PL83542B2 - - Google Patents

Download PDF

Info

Publication number
PL83542B2
PL83542B2 PL16097673A PL16097673A PL83542B2 PL 83542 B2 PL83542 B2 PL 83542B2 PL 16097673 A PL16097673 A PL 16097673A PL 16097673 A PL16097673 A PL 16097673A PL 83542 B2 PL83542 B2 PL 83542B2
Authority
PL
Poland
Prior art keywords
dam
segment
boom
mechanized mining
canopy
Prior art date
Application number
PL16097673A
Other languages
Polish (pl)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to PL16097673A priority Critical patent/PL83542B2/pl
Publication of PL83542B2 publication Critical patent/PL83542B2/pl

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

Pierwszenstwo: Zgloszenie ogloszono: 01.11.1974 Opis patentowy opublikowano: 15.06.1976 83542 MKP E21f 15/02 Int. Cl2. E21F 15/02 Twórcywynalazku: Rafal Piegrzyk, Jerzy Arkuszewski Uprawniony z patentu tymczasowego: Kopalnia Wegla Kamiennego „Barbara-Chorzów", Chorzów (Polska) Zmechanizowana obudowa górnicza do scian podsadzkowych Przedmiotem wynalazku jest zmechanizowana obudowa górnicza do scian wybieranych systemem z pod¬ sadzka hydrauliczna, zaopatrzona w tame podsadzkowa.Znana jest zmechanizowana obudowa z tasma podsadzkowa zwiazana z poszczególnymi sekcjami obudowy za pomoca przesuwników.Cykl pracy znanej obudowy zasadza sie na tym, ze najpierw do czola przodka przesuwaja sie poszczególne sekcje obudowy, zas sama tama zostaje w poprzednim polozeniu, po czym w nastepnym takcie przysuwa sie tame do obudowy. Sterowanie przesuwaniem tamy do obudowy odbywa sie z centralnego miejsca, tak by tama jednoczesnie na calej dlugosci wyrobiska postepowala do przodu.Niedogodnosc w stosowaniu znanej tasmy wyplywa z faktu, ze przez plótno podsadzkowe zawsze wydostaje sie przed tame czesc piasku, która wielce utrudnia, a przy malych nachyleniach wzdluz sciany wrecz uniemozliwia przysuniecie tamy do obudowy.Koniecznosc centralnego sterowania tama wyplywa z samej konstrukcji znanej tamy. Jest to konstrukcja jednolita o ksztalcie plaskiej ramy.Celem wynalazku jest usuniecie powyzszych niedogodnosci. Cel ten osiagnieto w wynalazku dzieki temu, ze górna czesc tamy zamocowana jest przegubowo wprost do stropnicy obudowy, zas do plozy zamocowany jest dolny segment tamy z korytem splywowym. Stropnica obudowy w swej czesci wysiegnikowej odpodsadzkowej ma przekrój skrzynkowy i sluzy do doprowadzenia mieszaniny podsadzkowej z rurociagu podsadzkowego do przestrzeni podsadzanej. Miejsce laczenia górnego segmentu tamy ze stropnica jest dla dwóch sasiednich sekcji przesuniete wzgledem siebie o pól skoku tak, ze tama w widoku z góry tworzy przy stropie linie lamana. Górny segment tamy jest teleskopowy, a dodatkowe urzadzenie rozpiete miedzy nim a stropnica pozwala ten segment odchylac, umozliwiajac wejscie za tame.Koryto splywowe ma scianke odciosowa wylozona nieprzepuszczalnym tworzywem, zas scianke odpod- sadzkowa wylozona przesaczalna tkanina. Scianka odpodsadzkowa tego koryta jest odchylna. Elastyczny rurociag zawieszony jest pod stropnicami na cieglach i ma wloty do wysiegnika stropnicy w co 4 sekcji obudowy.2 83542 Obudowa wedlug wynalazku pracuje w dwóch taktach, przy czym najpierw przesuwane sa do przodu sekcje, do stropnic których zamocowany jest górny segment w odleglosci blizszej przestrzeni podsadzanej niz w sekcji sasiedniej przesuwanej do przodu w takcie drugim. To niezwykle korzystne rozwiazanie pozwolilo polaczyc tame bezposrednio z obudowa, bez dodatkowych przesuwników.Wielka zaleta obudowy wedlug wynalazku jest konstrukcja koryta splawnego. Otóz pomiedzy dolnym segmentem szkieletu tamy a przypodsadzkowa scianka koryta splywowego tworzy sie rodzaj drugiego stopnia tamy. W te przestrzen swobodnie wplywa mieszanina podsadzkowa, tutaj osadza sie material podsadzkowy, dajac korzystne przyspagowe uszczelnienie