SU1006844A1 - Pipe-line construction method - Google Patents

Pipe-line construction method Download PDF

Info

Publication number
SU1006844A1
SU1006844A1 SU813370622A SU3370622A SU1006844A1 SU 1006844 A1 SU1006844 A1 SU 1006844A1 SU 813370622 A SU813370622 A SU 813370622A SU 3370622 A SU3370622 A SU 3370622A SU 1006844 A1 SU1006844 A1 SU 1006844A1
Authority
SU
USSR - Soviet Union
Prior art keywords
cleaning
testing
pipeline
cavity
soil
Prior art date
Application number
SU813370622A
Other languages
Russian (ru)
Inventor
Анатолий Павлович Сажнев
Валерий Адрикович Шукаев
Сергей Павлович Гурьяшов
Николай Павлович Васильев
Ирина Николаевна Кузьмина
Вадим Георгиевич Шаронов
Original Assignee
Sazhnev Anatolij P
Shukaev Valerij A
Guryashov Sergej P
Vasilev Nikolaj P
Kuzmina Irina N
Sharonov Vadim G
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sazhnev Anatolij P, Shukaev Valerij A, Guryashov Sergej P, Vasilev Nikolaj P, Kuzmina Irina N, Sharonov Vadim G filed Critical Sazhnev Anatolij P
Priority to SU813370622A priority Critical patent/SU1006844A1/en
Application granted granted Critical
Publication of SU1006844A1 publication Critical patent/SU1006844A1/en

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

1. СПОСОБ СООРУЖЕНИЯ МАГИСТРАЛЬНОГО ТРУБОПРОВОДА, заключающийс  в отрывке траншеи в обводн емых грунтах, монтаже и укладке в нее трубопровода, его закреплении от всплыти  установкой анкеров на откосах траншеи, балластировке засыпкой грунта, очистке полости поршн ми и испытании, отличающийс  тем, что, с целью сокращени  срока строительства трубопровода путем обеспечени  возможности совмещени  во времени операции по его очистке с операцией по закреплению его анкерами или опережени  этой операции, последнюю ведут с расстановкой анкеров гнездами без изменени  их общего количества и с расположением гнезд одно от другого на расчетных рассто ни х по длине трубопровода, а балластировку трубопровода засыпкой грунта ведут в два этапа, на первом из которых грунтом засыпают трубопровод на участках между гнездами анкеров дл  исключени  подвижки трубопровода при его очистке. 2. Способ по п. 1, отличающийс  тем, что, с целью сокращени  объема земл ных работ S при отрывке траншеи и балластировке засыпкой грунта, траншею на расчетных рас (Л сто ни х между гнездами анкеров, выполн ют безоткосной. t ,J1. METHOD OF CONSTRUCTION OF THE MAIN PIPELINE, which consists in extracting a trench in watering soil, installing and installing a pipeline into it, fixing it from floating up by installing anchors on the slopes of the trench, ballasting backfill, cleaning the cavity with pistons and testing, distinguishing threads, pulverizing the soil, cleaning the cavity with pistons and testing, distinguishing threads, plastering the ground, cleaning the cavity with pistons and testing, distinguishing threads, pulverizing the soil, cleaning the cavity with pistons and testing, distinguishing threads, plastering the ground, cleaning the cavity with pistons and testing, distinguishing threads, pulverizing the soil, cleaning the cavity with pistons and testing, distinguishing threads, plastering the ground, cleaning the cavity with pistons and testing, distinguishing themes, plastering the ground, cleaning the cavity with pistons and testing, distinguishing themes, plastering the ground, cleaning the cavity with pistons and testing, distinguishing threads, pulverizing the soil, cleaning the cavity with pistons and testing, distinguishing themes, piston cleaning and testing, cleaning the piston and testing the cavity, differing themes, piston cleaning and testing, cleaning the piston and testing the cavity. in order to shorten the construction period of the pipeline by providing the possibility of combining in time the operation of cleaning it with the operation of fixing it with anchors or advancing this operation, the latter is carried out with the arrangement of anchors Ditch nests without changing their total number and with the location of the nests from one another to the calculated distances along the pipeline, and ballasting the pipeline by filling up the soil is carried out in two stages, in the first of which the pipeline is filled up with soil in sections between the anchor sockets to prevent movement of the pipeline clean it up. 2. The method according to claim 1, characterized in that, in order to reduce the volume of earthworks S, when taking a trench and ballasting by filling the soil, a trench for the calculated races (L = 0 between the anchors' slots) is made dead-free. T, J

