NO320938B1 - Device for founding an installation on a seabed as well as a method for installing the device - Google Patents

Device for founding an installation on a seabed as well as a method for installing the device Download PDF

Info

Publication number
NO320938B1
NO320938B1 NO20023834A NO20023834A NO320938B1 NO 320938 B1 NO320938 B1 NO 320938B1 NO 20023834 A NO20023834 A NO 20023834A NO 20023834 A NO20023834 A NO 20023834A NO 320938 B1 NO320938 B1 NO 320938B1
Authority
NO
Norway
Prior art keywords
pile
anchoring
seabed
inner tube
pipe
Prior art date
Application number
NO20023834A
Other languages
Norwegian (no)
Other versions
NO20023834D0 (en
Inventor
Harald Johansen
Bjorn Bekken
Original Assignee
Hammerfest Strom As
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hammerfest Strom As filed Critical Hammerfest Strom As
Priority to NO20023834A priority Critical patent/NO320938B1/en
Publication of NO20023834D0 publication Critical patent/NO20023834D0/en
Priority to PCT/NO2003/000268 priority patent/WO2004015207A1/en
Priority to AU2003248519A priority patent/AU2003248519A1/en
Publication of NO320938B1 publication Critical patent/NO320938B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03BMACHINES OR ENGINES FOR LIQUIDS
    • F03B13/00Adaptations of machines or engines for special use; Combinations of machines or engines with driving or driven apparatus; Power stations or aggregates
    • F03B13/12Adaptations of machines or engines for special use; Combinations of machines or engines with driving or driven apparatus; Power stations or aggregates characterised by using wave or tide energy
    • F03B13/26Adaptations of machines or engines for special use; Combinations of machines or engines with driving or driven apparatus; Power stations or aggregates characterised by using wave or tide energy using tide energy
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03BMACHINES OR ENGINES FOR LIQUIDS
    • F03B17/00Other machines or engines
    • F03B17/06Other machines or engines using liquid flow with predominantly kinetic energy conversion, e.g. of swinging-flap type, "run-of-river", "ultra-low head"
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0091Offshore structures for wind turbines
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05BINDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
    • F05B2240/00Components
    • F05B2240/90Mounting on supporting structures or systems
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/30Energy from the sea, e.g. using wave energy or salinity gradient

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Oceanography (AREA)
  • Power Engineering (AREA)
  • Artificial Fish Reefs (AREA)
  • Revetment (AREA)
  • Other Liquid Machine Or Engine Such As Wave Power Use (AREA)
  • Foundations (AREA)

Description

Oppfinnelsen angår en forankring for en pel til en havbunn, spesielt for en anordning for å produsere elektrisk energi fra hav- og elvestrømmer. Videre vedrører oppfinnelsen en fremgangsmåte for forankring av en pel. The invention relates to an anchorage for a pile to a seabed, in particular for a device for producing electrical energy from sea and river currents. Furthermore, the invention relates to a method for anchoring a pile.

Forskning og utvikling på tidevannskraftverk eller anlegg for produksjon av elektrisk energi har pågått i mange tiår. Fordelene med tidevannsanlegg er blant annet at de eksempelvis i forhold til vindmøller, er forutsigbare og lite avhengige av vær. Likevel er svært få anlegg bygd til tross for at det på verdensbasis er svært store energimengder i tidevannsstrømmer. Årsaken er hovedsakelig av økonomisk og/eller miljømessig art. Disse og andre årsaker har medført at det er blitt utviklet anlegg som i sin helhet er plassert under havbunnen. Disse anleggene er bygget opp av moduler plassert på et fundament på havbunnen. Research and development on tidal power plants or facilities for the production of electrical energy has been ongoing for many decades. The advantages of tidal systems include, for example, that compared to wind turbines, they are predictable and little dependent on the weather. Nevertheless, very few facilities have been built despite the fact that there are very large amounts of energy in tidal currents worldwide. The reason is mainly of an economic and/or environmental nature. These and other reasons have led to the development of facilities that are entirely located under the seabed. These facilities are built up of modules placed on a foundation on the seabed.

Imidlertid er det en utfordring å installere et solid fundament i en riktig vinkel under havflaten på en økonomisk måte, fordi bunnforholdene kan være vanskelige og varierende, og fordi modulene som skai fundamenteres kan ha betydelige dimensjoner. Fundamentet må nødvendig vis plasseres i strømmende vannmasser, og i noen tilfeller installeres forholdsvis dypt. Fundamentet utsettes for betydelige mekaniske belastninger fra de strømmende vannmassene og fra turbinen de er ment å bære, og disse belastningene kan være fluktuerende og skape egensvtngninger i konstruksjonen. Fundamentene må kunne installeres raskt fordi arbeidet med installasjonen i mange tilfeller må skje i tidevannsskiftet for at strømmen i området ikke skal være så sterk at den hindrer arbeidet. However, it is a challenge to install a solid foundation at the right angle under the sea surface in an economical way, because the bottom conditions can be difficult and variable, and because the modules to be founded can have significant dimensions. If necessary, the foundation must be placed in flowing bodies of water, and in some cases installed relatively deep. The foundation is exposed to significant mechanical loads from the flowing water masses and from the turbine they are intended to carry, and these loads can be fluctuating and create inherent oscillations in the construction. The foundations must be able to be installed quickly because the installation work in many cases must take place at the change of tide so that the current in the area is not so strong that it hinders the work.

Det er tidligere utviklet lite teknikk på dette området fordi anlegg for produksjon av energi fra strømmende vannmasser, plassert på et fundament, og som i sin helhet er plassert under vann, har vært lite utbredt, og er av nyere dato. In the past, little technology has been developed in this area because facilities for the production of energy from flowing bodies of water, placed on a foundation, and which are placed entirely under water, have not been widespread, and are of recent date.

Montering av undervannskraftverk har i de fleste tilfeller tidligere nødvendig-gjort vanskelig, omfattende og kostbart dykkerarbeide. Installation of underwater power plants has in most cases previously necessitated difficult, extensive and expensive diving work.

