NL2005415C2 - Improvements in manufacturing and installing multiple offshore constructions. - Google Patents

Improvements in manufacturing and installing multiple offshore constructions. Download PDF

Info

Publication number
NL2005415C2
NL2005415C2 NL2005415A NL2005415A NL2005415C2 NL 2005415 C2 NL2005415 C2 NL 2005415C2 NL 2005415 A NL2005415 A NL 2005415A NL 2005415 A NL2005415 A NL 2005415A NL 2005415 C2 NL2005415 C2 NL 2005415C2
Authority
NL
Netherlands
Prior art keywords
jacket
construction
offshore
distance
piles
Prior art date
Application number
NL2005415A
Other languages
Dutch (nl)
Inventor
Robert Reinder Narold
Frank Cornelis Lange
Original Assignee
Heerema Marine Contractors Nl
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Heerema Marine Contractors Nl filed Critical Heerema Marine Contractors Nl
Priority to NL2005415A priority Critical patent/NL2005415C2/en
Application granted granted Critical
Publication of NL2005415C2 publication Critical patent/NL2005415C2/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/02Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
    • E02B17/027Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto steel structures
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/20Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
    • F03D13/22Foundations specially adapted for wind motors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039Methods for placing the offshore structure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039Methods for placing the offshore structure
    • E02B2017/0043Placing the offshore structure on a pre-installed foundation structure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0091Offshore structures for wind turbines
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/50Manufacturing or production processes characterised by the final manufactured product

