SU1273569A1 - Method of sinking mine shafts - Google Patents

Method of sinking mine shafts Download PDF

Info

Publication number
SU1273569A1
SU1273569A1 SU843776813A SU3776813A SU1273569A1 SU 1273569 A1 SU1273569 A1 SU 1273569A1 SU 843776813 A SU843776813 A SU 843776813A SU 3776813 A SU3776813 A SU 3776813A SU 1273569 A1 SU1273569 A1 SU 1273569A1
Authority
SU
USSR - Soviet Union
Prior art keywords
trunk
contour
rock
coal seam
wells
Prior art date
Application number
SU843776813A
Other languages
Russian (ru)
Inventor
Петр Назарович Васильев
Радион Федорович Уманцев
Феликс Михайлович Киржнер
Original Assignee
Производственное Объединение "Якутуголь"
Институт горного дела Севера Якутского филиала СО АН СССР
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Производственное Объединение "Якутуголь", Институт горного дела Севера Якутского филиала СО АН СССР filed Critical Производственное Объединение "Якутуголь"
Priority to SU843776813A priority Critical patent/SU1273569A1/en
Application granted granted Critical
Publication of SU1273569A1 publication Critical patent/SU1273569A1/en

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

1. СПОСОБ ПРОХОДКИ ШАХТНОГО СТВОЛА, включающий крепление ствола путем бурени  по его контуру сопр женных скважин ниже уровн  дна ствола , заполнение этих скважин крепежным материалом и выемку породы, о тличающийс  тем, что, с целью повьшени  безопасности работ за счет вьшода рабочих из забо  ствола при вскрытии угольных месторождений, внутри контура ствола бур т второй р д сопр женных скважин до почвы угольного пласта, после чего угольный пласт в контуре ствола удал ют, заполн ют часть образованной при этом полости твердыми шарами, а выемку породы осуществл ют путем заливки свободного пространства в стволе т желой жидкостью и среза внутреннего породного цилиндра по мере его всплыти , причем после выемки всей породы т желую жидкость выкачивают. 2. Способ ПОП.1, отличаю (Л щийс  тем, что угольный пласт удал ют путем выжигани .1. METHOD OF DRIVING THE MINE STEM, including mounting the barrel by drilling along its contour of adjacent wells below the level of the bottom of the trunk, filling these wells with fixing material and excavating the formation, in order to improve the safety of work due to the height of workers from the trunk when opening coal deposits, a second row of adjacent wells is drilled into the coal seam inside the wellbore contour, after which the coal seam in the wellbore contour is removed, part of the cavity formed is filled with solid balls , and the excavation of the rock is carried out by pouring free space in the barrel with a thick liquid and cutting off the internal rock cylinder as it ascends, and after the excavation of the whole rock, the heavy liquid is pumped out. 2. Method POP.1, distinguished (in general, in that the coal seam is removed by burning.

