成完整的临时支撑体系,从而使用方便,通过将锚杆锚固钢筋5伸出部进行折弯加工,节约钢材,降低材料成本以及施工时间,又利于绿色施工且防水效果好。Please refer to FIG. 1-FIG. 3, the present invention provides a technical solution: a concave waterproof reinforced anti-floating anchor rod structure of the foundation floor, including a self-base rock 1, a concrete cushion 2, an asphalt coil 3, and a concrete waterproof protective layer 4 , bolt anchoring steel bar 5, grouting pipe 6, asphalt caulking ointment 7, water stop strip 9 and steel temporary support system 10. Connected to the upper end of the concrete cushion 2, the concrete waterproof protective layer 4 is laid on the upper end of the asphalt membrane 3, the lower end of the anchor rod anchoring steel bar 5 passes through the concrete waterproof protection layer 4, the asphalt membrane 3 and the concrete cushion 2 in turn, and is inserted into the self-base In the rock 1, the lower end of the grouting pipe 6 extends from the bedrock 1, the asphalt caulking grease 7 is fixed on the annular side of the bolt anchoring steel bar 5, and the water stop strip 9 is wound around the annular side of the bolt anchoring steel bar 5, and is arranged on the On the lower side of the asphalt caulking paste 7, the temporary reinforcement system 10 is bundled on the anchor rod anchoring reinforcement 5, and the loose soil, stones and sundries in the pouring cushion part are cleaned up. When the concrete cushion layer is 2, make a control line to ensure that the thickness of the concrete layer should not be less than 100mm, and use ordinary shale bricks for the enclosure at the 5 nodes of the anti-floating bolt anchoring steel bar. The diameter of the enclosure is 500mm to prevent the cushion concrete from flowing. In the shortlisted block, after the concrete cushion layer 2 is poured, the shale bricks surrounded by the 5 anti-floating anchor rod anchoring steel bars shall be cleaned. The slurry on the anchor rod 5 is shaved. The size of the chisel is 500mm for the upper port, 200mm for the bottom port, and 400mm for the height. After shaving and chiseling, clean the upper sand and gravel of the cushion in time, and the anchor rod anchors the 5 nodes of the steel rod. After the sand, gravel and slurry are cleaned according to the requirements, the pre-processed iron cup groove mold is inserted along the top of the anchor rod anchoring steel bar 5 into the anchor rod anchorage steel bar 5 node, and the iron cup groove mold is made of C15 concrete. Fill the gap between the outer side and the gravel. After the concrete reaches the strength, take out the mold. After the iron cup groove mold is taken out, use cement mortar to smooth out the unevenness inside the cup groove. Check whether the bottom of the cup groove is leveled. The water-swelling water-stop strip 9 is tightly wound on the anti-floating anchor rod anchoring steel bar 5, and the winding height is greater than 100mm, and finally the water-stopping strip 9 is fixed with cement nails. After the water stop strip 9 is wound, the building waterproof asphalt caulking ointment 7 should be poured between the BW water-swelling water stop strip 9 and the anchor rod anchoring steel bar 5 immediately. Fill the BW water-swellable water-stop strip 9 tightly without leaving any gaps. After the first time of building waterproof asphalt caulking ointment 7 is poured for 10 minutes, the second time of asphalt caulking ointment 7 is poured to ensure that the BW meets the requirements. The compactness between the water-swelling water stop strip 9 and the anchoring steel bar 5, the 5 nodes of the anchoring steel bar at the top of the construction cup groove are sealed with ointment, and the sealing height of the ointment is 100mm. 5 After the waterproof construction at the node is completed, the cup groove should be sealed with C15 concrete immediately. , After the cup-shaped groove concrete is closed, the upper mouth of the cup-shaped groove should be polished with concrete raw slurry immediately. When SBS modified bitumen waterproof coating is used, the anti-floating anchor anchoring steel bar 5 is the center, and the radius is greater than 550mm. The thickness of the coating is 1.5mm thick. When it is uneven or the pit is large, use 1:2.5 cement mortar to smooth it. The corners such as the inner corners and other inner and outer corners connected to the base layer and the pipeline should