Description

P30467NL00/WHA
Title: Improvements in manufacturing and installing multiple offshore constructions
Field of the invention
The present invention relates to offshore constructions and to a method of manufacturing and installing multiple offshore constructions.
5 Background and description of the prior art
In recent years, more and more constructions are built offshore. The constructions may be wind turbines, constructions for production of hydrocarbons, and other types of constructions.
A known problem of many of these constructions at sea is that a time consuming and 10 costly process is involved for construction and installation. Installation vessels can generally only work in good weather conditions in order to limit movements due to wind and waves. This means that only during a part of the year installation work can be performed. Other factors may also play a role.
Many different methods for installing offshore constructions have been conceived.
15 Some methods involve manufacturing the entire construction on land and towing the construction out to sea, followed by the installation of the construction.
Other methods involve constructing an offshore construction at sea with a purpose-built installation vessel. Such a vessel generally is very expensive.
Some methods involve the use of underwater divers, which are also costly and bring 20 along safety issues.
Some methods involve the use of gravity bases, which necessitates transport of these extremely heavy bases, or transport and placement of rock fill or concrete or other building materials.
Some methods involve a combination of the above aspects.
25 GB2378679A1 discloses a floating offshore construction for a wind turbine which uses tendons. This construction is suitable for deep water, but relatively expensive for medium and low water depths.
DE102004042066A1 discloses an offshore construction for wind turbines which uses piles. This construction works but is relatively expensive.
30 US2007269272A1 discloses a method which utilizes a gravity base. The method of US2007269272A1 is also quite expensive and quite cumbersome during installation.
Wind power is environmentally friendly and sustainable and demand for wind power is growing. Since the wind is stronger at sea and more space is available at sea, increasing -2- numbers of wind turbines are constructed at sea. Projects for generation of wind power generally involve large numbers of wind turbines. The cost per MW of power generated by wind energy is in general higher than the cost per generated MW in a more traditional manner, e.g. from coal or gas. To make wind energy more attractive from economical point 5 of view the cost per generated MW must be kept as low as possible. The mentioned examples are too expensive for this purpose.
Object of the invention
It is an object of the invention to provide a reliable and cost-effective alternative to 10 the prior art.
It is an object of the invention to provide a reliable and cost-effective way of manufacturing and installing offshore constructions in large numbers and in varying water depths.
15 Description of the invention
In one aspect, the invention provides a method of manufacturing and installing multiple offshore constructions, the method comprising: a. inserting at least three piles proximate to one another for each offshore construction at a target location into a seabed, such that the upper ends of the 20 piles are located at a distance D2 below the water level, b. manufacturing a jacket on shore and transporting the jacket to the target location, c. connecting the jacket to the upper ends of the piles, wherein the jacket intersects the water level and extends upwardly from the water level over a predetermined third distance D3, 25 d. repeating steps a), b) and c) for multiple offshore constructions at multiple target locations having different water depths, wherein the distance D2 is substantially the same for each offshore construction by variation of a distance D1 of the upper ends of the piles above the sea bed, and wherein a substantially same jacket is provided for each offshore construction such that the third distance D3 is 30 also substantially the same for each offshore construction.
The invention allows a simple and efficient construction of large numbers of offshore constructions through standardization of the design.
A pile is an elongate object suitable to be driven into the seabed. A pile may be hollow or solid. A pile may be - in top view - circular or square or have another form.
35 Generally, a pile is an elongate circular tubular object manufactured from steel.
A jacket or jacket structure is a 3-dimensional frame composed of beams. The beams are generally welded to one another. The jacket has legs which generally extend at a -3- relatively small angle to the vertical. The legs may also extend vertically. The jacket generally has cross-beams which extend substantially horizontally or diagonally. The legs and the cross-beams form a lattice structure.
The upper end of the jacket generally has a smaller footprint than the lower end of 5 the jacket, but this is not required. Generally, a jacket has four legs. However, three, five, six or a different number of legs are also possible.
In an embodiment, the water depth at the target locations lies between 10 and 60 meter and varies. The invention is particularly suitable for these water depths, which are found in the North Sea, amongst other places. The same jacket may be used in target 10 locations having a variation in water depth of at least 10 percent. In practice, the invention allows the use of standardized jackets in wind turbine fields of substantial size and with a substantial variation in water depth..