Et eksempel på et slikt moduloppbygd tidevannsanlegg er beskrevet i patent-søknad NO 2001 0737, Hammerfest Strøm. Dette anlegget omfatter et fundament plassert på havbunnen og en eller flere moduler plassert på fundamentet. Modulene kan omfatte turbin, generator for elektrisk kraft, gir, og diverse elektriske komponenter. Disse turbinene er innfestet i fundamenter som kan omfatte søyler eller peler. An example of such a modular tidal system is described in patent application NO 2001 0737, Hammerfest Strøm. This facility comprises a foundation placed on the seabed and one or more modules placed on the foundation. The modules can include a turbine, generator for electrical power, gears, and various electrical components. These turbines are attached to foundations which may include columns or piles.

Det er vanskelig å få til en forankring på en havbunn på en holdbar og økonomisk måte, særlig ved vanskelige bunnforhold. Vannmasser som strømmer rundt konstruksjoner av denne type skaper lett egensvingninger i konstruksjonen, hvilket stiller store krav til fundamentet. Det er også en utfordring å få slike fundamenter, peler eller tårnrør plassert i riktig vinkel. Konstruksjoner som ikke går over vann er gunstige for å for å redusere forstyrrelse og oppbremsing av vannstrømmen. Oppbremsing og forstyrrelser i vannstrømmen kan påvirke turbinen på en uheldig måte. It is difficult to achieve an anchorage on a seabed in a durable and economical way, especially in difficult bottom conditions. Masses of water flowing around constructions of this type easily create inherent oscillations in the construction, which places great demands on the foundation. It is also a challenge to get such foundations, piles or tower pipes placed at the right angle. Constructions that do not go over water are beneficial in order to reduce disturbance and slowing down of the water flow. Slowing down and disturbances in the water flow can adversely affect the turbine.

Fra US 4,102,147 fremgår det en justerbar føringsjigg for å sikre at peler blir drevet med en riktig vinkel ned i en havbunn. Etter at en pel er drevet ned i havbunnen fjernes jiggen og brukes på nytt for å drive ned en ny pel. US 4,102,147 discloses an adjustable guide jig to ensure that piles are driven at a correct angle into a seabed. After a pile has been driven into the seabed, the jig is removed and used again to drive a new pile.

Det er et formål med den foreliggende oppfinnelsen å forenkle installasjon av fundamenter for komponenter for anlegg som i sin helhet er plassert under vann. Oppfinnelsen kan selvsagt også brukes som fundament for installasjon av moduler som stikker over vann. It is an aim of the present invention to simplify the installation of foundations for components for facilities that are entirely placed under water. The invention can of course also be used as a foundation for the installation of modules that protrude above water.

Dette oppnås med den foreliggende oppfinnelsen som angitt i de selvstendige krav. This is achieved with the present invention as stated in the independent claims.

Den foreliggende oppfinnelsen tilveiebringer en konstruksjon som kan fundamenteres på en enkel og økonomisk måte ved forskjellige bunnforhold, samt en fremgangsmåte for å installere konstruksjonen på bunnen. Det et formål med oppfinnelsen å tilveiebringe en konstruksjon som forenkler vedlikehold og utskiftning av komponenter. The present invention provides a construction that can be founded in a simple and economical way in different bottom conditions, as well as a method for installing the construction on the bottom. It is an object of the invention to provide a construction which simplifies the maintenance and replacement of components.

Fundamentet er spesielt tilpasset for en propellerturbin hvor bladene er pitchregulert for å kunne rotere bladene minst 180° fortrinnsvis i forbindelse med skifte av strømretning. Dermed kan den konstruksjonen monteres i en låst posisjon på en bærekonstruksjon (trenger ikke roteres, i motsetning til en vindmølle). The foundation is specially adapted for a propeller turbine where the blades are pitch-regulated to be able to rotate the blades at least 180°, preferably in connection with a change of current direction. Thus, that structure can be mounted in a locked position on a supporting structure (does not need to be rotated, unlike a windmill).

Bærekonstruksjonen eller fundamentet kan omfatte en kabelgate som over-føringskabelen festes til for å unngå utmattingsbrudd på grunn av kreftene fra vannstrømmen. The supporting structure or foundation may comprise a cable gate to which the transmission cable is attached to avoid fatigue failure due to the forces of the water flow.

Fundamentet omfatter fortrinnsvis en forankringspel eller et tårnrør. I en utførelsesform kan denne være drevet ned i bunnen. Et forsterkningsrør med forskaling kan være plassert rundt forankringspelen og være fylt med betong, og en bærepel kan bære huset og være fastgjort i forankringspelen for forankring av huset til bunnen. The foundation preferably comprises an anchoring pile or a tower pipe. In one embodiment, this can be driven into the bottom. A reinforcing pipe with formwork can be placed around the anchor pile and be filled with concrete, and a support pile can support the house and be fixed in the anchor pile to anchor the house to the bottom.

De beskrevne komponentene kan være satt sammen som moduler for å lette installasjon og vedlikehold. Under installasjon vil normalt huset med turbinen påmontert representere én modul og fundamentet en eller flere andre moduler. I en utførelsesform omfatter fundamentet tidligere nevnte forankringspel, forsterkningsrør med forskaling og bærepel som egne moduler. The described components can be assembled as modules to facilitate installation and maintenance. During installation, the house with the turbine attached will normally represent one module and the foundation one or more other modules. In one embodiment, the foundation comprises the previously mentioned anchoring pile, reinforcement pipe with formwork and bearing pile as separate modules.

Fordelene med moduloppbygning er vesentlig lavere anleggskostnader, muligheter for trinnvis utbygging, og enklere for nedbygging. The advantages of modular construction are significantly lower construction costs, possibilities for step-by-step expansion, and easier decommissioning.