be plastered into uniform, flat and smooth rounded corners, and the radius of the arc should not be less than 50mm, the yin and yang corners, pipe roots and other complex parts must be cleaned carefully and carefully. If there are oil stains, rust, etc., they should be cleaned with sandpaper, wire brushes, solvents, etc., and foreign objects protruding from the surface of the base must be removed. Sand and mortar lumps, etc. Remove, use high-pressure air to clean up the dust and debris, and when the moisture content of the base layer is below 9%, apply two coats of cold base oil to the base layer treatment agent. The next process can be carried out after the feet. For the yin and yang corners, construction joints and other parts, before laying the coil, do reinforcement treatment, the paste must be firm, the yin and yang corners are firmly glued with additional coils, and the waterproof layer of the coil is added at the corners. One layer, each side ≥ 250mm, when laying, the coil can be laid naturally without wrinkles, without tension, so as not to affect the quality of the additional layer, the distance between the flame nozzle and the coil is moderately controlled, and the width is heated within the width. Evenly, the surface of the coil is melted to bright black, and the coil is not heated too much. After the surface of the coil is hot-melted, the construction personnel should immediately roll the coil. When rolling, the air under the coil should be removed to make it flat and smooth. The sticking is firm, and the coils are overlapped with each other by 100mm to meet the requirements of waterproof specifications. When laying the coils, it should be flat and straight, the overlap size is accurate, and not twisted. The coil should be cut in a straight line, and a small triangular gap should be cut around the anchoring steel bar 5 for hot-melt paving. After the coil layer is paved, add a coil reinforcement layer 8 on the upper part of the coil, and finally pour it. 50mm thick C20 fine stone concrete protective layer, when pouring concrete, do not damage the plane of the membrane waterproof layer, use the characteristics of various waterproof materials, in the order of the anchor rods in the concrete cup grooves that have been constructed Anchor steel bars 5 Wind the BW water-swellable water-stop strip 9 on top, pour the building asphalt caulking ointment 7, seal the cup-shaped groove with concrete and apply the water-emulsion SBS waterproof coating on the concrete surface, and finally pave a large area with 4mm thick waterproof membrane , Overlap construction of various waterproof materials, so that the characteristics of various waterproof materials are optimal in the construction, avoiding the leakage phenomenon of the anti-floating anchor rod anchoring steel bar 5 and the concrete at the node due to the occurrence and development of the capillary channel phenomenon, Ensure that the waterproofing of the 5 nodes of the anchoring steel bar achieves the effect of combining internal and external and complementing each other, so that the waterproof quality of the 5 nodes of the anchoring steel bar meets the requirements of the construction specification. Finally, the anchoring steel bar 5 is bent and bent by a portable hydraulic bending machine. The folding angle is 90°, and the anchor rod is clamped between the anchoring steel bars 5 The angle is 120°, and then the steel bar 7 with a diameter of C12 or C14 is bound at the horizontal part of the anchoring steel bar 5 after bending, and is arranged in one direction, and part of the main bar acts as a temporary support for the horizontal structure, forming a complete temporary support system Therefore, it is convenient to use. By bending the projecting part of the anchoring steel bar 5, the steel material is saved, the material cost and construction time are reduced, and it is also conducive to green construction and has a good waterproof effect.
止水条9为BW遇水膨胀止水条,缠绕高度大于100mm,并用水泥钉固定牢固。The water stop strip 9 is a BW water-swellable water stop strip, the winding height is greater than 100mm, and it is firmly fixed with cement nails.
沥青卷材3为4mm厚SBS聚酯胎 -25°Ⅱ型改性沥青卷材,且沥青卷材3上端铺设卷材加强层8。The asphalt coil 3 is a 4mm thick SBS polyester tire -25° type II modified asphalt coil, and a coil reinforcement layer 8 is laid on the upper end of the asphalt coil 3 .
