Method of backfilling post-mining voids or workings from the ground surfaceInfo
- Publication number
- PL442442A1 PL442442A1 PL442442A PL44244222A PL442442A1 PL 442442 A1 PL442442 A1 PL 442442A1 PL 442442 A PL442442 A PL 442442A PL 44244222 A PL44244222 A PL 44244222A PL 442442 A1 PL442442 A1 PL 442442A1
- Authority
- PL
- Poland
- Prior art keywords
- hole
- backfilling
- workings
- ground surface
- water
- Prior art date
Links
- 238000000034 method Methods 0.000 title abstract 5
- 238000005065 mining Methods 0.000 title abstract 3
- 230000003245 working effect Effects 0.000 title abstract 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract 4
- 238000002347 injection Methods 0.000 abstract 3
- 239000007924 injection Substances 0.000 abstract 3
- 239000000463 material Substances 0.000 abstract 2
- 238000005086 pumping Methods 0.000 abstract 1
- 238000013022 venting Methods 0.000 abstract 1
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
Przedmiotem zgłoszenia jest sposób podsadzania pustek poeksploatacyjnych lub zrobów z powierzchni terenu, który polega na tym, że uprzednio zlokalizowane pustki eksploatacyjne lub zroby udostępnia się z powierzchni terenu za pomocą co najmniej jednego otworu podsadzkowego (3), co najmniej jednego otworu odpowietrzającego (4) oraz za pomocą co najmniej jednego otworu odwadniającego (5). Otwory wykonuje się z wykorzystaniem metody udarowo-obrotowej z dolnym młotkiem i świdrem, przy równoczesnym zapuszczaniu do otworu kolumny rur okładzinowych wyposażonych w but z koronką. W trakcie zatłaczania otworem podsadzkowym (3) materiału podsadzkowego do zrobów (2), za pomocą otworu odwadniającego (5) odpompowuje się dopływającą do niego wodę, zatłaczanie kończy się po stwierdzeniu obecności wody w otworze odpowietrzającym (4), natomiast proces odpompowywania wody w otworze odwadniającym (5) kończy się po ustaleniu się wielkości dopływu wody do otworu odwadniającego (5) na poziomie mniejszym lub równym od dopływu naturalnego, zmierzonego przed rozpoczęciem zatłaczania, materiału podsadzkowego, po czym otwory likwiduje się znanymi metodami.The subject of the application is a method of backfilling mining voids or workings from the ground surface, which consists in making previously located mining voids or workings accessible from the ground surface using at least one backfilling hole (3), at least one vent hole (4) and using at least one drainage hole (5). The holes are made using the percussion-rotary method with a lower hammer and a drill, while simultaneously inserting a column of casing pipes equipped with a shoe with a crown into the hole. During the injection of backfilling material into the goafs (2) through the backfilling hole (3), the water flowing into it is pumped out through the drainage hole (5), the injection ends after the presence of water is detected in the venting hole (4), and the process of pumping out the water in the hole drainage hole (5) ends when the amount of water inflow to the drainage hole (5) is set at a level lower or equal to the natural inflow of backfill material, measured before the injection, and then the holes are closed using known methods.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
PL442442A PL442442A1 (en) | 2022-10-04 | 2022-10-04 | Method of backfilling post-mining voids or workings from the ground surface |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
PL442442A PL442442A1 (en) | 2022-10-04 | 2022-10-04 | Method of backfilling post-mining voids or workings from the ground surface |
Publications (1)
Publication Number | Publication Date |
---|---|
PL442442A1 true PL442442A1 (en) | 2024-04-08 |
Family
ID=90623520
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PL442442A PL442442A1 (en) | 2022-10-04 | 2022-10-04 | Method of backfilling post-mining voids or workings from the ground surface |
Country Status (1)
Country | Link |
---|---|
PL (1) | PL442442A1 (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4000621A (en) * | 1975-06-19 | 1977-01-04 | The United States Of America As Represented By The Secretary Of The Interior | Remote sealing of mine passages containing flowing water |