I en fremgangsmåte for installasjon av anordningen ifølge oppfinnelsen tillates en stegvis installasjon, og på denne måten muliggjøres installasjon til tross for at store krefter forårsaket av vannstrømmer virker på konstruksjonen. In a method for installing the device according to the invention, a step-by-step installation is permitted, and in this way, installation is made possible despite large forces caused by water currents acting on the structure.

Et fundament i henhold til oppfinnelsen er beregnet for å bli senket ned på en havbunn fra et fartøy. Fundamentet omfatter et ytterrør som etter fullføring av fundamentet står støtt på havbunnen. Inne i ytterrøret er det installert et innerrør. I en alternativ utførelsesform blir innerrøret installert etter at ytterøret er plassert på havbunnen. Innerrørets vinkel i forhold til ytterrøret og derved det øvrige fundamentet og bunnen kan justeres med en innretning for dette formålet, slik at det etterfølgende tårnrøret eller pelen kan plasseres vertikalt eller i en annen ønsket vinkel. Vinkeljusteringen kan foregå ved at innerrørets nedre ende holdes på plass, og innerrørets øvre ende justeres med en egnet mekanisme for dette. Eksempler på slike mekanismer kan omfatte manuelt eller maskinelt opererte drivskruer, tannstenger eller hydrauliske sylindere. Mekanismen tillater fortrinnsvis justering om to akser, slik at innerrørets vinkel kan justeres fritt. A foundation according to the invention is intended to be lowered onto a seabed from a vessel. The foundation comprises an outer pipe which, after completion of the foundation, rests on the seabed. An inner tube is installed inside the outer tube. In an alternative embodiment, the inner pipe is installed after the outer pipe is placed on the seabed. The angle of the inner pipe in relation to the outer pipe and thereby the rest of the foundation and the bottom can be adjusted with a device for this purpose, so that the subsequent tower pipe or pile can be placed vertically or at another desired angle. The angle adjustment can take place by holding the lower end of the inner tube in place, and adjusting the upper end of the inner tube with a suitable mechanism for this. Examples of such mechanisms may include manually or mechanically operated drive screws, racks or hydraulic cylinders. The mechanism preferably allows adjustment about two axes, so that the angle of the inner tube can be adjusted freely.

I en utførelsesform er ytterrøret montert til kasseformede elementer ved hjelp av fagverk eller lignende. Kassene kan være lager av et tungt materiale, men er fortrinnsvis hule og fylles med vektmateriale ved installasjon. Kassenes innbyrdes avstand velges i forhold til antatt belastning, slik at fundamentets "fotavtrykk" er tilstrekklig til at det skapes en ønsket stabilitet. Etter inn-justering av innerrøret i forhold til ytterrøret, kan hulrommet mellom disse fylles med betong slik at rørene stabiliseres i forhold til hverandre. Ytterrørets diameter i forhold til innerrøret er tilpasset slik at en oppnår et ønsket justeringsintervall i forhold til vinkelen mellom rørene og slik at mellomrummet lett kan fylles med betong eller annet egnet fyllmateriale. In one embodiment, the outer tube is mounted to box-shaped elements by means of trusses or the like. The boxes can be made of a heavy material, but are preferably hollow and filled with weight material during installation. The mutual distance between the boxes is chosen in relation to the assumed load, so that the foundation's "footprint" is sufficient to create the desired stability. After adjusting the inner pipe in relation to the outer pipe, the cavity between these can be filled with concrete so that the pipes are stabilized in relation to each other. The diameter of the outer pipe in relation to the inner pipe is adapted so that a desired adjustment interval is achieved in relation to the angle between the pipes and so that the space can be easily filled with concrete or other suitable filling material.

Etter fundamenteringen, isettes et tårnrør eller pel tilpasset for påmontering av eksempelvis en turbin med hus og generator som beskrevet. Tårnrøret omfatter fortrinnsvis innstyringskoner som sikrer at tårnrøret blir sentrert i innerrøret og er innrettet parallelt med dette. Innstyringskonene er plassert rundt den delen av tårnrøret som er tilpasset for å gå inn i innerrøret, og er plassert slik at innstyring lettes, samtidig som det sikres at disse kan ta opp moment som påføres tårnrøret. Tårnrøret kan videre omfatte en eller flere kiler som kan gå inn i en eller flere slisse i innerrøret for riktig orientering av tårnrøret, fortrinnsvis i forhold til en strømretning av strømmende tidevann. Følgelig bør også innerrøret kunne justeres om sin lengdeakse i forhold til dette. Slissen bør være åpen i den ene enden med en åpning som er vesentlig bredere enn kilen, og avsmalne nedover for å lette innstyring av tårnrøret og kilen. Etter innstyring kan mellomrommet mellom tårnrøret og innerrøret sementeres, eller tårnrøret kan fastsettes på annen måte. After the foundation, a tower pipe or pile is inserted adapted for mounting, for example, a turbine with housing and generator as described. The tower pipe preferably comprises guide cones which ensure that the tower pipe is centered in the inner pipe and is aligned parallel to this. The steering cones are placed around the part of the tower tube that is adapted to go into the inner tube, and are positioned so that steering is facilitated, while also ensuring that these can take up the torque applied to the tower tube. The tower pipe can further comprise one or more wedges which can enter one or more slits in the inner pipe for correct orientation of the tower pipe, preferably in relation to a current direction of flowing tides. Consequently, the inner tube should also be able to be adjusted about its longitudinal axis in relation to this. The slot should be open at one end with an opening that is significantly wider than the wedge, and taper downwards to facilitate the insertion of the tower tube and the wedge. After alignment, the space between the tower pipe and the inner pipe can be cemented, or the tower pipe can be fixed in some other way.