tamy. Odsaczajaca sie z drugiego stopnia tamy woda uchodzi poprzez tkanine podsadzkowa do koryta splawnego. Z praktyki wiadomo jednak, ze pewna czesc ziarn materialu podsadzkowego zabierana bedzie z woda i osadzac sie bedzie w korycie splawnym. Ale i ten problem zostal w wynalazku rozwiazany, bowiem koryto splawne jest korytem samoczyszczacym sie. Material podsadzkowy . zgromadzony w nim zostaje po przesunieciu obudowy w poprzednim miejscu, gdyz na czas przesuwania obudowy odchyla sie ku górze odpodsadzkowa scianka koryta splawnego. Górny segment tamy jest tak skonstruowany, ze pozwala na odchylenie tamy i umozliwia wejscie pracownika do przestrzeni podsadzonej, dla dokonania obserwacji stropu, pomiarów konwergencji wyrobiska lub nawet wzmocnienia stropu zrobów.Istotnie nowym i korzystnym rozwiazaniem obudowy wedlug wynalazku jest wykorzystanie skrzynkowego przekroju stropnicy dla doprowadzenia mieszaniny podsadzkowej z rurociagu do przestrzeni podsadzanej, w miejsce dotychczas stosowanych odgalezien rurowych.Wynalazek przedstawiony jest w przykladzie wykonania na rysunku, na którym fig. 1 przedstawia sekcje obudowy w widoku z boku, zas fig. 2 kilka sekcji w widoku z góry. Stropnica 1 obudowy ma odpodsadzkowy wysiegnik 2 uksztaltowany w postaci skrzynki z wlotem 8 i wylotowym otworem 9. Górny segment 3 tamy zlozony z teleskopowych elementów 3' i 3" zawieszony jest do stropnicy 1 za pomoca przegubu 10. Miejsce zamocowania przegubu 10 jest przesuniete o pól skoku obudowy w stosunku do miejsca zamocowania przegubu 10' na sasiedniej sekcji tak, ze tama w widoku z góry tworzy lamana linie 11. Segment 3 opiety jest podsadzkowa tkanina 12. Silownikowe urzadzenie 13 rozpiete miedzy stropnica 1 a górnym segmentem 3 pozwala na odchylanie tego segmentu 3 z pozycji nieomal poziomej do pozycji nieomal pionowej. Do plozy 4 obudowy umocowany jest dolny segment 5 tamy podsadzkowej. Splywowe koryto 6 utworzone jest przez dwie scianki: odpodsadzkowa scianke 16 wylozona przepuszczalna tkanina 17, odociosowa scianke 14 wylozona nieprzepuszczalnym tworzywem 15. Odpodsadzkowa scianka 16 polaczona jest zodosiosowa scianka 14 poziomym ramieniem 18 odchylanym wraz z odpodsadzkowa scianka 16 wokól osi 19. Rurociag podsadzkowy 7 zawieszony jest pod stropnica 1 na cieglach 20. PL PLPriority: Application announced: November 1, 1974 Patent description was published: June 15, 1976 83542 MKP E21f 15/02 Int. Cl2. E21F 15/02 Inventors: Rafal Piegrzyk, Jerzy Arkuszewski Authorized under the provisional patent: "Barbara-Chorzów" Stone Coal Mine, Chorzów (Poland) Mechanized mining support for backfill walls The subject of the invention is a mechanized mining support for walls selected with a hydraulic undercutting system There is a well-known mechanized casing with a filling belt connected to individual sections of the casing by means of shifters. The working cycle of the known casing is based on the fact that the individual sections of the casing first move to the face of the face, while the dam itself remains in its previous position, then, in the next cycle, the dam is moved to the housing. The dam is moved to the housing from a central place, so that the dam simultaneously moves forward along the entire length of the excavation. The inconvenience of using the known tape is due to the fact that it always comes out through the backfilling cloth. in front of that part of the sand that is very grind day, and at low slopes along the wall it even prevents the dam from slipping towards the housing. The need for central control of the dam arises from the very structure of the known dam. It is a unitary structure in the shape of a flat frame. The object of the invention is to remedy the above drawbacks. This aim was achieved in the invention due to the fact that the upper part of the