In an embodiment, the first distance D1 is selected in a range from 0 to 30 meter.
In an embodiment, a height of the multiple substantially same jackets, i.e. the second 15 distance D2 plus the third distance D3, lies in a range of 10-40 meter.
In an embodiment, the method comprises placing a wind turbine on top of each jacket, wherein the wind turbines are substantially the same for each offshore construction.
In an embodiment, the method comprises: placing an intermediate frame on the upper ends of the piles, wherein the intermediate 20 frame connects the upper ends of the piles to one another, and - placing the jacket on the intermediate frame.
The invention also relates to a plurality of offshore constructions, each offshore construction comprising: a. at least three piles which are inserted into a seabed proximate to one another at a 25 target location, such that the upper ends of the piles are located at a first distance D1 above the seabed and at a second distance D2 below the water level, b. a jacket being connected to the upper ends of the piles, wherein the jacket intersects the water level and extends upwardly from the water level over a predetermined third distance D3, 30 wherein the first distance D1 is chosen in dependence of the water depth at the respective target locations, such that the second distance D2 is substantially the same for each offshore construction, and wherein a substantially same jacket is provided for each offshore construction such that the third distance D3 is also substantially the same for each offshore construction.
35 In an embodiment, the water depth at the target locations lies between 10-60 meter and varies.
-4-
The invention also relates to a plurality of jackets for use in the method according to claim 1 or for use in the plurality of offshore constructions according to claim 8, the jackets being substantially the same and each jacket comprising connectors at the lower ends for connection to at least three piles.
5
List of figures
The invention is illustrated by way of example and not by way of limitation in the figures of the accompanying drawing in which like reference numerals refer to similar elements.
10 Figure 1 shows an offshore construction of the prior art.
Figure 2 shows another offshore construction of the prior art.
Figure 3 shows a side view of an offshore construction according to the invention.
Figure 4 shows a side view of multiple offshore constructions according to the invention.
15 Figure 5 shows a side view of another embodiment of the invention.
Detailed description of the figures
Turning to Figure 1, an offshore construction according to DE102004042066 is shown. The construction has three piles 2 and a tripod construction placed on top of the 20 three piles. The three piles 2 extend upwards from the seabed, intersect the water line and rise above the water over a substantial height. An advantage of this construction is that most installation work can be performed above the water line. A disadvantage of this embodiment is that it is heavy and costly
Turning to Figure 2, an embodiment according to US20070269272 is shown. This 25 construction has a gravity base, which is very heavy and cumbersome to construct.
Turning to Figure 3, the offshore construction 10 according to the invention is shown. The offshore construction 10 is located at a target location 11 and comprises four piles 12. Three piles 13 may also be provided, and a number of piles greater than four may also be provided. The piles 12 are hollow circular tubes, manufactured from steel. The piles 12 are 30 provided at a distance 42 from one another.
The piles 12 extend into the seabed 14 over a distance D4. This distance D4 is determined by the local soil conditions as well as the pile diameter.
The piles may typically have a diameter 50 of between 50 cm - 3 meter, depending on the load to be carried as well as the soil conditions.
35 The piles 12 extend upwards from the seabed 14 over a distance D1. The upper ends 16 of the piles 12 of the offshore construction 10 are provided at a distance (or altitude) D1 above the seabed. The upper ends 16 of the four piles 12 are located at a -5- substantially same distance D1 above the seabed 14. The upper ends 16 are submerged and are provided at a distance D2 beneath the water level. Thus, contrary to the device of DE102004042066, the piles 12 do not intersect the water line.
The at least three piles 12 provide a solid substructure for a jacket 20. The piles 12 are 5 relatively inexpensive to produce and install in varying lengths.
The jacket 20 comprises four legs 22 which extend upwards at a slight angle to the vertical. The jacket 20 further comprises diagonal cross-beams 24 which extend between the legs 22. The jacket has a height 26, a width and a length.
The jacket 20 has a base 30 which comprises four connectors 32 for connection of 10 the jacket 20 to the piles 12. Alternatively, connectors 32 are provided in a frame that is placed on top of the piles prior to installation of the jacket. The base 30 further comprises a number of horizontal cross beams 35 extending between the connectors 32. The base 30 has a footprint with a width and length which corresponds to the mutual distance 42 between the piles 12. The connectors 32 may be tubular sections with an open bottom and 15 a closed top, which fit over the upper end of the piles. The closed top of the connectors 32 acts as a bearing surface for transferring the weight of the jacket 20 onto the upper ends of the piles 12. The connectors may flare outwardly, to provide a guiding surface for the piles 12 during installation of the jacket 20.
