PL137053B1 - Method of preparing a longwall-type working for putting it out of exploitation - Google Patents

Method of preparing a longwall-type working for putting it out of exploitation Download PDF

Info

Publication number
PL137053B1
PL137053B1 PL23791282A PL23791282A PL137053B1 PL 137053 B1 PL137053 B1 PL 137053B1 PL 23791282 A PL23791282 A PL 23791282A PL 23791282 A PL23791282 A PL 23791282A PL 137053 B1 PL137053 B1 PL 137053B1
Authority
PL
Poland
Prior art keywords
wall
excavation
mechanized
preparing
liquidation
Prior art date
Application number
PL23791282A
Other languages
Polish (pl)
Other versions
PL237912A1 (en
Inventor
Kazimierz Maziarczyk
Jan Strojny
Lech Pietraszek
Rudolf Wieszala
Original Assignee
Kopalnia Wegla Kamiennego Nowy
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kopalnia Wegla Kamiennego Nowy filed Critical Kopalnia Wegla Kamiennego Nowy
Priority to PL23791282A priority Critical patent/PL137053B1/en
Publication of PL237912A1 publication Critical patent/PL237912A1/en
Publication of PL137053B1 publication Critical patent/PL137053B1/en

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Description

Przedmiotem wynalazku jest sposób przygotowania do likwidacji wyrobiska soianowego wy¬ posazonego w zmechanizowana obudowe typu oslonowego po zakonczeniu ekspluataoji w tym wy¬ robisku* W pokladach wegla wybieranych podziemnym systemem scianowym, oelem zabezpieczenia prze¬ strzeni roboozej wyrobiska scianowego, stosuje sie obudowy zmeohanizowane róznego typu, miedzy innymi obudowy typu oslonowego* Waznym problemem w stosowaniu tyoh obudów jest mo¬ ment zbrojenia wyrobisk® scianowego obudowa zmechanizowana oraz likwidowanie tej obudowy po zakonczeniu eksploatacji w tym wyrobisku* Dotychozas w celu stworzenia dodatkowej prze¬ strzeni, w której moznaby swobodnie manipulowac poszczególnymi zestawami obudowy zmechani¬ zowanej dokonywano przybierki ociosu na glebokosc okolo 2,5 »• Przybierki tej dokonywano po zlikwidowaniu w scianie kombajnu za pomoca materialów wybuchowych. W tym oelu najpierw wyko¬ nywano w scianie wneki, z których nastepnie prowadzono przybierke ociosu na calej dlugosci tej sciany, przy czym urobek ladowano reoznle na przenosnik scianowy* W tak wykonywanej przestrzeni strop zabezpieczano obudowa tymczasowa zlozona ze stropnio metalowych utrzymy¬ wanych wysiegnikowe przez stropnice zestawów obudowy zmechanizowanej* Taki sposób przygoto¬ wania wyrobiska soianowego do likwidacji obudowy zmechanizowanej jest praoochlonny, a przy tym niezbyt bezpieozny poniewaz wysiegnikowe zamocowane stropnice nie gwarantuja dostatecz¬ nego zabezpieczenia przestrzeni roboczej, zwlaszcza w warunkaoh wzmozonego cisnienia góro¬ tworu jakie zwykle towarzyszy podczas likwidacji wyrobiska scianowego* Wymienionych w$d i niedogodnosci nie ma sposób przygotowania wyrobiska soianowego do likwidacji bedacy przedmiotem niniejszego wynalazku. Istota tego sposobu polega na tym, ze najpierw po zakonczeniu eksploatacji sciany pod stropem pokladu wykonuje sie otwory wielko- srednioowe o dlugosci od 2 do 3 m rozmieszczone w odstepach od 0,3 do 1 m, a najkorzystniej oo 0,75 m. Nastepnie do kazdego otworu wklada sie jeden koniec stropnicy wyprofilowanej ze stali* Natomiast drugi koniec stropnicy uklada sie na plytowej stropnicy zestawu obudowy*/ / i 2 137 053 Po dokonaniu tyoh czynnosci wykonuje sie dodatkowo 2 do 3 skrawów kombajnem, po ozym demon¬ tuje sie ten kombajn wraz z przenosnikiem scianowym. Na konieo zas oba konce kazdej 8trop¬ nioy podbudowuje sie stojakami korzystnie metalowymi ciernymi lub hydraulicznymi? W tak przygotowanym wyrobisku scianowym mozna bezpieoznie manipulowac zestawami obudowy zmechani¬ zowanej oelea wytransportowania jej i calkowitego zlikwidowania tego wyrobiska. Zaleta spo¬ sobu wedlug wynalazku jest równiez tot ze wiekszosc prao przygotowawozyoh wykonuje sie w sposób zmeohanizowany przy zapewnieniu maksymalnego bezpieozenstwa.Przedmiot wynalazku jest dokladniej wyjasniony na zalaozonym rysunku, na którym fig* 1-3 przedstawiaja kolejne fazy zabezpieczania stropu w likwidowanym wyrobisku scianowym, a fig* 4 - sposób rozmieszczenia stropnic w scianie w widoku z góry.Jak uwidoozniono na rysunku przygotowanie wyrobiska scianowego z obudowa zmechanizowana