一种基础底板凹式防水加强型抗浮锚杆结构的施工方法,包括:A construction method for a concave waterproof reinforced anti-floating anchor structure of a foundation floor, comprising:
基础垫层浇筑,锚杆锚固钢筋节点处混凝土预留;The foundation cushion is poured, and the concrete is reserved at the anchorage of the anchor rod;
垫层与锚杆锚固钢筋节点间土层清理;Cleaning the soil layer between the cushion layer and the anchor bolt anchoring steel bar nodes;
混凝土杯型槽施工;Concrete cup groove construction;
缠绕止水条并灌注沥青嵌缝油膏;Wind the waterstop and pour asphalt caulking ointment;
杯型槽顶部锚杆锚固钢筋节点处油膏密封;Grease seal at the top anchor rod anchoring steel bar nodes of the cup groove;
混凝土封闭杯型槽;Concrete closed cup groove;
涂刷水乳型SBS改性沥青防水涂料;Apply water-emulsion SBS modified bitumen waterproof coating;
基层清理,刷冷底子油;Basic cleaning, brushing cold base oil;
铺贴4mm厚SBS聚酯胎 -25°Ⅱ型改性沥青卷材防水层及沥青卷材加强层;Paving 4mm thick SBS polyester tire -25°Type II modified bitumen membrane waterproof layer and bitumen membrane reinforcement layer;
混凝土防水保护层施工;Construction of concrete waterproof protective layer;
对锚杆锚固钢筋锚固钢筋进行弯折;Bending the anchor rod anchoring steel bar;
绑扎钢筋临时支撑体系。Temporary support system for binding steel bars.
本文所描述的概念在不偏离其精神和特性的情况下可以实施成其它形式。所公开的具体实施例应被视为例示性而不是限制性的。因此,本发明的范围是由所附的权利要求,而不是根据之前的这些描述进行确定。在权利要求的字面意义及等同范围内的任何改变都应属于这些权利要求的范围。The concepts described herein may be embodied in other forms without departing from the spirit and characteristics thereof. The specific embodiments disclosed are to be regarded as illustrative and not restrictive. Accordingly, the scope of the invention is to be determined by the appended claims, rather than by the foregoing description. Any changes that come within the literal meaning and equivalency of the claims are intended to fall within the scope of these claims.
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910197021.XA CN110056015A (en) | 2019-03-15 | 2019-03-15 | Concave reinforced anti-floating anchor rod waterproof node structure and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910197021.XA CN110056015A (en) | 2019-03-15 | 2019-03-15 | Concave reinforced anti-floating anchor rod waterproof node structure and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110056015A true CN110056015A (en) | 2019-07-26 |
Family
ID=67316995
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910197021.XA Pending CN110056015A (en) | 2019-03-15 | 2019-03-15 | Concave reinforced anti-floating anchor rod waterproof node structure and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110056015A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110616746A (en) * | 2019-09-18 | 2019-12-27 | 中国五冶集团有限公司 | Be used for waterproof recess mould of anti-floating anchor rod |
CN111519670A (en) * | 2020-05-06 | 2020-08-11 | 无锡锡晟建设有限公司 | Concave reinforced anti-floating anchor rod structure and verticality measuring device thereof |
CN112575743A (en) * | 2020-11-12 | 2021-03-30 | 中国电建集团中南勘测设计研究院有限公司 | Geomembrane anchor seal structure |
CN113863393A (en) * | 2021-10-22 | 2021-12-31 | 上海宝冶建筑装饰有限公司 | Construction method for waterproofing end of anti-floating anchor rod |
CN115182339A (en) * | 2022-08-19 | 2022-10-14 | 中国建筑第八工程局有限公司 | Construction method for anti-floating anchor rod by grouting first and then bending |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202509532U (en) * | 2011-12-22 | 2012-10-31 | 深圳市市政工程总公司 | Multi-rib tension type anti-floating anchor |
CN103422501A (en) * | 2013-03-13 | 2013-12-04 | 中国建筑第四工程局有限公司 | Anti-floating anchor structure in sand layer geology and construction method thereof |
US9657453B1 (en) * | 2015-12-15 | 2017-05-23 | Samjin Steel Ind. Co., Ltd. | Removable ground anchor body using spring |
CN206495241U (en) * | 2017-02-27 | 2017-09-15 | 青岛东捷建设工程有限公司 | A kind of new waterproof construction of anti-float anchor rod |
CN108331031A (en) * | 2018-02-08 | 2018-07-27 | 中建六局土木工程有限公司 | A kind of anti-float anchor rod waterproof construction method |
CN210031925U (en) * | 2019-03-15 | 2020-02-07 | 中建一局集团第五建筑有限公司 | Waterproof strenghthened type anti-floating anchor rod structure of soleplate concave type |
-
2019
- 2019-03-15 CN CN201910197021.XA patent/CN110056015A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202509532U (en) * | 2011-12-22 | 2012-10-31 | 深圳市市政工程总公司 | Multi-rib tension type anti-floating anchor |
CN103422501A (en) * | 2013-03-13 | 2013-12-04 | 中国建筑第四工程局有限公司 | Anti-floating anchor structure in sand layer geology and construction method thereof |