The jacket 20 has an upper platform 36 which connects the four legs 24 and provides 20 further strength and stiffness to the jacket 20. The platform also serves as the support for a wind turbine 40, or any other construction which may be placed on the jacket 20. The width and length 37 of the platform 36 is smaller than the width and length 42 of the base 30 of the jacket 20. The jacket may have the same width and length but may (in top view) also be elongate, i.e. have a greater length than width.
25 The upper platform is provided at a distance D3 above the mean water level 33. This distance D3 is the same for all jackets in a certain field. The distance D3 may be dependent on the expected wave height in a certain area. The upper platform comprises a base for the installation of a wind turbine.
Turning to figure 4, three offshore constructions 10 at target locations 11 are shown. 30 Each target location 11 has a different water depth 28 (= D1 + D2), due to the varying level of the seabed 14.
For each target location, the distance D1 is different, i.e. the piles 12 extend above the seabed 14 over a different distance D1. The piles 12 may be of the same length for each target location 11, but may also have different lengths if the soil conditions allow.
35 The upper ends 16 of the piles 12 are all provided at substantially the same distance D2 from the water level 33. The jackets 20 are all the same, or substantially the same. This implies that the jackets 20 rise above the water over equal distances D3.
-6-
On the right hand side in Figure 4 it can be seen that the distance D1 may become zero or substantially zero. The upper ends 16 of the piles 12 of the offshore construction on the right are located at the level of the seabed 14 or are slightly above the level of the seabed 14. The connectors 32 are also located at or just above the level of the seabed 14.
5 Figure 5 shows an alternative embodiment. An intermediate frame 60 is placed on top of the piles 12 after these are installed. This intermediate frame 60 may form an interface between the piles 12 and the jacket 20. The connectors 61 may be adjustable in height and used to provide guidance and a level landing area for the connectors 32 of the jacket 20.
10
Method of construction and installation
During construction, the piles 12 are driven into the ground. This may be performed with an installation vessel as is known in the field of the art.
The piles may be guided by a framework which ensures that the piles 12 are 15 positioned in a correct position relative to one another. This framework may be laid on the seabed or may be attached to - or defined by - the installation vessel itself. Also, an auxiliary vessel holding an auxiliary frame may be provided.
An intermediate frame may be placed on top of the piles after installation. This intermediate frame may be adjustable and used to provide guidance and a level landing 20 area for the jacket.
The jacket 20 is constructed on land. The jacket may be constructed prior to installation of the piles 12, during the installation of the piles 12 or after the installation of the piles 12.
The jacket 20 is constructed in series in a controlled environment in a factory. This 25 allows mass-production of a large number of the same jackets 20 at relatively limited costs.
After construction, the jacket is transported to the target location 11. The jacket is positioned upright and lowered onto the upper ends 16 of the piles 12. The connectors 32 of the jacket 20 are constructed to form a connection with the upper ends 12 of the piles. The connection is made under water, at a distance D1 from the seabed and a distance D2 from 30 the water level.
In an embodiment, a locking device is provided to lock the jacket in position 20. However, the jacket 20 may also rest on the piles 12 under the influence of gravity.
After the jacket is installed, the wind turbine 40 may be installed. This may be performed in a separate operation with a separate vessel, at a later time.
35 A skilled person will understand that the average water depth of a group of target locations 11 may vary. Thus, it is possible that for one field of wind turbines, multiple first -7- jackets 20 having a first height 26 are used, whereas for another field of wind turbines, multiple second jackets with a different height are used.
It is also possible that multiple first as well as second or even third or more standardized jackets are used within a single field. This way an optimum between cost of 5 pile and jacket fabrication can be achieved.
As long as multiple jackets of the same dimensions are produced for varying water depths, the benefit of the invention is enjoyed.
The invention provides a lighter and more cost-effective offshore construction than the device of DE102004042066, in particular when large numbers are produced.
10 The invention is typically suitable for depths between 10 and 60 meter. A distance D1 of between 0 and 30 meter was found to provide satisfactory results, with a height 26 of the jacket of between 10 and 40 meter.
A skilled person will readily understand that the invention can be varied in multiple ways without departing from the scope of protection as is defined by the claims.

