SU1165790A1 - Method of enhancing stability of excavation working - Google Patents

Method of enhancing stability of excavation working Download PDF

Info

Publication number
SU1165790A1
SU1165790A1 SU823522200A SU3522200A SU1165790A1 SU 1165790 A1 SU1165790 A1 SU 1165790A1 SU 823522200 A SU823522200 A SU 823522200A SU 3522200 A SU3522200 A SU 3522200A SU 1165790 A1 SU1165790 A1 SU 1165790A1
Authority
SU
USSR - Soviet Union
Prior art keywords
belt
roof
excavation
lava
rocks
Prior art date
Application number
SU823522200A
Other languages
Russian (ru)
Inventor
Stanislav S Kvon
Pavel F Lukyanov
Petr V Egorov
Andrej V Brajtsev
Evgenij V Ignatov
Original Assignee
Kuzbassk Polt Inst
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kuzbassk Polt Inst filed Critical Kuzbassk Polt Inst
Priority to SU823522200A priority Critical patent/SU1165790A1/en
Application granted granted Critical
Publication of SU1165790A1 publication Critical patent/SU1165790A1/en

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Description

Изобретение относится к горнодобывающей промышленности и может быть использовано при подземной разработке месторождений полезных ископаемых, залегающих, пластами малой и средней мощности при труднообрушаемых кровлях.The invention relates to the mining industry and can be used in the underground mining of mineral deposits, the underlying, layers of small and medium power with hard to destroy roofs.

Цель изобретения - снижение нагрузки на крепь выработки от зависающей консоли пород кровли и уменьшение расхода бетонного раствора.The purpose of the invention is to reduce the load on the lining of production from the hanging console rocks of the roof and reducing the consumption of concrete solution.

На фиг. 1 показана система раз-; работки · с. сохраняемой' после прохода лавы выемочной выработкой, план4, на фиг,2 - разрез А-А на фиг.1*, на фиг.3 - разрез Б-Б на фиг. 1.FIG. 1 shows a system of; work · s. preserved 'after the passage of lava by excavation production, plan 4 , fig 2, section aa-a in figure 1 *, figure 3 - section bb in fig. one.

Система разработки содержит вы- . емочную выработку 1, сохраняемую после прохода лавы на границе массив полезного ископаемого - выработанное пространство, лаву 2, создаваемый до подхода лавы пояс 3 упрочненных пород, шпуры 4 для введения упрочняющих растворов, насосную установку 5. для закачивания упрочняющего раствора, жёсткую крепь 6, секции 7 механизированной крепи со снятым ограждением и оборудованные выдвижными козырьками 8, зону 9 необрушенных пород не-’The development system contains you-. capacitive production 1, saved after the passage of lava on the border of the mineral massif - the developed space, lava 2, created before the approach of the lava belt 3 hardened rocks, bore-holes 4 for the introduction of reinforcing solutions, pump installation 5. for injection of reinforcing solution, rigid lining 6, section 7 mechanized roof supports with the fencing removed and equipped with retractable visors 8, zone 9 unbroken non- 'rocks

«к» 7."To" 7.

11657901165790

А-АAa

Фиг.ЗFig.Z

Claims (1)