dam is articulated directly to the canopy of the housing, while the lower dam segment with a drainage channel is attached to the skid. The casing ridge has a box section in its cantilever part, and serves to deliver the proppant mixture from the backwater pipeline to the backfill space. The junction of the upper dam segment with the canopy is for two adjacent sections shifted relative to each other by a jump half so that the dam in the top view forms a lamella line at the ceiling. The upper segment of the dam is telescopic, and an additional device stretched between it and the canopy allows this segment to be tilted, allowing entry behind the dam. The drainage trough has a soffit wall lined with impermeable material, while the drainage wall is lined with permeable fabric. The trapdoor of this trough is foldable. The flexible pipeline is suspended under the canopies on poles and has inlets to the canopy boom in every 4 sections of the support. 2 83542 According to the invention, the support works in two cycles, with the sections being moved forward first, to which the upper segment is attached at a distance closer to the space inserted than in the adjacent section moved forward in the second bar. This extremely advantageous solution allowed to connect it directly to the housing, without additional translators. The great advantage of the housing according to the invention is the structure of the weld trough. A kind of second stage of the dam is formed between the lower segment of the dam skeleton and the sub-floor wall of the drainage channel. The proppant mixture freely flows into this space, here the proppant is deposited, giving a favorable weld seam of the dam. Water discharging from the second stage of the dam escapes through the backing fabric into the spill trough. However, it is known from practice that a certain part of the grains of the proppant will be taken with the water and will settle in the spill trough. But this problem was solved in the invention as well, because the spill bed is a self-cleaning bed. Backfilling material. it is accumulated in it after moving the housing in its previous place, because when the housing is moved, the sagging wall of the spill trough swings upwards. The upper segment of the dam is constructed in such a way that it allows the dam to be deflected and allows the worker to enter the backfill space to observe the roof, measure the convergence of the excavation or even strengthen the goaf ceiling. An essentially new and advantageous solution of the casing according to the invention is the use of a box-shaped section of the canopy for supplying the mixture The invention is illustrated in an exemplary embodiment in the drawing, in which Fig. 1 shows sections of the casing in a side view, and Fig. 2 shows several sections in a top view. The roof ridge 1 of the casing has a sagging boom 2 shaped as a box with an inlet 8 and an outlet opening 9. The upper dam segment 3 composed of 3 'and 3 "telescopic elements is suspended to the canopy 1 by means of a joint 10. The joint 10 mounting place is shifted by half the stroke of the housing in relation to the joint 10 'mounting point on the adjacent section, so that the dam in the top view forms a broken line 11. The segment 3 of the support is a filling fabric 12. The actuator device 13 stretched between the canopy 1 and the upper segment 3 allows for tilting this segment 3 from an almost horizontal position to an almost vertical position. The bottom section 5 of the filling dam is attached to the skid 4 of the casing. The drainage trough 6 is formed by two walls: it is connected with the zodosias wall 14 by a horizontal arm 18 hinged with the sump a wall 16 around the axis 19. The filling pipeline 7 is suspended under the canopy 1 on the cross-pieces 20. PL PL