Kort beskrivelse av de vedlagte figurer: Brief description of the attached figures:

Fig. 1a, 1 b er henholdsvis et topp og et sideriss av et fundament i henhold til en utførelsesform av oppfinnelsen; Fig. 2a-2c er et sideriss der en installasjonssekvens illustreres for utførelsesformen vist på fig 1, fra venstre mot høyre; Fig. 3a-3c viser ytterligere to trinn av installasjonssekvensen fra fig. 2, der fig. 3b er et toppriss av fig 3a; Fig. 4a-4c viser de to ytterligere trinn ved installasjonssekvensen fra fig. 2 og fig. 3 der fig. 4b er et toppriss av fig 4a; Fig.5a og 5b viser de to siste trinnene ved installasjonssekvensen fra fig. 2, fig. 3 og fig.4; Fig. 6 er et sideriss av et tidevannsanlegg påmontert en pel og et fundament i henhold til oppfinnelsen; Fig. 7a-7c er et sideriss av en installasjonssekvens av en annen utførelses-form av oppfinnelsen; Fig. 1a, 1b are respectively a top and a side view of a foundation according to an embodiment of the invention; Fig. 2a-2c is a side view in which an installation sequence is illustrated for the embodiment shown in Fig. 1, from left to right; Fig. 3a-3c show two further steps of the installation sequence from fig. 2, where fig. 3b is a top view of Fig. 3a; Fig. 4a-4c show the two further steps in the installation sequence from fig. 2 and fig. 3 where fig. 4b is a top view of Fig. 4a; Fig.5a and 5b show the last two steps of the installation sequence from fig. 2, fig. 3 and fig. 4; Fig. 6 is a side view of a tidal system mounted on a pile and a foundation according to the invention; Fig. 7a-7c is a side view of an installation sequence of another embodiment of the invention;

Fig 8a-8g viser ytterligere tre trinn av installasjonssekvensen fra fig. 7; og Fig 8a-8g show a further three steps of the installation sequence from fig. 7; and

Fig 9 viser en alternativ utførelsesform av installasjonen vist på fig. 7 og 8. Fig 9 shows an alternative embodiment of the installation shown in fig. 7 and 8.

I det følgende vil oppfinnelsen bli beskrevet med et utførelseseksempel. Figur 1 viser et fundament i henhold tit en utførelsesform av oppfinnelsen. Fundamentet er beregnet for å bli senket ned på en havbunn fra et fartøy. Fundamentet er sett henholdsvis ovenfra og fra siden og omfatter et ytterrør (1) som er forbundet ved hjelp av fagverk eller lignende til to kasseformede elementer (2). Kassene kan være lager av et tungt materiale, men er fortrinnsvis hule og fylles med vektmateriale ved installasjon. I ytterrøret (1) er det installert et innerrør (3). Innerrørets (3) vinkel i forhold til ytterrøret (1) og derved det øvrige fundamentet kan justeres med en skruinnretning som vist på bildet, med hydrauliske sylindere, tannstenger, drivskruer eller på annen måte. Figur 2 viser tre trinn under installasjon av fundamentet med ytterrør (1), innerrør (3) og kasseformede elementer (2). Trinnene viser fra venstre mot høyre nedsenkning av fundamentet og fylling av fundamentkassene med vektmateriale i de kasseformede elementer (2), eksempelvis stein, ved hjelp av et egnet fartøy, og fundamentet ferdig installert på bunnen. Figur 3 viser tre skisser der, fig 3a er et sideriss av et fundament plassert på en havbunn, og der det fremgår at dette kan bli plassert i en skrå vinkel for etterfølgende justering. Fig. 3b er et toppris av fig. 3a og viser hvordan vinkelen til fundamentets innerrør (3) justeres ved hjelp av skruer, hydrauliske stempeler/sylindere eller tilsvarende (4), skjematisk vist som skruer. Den viste utførelsesformen viser en dykker som justerer skruer med ratt manuelt, men justeringen kunne godt ha foregått automatisk med aktuatorer godt kjent på fagområdet. Når innerøret (3) er i vertikal stilling kan dette låses ved å sementere hulrommet mellom innerrøret (3) og ytterrøret (1) ved hjelp av slange fra overflaten (5) som vist på fig. 3c. Under installasjon av fundamentet er det sannsynlig at dette blir stående på skrå i forhold til en horisontal retning. Følgelig blir ikke ytterrøret (3) plassert i en vertikal stilling. Det er derfor nød-vendig å kunne justere den ovenfor beskrevne vinkel. Figur 4 viser hvordan tårnrøret installeres. Det fremgår tre skisser der. fig 4a viser et sideriss av hvordan tårnrøret (6) posisjoneres over fundamentets innerrør (3). Dette vil i de fleste tilfeller lettest utføres ved å etablere en ledewire mellom overflaten og fundamentet som tårnrøret styres ned langs (ikke vist på figuren). Tårnrøret er utstyrt med to eller flere sentreringskoner (7) på den delen av tårnrøret som skal entre inn i fundamentets innerrør (3). Disse skal sikre at tårnrøret (6) oppnår samme vertikale vinkel som fundamentets innerrør (3). In the following, the invention will be described with an exemplary embodiment. Figure 1 shows a foundation according to an embodiment of the invention. The foundation is designed to be lowered onto the seabed from a vessel. The foundation is seen respectively from above and from the side and comprises an outer pipe (1) which is connected by means of trusses or the like to two box-shaped elements (2). The boxes can be made of a heavy material, but are preferably hollow and filled with weight material during installation. An inner tube (3) is installed in the outer tube (1). The angle of the inner tube (3) in relation to the outer tube (1) and thereby the rest of the foundation can be adjusted with a screw device as shown in the picture, with hydraulic cylinders, racks, drive screws or in some other way. Figure 2 shows three steps during installation of the foundation with outer pipe (1), inner pipe (3) and box-shaped elements (2). The steps show from left to right the sinking of the foundation and filling of the foundation boxes with weight material in the box-shaped elements (2), for example stone, using a suitable vessel, and the foundation fully installed on the bottom. Figure 3 shows three sketches where, figure 3a is a side view of a foundation placed on a seabed, and where it appears that this can be placed at an oblique angle for subsequent adjustment. Fig. 3b is a top view of fig. 3a and shows how the angle of the foundation's inner tube (3) is adjusted using screws, hydraulic pistons/cylinders or equivalent (4), schematically shown as screws. The embodiment shown shows a diver adjusting screws with a steering wheel manually, but the adjustment could well have taken place automatically with actuators well known in the field. When the inner tube (3) is in a vertical position, this can be locked by cementing the cavity between the inner tube (3) and the outer tube (1) using a hose from the surface (5) as shown in fig. 3c. During installation of the foundation, it is likely that this will be left at an angle in relation to a horizontal direction. Consequently, the outer tube (3) is not placed in a vertical position. It is therefore necessary to be able to adjust the angle described above. Figure 4 shows how the tower pipe is installed. Three sketches appear there. fig 4a shows a side view of how the tower pipe (6) is positioned over the foundation's inner pipe (3). In most cases, this will most easily be done by establishing a guide wire between the surface and the foundation along which the tower pipe is guided down (not shown in the figure). The tower pipe is equipped with two or more centering cones (7) on the part of the tower pipe that must enter the foundation's inner pipe (3). These must ensure that the tower pipe (6) achieves the same vertical angle as the foundation's inner pipe (3).