Description

Изобретение относитс  к строительству и может найти п|эименение при сооружении « агистрального трубопровода, преимущественно , в обводненных грунтах. Известен способ сооружени  магистрального трубопровода, заключающийс  в монтаже на берме и укладке на дно транщеи упругим изгибанием трубных плетей больщей длины с образованием расчетных зазоров между их концами, первом этапе засыпки трубопровода на участках между концами плетей с защемлением плетей в грунте, раст гивании концов дл  выбора зазоров нагреванием этих концов, их сварке, втором этапе засыпкки трубопровода на стыках плетей, очистке порщн ми и испытании 1. Однако, предусматрива  двухэтапную засыпку трубопровода по участкам, способ не может быть применен дл  сооружени  трубопровода в обводненных грунтах, поскольку не св зан с закреплением трубопровода от всплыти . Наиболее близким техническим рещением к изобретению  вл етс  способ сооружени  магистрального трубопровода, заключающийс  в отрывке транщеи, монтаже и укладке в нее трубопровода, его закреплеНИИ от всплыти  установкой анкеров на откосах трайщеи, балластировке засыпкой грунта, очистке полости поршн ми и испытании 2. Недостатком известного технического рещени   вл етс  невозможность приступить к очистке трубопровода порщн ми до засыпки трубопровода по услови м техники безопасности, в результате чего сроки строительства трубопровода, особенно в обводненных грунтах, остаютс  больщими. Целью изобретени   вл етс  сокращение срока строительства трубопровода в обводненных грунтах путем обеспечени  возможности совмещени  -во времени операции по очистке трубопровода с операцией по закреплению его анкерами или опережени  этой операции. Цель достигаетс  тем, что согласно способу сооружени  магистрального трубопровода закрепление его анкерами ведут с расстановкой анкеров гнездами без изменени  их общего количества и с расположением гнезд одно от другого на расчетных рассто ни х по длине трубопровода, а балластировку трубопровода засыпкой грунта ве442 дут в два этапа, на первом из которых грунтом засыпают трубопровод на участках между гнездами анкеров дл  исключени  подвижки трубопровода при его очистке. С целью сокращени  объема земл ных работ при отрывке тракщеи и балластировке засыпкой грунта, транщею на расчетных рассто ни х между гнездами анкеров выполн ют безоткосной. На чертеже изображен участок сооружаемого трубопровода, вид в плане. В соответствии со способом сооружени  магистрального трубопровода отрывают транщею 1 переменного профил , монтируют и укладывают в нее трубопровод 2, его закрепл ют от всплыти  установкой анкеров 3 на откосах 4 транщеи 2, балластируют засыпкой грунта 5, очищают внутреннюю полость пропуском порщней и испытывают водой или газом на прочность и герметичность . При этом закрепление трубопровода анкерами 3 ведут с расстановкой их гнездами 6 без изменени  их общего количества и с расположением гнезд 6 одно от другого на расчетных рассто ни х А по длине трубопровода, а балластировку трубопровода засыпкой грунта 5 ведут в два этапа . На первом этапе грунтом засыпают трубопровод на участках Б между гнездами б анкеров дл  исключени  подвижки трубопровода при его очистке порщн ми и обеспечивают тем самым возможность производить очистку до закреплени  трубопровода анкерами или одновременно с закреплением . В результате этого закрепление анкерами может быть при необходимости отодвинуто по времени и не преп тствует подготовке к испытани м. Второй этап засыпки производитс  после заверщени  установки анкеров и сводитс  к засыпке участков трубопровода в гнездах 6. Сосредоточение анкеров в гнездах способствует сокращеению объема земл ных работ, поскольку откосной транще  необходима только в местах гнезд. Таким образом, благодар  выполнению балластировки трубопровода засыпкой грунта в два этапа обеспечиваетс  возможность совмещени  двух операций строительства и даже опережени , что, в свою очередь, способствует сокращению срока строительства. Также обеспечиваетс  сокращение количества землеройной техники.The invention relates to the construction and may find a name in the construction of the main pipeline, mainly in