typu oslonowego do likwidacji zgodnie z wynalazkiem odbywa sie w nastepujacy sposób. Po za¬ konczeniu eksploataoji solany najpierw pod stropem w pokladzie wegla wierci sie otwory wiel- kosrednicowe 1 o dlugosoi od 2 do 3 m9 rozmieszczone w odstepaoh od 0,5 do 1 mf a najkorzy¬ stniej co 0,75 m, na calej dlugosoi frontu sciany. Nastepnie do kazdego z tyoh otworów wkla¬ da sie jednym konoem stropnioe metalowa 2 o dlugosoi okolo 4,5 m 2 wyprofilowanej stali.Drugi konieo kazdej z tyoh stropnic uklada sie na plytowej stropnicy 3 zestawu obudowy zme¬ chanizowanej miedzy drewnianymi wykladzinami 4, które uklada sie równiez na stropnicach 2 wpuszczonyoh do otworów 1. Po wykonaniu tych ozynnosoi za porno oa kombajnu urabia sie dodat¬ kowo jeszoze 2 lub 3 zabiory, przy ozym w czasie tego urabiania zestawy obudowy zmechanizo¬ wanej pozostaja na swoim miejscu, a przesuwanie przenosnika scianowego odpietego od obudowy odbywa sie za pomoca dodatkowyoh przesuwnlkow hydraulicznych.Po uzyskaniu przestrzeni niezbednej dla dokonywania operaoji zwiazanych z transportem zestawów obudowy zmechanizowanej miedzy innymi takich jak obracanie i przemieszczanie wzdluz wyrobiska scianowego zestawów, pod oba konce kazdej stropnicy 2 zabudowuje sie stojaki 5 drewniane lub metalowe cierne wzglednie hydrauliczne. Z tak przygotowanego wyrobiska soia- nowego mozna w sposób bezpieczny wytransportowac wszystkie zestawy obudowy zmechanizowanej typu oslonowego, a nastepnie samo wyrobisko zlikwidowac przez wywolanie w rHm zawalu lub przez podsadzenie go podsadzka.Sposób przygotowania wyrobiska scianowego do likwidacji wedlug wynalazku Jest prosty w stosowaniu 1 nie wymaga zadnych dodatkowych urzadzen ani narzedzi. Dlatego moze on byc stosowany we wszystkioh wyrobiskach scianowych wyposazonych w obudowe zmeohanizowana typu oslonowego, zwlaszcza wszedzie tam, gdzie likwidacji sciany towarzyszy wzmozone olsnienie górotworu.Zastrzezenie patentowe Sposób przygotowania do likwidacji wyrobiska scianowego z obudowa oslonowa po zakoncze¬ niu jego eksploataoji ,znamienny tym, ze najpierw pod stropem pokladu wieroi sie otwory wielkosrednioowe o dlugosoi od 2 do 3 m rozmieszczone w odstepach od 0,5 do 1 m, a najkorzystniej oo 0,75 *, na calej dlugosoi frontu sciany, po czym do kazdego otworu wkla¬ da sie jeden konieo stropnicy z wyprofilowanej stali o dlugosci okolo 4,5 m, której drugi konieo uklada sie na plytowej stropnicy zestawu obudowy zmeohanizowanej i po tak wykonanym zabezpieczeniu stropu wykonuje sie dodatkowo od 2 do 3 zabiorów kombajnem, a nastepnie de¬ montuje sie ten kombajn i przenosnik, a pod oba konce stropnio wpuszozonych do otworów za¬ budowuje sie stojaki, korzystnie metalowe cierne lub hydrauliczne.137 053 Fig. i Fig.2lzon*u33 *% e% SSO 4ct PLThe subject of the invention is a method of preparation for liquidation of a soybean excavation equipped with a mechanized casing of the shield type after the completion of mining in this work. * In coal seams selected with an underground wall system, the purpose of securing the working space of a wall excavation, various types of haemanized casings are used, inter alia, shield type supports * An important problem in the use of these supports is the moment of reinforcement of the wall excavations mechanized support and the liquidation of this support after the end of exploitation in this excavation * Until then, in order to create additional space in which individual sets of supports could be freely manipulated the mechanized side, the side was trimmed to a depth of about 2.5 cm. This topping was made after removing the roadhead from the roadheader using explosives. In this oel, first recesses were made in the wall, from which a chisel trim was then carried out along the entire length of the wall, while the excavated material was loaded onto the wall conveyor * In such a space, the ceiling was secured with a temporary housing consisting of metal ceilings held by cantilevers sets of mechanized support * Such a method of preparing a soybean excavation for the liquidation of a mechanized support is pro-absorbent, and at the same time not very safe because the cantilever mounted canopies do not guarantee sufficient protection of the working space, especially in the conditions of