Med tanke på turbinen som senere skal monteres på tårnrøret (6), må tårn-røret (6) installeres med en gitt orientering i forhold til retningen på vann-strømmen. Innerrøret (3) er derfor utstyrt med en orienteringsslisse (8) som vist på fig. 4b som er et toppris av fig. 4a. Considering the turbine that will later be mounted on the tower pipe (6), the tower pipe (6) must be installed with a given orientation in relation to the direction of the water flow. The inner tube (3) is therefore equipped with an orientation slot (8) as shown in fig. 4b which is a top view of fig. 4a.

Lokaliseringen av denne bestemmes etter at vannstrømmens retning er observert og benyttes for å montere en orienteringskile (9) på tårnrøret (6) som vist på fig 4c. Ved nedsenking av tårnrøret (6) vil denne orienteringskilen støte på kanten av innerrøret. Når dette skjer dreies tårnrøret (6) inntil orienteringskilen (9) glir inn i orienteringsslissen (8), og tårnrøret (6) kan senkes ned til endelig posisjon. På dette stadiet er tårnrøret (6) i riktig posisjon både med hensyn til vertikal vinkel og orientering, og mellomrommet mellom tårnrøret (6) og innerrøret (3) kan sementeres. Figur 5 viser installasjon av kabelrør (10) og inntrekking av kabelen. Kabelrøret (10) er festet til tårnrøret (6) og kan gjøres hengslet som vist på figuren. Kabelen til land kan installeres i dette røret enten ved at den trekkes inn i røret, som vist på figuren, eller ved at kabelrøret er delt og hengslet, og at kabelen dermed kan legges inn i kabelrøret. Kabelen vil normalt ha flere funksjoner integrert, slik som kraftledere, signallinjer og eventuelle hydrauliske/pneumatiske linjer. Når kabelen er ferdig installert i kabelrøret henges det av slik at koblingene mot nacellen er tilgjengelige i overkant av kabelrøret. Fig 6 viser en løftindusert propellerturbin (1t) som et eksempel på et element, i fonn av en modul for å generere kraft fra strømmende vannmasser, som kan monteres på et fundament i henhold til oppfinnelsen. Modulen omfatter en turbin (1t) med turbinblader. Bladene er pitchregulert for å kunne rotere minst 180 <0> i forbindelse med skifte av strømretning og er påmontert en vanntett kapsel eller hus (2t) med utstyr for omdanne turbinens rotasjon til elektrisk kraft, inklusiv en generator, eventuelt et gir og kontrollsystem. The location of this is determined after the direction of the water flow has been observed and is used to mount an orientation wedge (9) on the tower pipe (6) as shown in fig 4c. When lowering the tower tube (6), this orientation wedge will hit the edge of the inner tube. When this happens, the tower tube (6) is turned until the orientation wedge (9) slides into the orientation slot (8), and the tower tube (6) can be lowered to its final position. At this stage, the tower tube (6) is in the correct position both in terms of vertical angle and orientation, and the space between the tower tube (6) and the inner tube (3) can be cemented. Figure 5 shows the installation of the cable pipe (10) and the retracting of the cable. The cable pipe (10) is attached to the tower pipe (6) and can be hinged as shown in the figure. The cable to land can be installed in this pipe either by pulling it into the pipe, as shown in the figure, or by dividing the cable pipe and hinged it, and that the cable can thus be inserted into the cable pipe. The cable will normally have several functions integrated, such as power conductors, signal lines and any hydraulic/pneumatic lines. When the cable has been installed in the cable duct, it is suspended so that the connections to the nacelle are accessible above the cable duct. Fig 6 shows a lift-induced propeller turbine (1t) as an example of an element, in the form of a module for generating power from flowing water masses, which can be mounted on a foundation according to the invention. The module includes a turbine (1t) with turbine blades. The blades are pitch-regulated to be able to rotate at least 180 <0> in connection with a change of current direction and are mounted on a waterproof capsule or housing (2t) with equipment to convert the turbine's rotation into electrical power, including a generator, possibly a gear and control system.

Ved at turbinbladene kan roteres som beskrevet, kan den viste konstruksjonen monteres i en låst posisjon på bærekonstruksjonen eller fundamentet (trenger ikke roteres, i motsetning til en vindmølle). As the turbine blades can be rotated as described, the construction shown can be mounted in a locked position on the supporting structure or foundation (does not need to be rotated, unlike a windmill).