flooded soils. There is a method of constructing a trunk pipeline, which consists of mounting on a berm and laying at the bottom of a trench by elastic bending of pipe lashes of greater length with the formation of design gaps between their ends, the first stage of backfilling of the pipeline in areas between the ends of the lashes, pinching the lashes in the ground, stretching the ends for selection gaps by heating these ends, their welding, the second stage of backfilling of the pipeline at the joints of lashes, cleaning with pores and testing 1. However, a two-stage filling of the pipeline over the section Am, the method cannot be applied to construct a pipeline in flooded soils, since it is not associated with securing the pipeline from floating up. The closest technical solution to the invention is the method of constructing the trunk pipeline, which consists of a passage fragment, installation and installation of the pipeline into it, securing it from ascent by installing anchors on the slopes, ballasting backfill, testing the piston cavity and testing 2. A disadvantage of the known technical The solution is the inability to proceed with cleaning the pipeline with powder before filling the pipeline under the terms of safety, resulting in Water, especially in flooded soils, remains high. The aim of the invention is to reduce the construction time of the pipeline in the flooded soils by providing the possibility of combining the operation of cleaning the pipeline with the operation of securing it with anchors or advancing this operation. The goal is achieved by the fact that according to the method of construction of the main pipeline, fastening it with anchors is carried out by placing the anchors in the sockets without changing their total number and placing the sockets one from another at the calculated distances along the pipeline, and the ballasting of the pipeline by filling the soil 442 is done in two stages, in the first of which, the pipeline is filled up with soil in the areas between the nests of the anchors to prevent movement of the pipeline during its cleaning. In order to reduce the volume of earthworks, when extracting the ballast and ballasting, filling the soil with a trench for the calculated distances between the anchors' slots is performed without dead-bars. The drawing shows a section of the pipeline being constructed, plan view. In accordance with the method of construction of the main pipeline, they tear off the transverse 1 of the variable profile, assemble and stack the pipeline 2 into it, fix it up from the ascent by installing anchors 3 on the slopes 4 of the trunk 2, ballast it with filling of soil 5, clean the internal cavity by letting passages and test it with water or gas on durability and tightness. In this case, the fastening of the pipeline with anchors 3 is carried out with their nests 6 without changing their total number and with the location of the sockets 6 one from another for the calculated distances A along the length of the pipeline, and the ballasting of the pipeline is filled with soil 5 in two stages. At the first stage, the pipeline is filled up with soil in sections B between the nests of the anchor b to prevent the pipeline from moving during cleaning with powder and thus provide the opportunity to perform cleaning before the pipeline is fixed with anchors or simultaneously with fixing. As a result, securing with anchors can, if necessary, be postponed in time and does not interfere with preparation for testing. The second stage of backfilling is done after the installation of the anchors is completed and reduces to filling the pipeline sections in the sockets 6. Concentrating the anchors in the sockets reduces the amount of earthworks, since a sloping trench is needed only in the nest areas. Thus, by performing ballasting of the pipeline by filling the soil in two stages, it is possible to combine the two construction operations and even advance them, which, in turn, contributes to the shortening of the construction period. A reduction in the number of earthmoving equipment is also provided.