increased pressure of the top of the formation that usually accompanies the liquidation of the excavation The method of preparing the soybean workings for liquidation, which is the subject of the present invention, does not have the disadvantages mentioned in the wall. The essence of this method consists in the fact that, firstly, after the end of the wall operation, medium-sized openings are made under the deck ceiling, 2 to 3 m long, spaced at 0.3 to 1 m, and most preferably 0.75 m. at each opening, one end of the bar made of steel is inserted * The other end of the bar is placed on the plate bar of the casing set * / / i 2 137 053 After completing these activities, an additional 2 to 3 cuts are made with the shearer, after which the shearer is disassembled along with a wall conveyor. On the horse, both ends of each 8-stage are supported with frictional or hydraulic props? In a wall excavation prepared in such a way, it is possible to safely manipulate the sets of mechanized lining, to transport it and completely eliminate this excavation. The advantage of the method according to the invention is also that most of the preparatory work is carried out in a humane manner, ensuring the maximum safety. The subject of the invention is more precisely explained in the drawing, in which Figures 1-3 show the subsequent phases of securing the ceiling in the wall excavation being liquidated, and Fig. 4 shows the arrangement of the roof canopies in the wall in plan view. As shown in the drawing, the preparation of a wall excavation with a shield type mechanized support for liquidation according to the invention is carried out in the following manner. After the end of the saline operation, first, under the roof in the coal deck, large-diameter holes 1 are drilled with a length of 2 to 3 m, spaced at intervals of 0.5 to 1 m, and preferably every 0.75 m, over the entire length of the front. walls. Then, a metal roof 2 with a length of about 4.5 m 2 of profiled steel is inserted into each of these openings. The other end of each of these roofs is placed on a plate canopy 3 of a set of casing mechanized between wooden coverings 4, which are arranged also on the canopies 2 recessed into the holes 1. After the construction of the combine harvester, an additional 2 or 3 zabiory are cut, while the shaft during this excavation the sets of the powered support remain in their place, and the movement of the wall conveyor is detached from the support is carried out with the use of additional hydraulic shifting. After obtaining the space necessary for carrying out operations related to the transport of the powered support sets, such as rotation and displacement of the sets along the wall excavation, stands 5 wooden or metal abrasive, respectively, are installed under both ends of each canopy 2 hydraulic. From such prepared soybean excavation, it is possible to safely transport all sets of mechanized support of the shield type, and then the excavation itself can be liquidated by causing a collapse in rHm or by filling it with filling. The method of preparing the wall excavation for liquidation according to the invention It is simple to use 1 does not require any additional devices or tools. Therefore, it can be used in all wall excavations equipped with a mechanized casing of the shield type, especially wherever the removal of the wall is accompanied by increased glare of the rock mass. Patent claim A method of preparation for the liquidation of a wall excavation with a casing after completion, characterized by its operation, first, large-diameter holes, 2 to 3 m long, spaced 0.5 to 1 m apart, and most preferably 0.75 *, are drilled under the deck ceiling, over the entire length of the wall front, and then one is inserted into each opening. The horse of the roof riser made of profiled steel, about 4.5 m long, the second horse of which is placed on the slab canopy of the mechanized casing set, and after securing the roof in this way, additionally 2 to 3 hauls are made with the combine, and then the combine and the conveyor are disassembled , and at both ends of the ceiling recessed into the openings, stands are erected, preferably metal frictional or hydraulic. 137 053 Fig. and Fig. 2 zon * u33 *% e% SSO 4ct PL