Description

Фиг.1 12 Изобретение относитс  к горной промьшшенности и может быть использо вано дл  проходки шахтных стволов при вскрытии угольных месторождений. Цель изобретени  - повышение безопасности работ за счет вьгоода рабо чих из забо  ствола при вскрытии угольных месторождений. На фиг.1-4 показан шахтный ствол в разные периоды строительства, вертикальный разрез; на фиг.5-8 - то же вид в плане. Способ проходки шахтных стволов реализуют следующим образом. С дневной поверхности бур т по контуру ствола сопр женные скв.ажины 1 ниже уровн  дна ствола. При этом угольный пласт 2 перебуривают на глубину, необходимую дл  последующего строитель:ства там зумпфа. Дл  контактировани  скважин одна с другой на буровьтх станках примен ют специальное направл ющее устройство, которое использует ранее пробуренную скважину как направл ющую. По мере бурени  скважин их полости бетонируют с установкойарматуры . Затем аналогичным образом бур т второй р д скважин 3 контура ствола до почвы угольного пласта 2, обнажа  внутренний породный цилиндр 4 по боковой его поверхности. В образовавшуюс  между цилиндром 4 и р дом забетонированных скважин 1 полость щель 5 помещают диафрагмы 6 на глубину от поверхности до кровли пласта 2, раздел   щель 5 на две части, после чего уголь, оконтуренный р дом скважин 3, подлшгают и выжигают. Дл  этой цели через одну часть полости Щели 5 подают свежий воздух, а через другз о его отсасывают. Удаление угл  в замкнутом контуре может быть произведено и другими способами физическо9 го, физико-химического, химического и микробиологического воздействи  на угольный массив, позвол кнцими переводить уголь из твердого состо ни  в текучее транспортабельное в виде суспензий, жидкости, газа. По мере удалени  угл  в образующие- ; с  пустоты опускают твердые шары 7,выполненные , например, из железобетона дл  предупреждени  полного опускани  породного цилиндра 4 на почву пласта 2. После выгорани  угл  все имеющиес  пустоты вокруг цилиндра 4 заполн ют т желой жидкостью 8,. имеющей объемный вес, превышакнций средний объемный вес породного цилиндра 4. Так, при объемном весе породного цилиндра 2,5-3 т/м может быть применена жидкость с объемным весом в 3,2-3,5 т/м, В качестве такой жидкости может выступать суспензи  с ут желител ми из ферросилици  или . аленита, объемный вес которых равен 3-3,5 т/м. Породный цилиндр 4, имеющий меньший объемный вес, всплывает. Его верхнюю часть, выступающую над поверхностью, периодически срезают с помощью средств механизации (бульдозерами , пилами) или с помощью буровзрывных работ. По мере удалени  выступающей части, цилиндр 4 посто нно всплывает, а в ствол добавл ют т желую жидкость 8 до полного удалени  из ствола породного цилиндра 4. Чтобы т желые частицы ут желител  не выпадали в осадок, в полость - щель 5 опускают погружной насос 9, который создает циркул цию т желой жидкости В. После полного удалени  породного цилиндра 4 т желую жидкость 8 откачивают из ствола дп  повторного использовани . Ствол, таким образом, готов к оборудованию и эксплуатации.Fig.1 12 The invention relates to the mining industry and can be used to drill shafts when opening coal deposits. The purpose of the invention is to increase the safety of work at the expense of working from the borehole when opening coal deposits. Figure 1-4 shows the shaft shaft in different periods of construction, a vertical section; Fig.5-8 - the same view in the plan. The method of driving shafts implemented as follows. From the day surface, the wellbores 1 adjoining along the contour of the trunk are below the level of the bottom of the trunk. At the same time, coal seam 2 is re-drilled to the depth necessary for the subsequent construction: sump there. For contacting wells with each other on a drilling machine, a special guide device is used, which uses a previously drilled well as a guide. As wells are drilled, their cavities are concreted with the installation of the fitting. Then, in a similar way, a second row of wells 3 contours of the trunk are drilled to the soil of the coal seam 2, exposing the internal rock cylinder 4 along its lateral surface. A cavity 5 formed between cylinder 4 and a row of concrete wells 1, cavity 5 places diaphragms 6 to a depth from the surface to the top of formation 2, dividing slot 5 into two parts, after which coal, outlined by a series of wells 3, is burned out and burned out. For this purpose, fresh air is supplied through one part of the cavity of the Gap 5, and through it is sucked off. The removal of coal in a closed circuit can be made by other methods of physical, physicochemical, chemical, and microbiological effects on the coal mass, allowing the coal to transform coal from a solid state into a transportable fluid in the form of suspensions, liquid, gas. As the coal is removed to form-; From the void, solid balls 7, made, for example, of reinforced concrete, are lowered to prevent the rock cylinder 4 from being completely lowered onto the soil of formation 2. After coal burnout, all existing voids around cylinder 4 are filled with heavy liquid 8. having a volume weight exceeding the average volume weight of the rock cylinder 4. Thus, with a volume weight of the rock cylinder 2.5-3 t / m, a liquid with a volume weight of 3.2-3.5 t / m can be used. As such a liquid suspension may come from the ut gels of ferrosilicon or. alenite, the volumetric weight of which is 3-3.5 t / m. Breed cylinder 4, having a lower volumetric weight, floats. Its upper part, which protrudes above the surface, is periodically cut by means of mechanization (by bulldozers, saws) or by means of blasting. As the protruding part is removed, cylinder 4 constantly floats, and heavy liquid 8 is added to the barrel until the rock cylinder 4 is completely removed from the barrel. In order to prevent heavy particles of air from settling out, the submersible pump is lowered into the cavity 5 which creates a circulation of heavy fluid B. After complete removal of the rock cylinder 4, the heavy fluid 8 is pumped out of the barrel dp reuse. The barrel, therefore, is ready for equipment and operation.