Claims (2)

1. СПОСОБ СООРУЖЕНИЯ МАГИСТРАЛЬНОГО ТРУБОПРОВОДА, заключающийся в отрывке траншеи в обводняемых грунтах, монтаже и укладке в нее трубопровода, его закреплении от всплытия установкой анкеров на откосах траншеи, балластировке засыпкой грунта, очистке по лости поршнями и испытании, отличающийся тем, что, с целью сокращения срока строительства трубопровода путем обеспечения возможности совмещения во времени операции по его очистке с операцией по закреплению его анкерами или опережения этой операции, последнюю ведут с расстановкой анкеров гнездами без изменения их общего количества и с расположением гнезд одно от другого на расчетных расстояниях по длине трубопровода, а балластировку трубопровода засыпкой грунта ведут в два этапа, на первом из которых грунтом засыпают трубопровод на участках между гнездами анкеров для исключения подвижки трубопровода при его очистке.1. METHOD FOR STRUCTURING A MAIN PIPELINE, which consists in tearing a trench in irrigated soils, installing and laying a pipeline in it, securing it from surfacing by installing anchors on the slopes of the trench, ballasting by filling the soil, cleaning the cavity with pistons and testing, characterized in that reduction of the pipeline construction period by providing the possibility of combining in time the operation of cleaning it with the operation of securing it with anchors or anticipating this operation, the latter being carried out with the placement of anchors nezdami without changing their total number and arrangement of slots from one another on the calculated distances along the pipe, and ballasting backfilling pipeline soil is carried out in two stages, the first of which soil is filled conduit in areas between the sockets anchors to avoid pipeline advances during its purification. 2. Способ по π. 1, отличающийся тем, что, с целью сокращения объема земляных работ при отрывке траншеи и балластировке засыпкой грунта, траншею на расчетных расстояниях между гнездами анкеров, выполняют безоткосной.2. The method according to π. 1, characterized in that, in order to reduce the amount of excavation work when excavating the trench and ballasting by filling the soil, the trench at the estimated distances between the anchor nests, perform bezkosno.
SU813370622A 1981-12-24 1981-12-24 Pipe-line construction method SU1006844A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU813370622A SU1006844A1 (en) 1981-12-24 1981-12-24 Pipe-line construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU813370622A SU1006844A1 (en) 1981-12-24 1981-12-24 Pipe-line construction method

Publications (1)

Publication Number Publication Date
SU1006844A1 true SU1006844A1 (en) 1983-03-23

Family

ID=20988322

Family Applications (1)

Application Number Title Priority Date Filing Date
SU813370622A SU1006844A1 (en) 1981-12-24 1981-12-24 Pipe-line construction method

Country Status (1)

Country Link
SU (1) SU1006844A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Авторское свидетельство СССР по за вке № 2965016, кл. F 16 L 1/00, 1980. 2. Зиневич А. М и др. Технологи и организаци строительства магистральных трубопроводов больших диаметров. М., «Недра, 1979, с. 285-288 (прототип). *

Similar Documents

Publication Publication Date Title
KR100952608B1 (en) Concrete pipe structure
JPH04179726A (en) Wall member in simplified underground continuous wall construction method and simplified underground continuous wall construction method using the same
SU1006844A1 (en) Pipe-line construction method
JP2013113010A (en) Connecting fitting for u-shaped groove and pipe, and vertical drainage method for slope using the same
JPH0828195A (en) Lining of tunnel
KR20050112893A (en) Method of drain construction for basement
SU821647A1 (en) Method of constructing horizontal closed drain system
SU1668548A1 (en) Arena construction method
RU2024687C1 (en) Method for construction of systems for joint drainage of rain and sewage water
SU1458482A1 (en) Canal construction method
SU1651004A1 (en) Method of laying subsurface pipelines
RU2046883C1 (en) Method for erection of dismountable assembled wall in soil
JPH07127051A (en) Construction and erecting method for reinforcement cage for continuous underground wall execution
JPH0447246Y2 (en)
RU2176758C1 (en) Method of laying preliminarily ballasted pipe line in flooded sections
KR100637048B1 (en) Concrete fume pipe for water and sewage pipe in civil works
SU1372009A1 (en) Method of constructing enclosed horizontal pipeline
SU1135856A1 (en) Subterranean structure
JPH0447247Y2 (en)
KR100465921B1 (en) Reinforcement device for sewage pipe safety in civil engineering and road construction
SU1191519A1 (en) Method of constructing tubular hydraulic structures on sagging soils
SU881188A1 (en) Trenchless method of plastic drainage construction
JPH06287970A (en) Construction method for retaining wall block installation, and retaining wall block
SU1664964A1 (en) Method for constructing drainage system
KR0178293B1 (en) Under ground water drainage device

Legal Events

Date Code Title Description
REG Reference to a code of a succession state

Ref country code: RU

Ref legal event code: RH4F

Effective date: 20130114