US9657453B1 (en) * | 2015-12-15 | 2017-05-23 | Samjin Steel Ind. Co., Ltd. | Removable ground anchor body using spring |
CN206495241U (en) * | 2017-02-27 | 2017-09-15 | 青岛东捷建设工程有限公司 | A kind of new waterproof construction of anti-float anchor rod |
CN108331031A (en) * | 2018-02-08 | 2018-07-27 | 中建六局土木工程有限公司 | A kind of anti-float anchor rod waterproof construction method |
CN210031925U (en) * | 2019-03-15 | 2020-02-07 | 中建一局集团第五建筑有限公司 | Waterproof strenghthened type anti-floating anchor rod structure of soleplate concave type |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110616746A (en) * | 2019-09-18 | 2019-12-27 | 中国五冶集团有限公司 | Be used for waterproof recess mould of anti-floating anchor rod |
CN110616746B (en) * | 2019-09-18 | 2021-02-09 | 中国五冶集团有限公司 | Be used for waterproof recess mould of anti-floating anchor rod |
CN111519670A (en) * | 2020-05-06 | 2020-08-11 | 无锡锡晟建设有限公司 | Concave reinforced anti-floating anchor rod structure and verticality measuring device thereof |
CN111519670B (en) * | 2020-05-06 | 2021-12-10 | 无锡锡晟建设有限公司 | Verticality measuring device for concave reinforced anti-floating anchor rod structure |
CN112575743A (en) * | 2020-11-12 | 2021-03-30 | 中国电建集团中南勘测设计研究院有限公司 | Geomembrane anchor seal structure |
CN113863393A (en) * | 2021-10-22 | 2021-12-31 | 上海宝冶建筑装饰有限公司 | Construction method for waterproofing end of anti-floating anchor rod |
CN115182339A (en) * | 2022-08-19 | 2022-10-14 | 中国建筑第八工程局有限公司 | Construction method for anti-floating anchor rod by grouting first and then bending |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110056015A (en) | Concave reinforced anti-floating anchor rod waterproof node structure and construction method thereof | |
CN110607809B (en) | Waterproof construction method for basement of building engineering | |
CN201924254U (en) | Novel expansion joint structure for continuously reinforced concrete composite road surface | |
CN207987983U (en) | A kind of waterproof construction being used for underground engineering main body construction seam and post-cast strip | |
CN107190844A (en) | The waterproof and water drainage system and construction method of a kind of basement bottom board and exterior wall | |
CN104404985B (en) | The construction method of basement bottom plate rear pouring tape waterproof construction | |
CN107489167A (en) | A kind of underground pipe gallery socket joint deformation joint structure and its construction method | |
CN110080530A (en) | Severe cold area glazed tiles pitched roof pastes anchor construction method | |
CN108708453A (en) | Basementwaterproofing construction method | |
CN105862928A (en) | Post-cast strip outer wall in-advance water stopping treatment structure and construction process thereof | |
CN105040554A (en) | Garden path structure and paving construction technology thereof | |
CN102587416A (en) | Basement attached lane structure and construction method thereof | |
CN106567554A (en) | Reinforcing construction method of masonry structural building | |
CN207775948U (en) | Pulling-Resistant Anchor Rod root waterproofing node structure | |
CN210031925U (en) | Waterproof strenghthened type anti-floating anchor rod structure of soleplate concave type | |
CN110725340A (en) | Post-cast strip advanced water stop structure and construction method thereof | |
CN115419155A (en) | Construction method of underground garage floor drainage ditch | |
CN206616587U (en) | A kind of underground structrue engineering bottom plate dowel anti-floating sealing structure | |
CN112392157A (en) | Toilet waterproof structure, construction process and protection process thereof | |
CN206174293U (en) | Prefabricated constructional column | |
CN215105439U (en) | New and old underpass links up waterproof construction | |
CN110528593B (en) | Heat-insulation waterproof structure for joint of main body and auxiliary structure top plate of station and construction method | |
CN114215116A (en) | Waterproof construction method for circular truncated cone-shaped groove of basement anti-floating anchor rod end node | |
CN107780442B (en) | High slope surface advanced water stop construction method combined with soil nails | |
CN209397697U (en) | A landscape pool bottom built on both the basement roof and the plain soil layer |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190726 |