RU2012147662A - WELL STRUCTURE METHOD - Google Patents

WELL STRUCTURE METHOD Download PDF

Info

Publication number
RU2012147662A
RU2012147662A RU2012147662/03A RU2012147662A RU2012147662A RU 2012147662 A RU2012147662 A RU 2012147662A RU 2012147662/03 A RU2012147662/03 A RU 2012147662/03A RU 2012147662 A RU2012147662 A RU 2012147662A RU 2012147662 A RU2012147662 A RU 2012147662A
Authority
RU
Russia
Prior art keywords
drill string
well
outer pipe
drilling
double drill
Prior art date
Application number
RU2012147662/03A
Other languages
Russian (ru)
Other versions
RU2515647C1 (en
Inventor
Владимир Владимирович Тимонин
Андрей Сергеевич Кондратенко
Original Assignee
Федеральное государственное бюджетное учреждение науки Институт горного дела им. Н.А. Чинакала Сибирского отделения Российской академии наук
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Федеральное государственное бюджетное учреждение науки Институт горного дела им. Н.А. Чинакала Сибирского отделения Российской академии наук filed Critical Федеральное государственное бюджетное учреждение науки Институт горного дела им. Н.А. Чинакала Сибирского отделения Российской академии наук
Priority to RU2012147662/03A priority Critical patent/RU2515647C1/en
Application granted granted Critical
Publication of RU2012147662A publication Critical patent/RU2012147662A/en
Publication of RU2515647C1 publication Critical patent/RU2515647C1/en

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

1. Способ сооружения скважины, включающий бурение ее породоразрушающим инструментом забойного снаряда, соединенного с двойной бурильной колонной, с непрерывным удалением шлама от забоя скважины, транспортировку шлама потоком отработанного рабочего тела под давлением по центральному каналу двойной бурильной колонны, отличающийсятем, что для бурения скважины используют двойную бурильную колонну, образованную невращающейся наружной трубой и размещенной в ней буровой штангой, передающей крутящий момент и осевое усилие на забойный снаряд с породоразрушающим инструментом, причем одновременно с бурением скважины осуществляют затяжку в нее указанной наружной трубы, которую после завершения бурения оставляют в скважине в качестве обсадной трубы, при этом центральным каналом двойной бурильной колонны является канал буровой штанги.2. Способ по п.1, отличающийся тем, что в двойной бурильной колонне используют наружную трубу из неметаллического материала.1. The method of constructing a well, including drilling its rock cutting tool downhole connected to a double drill string, with the continuous removal of sludge from the bottom of the well, transporting the slurry by the flow of the spent working fluid under pressure through the Central channel of the double drill string, characterized in that they use for drilling a well a double drill string formed by a non-rotating outer pipe and a drill rod placed in it, transmitting torque and axial force to the bottom hole d with a rock cutting tool, and at the same time as the well is being drilled, the specified outer pipe is drawn into it, which, after the completion of drilling, is left as a casing in the well, while the central channel of the double drill string is the drill rod channel. 2. The method according to claim 1, characterized in that in the double drill string an outer pipe of non-metallic material is used.

Claims (2)