СПОСОБ ПОВЫШЕНИЯ УСТОЙЧИВОСТИ ВЫЕМОЧНОЙ ВЫРАБОТКИ, включающий поддержание выработки на границе массив полезного ископаемого выработанное пространство при труднообрушаемых кровлях, упрочнение окружающих выработку пород методом нагнетания упрочняющего раствора отличающийся тем, что, с целью снижения нагрузки на крепь выработки от зависающей консоли пород кровли и уменьшения расхода бетонного раствора, упрочнение пород выработки производят до подхода очистного забоя через расстояние, равное шагу обрушения основной кровли в виде поясов, при этом после пересечения лавой пояса в местах выемки пласта пород под поясом устанавливают жесткое крепление.METHOD OF INCREASING THE STABILITY OF THE EXTRACTIVE EXTRACT, including maintaining mining at the border of the mineral massif developed space in hard-to-damage roofs, hardening the surrounding rock formations by pumping reinforcement mortar, in order to reduce the load on the roof structure of the suspended concrete , the hardening of the production rocks is carried out before the approach of the cleaning face through a distance equal to the step of collapse of the main roof in the form of s, while after the crossing zone in places lava recess formation rock below the belt mounted stiffener. ЗУ „,1165790Storage device „1165790 1165790 21165790 2 посредственной кровли, пояса 10 упрочненных пород, воспринимающие нагрузку консоли основной кровли, линию обрушения основной кровли 11.mediocre roof, belt 10 reinforced rocks, perceiving the load of the cantilever of the main roof, line of collapse of the main roof 11. 5 - В выемочной выработке 1 до подхода лавы 2 через расстояния, равные шагу обрушения основной кровли пласта, производят комплекс работ по созданию пояса 3 упрочненных по10 род по контуру выработки. Для этого бурят шпуры 4, через которые при помощи насосной установки 5 в окружающий выработку массив нагнетают упрочняющий раствор. После 15 . прохода лавы для сохранения несущей способности упрочненного пояса пород в месте разрыва пояса после выемки пласта полезного ископаемого устанавливают жесткую крепь 6.5 - In excavation development 1 before the approach of lava 2 through distances equal to the collapse of the main roof of the reservoir, a complex of works is carried out to create a belt 3 of reinforced 10 along the contour of the excavation. For this, boreholes 4 are drilled through which, using a pumping unit 5, a reinforcement solution is injected into the massif surrounding the production. After 15. the passage of lava to maintain the bearing capacity of the hardened belt of rocks in the place of the rupture of the belt after excavation of the mineral layer establish a rigid lining 6. 20 Жесткую крепь устанавливают из-под секций механизированной крепи 7 со снятым, ограждением, оборудованных для обеспечения безопасности работ выдвижными козырьками 8.20 Hard roofing is installed from under the sections of mechanized roof supports 7 with the fencing removed, equipped to provide work safety with retractable visors 8. Предложенный способ позволяет уменьшить расход упрочняющего раствора и снизить трудоемкость поддержания выемочной выработки на 30 границе массив полезного ископаемого выработанное пространство за счет повышения ее устойчивости.The proposed method allows to reduce the consumption of the hardening solution and reduce the complexity of maintaining excavation production at the 30th border of the mineral array, the developed space by increasing its stability. . 1. one
SU823522200A 1982-12-16 1982-12-16 Method of enhancing stability of excavation working SU1165790A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU823522200A SU1165790A1 (en) 1982-12-16 1982-12-16 Method of enhancing stability of excavation working

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU823522200A SU1165790A1 (en) 1982-12-16 1982-12-16 Method of enhancing stability of excavation working

Publications (1)

Publication Number Publication Date
SU1165790A1 true SU1165790A1 (en) 1985-07-07

Family

ID=21039280

Family Applications (1)

Application Number Title Priority Date Filing Date
SU823522200A SU1165790A1 (en) 1982-12-16 1982-12-16 Method of enhancing stability of excavation working

Country Status (1)

Country Link
SU (1) SU1165790A1 (en)

Similar Documents

Publication Publication Date Title
RU2287666C2 (en) Method for controlling usage of accompanying products from underground zones
CN113175325B (en) Coal and intergrown sandstone type uranium ore coordinated mining method based on key layer protection
CN102352769A (en) Integrated mining method for commonly mining coal and gas of high mine
CN114837663B (en) Construction method for improving recovery rate of fault waterproof coal pillar through ground pre-grouting
CN106150502A (en) The method of coal column group is left in a kind of multistage ladder type construction residual exploiting field of filling second mining
SU1165790A1 (en) Method of enhancing stability of excavation working
RU2405108C1 (en) Method of mining thick steep deposits of unstable ores
US3026096A (en) Methods for controlling underground water
Bell Salt and subsidence in Cheshire, England
CN112879010B (en) Foundation construction method for municipal engineering
CN114673502A (en) Multi-mode disaster chain type treatment method based on bottom plate rock roadway
CN112593938A (en) Intelligent mining-based large-section roadway prefabricated wall body coal-pillar-free mining method
RU2200840C2 (en) Process of development of gently dipping and inclined coal formations with use of cleaning powered complexes
SU881331A1 (en) Method of constructing shallow-depth tunnel in unsolid rock
RU2107818C1 (en) Method for development of flat and inclined seams of minerals
CN113107579B (en) Directional long drilling combined bottom plate cross drilling stereoscopic gas extraction method
RU2069268C1 (en) Method for control of rock pressure in extraction of mineral beds at large depths
RU2536514C1 (en) Chamber method of mining heavy, valuable, comminuted ore deposits
CN208280956U (en) To waste fill oper cylinler shallow-hole shrinkage mining mineral building in one kind
SU1795100A1 (en) Method for mining thick steeply dipping coal seams
RU2039259C1 (en) Method for drainage of stoping block
RU2127367C1 (en) Method for protecting soil from pollution with mine water
SU1754906A1 (en) Method for degassing underworked coal measures
RU2065038C1 (en) Method for increasing stability of roof rock
RU2034991C1 (en) Method of suppressing dynamic effects at developing coal seams