Claims (7)

1. Zastrzezenia patentowe 1. Zmechanizowana obudowa górnicza do scian z podsadzka hydrauliczna, znamienna tym, ze do odpodsadzkowego wysiegnika (2) o przekroju skrzynkowym stropnicy (1) obudowy, zamocowany jest przegubo¬ wo górny segment (3) szkieletu tamy, zas do plozy (4) do co drugiej lub co 2 n—tej sekcji zamocowany jest dolny segment (5) tamy ze splywowym korytem (6) przy czym podsadzkowy rurociag (7) ma wloty (8) do wnetrza odpodsadzkowego wysiegnika (2) stropnicy (1) który to wysiegnik (2) w poblizu swego konca ma wylotowy otwór (9) dla dostarczenia mieszaniny podsadzkowej zatame. \1. Claims 1. Mechanized mining support for walls with a hydraulic propelling, characterized in that the upper segment (3) of the dam frame is articulated to the descaling boom (2) with a box-section of the canopy (1) of the support. (4) the lower segment (5) of the dam with a runoff trough (6) is attached to every second or every 2 nth section, while the backfilling pipeline (7) has inlets (8) to the interior of the descent boom (2) of the canopy (1) which boom (2) has an outlet opening (9) near its end for delivering a proppant mixture. \ 2. Zmechanizowana obudowagórnicza wedlug zastrz. 1, znamienna tym, ze miejsce przegubu (10) i (10') laczacego wysiegnik (2) z górnym segmentem \3) tamy, jest dla dwóch sasiednich sekcji przesuniete wzgledem siebie o pól skoku obudowy tak, ze tama w widoku z góry tworzy przy stropie lamana linie (11), przy czym dla sekcji przesuwanej w pierwszym takcie, przegub (10) znajduje sie blizej przestrzeni podsadzanej, zas dla sekcji przesuwanej w drugim takcie dalej od tej przestrzeni.2. Mechanized mining support according to claim 3. The point of claim 1, characterized in that the position of the hinge (10) and (10 ') connecting the boom (2) with the upper segment \ 3) of the dam, for two adjacent sections shifted relative to each other by the half of the housing pitch, so that the dam in the top view at the roof there is a broken line (11), where for the section moved in the first cycle, the articulation (10) is closer to the support space, and for the section moved in the second cycle, further away from this space. 3. Zmechanizowana obudowa górnicza wedlug zastrz. 1 albo 2, znamienna t y m, ze górny segment (3) tamy sklada sie z dwu teleskopowych elementów (3') i (3") których dlugosc wstanie wysunietym jest mniejsza niz wysokosc obudowy i do których mocuje sie podsadzkowa tkanine (12).3. Mechanized mining support according to claim A method as claimed in claim 1 or 2, characterized in that the upper dam segment (3) consists of two telescopic elements (3 ') and (3 ") whose extended length is less than the height of the casing and to which the prop cloth (12) is attached. 4. Zmechanizowana obudowa górnicza wedlug zastrz. 1,znamienna tym, ze miedzy stropnica (1) a górnym segmentem (3) znajduje sie silownikowe urzadzenie (13) do zmiany polozenia segmentu (3) z polozenia nieomal pionowego do polozenia nieomal poziomego.4. Mechanized mining support according to claim A device according to claim 1, characterized in that between the canopy (1) and the upper segment (3) there is a motorized device (13) for changing the position of the segment (3) from an almost vertical position to an almost horizontal position. 5. Zmechanizowana obudowa górnicza wedlug zastrz. 1,znamienna tym, ze splywowe koryto (6) ma odociosowa scianke (14) polozona blizej ociosu wylozona nieprzepuszczalnym tworzywem (15), zas scianke (16) blizsza przestrzeni podsadzanej wylozona przepuszczalna tkanina (17).5. Mechanized mining support according to claim The method as claimed in claim 1, characterized in that the drainage trough (6) has a corrugated wall (14) lined with impermeable material (15) closer to the hewn, and the wall (16) lined with permeable fabric (17) closer to the backfill space. 6. Zmechanizowana obudowa górnicza wedlug zastrz. 1 albo 5, znamienna t y m, ze scianka (16) splywowego koryta (6) jest wraz z poziomym ramieniem (18) odchylna wokól osi (19).8o542 36. A mechanized mine support according to claim 1 or 5, characterized by the fact that the wall (16) of the drainage trough (6) is, together with the horizontal arm (18), pivotable around the axis (19). 7. Zmechanizowana obudowa górnicza wedlug zastrz. 1,znamienna tym, ze elastyczny podsadzko¬ wy rurociag (7) zawieszony jest pod stropnica (1) na cieglach (20) i ma wloty do wysiegnika (2) w co 4 sekcji obudowy. Fig.1 Fig.2 PL PL7. Mechanized mining support according to claim 3. The method of claim 1, characterized in that the flexible proppant (7) is suspended from the canopy (1) on the rods (20) and has openings to the boom (2) in every 4 sections of the casing. Fig. 1 Fig. 2 PL EN
PL16097673A 1973-02-28 1973-02-28 PL83542B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PL16097673A PL83542B2 (en) 1973-02-28 1973-02-28

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PL16097673A PL83542B2 (en) 1973-02-28 1973-02-28

Publications (1)

Publication Number Publication Date
PL83542B2 true PL83542B2 (en) 1975-12-31

Family

ID=19961750

Family Applications (1)

Application Number Title Priority Date Filing Date
PL16097673A PL83542B2 (en) 1973-02-28 1973-02-28

Country Status (1)

Country Link
PL (1) PL83542B2 (en)

Similar Documents

Publication Publication Date Title
US4120164A (en) Underground roadway or tunnel support
CN102704935A (en) Extra-long working surface fully mechanized coal mining process
PL83542B2 (en)
PL149218B1 (en) Method of filling mined-out longwall workings and filling stopping therefor
CN209308079U (en) Water draw-off for Underground Building for Anti-floating
SU1373829A1 (en) Power support unit
PL84289B1 (en)
RU2526074C2 (en) Mechanised second working complex
SU1388566A1 (en) Fill-in stopper
RU1798502C (en) Method for making embarkments
SU1184949A1 (en) Power support unit
SU1758245A1 (en) Mine fill stopping
SU1573196A1 (en) Mine powered support section
PL143579B1 (en) Moving filling dam for longwalls with self advancing roof supports
SU918200A1 (en) End station of flight conveyer
SU972151A1 (en) Method of erecting man-made pillar in steep seams
PL174781B1 (en) Filling dam
SU1745938A1 (en) Thick pitching coal seam exploitation method
CS239243B1 (en) Unit of mechanized framing
SU1566036A1 (en) Shield support
PL158723B1 (en) Method of and hydraulic roof support system for rearranging a packing dam
PL65116B1 (en)
SU1548447A1 (en) Mechanized forms for erecting safety strips
PL193924B1 (en) Endmost unit of self-advancing roof supports
PL137846B2 (en) Filling dam for mechanical housing