1. Способ сооружения скважины, включающий бурение ее породоразрушающим инструментом забойного снаряда, соединенного с двойной бурильной колонной, с непрерывным удалением шлама от забоя скважины, транспортировку шлама потоком отработанного рабочего тела под давлением по центральному каналу двойной бурильной колонны, отличающийся тем, что для бурения скважины используют двойную бурильную колонну, образованную невращающейся наружной трубой и размещенной в ней буровой штангой, передающей крутящий момент и осевое усилие на забойный снаряд с породоразрушающим инструментом, причем одновременно с бурением скважины осуществляют затяжку в нее указанной наружной трубы, которую после завершения бурения оставляют в скважине в качестве обсадной трубы, при этом центральным каналом двойной бурильной колонны является канал буровой штанги.1. The method of constructing a well, including drilling its rock cutting tool downhole connected to a double drill string, with the continuous removal of sludge from the bottom of the well, transporting the sludge by the flow of the spent working fluid under pressure through the Central channel of the double drill string the fact that a double drill string is used to drill a well, formed by a non-rotating outer pipe and a drill rod placed in it, transmitting torque and axial force to the bottom hole with a rock cutting tool, and at the same time as drilling the hole, the specified outer pipe is pulled into it, which after completion of drilling is left in the borehole as a casing pipe, while the central channel of the double drill string is the channel of the drill rod. 2. Способ по п.1, отличающийся тем, что в двойной бурильной колонне используют наружную трубу из неметаллического материала. 2. The method according to claim 1, characterized in that in the double drill string an outer pipe of non-metallic material is used.
RU2012147662/03A 2012-11-08 2012-11-08 Method of well configuring RU2515647C1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2012147662/03A RU2515647C1 (en) 2012-11-08 2012-11-08 Method of well configuring

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2012147662/03A RU2515647C1 (en) 2012-11-08 2012-11-08 Method of well configuring

Publications (2)

Publication Number Publication Date
RU2012147662A true RU2012147662A (en) 2014-05-20
RU2515647C1 RU2515647C1 (en) 2014-05-20

Family

ID=50695440

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2012147662/03A RU2515647C1 (en) 2012-11-08 2012-11-08 Method of well configuring

Country Status (1)

Country Link
RU (1) RU2515647C1 (en)

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2919121A (en) * 1957-09-25 1959-12-29 Joseph P Ruth Mining and excavating machine of the rotary type
FI86332C (en) * 1989-09-27 1992-08-10 Valto Ilomaeki Tunnel drill and procedure for its control
BE1004330A3 (en) * 1990-05-31 1992-11-03 Diamant Boart Stratabit Sa Dual core drilling devie.

Also Published As

Publication number Publication date
RU2515647C1 (en) 2014-05-20

Similar Documents

Publication Publication Date Title
AU2013228112B2 (en) Method for removal of casings in an underground well
MY166114A (en) Method of and apparatus for drilling a subterranean borehole
EA201490942A1 (en) DEVICE AND METHOD FOR DRILLING WELLS IN THE UNDERGROUND PLATE
SA519410150B1 (en) Notching a wellbore while drilling
MX2012001983A (en) Method of drilling a subterranean borehole.
GB201318047D0 (en) Method of drilling and running casing in large diameter wellbore
GB2490451A (en) Reverse circulation apparatus and methods for using same
EA201591602A1 (en) DRILLING WELLS WITH THE USE OF DOUBLE DRILLING COLUMNS
MY175727A (en) Method of drilling a subterranean borehole
WO2014186415A3 (en) Method and apparatus for operating a downhole tool
MY192204A (en) A method of plugging and abandoning a well
MX2016003565A (en) Use of downhole isolation valve to sense annulus pressure.
GB2485731A (en) Offshore casing drilling method
WO2016090209A3 (en) Down-hole vibrational oscillator
CN104632112A (en) Through-type downhole hammer reverse circulation drilling structure
MX2015015169A (en) Resuming interrupted communication through a wellbore.
GB2520187A (en) Wellbore completion system with reaming tool
BR112015009615A2 (en) effect of reinforced plaster in well drilling
RU138113U1 (en) CHISEL WITH ADVANCED BLADES
GB2549051A (en) Anti-balling drill bit and method of making same
RU131061U1 (en) TECHNOLOGICAL COMPLEX FOR DRILLING AND DEPRESSIONAL CLEANING OF THE SAND PLUG
RU2012147662A (en) WELL STRUCTURE METHOD
CN204238925U (en) A kind of drilling rod pressure testing device of completion practice
CN204024548U (en) A kind of half novel box-like single rotary double core barrel
GB2511660A (en) Method and device for riserless drilling fluid recovery

Legal Events

Date Code Title Description
MM4A The patent is invalid due to non-payment of fees

Effective date: 20141109