RU2000112933A - METHOD FOR INSTALLING MORTGAGE PARTS AND THEIR ANCHORING OF VERTICAL HYDRAULIC MACHINES - Google Patents

METHOD FOR INSTALLING MORTGAGE PARTS AND THEIR ANCHORING OF VERTICAL HYDRAULIC MACHINES

Info

Publication number
RU2000112933A
RU2000112933A RU2000112933/06A RU2000112933A RU2000112933A RU 2000112933 A RU2000112933 A RU 2000112933A RU 2000112933/06 A RU2000112933/06 A RU 2000112933/06A RU 2000112933 A RU2000112933 A RU 2000112933A RU 2000112933 A RU2000112933 A RU 2000112933A
Authority
RU
Russia
Prior art keywords
suction
anchoring
installing
stator
hydraulic machine
Prior art date
Application number
RU2000112933/06A
Other languages
Russian (ru)
Other versions
RU2180944C2 (en
Inventor
Виталий Константинович Березин
Георгий Прокопьевич Лохматиков
Валерий Ростиславович Мигуренко
Михаил Петрович Сложеникин
Original Assignee
Виталий Константинович Березин
Георгий Прокопьевич Лохматиков
Валерий Ростиславович Мигуренко
Михаил Петрович Сложеникин
Filing date
Publication date
Application filed by Виталий Константинович Березин, Георгий Прокопьевич Лохматиков, Валерий Ростиславович Мигуренко, Михаил Петрович Сложеникин filed Critical Виталий Константинович Березин
Priority to RU2000112933/06A priority Critical patent/RU2180944C2/en
Priority claimed from RU2000112933/06A external-priority patent/RU2180944C2/en
Application granted granted Critical
Publication of RU2180944C2 publication Critical patent/RU2180944C2/en
Publication of RU2000112933A publication Critical patent/RU2000112933A/en

Links

Claims (1)

Способ монтажа закладных частей и их анкеровки вертикальной гидромашины, включающий установку облицовки конуса отсасывающей (всасывающей) трубы, установку фундаментного кольца или камеры рабочего колеса, их предварительное центрирование совместно с облицовкой конуса отсасывающей (всасывающей) трубы, установку содержащего статор укрупненного узла закладных частей с их анкеровкой в проектное положение с подвешенными к статору, предварительно изготовленными фундаментными тумбами с последующим их бетонированием, отличающийся тем, что, с целью сокращения технологического срока строительно-монтажных работ, уменьшения трудоемкости и повышения удобства проведения работ, формируют временную опорную монтажную базу максимально укрупненного узла закладных частей гидромашины, используя верхний торец несущей конструкции конуса отсасывающей (всасывающей) трубы или ребра жесткости фундаментного кольца, на которую устанавливают с помощью временных опор со средствами регулировки статор гидромашины с закрепленными на нем фундаментными тумбами и облицовками шахты турбины, проводят выверку положения статора в проектное положение, фиксируют это положение бетонированием фундаментных тумб, выдерживают до набора бетоном не менее 80% его расчетной жесткости, после чего демонтируют временные опоры со средствами регулировки выверки проектного положения и производят поярусное бетонирование закладных частей и их анкеровки гидромашины известным способом.A method of mounting embedded parts and their anchoring of a vertical hydraulic machine, including installing a facing of a cone of a suction (suction) pipe, installing a foundation ring or a chamber of an impeller, pre-centering it together with a facing of a cone of a suction (suction) pipe, installing a stator of an enlarged assembly of embedded parts with their anchoring in the design position with suspended to the stator, prefabricated foundation pedestals with their subsequent concreting, characterized in that, in order to reduce the technological period of construction and installation work, reduce labor intensity and increase the convenience of work, form a temporary support mounting base of the largest enlarged assembly of embedded parts of the hydraulic machine using the upper end of the supporting structure of the cone of the suction (suction) pipe or stiffener of the foundation ring, on which using temporary supports with means of adjusting the stator of the hydraulic machine with the foundation pedestals and lining of the turbine shaft fixed to it, etc. they reconcile the stator position to the design position, fix this position by concreting the foundation pedestals, maintain at least 80% of its design stiffness until concrete is set, then remove the temporary supports with the means to adjust the design position reconciliation and perform half-level concreting of embedded parts and their anchoring of the hydraulic machine in a known manner .
RU2000112933/06A 2000-05-25 2000-05-25 Method of mounting of inserted parts and their anchorage in vertical hydraulic machines RU2180944C2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2000112933/06A RU2180944C2 (en) 2000-05-25 2000-05-25 Method of mounting of inserted parts and their anchorage in vertical hydraulic machines

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2000112933/06A RU2180944C2 (en) 2000-05-25 2000-05-25 Method of mounting of inserted parts and their anchorage in vertical hydraulic machines

Publications (2)

Publication Number Publication Date
RU2180944C2 RU2180944C2 (en) 2002-03-27
RU2000112933A true RU2000112933A (en) 2002-04-27

Family

ID=20235018

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2000112933/06A RU2180944C2 (en) 2000-05-25 2000-05-25 Method of mounting of inserted parts and their anchorage in vertical hydraulic machines

Country Status (1)

Country Link
RU (1) RU2180944C2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2679214C1 (en) * 2018-03-16 2019-02-06 Общество с ограниченной ответственностью Производственно строительная фирма "СТАЛЬКОН" (ООО ПСФ "СТАЛЬКОН") Device for adjustment and temporary attachment of structures on a horizontal base
CN114293522B (en) * 2021-12-31 2023-10-31 中铁二十局集团第六工程有限公司 Tubular seat mounting method and tubular seat of hydroelectric generating set

Similar Documents

Publication Publication Date Title
CN103114604B (en) Prestressed concrete tubular type wind generating set foundation
WO2008036934A3 (en) Partially prefabricated modular foundation system
CN210621742U (en) Tower drum supporting seat
AU2008262617B2 (en) A wind-power unit with vertical axis and method for production of a foundation for same
CN111335611B (en) Large-span cantilever member construction system and construction method thereof
RU2000112933A (en) METHOD FOR INSTALLING MORTGAGE PARTS AND THEIR ANCHORING OF VERTICAL HYDRAULIC MACHINES
CN110565962A (en) Tool type chute and construction method
CN1100205C (en) Hydraulic machinery
KR20060096706A (en) Deck suspension top-down method of sub-structure
KR200390421Y1 (en) Top-down substructure by deck suspension
SU1463763A1 (en) Method of reconstructing a blast furnace
KR100650134B1 (en) Early remove support method
RU2180944C2 (en) Method of mounting of inserted parts and their anchorage in vertical hydraulic machines
SU487978A1 (en) The method of installation and ankirovka stator and spiral chamber of the turbine
RU2453657C2 (en) Design of foundation for structure or building and method of its manufacturing
KR20070095695A (en) Half assembly-typed construction system and method of common duct
CN215211140U (en) Novel generator foundation structure of pumped storage power station
CN218816754U (en) Outdoor wind-resistant type base reinforced structure
CN216515416U (en) Steel bar structure of water conservancy project water diversion canal
CN218373897U (en) Assembly type reinforced concrete inner supporting structure capable of adjusting axial force
SG131743A1 (en) In-situ construction of concrete building
CN207455080U (en) A kind of prefabricated earth plate fixing device of equipment
JPH1030543A (en) Bulb type water-wheel generator, assembly and disassembly method thereof, and guide vane gap adjusting method
RU125232U1 (en) CHIMNEY
JPH03284143A (en) Method of installing and adjusting rotary electric machine