En bærekonstruksjon (3t) som bærer turbinen (1t) og kapselen (2t) kan også omfatte en kabelgate som en overføringskabel (4t) er festet til, for å unngå utmattingsbrudd på grunn av kreftene fra vannstrømmen. Overføringskabelen (4t) for den genererte kraften går fra den elektriske generatoren, gjennom den vanntette kapselen, og til et landanlegg (5t). Landanlegget (5t) transformerer den genererte kraften før den fases inn på et eksisterende strømnett. A support structure (3t) carrying the turbine (1t) and the capsule (2t) may also comprise a cableway to which a transmission cable (4t) is attached, to avoid fatigue failure due to the forces of the water flow. The transmission cable (4t) for the generated power runs from the electric generator, through the watertight capsule, and to a land plant (5t). The land plant (5t) transforms the generated power before it is phased into an existing power grid.

Installasjonen av anordningen i henhold til en annen utførelsesform av oppfinnelsen er vist på fig. 7 og fig. 8. Installasjonen er vist utført stegvis i trinnene (a) til (g). Trinnene (a), (b), (c) og (d) på fig 7 viser at en forankringspel eller et forankringsrør (11) først drives ned i bunnmassene. Utenpå dette installeres et kombinert forskaling og forsterkningsrør (12). Forskalingen (15) (vist som en kon) kan være av ulike materialer, inklusiv tøystoff som får en konisk form når den fylles med betong (senere i installasjonssekvensen). Dersom bunnmassene er ustabile med hensyn til utvasking kan dette avhjelpes med å plassere en stein/grusfylling (13) rundt kanten av forskalingen (15). Det bærende fundamentet for turbin (1) og kapsel (2) vist på fig. 6 installeres i forankringspelen (11) som er drevet ned i bunnen, og orienteres i forhold til strømretningen. Orienteringen kan foregå som angitt på figurene 4a, 4b og 4c ved at det monteres en orienteringskile (9) på tårnrøret (6) som vist på fig 4c. Ved nedsenking av tårnrøret (6) vil denne orienteringskilen støte på kanten av innerrøret. Når dette skjer dreies tårnrøret (6) inntil orienteringskilen (9) glir inn i orienteringsslissen (8), og tårnrøret (6) kan senkes ned til endelig posisjon Trinnene (e), (f) og (g) på fig. 8 viser at tomrommene mellom forankringspelen (6) og forsterkningsrøret (12), i forskalingen (15) samt mellom bærepelen (6) og forsterkningsrøret (12) fylles med betong. For å sørge for at tårnrøret står i riktig vinkel, kan dette i én utførelsesform justeres som angitt på fig. 3a, 3b og 3c. Justeringen må foregå før tårnrøret sementeres. Deretter frigjøres den hengslede kabelgaten (17), slik at den nedre delen roterer og faller ned til bunnen. The installation of the device according to another embodiment of the invention is shown in fig. 7 and fig. 8. The installation is shown to be carried out step by step in steps (a) to (g). Steps (a), (b), (c) and (d) in Fig. 7 show that an anchoring pile or an anchoring pipe (11) is first driven down into the bottom masses. On top of this, a combined formwork and reinforcement pipe (12) is installed. The formwork (15) (shown as a cone) can be made of various materials, including fabric which takes on a conical shape when filled with concrete (later in the installation sequence). If the bottom masses are unstable with regard to washing out, this can be remedied by placing a stone/gravel filling (13) around the edge of the formwork (15). The supporting foundation for turbine (1) and capsule (2) shown in fig. 6 is installed in the anchoring stake (11) which is driven into the bottom, and oriented in relation to the direction of the current. Orientation can take place as indicated in figures 4a, 4b and 4c by mounting an orientation wedge (9) on the tower pipe (6) as shown in figure 4c. When lowering the tower tube (6), this orientation wedge will hit the edge of the inner tube. When this happens, the tower tube (6) is turned until the orientation wedge (9) slides into the orientation slot (8), and the tower tube (6) can be lowered to its final position Steps (e), (f) and (g) in fig. 8 shows that the voids between the anchor pile (6) and the reinforcement pipe (12), in the formwork (15) and between the support pile (6) and the reinforcement pipe (12) are filled with concrete. To ensure that the tower tube stands at the correct angle, this can be adjusted in one embodiment as indicated in fig. 3a, 3b and 3c. The adjustment must take place before the tower pipe is cemented. The hinged cable gate (17) is then released, so that the lower part rotates and falls to the bottom.

Figur 9 viser en enkel utførelsesform der et ytterrør er drevet ned i en havbunn, og et tårnrør (6) med sentreringskoner (7) sementeres i ytterrøret. Figure 9 shows a simple embodiment where an outer pipe is driven down into a seabed, and a tower pipe (6) with centering cones (7) is cemented into the outer pipe.

Claims (9)