Claims (12)

1. Werkwijze voor het vervaardigen en het installeren van meerdere offshoreconstructies, de werkwijze omvattende: a. het op een doellocatie dicht bij elkaar in een zeebodem inbrengen van ten minste drie palen voor iedere offshoreconstructie, zodat de bovenste einden 5 van de palen zich op een afstand D2 onder het wateroppervlak bevinden, b. het op land vervaardigen van een jacket-constructie en het transporteren van de jacket-constructie naar de doellocatie, c. het verbinden van de jacket-constructie met de bovenste einden van de palen, waarbij de jacket-constructie de waterlijn snijdt en zich naar boven toe 10 over een vooraf bepaalde derde afstand D3 boven het wateroppervlak uitstrekt, d. het herhalen van stappen a, b en c voor meerdere offshoreconstructies op meerdere doellocaties met verschillende waterdieptes, waarbij de afstand D2 in hoofdzaak dezelfde is voor iedere offshoreconstructie door het variëren van 15 een afstand D1 van de bovenste einden van de palen tot de zeebodem, en waarbij in hoofdzaak dezelfde jacket-constructie wordt toegepast voor iedere offshoreconstructie, zodanig dat de derde afstand D3 ook in hoofdzaak hetzelfde is voor iedere offshoreconstructie.Method for manufacturing and installing multiple offshore constructions, the method comprising: a. Inserting at least three piles at a target location close to each other in a seabed for each offshore construction, so that the upper ends of the piles are positioned on a distance D2 below the water surface, b. producing a jacket construction on land and transporting the jacket construction to the target location, c. connecting the jacket structure to the upper ends of the posts, wherein the jacket structure intersects the water line and extends upwards over a predetermined third distance D3 above the water surface, d. repeating steps a, b and c for a plurality of offshore structures at a plurality of target locations with different water depths, wherein the distance D2 is substantially the same for each offshore construction by varying a distance D1 from the upper ends of the posts to the seabed, and wherein substantially the same jacket construction is used for each offshore construction, such that the third distance D3 is also substantially the same for each offshore construction. 2. Werkwijze volgens conclusie 1, waarbij de waterdiepte op de doellocaties ligt 20 tussen 10 en 60 meter en varieert.2. Method as claimed in claim 1, wherein the water depth at the target locations is between 10 and 60 meters and varies. 3. Werkwijze volgens conclusie 1 of 2, waarbij de waterdiepte op de doellocaties met een in hoofdzaak dezelfde jacket-constructie varieert met ten minste 10% tussen een doellocatie met een minimale waardediepte en een doellocatie met een maximale waterdiepte.Method according to claim 1 or 2, wherein the water depth at the target locations with a substantially the same jacket construction varies by at least 10% between a target location with a minimum value depth and a target location with a maximum water depth. 4. Werkwijze volgens een van de voorgaande conclusies, waarbij de eerste afstand D1 is gekozen uit een bereik van 0 tot 30 meter.Method according to any of the preceding claims, wherein the first distance D1 is selected from a range of 0 to 30 meters. 5. Werkwijze volgens een van de voorgaande conclusies, de werkwijze omvattende het plaatsen van een windturbine op iedere jacket-constructie, waarbij de windturbines in hoofdzaak hetzelfde zijn voor iedere offshoreconstructie.A method according to any one of the preceding claims, the method comprising placing a wind turbine on each jacket construction, wherein the wind turbines are substantially the same for each offshore construction. 6. Werkwijze volgens een van de voorgaande conclusies, omvattende: - het plaatsen van een tussenframe op de bovenste einden van de palen, waarbij het tussenframe de bovenste einden van de palen met elkaar verbindt, en - het plaatsen van de jacket-constructie op het tussenframe. -9-Method as claimed in any of the foregoing claims, comprising: - placing an intermediate frame on the upper ends of the posts, the intermediate frame connecting the upper ends of the posts to each other, and - placing the jacket construction on the intermediate frame. -9- 7. Meervoudig aantal offshoreconstructies, waarbij iedere offshoreconstructie omvat: a. ten minste drie palen die op een doellocatie dicht bij elkaar zijn ingebracht in 5 een zeebodem, zodanig dat de bovenste einden van de palen zich op een eerste afstand D1 boven de zeebodem bevinden en op een tweede afstand D2 onder het wateroppervlak, b. een jacket-constructie die is verbonden met de bovenste einden van de palen, waarbij de jacket-constructie de waterlijn snijdt en zich over een vooraf 10 bepaalde derde afstand D3 boven het wateroppervlak uitstrekt, waarbij de eerste afstand D1 in afhankelijkheid van de waterdiepte op de respectieve doellocaties is gekozen, zodanig dat de tweede afstand D2 in hoofdzaak hetzelfde is voor iedere offshoreconstructie, en waarbij een in hoofdzaak dezelfde jacket-constructie is verschaft voor iedere offshoreconstructie 15 zodanig dat de derde afstand D3 ook in hoofdzaak hetzelfde is voor iedere offshoreconstructie.7. Multiple number of offshore structures, each offshore structure comprising: a. At least three piles that are inserted close to each other at a target location in a seabed, such that the upper ends of the piles are at a first distance D1 above the seabed and at a second distance D2 below the water surface, b. a jacket construction connected to the upper ends of the posts, the jacket construction intersecting the water line and extending over a predetermined third distance D3 above the water surface, the first distance D1 depending on the water depth on the respective target locations is chosen such that the second distance D2 is substantially the same for each offshore construction, and wherein a substantially the same jacket construction is provided for each offshore construction such that the third distance D3 is also substantially the same for each offshore construction. 8. Meervoudig aantal offshoreconstructies volgens conclusie 7, waarbij de waterdiepte op de doellocaties ligt tussen 10 en 60 meter en varieert.A plurality of offshore structures according to claim 7, wherein the water depth at the target locations is between 10 and 60 meters and varies. 9. Meervoudig aantal offshoreconstructies volgens conclusies 7 of 8, waarbij de 20 eerste afstand D1 is gekozen uit een bereik van 0 tot 30 meter.9. Multiple number of offshore structures according to claims 7 or 8, wherein the first distance D1 is selected from a range of 0 to 30 meters. 10. Meervoudig aantal offshoreconstructies volgens een van de conclusies 7-9, waarbij iedere offshoreconstructie een tussenframe omvat dat op de palen steunt, en een jacket-constructie omvat die steunt op het tussenframe.A plurality of offshore structures according to any of claims 7-9, wherein each offshore structure comprises an intermediate frame that rests on the posts, and a jacket structure that rests on the intermediate frame. 11. Meervoudig aantal jacket-constructies voor gebruik in de werkwijze volgens 25 conclusie 1 of voor gebruik in het meervoudig aantal offshoreconstructies volgens conclusie 7, waarbij de jacket-constructies in hoofdzaak hetzelfde zijn en waarbij iedere jacket-constructie connectoren omvat nabij de onderste einden voor verbinding met de ten minste drie palen.11. Multiple number of jacket structures for use in the method of claim 1 or for use in the multiple number of offshore structures according to claim 7, wherein the jacket structures are substantially the same and each jacket structure comprises connectors near the lower ends for connection to the at least three posts. 12. Meervoudig aantal jacket-constructies volgens conclusie 11, waarbij de jacket- 30 constructies in hoofdzaak hetzelfde zijn en waarbij iedere jacket-constructie connectoren omvat nabij de onderste uiteinden voor verbinding met een frame dat is gemonteerd op de ten minste drie palen of voor directe verbinding met de bovenste einden van de palen.12. A plurality of jacket constructions according to claim 11, wherein the jacket constructions are substantially the same and wherein each jacket construction comprises connectors near the lower ends for connection to a frame mounted on the at least three posts or for direct connection to the upper ends of the posts.
NL2005415A 2010-09-28 2010-09-28 Improvements in manufacturing and installing multiple offshore constructions. NL2005415C2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
NL2005415A NL2005415C2 (en) 2010-09-28 2010-09-28 Improvements in manufacturing and installing multiple offshore constructions.