zz

vv

::

//у// at

:1ШШШ|: 1ShShSh |

Фиг. 2FIG. 2

Фиг,3FIG 3

г. year

Claims (2)

1. СПОСОБ ПРОХОДКИ ШАХТНОГО СТВОЛА, включающий крепление ствола путем бурения по его контуру сопряженных скважин ниже уровня дна ствола, заполнение этих скважин крепеж личающийся тем, что, с целью повышения безопасности работ за счет вывода рабочих из забоя ствола при вскрытии угольных месторождений, внутри контура ствола бурят второй ряд сопряженных скважин до почвы угольного пласта, после чего угольный пласт в контуре ствола удаляют, заполняют часть образованной при этом полости твердыми шарами, а выемку породы осуществляют путем заливки свободного пространства в стволе тяжелой жидкостью и среза внутреннего породного цилиндра по мере его всплытия , причем после выемки всей породы тяжелую жидкость выкачивают.1. METHOD FOR DRIVING A SHAFT SHAFT, including fixing the trunk by drilling conjugate wells along its contour below the level of the bottom of the trunk, filling these wells with fasteners, characterized in that, in order to increase the safety of work by removing workers from the bottom of the trunk when opening coal deposits, inside the contour the second row of conjugate wells is drilled to the soil of the coal seam, after which the coal seam in the well contour is removed, part of the cavity formed in this case is filled with hard balls, and the rock is excavated by filling ki free space in the trunk and a heavy fluid cutoff inner cylinder rock as his ascent, and after the recess the whole rock heavy liquid pumped. 2. Способ поп.1, отличающийся тем, что угольный пласт2. The method of pop. 1, characterized in that the coal seam
SU843776813A 1984-08-02 1984-08-02 Method of sinking mine shafts SU1273569A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU843776813A SU1273569A1 (en) 1984-08-02 1984-08-02 Method of sinking mine shafts

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU843776813A SU1273569A1 (en) 1984-08-02 1984-08-02 Method of sinking mine shafts

Publications (1)

Publication Number Publication Date
SU1273569A1 true SU1273569A1 (en) 1986-11-30

Family

ID=21133173

Family Applications (1)

Application Number Title Priority Date Filing Date
SU843776813A SU1273569A1 (en) 1984-08-02 1984-08-02 Method of sinking mine shafts

Country Status (1)

Country Link
SU (1) SU1273569A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Патент US № 4230368, кл. Е 21 С 4/04, 1979. Авторское свидетельство СССР № 1117406, кл. Е 21 D 1/00, 1983. *

Similar Documents

Publication Publication Date Title
CA1123726A (en) Explosive fracturing of deep rock
US4488834A (en) Method for using salt deposits for storage
SU1273569A1 (en) Method of sinking mine shafts
RU2044998C1 (en) Method for rock blasting in open pit
US3999803A (en) In situ leaching of explosively fractured ore bodies
RU2054530C1 (en) Design of underground multihole well, method for its construction and method for its operation
SU1624155A1 (en) Method of mining steep ore deposits
SU740939A1 (en) Method of working mineral deposits by subterranean leaching in blocks
US1394192A (en) Process of drilling wells
SU898080A1 (en) Mine shaft sinking method
RU94026329A (en) Method for mining of mineral deposits and superstructure for its embodiment
SU1696733A1 (en) Method of prevention of rock and gas outbursts in driving openings
SU877031A1 (en) Method of constructing a vertical shaft
RU1789445C (en) Method for constructing underground cavities
SU1244239A1 (en) Method of consolidating a rock body
RU2096617C1 (en) Method for development of mineral deposits
SU1469027A1 (en) Method of working a pit
SU1684496A1 (en) Method for working ore bodies
SU1629566A1 (en) Method of seam-wise methane drainage
SU1546640A1 (en) Method of removing materials from underground formations
RU2077674C1 (en) Method for finishing open-pits
SU1278446A1 (en) Method of constructing geotechnological wells
SU1710763A1 (en) Method of sinking vertical shaft siding
SU1747702A1 (en) Method of sinking mine shafts