1. Forankring for forankring av en pel (6) til en havbunn, med et fundament omfattende et ytterrør (1) og et innerrør (3) plassert innvendig i ytterrøret (1), der pelens (6) nedre ende er tilpasset for plassering i innerrøret (3) og der ytterrøret (1) er fast forbundet med havbunnen, og der en justeringsanordning (4) kan justere en vinkel mellom innerrøret (3) og ytterrøret (1) karakterisert ved at: pelens (6) nedre ende for plassering i innerrøret (3), og innerrøret (3), omfatter en kile (9) og spor (8) for inngrep med hverandre for orientering av pelen (6) langs pelens (6) lengdeakse i forhold til fundamentet.1. Anchoring for anchoring a pile (6) to a seabed, with a foundation comprising an outer tube (1) and an inner tube (3) placed inside the outer tube (1), where the lower end of the pile (6) is adapted for placement in the inner tube (3) and where the outer tube (1) is firmly connected to the seabed, and where an adjustment device (4) can adjust an angle between the inner tube (3) and the outer tube (1) characterized in that: the lower end of the pile (6) for placement in the inner tube (3), and the inner tube (3), comprises a wedge (9) and groove (8) for engagement with each other for orientation of the pile (6) along the pile's (6 ) longitudinal axis in relation to the foundation. 2. Forankring for forankring av en pel (6) henhold til krav 1, hvor et mellomrom mellom ytterrøret (1) og innerrøret (3) er tilpasset for å bli sementert når forankringen er plassert på havbunnen.2. Anchorage for anchoring a pile (6) according to claim 1, where a space between the outer pipe (1) and the inner pipe (3) is adapted to be cemented when the anchorage is placed on the seabed. 3. Forankring for forankring av en pel (6) henhold til krav 1, hvor ytterrøret (1) er fastgjort til kasser (2), og hvor kassene (2) er tilpasset for ifylling av masse etter plassering på havbunnen.3. Anchorage for anchoring a pile (6) according to claim 1, where the outer pipe (1) is attached to boxes (2), and where the boxes (2) are adapted for filling in mass after placement on the seabed. 4. Forankring for forankring av en pel (6) henhold til krav 1, hvor pelen omfatter to eller flere sentreringskoner (7) på den delen av pelen som er tilpasset for å entre inn i innerrøret (3) for å sentrere pelen i innerrøret (3) og for å lette innstyring av pelen (6) i dette.4. Anchoring for anchoring a pile (6) according to claim 1, where the pile includes two or more centering cones (7) on the part of the pile which is adapted to enter the inner tube (3) to center the pile in the inner tube (3) and to facilitate the insertion of the pile (6) therein. 5. Forankring for forankring av en pel (6) henhold til krav 1, der innerrøret (3) utgjøres av en forankringspel (11) som er drevet ned i havbunnen og der ytterrøret (1) utgjøres av et forsterkningsrør (12), der en forskaling (15) er plassert rundt forankringspelen (12) og er fylt med betong, og der pelen (6) er fastgjort i forankringspelen (12).5. Anchoring for anchoring a pile (6) according to claim 1, where the inner pipe (3) consists of an anchoring pile (11) which is driven into the seabed and where the outer pipe (1) consists of a reinforcement pipe (12), where a formwork (15) is placed around the anchor pile (12) and is filled with concrete, and where the pile (6) is fixed in the anchor pile (12). 6. Forankring for forankring av en pel (6) henhold til krav 1, der pelen (6) er tilpasset for å bære et hus (2t) med en aksialturbin (1t), pelen (6) og huset (2t) utgjør moduler, og huset (2t) er tilpasset for fast forbindelse med pelen (6), slik at huset (2t) ikke kan rotere i forhold til havbunnen.6. Anchorage for anchoring a pile (6) according to claim 1, where the pile (6) is adapted to support a housing (2t) with an axial turbine (1t), the pile (6) and the housing (2t) constitute modules, and the housing (2t) is adapted for a fixed connection with the pile (6), so that the housing (2t) cannot rotate in relation to the seabed. 7. Forankring for forankring av en pel (6) henhold til krav 1, omfattende en forankringspel (11) og en kombinert forskaling (15) og forsterkningsrør (12), der forskalingen (15) kan være av ulike materialer, inklusiv tøystoff som får en konisk form når det fylles med betong.7. Anchoring for anchoring a pile (6) according to claim 1, comprising an anchoring pile (11) and a combined formwork (15) and reinforcement tube (12), where the formwork (15) can be made of different materials, including fabric that gets a conical shape when filled with concrete. 8. Forankring for forankring av en pel (6) henhold til krav 1, omfattende en kabelgate (17) som en overføringskabel (4t) er festet til for å unngå utmattingsbrudd på grunn av krefter vannstrømmen påfører, og overføringskabelen (4t) for den generert kraft fra huset og turbinen går fra en elektrisk generator gjennom huset (2t) og til et landanlegg (5t).8. Anchorage for anchoring a pile (6) according to claim 1, comprising a cable gate (17) to which a transmission cable (4t) is attached to avoid fatigue failure due to forces applied by the water flow, and the transmission cable (4t) for the generated power from the house and the turbine goes from an electric generator through the house (2t) and to a land plant (5t). 9. Fremgangsmåte for forankring med en forankring for en pel (6) i henhold til krav 1, karakterisert ved følgende trinn: plassere fundamentet omfattende ytterrøret (1) og innerrøret (3) plassert innvendig i ytterrøret (1), på en havbunn; justere en vinkel mellom innerrøret (3) og ytterrøret (1) med justeringsanordningen (4); og plassere pelens (6) nedre ende i innerrøret (3) ved å dreie pelen (6) inntil kilen (9) går i inngrep med spor (8).9. Procedure for anchoring with an anchor for a pile (6) according to claim 1, characterized by the following steps: placing the foundation comprising the outer tube (1) and the inner tube (3) located inside the outer tube (1), on a seabed; adjust an angle between the inner tube (3) and the outer tube (1) with the adjusting device (4); and place the lower end of the pile (6) in the inner tube (3) by turning the pile (6) until the wedge (9) engages with the groove (8).
NO20023834A 2002-08-13 2002-08-13 Device for founding an installation on a seabed as well as a method for installing the device NO320938B1 (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
NO20023834A NO320938B1 (en) 2002-08-13 2002-08-13 Device for founding an installation on a seabed as well as a method for installing the device
PCT/NO2003/000268 WO2004015207A1 (en) 2002-08-13 2003-08-06 Method and apparatus for the founding of an installation at the seabed
AU2003248519A AU2003248519A1 (en) 2002-08-13 2003-08-06 Method and apparatus for the founding of an installation at the seabed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
NO20023834A NO320938B1 (en) 2002-08-13 2002-08-13 Device for founding an installation on a seabed as well as a method for installing the device

Publications (2)

Publication Number Publication Date
NO20023834D0 NO20023834D0 (en) 2002-08-13
NO320938B1 true NO320938B1 (en) 2006-02-13

Family

ID=19913893

Family Applications (1)

Application Number Title Priority Date Filing Date
NO20023834A NO320938B1 (en) 2002-08-13 2002-08-13 Device for founding an installation on a seabed as well as a method for installing the device

Country Status (3)