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
NL2005415A NL2005415C2 (en) 2010-09-28 2010-09-28 Improvements in manufacturing and installing multiple offshore constructions.
NL2005415 2010-09-28

Publications (1)

Publication Number Publication Date
NL2005415C2 true NL2005415C2 (en) 2012-03-29

Family

ID=43927625

Family Applications (1)

Application Number Title Priority Date Filing Date
NL2005415A NL2005415C2 (en) 2010-09-28 2010-09-28 Improvements in manufacturing and installing multiple offshore constructions.

Country Status (1)

Country Link
NL (1) NL2005415C2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013213A (en) * 2016-07-25 2016-10-12 福建永福电力设计股份有限公司 Offshore wind power pile foundation capable of increasing unit capacity and using method thereof

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1634998A1 (en) * 2004-09-08 2006-03-15 Maierform Maritime Technology GmbH Transport and foundation of functional units, in particular offshore wind turbines.

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1634998A1 (en) * 2004-09-08 2006-03-15 Maierform Maritime Technology GmbH Transport and foundation of functional units, in particular offshore wind turbines.

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013213A (en) * 2016-07-25 2016-10-12 福建永福电力设计股份有限公司 Offshore wind power pile foundation capable of increasing unit capacity and using method thereof

Similar Documents

Publication Publication Date Title
CN109838351B (en) Floating type automatic wind-to-water wind power generation equipment with multiple wind power generators
EP3039192B1 (en) Method of installing a foundation for an offshore wind turbine and a template for use herein
US20180195250A1 (en) Modular offshore wind turbine foundation and modular substructure with suction caissons
JP4575061B2 (en) Construction method for offshore wind power generation facilities
CN202295230U (en) Floating-type offshore wind power foundation
KR101044753B1 (en) Apparatus for correcting inclination of offshore wind power generation facility using internal compartment
US8689721B2 (en) Vertically installed spar and construction methods
KR101459649B1 (en) Double layered floating-gravity structure for installing offshore substructure, and method for constructing offshore substructure using the same
JP2010539378A (en) Offshore vertical axis wind turbine and related systems and methods
EP2574698B1 (en) Method and device for driving a multiplicity of piles into a seabed
KR20140122219A (en) Foundation structure of an offshore plant, in particular an offshore wind turbine, which foundation structure is to be installed at a low noise level, and installation method therefor
KR101044752B1 (en) Apparatus for amending slope when installing marine wind power generation facility
KR101573064B1 (en) Jig for constructing pile of green energy generating plant on the sea and method for constructing pile on the sea using this same
KR101554939B1 (en) Suction pile substructure and constructing method using thereof
EP2963183A1 (en) Offshore support structure, offshore tower installation with the offshore support structure and offshore wind power plant with the offshore tower installation
EP2463524B1 (en) Marine wind turbine whole machine
KR20230026975A (en) Offshore wind farm structure installed by jacking method and its construction method
KR101342445B1 (en) Hybrid spport structure for offshore wind power generator
KR101597705B1 (en) Verticality control testing device for suction base of offshore wind power
CN105178347A (en) Offshore anemometer tower foundation, offshore anemometer platform and application method of offshore anemometer platform
KR101205576B1 (en) Pile Construction Apparatus to support Horizontal Stability on Irregular Sea-Bed
NL2005415C2 (en) Improvements in manufacturing and installing multiple offshore constructions.
JP2016084660A (en) Foundation structure of off-shore wind turbine generator
KR101384168B1 (en) installation method of slab foundation for offshore wind power generator using position senser
KR101629477B1 (en) A construction methode of marine structures

Legal Events

Date Code Title Description
SD Assignments of patents

Effective date: 20130808

V1 Lapsed because of non-payment of the annual fee

Effective date: 20140401