Claims (1)

1. Zastrzezenie patentowe Sposób przygotowania do likwidacji wyrobiska scianowego z obudowa oslonowa po zakoncze¬ niu jego eksploataoji ,znamienny tym, ze najpierw pod stropem pokladu wieroi sie otwory wielkosrednioowe o dlugosoi od 2 do 3 m rozmieszczone w odstepach od 0,5 do 1 m, a najkorzystniej oo 0,75 *, na calej dlugosoi frontu sciany, po czym do kazdego otworu wkla¬ da sie jeden konieo stropnicy z wyprofilowanej stali o dlugosci okolo 4,5 m, której drugi konieo uklada sie na plytowej stropnicy zestawu obudowy zmeohanizowanej i po tak wykonanym zabezpieczeniu stropu wykonuje sie dodatkowo od 2 do 3 zabiorów kombajnem, a nastepnie de¬ montuje sie ten kombajn i przenosnik, a pod oba konce stropnio wpuszozonych do otworów za¬ budowuje sie stojaki, korzystnie metalowe cierne lub hydrauliczne.137 053 Fig. i Fig.2lzon*u33 *% e% SSO 4ct PL1. Patent claim A method of preparation for liquidation of a wall excavation with a casing after the end of its operation, characterized in that first large-diameter holes with a length of 2 to 3 m, spaced at intervals of 0.5 to 1 m, are drilled under the deck roof, and most preferably about 0.75 *, over the entire length of the front wall, then one horse of a profiled steel bar, about 4.5 m long, is inserted into each opening, the other horse of which is placed on the plate bar of the mechanized casing set and then The roof protection thus made is additionally made from 2 to 3 haulers with the combine, and then the combine and the conveyor are disassembled, and stands are erected under both ends of the pit lowered into the holes, preferably metal friction or hydraulic stands. Figure 2lzon * u33 *% e% SSO 4ct PL
PL23791282A 1982-08-12 1982-08-12 Method of preparing a longwall-type working for putting it out of exploitation PL137053B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PL23791282A PL137053B1 (en) 1982-08-12 1982-08-12 Method of preparing a longwall-type working for putting it out of exploitation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PL23791282A PL137053B1 (en) 1982-08-12 1982-08-12 Method of preparing a longwall-type working for putting it out of exploitation

Publications (2)

Publication Number Publication Date
PL237912A1 PL237912A1 (en) 1984-02-13
PL137053B1 true PL137053B1 (en) 1986-04-30

Family

ID=20013787

Family Applications (1)

Application Number Title Priority Date Filing Date
PL23791282A PL137053B1 (en) 1982-08-12 1982-08-12 Method of preparing a longwall-type working for putting it out of exploitation

Country Status (1)

Country Link
PL (1) PL137053B1 (en)

Also Published As

Publication number Publication date
PL237912A1 (en) 1984-02-13

Similar Documents

Publication Publication Date Title
PL137053B1 (en) Method of preparing a longwall-type working for putting it out of exploitation
RU2101501C1 (en) Method of preservation of mine working
US3989302A (en) Continuous roof support system for tunnel boring
US4278293A (en) Apparatus for advancing a low-height drift through a subterranean structure
RU2295037C1 (en) Method for extracting thick inclined coal formation by column-chambers
RU1788256C (en) Method for mining and inclined coal seams of medium thickness
RU2209983C1 (en) Method of inrush space support
RU2011833C1 (en) Shaft-sinking complex for driving rock workings
RU2029086C1 (en) Method for extraction of thick gently dipping seams through their full thickness with seams separated by clay intercalation
GB2123457A (en) Excavating machine
SU848668A1 (en) Method of roof control at stoping face
Ahlbrecht Experiences and Outlook for Machine Sinking of Shafts and Developments in Conventional Sinking with Drilling and Blasting.
RU2059818C1 (en) Method for rill stoping of thick seams
SU1337522A1 (en) Method of mounting the support of machinized mining set on ground surface
GB2223044A (en) Setting mine roof arches
SU685826A1 (en) Method of mining gently sloping and sloping ore bodies
PL67148B1 (en)
SU1751334A1 (en) Method of isolating assembly site in mining coal seam from day surface
SU1250649A1 (en) Shield set for thick steep coal beds
PL77315B2 (en)
PL144062B1 (en) Method of rebuilding dog headings
RU2344292C1 (en) Method of development of thick flat-lying coal bed on clots of irregular shape
SU646054A1 (en) Method of mining steep ore deposits
PL153554B1 (en) Method for introducing mechanized wall lining to a newly formed wall excavation
PL138459B1 (en) Method of mining the rest of coal deposits using the longitudinal system with roof rock caving,in particular of deposits being endangered by crumps,fires and gases