PL194188B1 (en) * | 2000-11-24 | 2007-05-31 | Kubanski Andrzej | Method of closing down abandoned mine workings ar natural underground voids, in particular those filled with fluid medium, and set of equipment therefor |
PL194189B1 (en) * | 2000-11-17 | 2007-05-31 | Kubanski Andrzej | Method of introducing filling materials into abandoned mine working voids and set of equipment therefor |
CN202500606U (en) * | 2012-01-20 | 2012-10-24 | 山东大学 | Device for filling aggregate into formation cavity through ground surface borehole |
-
2022
- 2022-10-04 PL PL442442A patent/PL442442A1/en unknown
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4000621A (en) * | 1975-06-19 | 1977-01-04 | The United States Of America As Represented By The Secretary Of The Interior | Remote sealing of mine passages containing flowing water |
PL194189B1 (en) * | 2000-11-17 | 2007-05-31 | Kubanski Andrzej | Method of introducing filling materials into abandoned mine working voids and set of equipment therefor |
PL194188B1 (en) * | 2000-11-24 | 2007-05-31 | Kubanski Andrzej | Method of closing down abandoned mine workings ar natural underground voids, in particular those filled with fluid medium, and set of equipment therefor |
CN202500606U (en) * | 2012-01-20 | 2012-10-24 | 山东大学 | Device for filling aggregate into formation cavity through ground surface borehole |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106013049B (en) | Karst area foundation pile engineering construction method | |
Zhao et al. | Numerical simulation of the groundwater system for mining shallow buried coal seams in the ecologically fragile areas of western China | |
EA200200871A1 (en) | METHOD AND SYSTEM FOR SULFUR STORAGE | |
PL442442A1 (en) | Method of backfilling post-mining voids or workings from the ground surface | |
CN109723424B (en) | Method for predicting water discharge amount of underground drilling | |
Zdankus | Analysis of Shallow Hard Rock Well Pumping and Recovery Test Data a | |
US1342781A (en) | Method of shutting a deleterious fluid out of value-producing wells | |
CN209482334U (en) | Increase friction pile construction safety degree temporarilly reduces slope underground water device | |
CN209323545U (en) | A kind of ultra-deep foundation pit dewatering well shut-in well structure | |
RU2680089C1 (en) | Superhigh viscosity oil with aquifers deposit development method | |
Varayesi et al. | The Effect of the Drainage Area on Well and Reservoir Performance | |
RU2667210C1 (en) | Method of operation of hydrocarbon deposit | |
CN109971450A (en) | Low permeability coal seam fills the water erosion control reinforcing agent | |
CN109295991A (en) | A kind of ultra-deep foundation pit dewatering well shut-in well structure and its construction | |
RU2287674C1 (en) | Method for extracting oil deposit using horizontal wells | |
CN109356182A (en) | Increase friction pile construction safety degree temporarilly reduces slope underground water device and its construction method | |
CN108412442A (en) | A kind of disposable casing perforation completion mode | |
CN108397197A (en) | A kind of suppleing level super thick soil property country rock shaft excavation method | |
JP6401575B2 (en) | Determination method of proper air supply pressure to caisson working room in pneumatic caisson method. | |
RU2762321C9 (en) | Technology for the development of a highly permeable reservoir bed saturated with gas and underlain by reservoir water | |
Hua et al. | Use of artificial recharge to rectify adjacent building deformation due to dewatering | |
RU2724705C1 (en) | Method of intensification of well operation after its construction | |
Uglyanitsa | On the formation of a waterproofing shell around the underground structure lining in watered ground | |
Rafi et al. | Jacking of rocks fractures during pre-grouting in Scandinavian tunneling projects–a study of the effects from chosen grouting pressure | |
RU2454541C1 (en) | Drying method of rock-coal massif |