Country Link
AU (1) AU2003248519A1 (en)
NO (1) NO320938B1 (en)
WO (1) WO2004015207A1 (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ITBA20040027U1 (en) * 2004-10-06 2005-01-06 Enertec Ag (METHOD OF) CONSTRUCTION OF A SUBMERGED PLATFORM WITH A THRUST BLOCKED TO BE USED AS A SUPPORT FOR THE INSTALLATION OF AIRCONDITIONER, OF ELECTROLISER FOR THE ELECTROLYSIS OF WATER AND OF OTHER PLANTS AND / OR MACHINERY, COMBINED WITH ACTIVITY
AU2012232970B2 (en) * 2006-01-18 2014-07-24 Marine Current Turbines Limited Gravity foundations for tidal stream turbines
GB0600942D0 (en) * 2006-01-18 2006-02-22 Marine Current Turbines Ltd Improvements in gravity foundations for tidal stream turbines
US20090302611A1 (en) * 2006-04-28 2009-12-10 Ian Masters Turbine
EP1980746B2 (en) 2007-04-11 2013-08-07 OpenHydro Group Limited A method of installing a hydroelectric turbine
DE102007043268A1 (en) * 2007-09-11 2009-03-12 Jähnig GmbH Felssicherung und Zaunbau Metal skeleton for the construction of submarine foundations
GB0809521D0 (en) * 2008-05-24 2008-07-02 Marine Current Turbines Ltd Installation of structures in water
DE102008032625B3 (en) * 2008-07-11 2009-08-27 Voith Patent Gmbh Lifting device for turbine generator unit of underwater power plant, has immersion component comprising gripping device that includes movable clamping elements for detachably securing turbine generator unit
FR2948153B1 (en) 2009-07-15 2011-12-30 Saipem Sa VERTICALLY ADJUSTED PYLONE MARITIME WIND TURBINE
AU2010293935A1 (en) * 2009-09-14 2012-04-19 Blade Offshore Services Ltd Method, apparatus and system for attaching an anchor member to a floor of a body of water
DE102009051425A1 (en) 2009-10-30 2011-05-05 Voith Patent Gmbh Flow power plant and method for its creation
AU2011288967B2 (en) * 2010-08-10 2012-09-20 Atlantis Resources Corporation Pte Limited Support apparatus for underwater power generator and method for deployment

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB959265A (en) * 1963-02-28 1964-05-27 Alexander Matheson Robertson M Improvements in and relating to piles
FR2184147A5 (en) * 1972-05-08 1973-12-21 Gem
US4408932A (en) * 1980-12-30 1983-10-11 Armco Inc. Subsea template levelling system and method
US4497592A (en) * 1981-12-01 1985-02-05 Armco Inc. Self-levelling underwater structure
JPS6124726A (en) * 1984-07-12 1986-02-03 Mitsubishi Heavy Ind Ltd Method of securing pile and bed seat
JP3754800B2 (en) * 1997-06-12 2006-03-15 新日本製鐵株式会社 Method and apparatus for erection of insertion-type steel pipe columns
GB9904107D0 (en) * 1999-02-24 1999-04-14 I T Power Limited Water current turbine with pitch control
GB9904108D0 (en) * 1999-02-24 1999-04-14 I T Power Limited Water tubine sleeve mounting
JP2002097651A (en) * 2000-09-25 2002-04-02 Kajima Corp Structure foundation
NO322927B1 (en) * 2001-02-13 2006-12-18 Hammerfest Strom As Device for the production of energy from streams in water bodies, an anchorage, and method of installation of the device

Also Published As

Publication number Publication date
AU2003248519A1 (en) 2004-02-25
WO2004015207A1 (en) 2004-02-19
NO20023834D0 (en) 2002-08-13

Similar Documents

Publication Publication Date Title
US11448193B2 (en) Self-aligning to wind facing floating platform supporting multi-wind turbines and solar for wind and solar power generation and the construction method thereon
EP1366287B1 (en) Apparatus for production of energy from currents in bodies of water, a foundation, and a method for the installation of the apparatus.
JP6039097B2 (en) Floating transport and installation structure, and floating wind turbine
EP3430259B1 (en) A floating wind turbine and a method for the installation of such floating wind turbine
JP5274329B2 (en) Offshore wind power generation facility and its construction method
US8475084B2 (en) Tidal flow power generation
EP2606228B1 (en) Offshore wind turbine and methods of installing same
DE102012020052B3 (en) Wind turbine installed in offshore, has tower which is rotatably arranged by vertical pivoting extension arms, so that height adjustment of rotors is performed, and outer ring is rotated with horizontal arms
US20110107953A1 (en) Floating Platform with Improved Anchoring
US20120121340A1 (en) Offshore vertical-axis wind turbine and associated systems and methods
US20170218919A1 (en) Wind tracing, rotational, semi-submerged raft for wind power generation and a construction method thereof
GB2348249A (en) Submersible water flow turbine with buoyancy chamber
JP2010223114A5 (en)
CN106164482A (en) Including the floating type down-wind turbines of floating foundation with for the method installing such wind turbine
NO320938B1 (en) Device for founding an installation on a seabed as well as a method for installing the device
NO316980B1 (en) Device for installing modules for a plant for the production of energy from streams in water bodies, an anchoring, as well as a method for installing the device.
JP2009248792A (en) Spar-type floating body structure for wind power generation on ocean, manufacturing method of the same, and installation method of the same
WO2005107425A2 (en) Offshore windmill electric generator
NO326937B1 (en) Device and method of marine yarn structure
CN109790823A (en) The auxiliary floating system of installation and/or transport for offshore structure and including the method for the system
KR20140130863A (en) Large diameter steel-pipe pile of reclamation type for offshore wind generation, and constructing method thereof
WO2010003416A1 (en) Offshore construction
WO2004022968A1 (en) Apparatus with an inclined carrying pillar for anchoring an axial turbine for the production of electric energy from water currents
CA2438041C (en) Apparatus for production of energy from currents in bodies of water, a foundation, and a method for the installation of the apparatus
US20220170220A1 (en) Method for the Installation of an Offshore Wind Turbine Tower

Legal Events

Date Code Title Description
MM1K Lapsed by not paying the annual fees