KR960031717A - Prevention method of main girder collapse that occurs when the top of the composite girder is replaced with the precast top - Google Patents
Prevention method of main girder collapse that occurs when the top of the composite girder is replaced with the precast top Download PDFInfo
- Publication number
- KR960031717A KR960031717A KR1019950024255A KR19950024255A KR960031717A KR 960031717 A KR960031717 A KR 960031717A KR 1019950024255 A KR1019950024255 A KR 1019950024255A KR 19950024255 A KR19950024255 A KR 19950024255A KR 960031717 A KR960031717 A KR 960031717A
- Authority
- KR
- South Korea
- Prior art keywords
- precast
- main girder
- box
- girder
- top plate
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D22/00—Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2/00—Bridges characterised by the cross-section of their bearing spanning structure
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
목적purpose
합성거더 상판을 프리캐스트 상판으로 바꿀 경우의 이미 설치된 합성거더 상판을 철거하고, 프리캐스트 상판을 가설할때의 거더와 프리캐스트 상판을 합성하기전에 생기는 메인거더의 붕괴를 방지함과 동시에 기존의 방지대책에 있어서의 결점을 제거하는 것을 목적으로 한다.When replacing the composite girder top plate with the precast top plate, remove the already installed composite girder top plate and prevent the collapse of the main girder before combining the girder and the precast top plate when constructing the precast top plate. It aims at eliminating the fault in countermeasures.
구성Configuration
프리캐스트 상판에 형성한 상자빼기부를 메인거더의 상플랜지위에 위치시켜서 놓고 메인거더 방향의 상자빼기부 사이를 고정점간 거리로하고 상자빼기부에서 프리캐스트 상판과 메인거더를 임시 고정하고, 프리캐스트 상판의 가설완료후에 고정을 해제하여 상자빼기부에 콘크리트를 타설하는 것을 특징으로 한다.Place the box removing part formed on the precast upper plate on the upper flange of the main girder, and set the distance between the box removing parts in the direction of the main girder to a fixed point distance, and temporarily fix the precast upper plate and the main girder at the box removing part, and precast upper plate After the completion of the hypothesis of releasing the fixing is characterized in that the concrete is poured into the minus the box.
Description
본 내용은 요부공개 건이므로 전문내용을 수록하지 않았음Since this is an open matter, no full text was included.
제1도는 본 발명의 실시예 주요부를 도시하는 제4도의 부분 확대도,FIG. 1 is a partially enlarged view of FIG. 4 showing the main part of an embodiment of the present invention;
제2도는 본 발명의 실시예를 도시하는 평면도,2 is a plan view showing an embodiment of the present invention,
제3도는 본 발명의 실시예를 도시하는 측면도,3 is a side view showing an embodiment of the present invention,
제4도는 제3도의 A-A 단면도.4 is a cross-sectional view taken along line A-A of FIG.
제5도는 다른 실시예를 도시하는 단면도로, (A)는 메인거더와 프리캐스트 상판과의 고정전의 설명도, (B)는 메인거더와 프리캐스트 상판의 고정후의 설명도,5 is a cross-sectional view showing another embodiment, (A) is an explanatory diagram before fixing the main girder and the precast top plate, (B) is an explanatory diagram after fixing the main girder and the precast top plate,
제6도는 종래의 가로지지재 증강공법에 있어서의 증설 가로거더와 메인거더의 고정점간 거리를 도시하는 설명도,6 is an explanatory diagram showing the distance between the fixed transverse girder and the fixed point of the main girder in the conventional horizontal support material reinforcement method;
제7도는 프리캐스트 상판에 형성된 상자빼기부(箱拔部)와 메신거더의 고정점간 거리를 도시하는 설명도,FIG. 7 is an explanatory diagram showing the distance between the box removing portion formed on the precast upper plate and the fixed point of the messenger girder;
제8도는 치수를 특정한 메인거더의 개략도,8 is a schematic diagram of a main girder having dimensions,
제9도는 본 발명에 관한 실시예의 시공순서를 나타내는 흐름도.9 is a flowchart showing a construction procedure of an embodiment according to the present invention.
Claims (3)
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP95-43656 | 1995-02-09 | ||
JP7043656A JP2655120B2 (en) | 1995-02-09 | 1995-02-09 | Prevention method of side buckling of main girder falling when replacing precast slab with composite slab |
Publications (2)
Publication Number | Publication Date |
---|---|
KR960031717A true KR960031717A (en) | 1996-09-17 |
KR0163632B1 KR0163632B1 (en) | 1998-12-15 |
Family
ID=12669910
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1019950024255A KR0163632B1 (en) | 1995-02-09 | 1995-08-05 | Preventing girder method from its buckling in replacing composite girder deck with precast concrete deck |
Country Status (2)
Country | Link |
---|---|
JP (1) | JP2655120B2 (en) |
KR (1) | KR0163632B1 (en) |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5307682B2 (en) * | 2009-10-09 | 2013-10-02 | 大成建設株式会社 | Girder member and precast slab joint structure and slab erection method |
CN105507155A (en) * | 2015-12-04 | 2016-04-20 | 上海市基础工程集团有限公司 | Construction process for installation of small-segment steel box girder |
JP6771987B2 (en) * | 2016-08-05 | 2020-10-21 | オリエンタル白石株式会社 | Floor slab replacement method for steel synthetic girders and PC floor slab |
CN106320192B (en) * | 2016-10-27 | 2018-10-09 | 武汉理工大学 | A kind of beam section replacing and reinforcing method for large span concrete continuous beam bridge |
JP6826872B2 (en) * | 2016-12-05 | 2021-02-10 | 鹿島建設株式会社 | How to remove concrete slab and how to install new concrete slab |
JP6181332B1 (en) * | 2017-02-21 | 2017-08-16 | オリエンタル白石株式会社 | Simultaneous replacement method of floor slabs for multiple bridges |
JP7189807B2 (en) * | 2019-03-01 | 2022-12-14 | ショーボンド建設株式会社 | Temporary fixing jig for PCa floor slab |
CN110409314B (en) * | 2019-08-15 | 2023-10-10 | 中国五冶集团有限公司 | Automatic unidirectional limiting and locking device and method for closure section of continuous rigid frame bridge |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0387407A (en) * | 1989-05-10 | 1991-04-12 | Sato Tekko Kk | Floor slab by precast slab of bridge and its installing device |
-
1995
- 1995-02-09 JP JP7043656A patent/JP2655120B2/en not_active Expired - Fee Related
- 1995-08-05 KR KR1019950024255A patent/KR0163632B1/en not_active IP Right Cessation
Also Published As
Publication number | Publication date |
---|---|
KR0163632B1 (en) | 1998-12-15 |
JP2655120B2 (en) | 1997-09-17 |
JPH08218327A (en) | 1996-08-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR960031717A (en) | Prevention method of main girder collapse that occurs when the top of the composite girder is replaced with the precast top | |
IT1283189B1 (en) | METHOD FOR THE REALIZATION OF A COMPOSED BEAM AND BEAM MADE IN THIS | |
CN205077525U (en) | Basement waterproof concrete bottom plate post -cast strip is with novel waterstop structure | |
JPS6364565B2 (en) | ||
CN210622367U (en) | Prestressed concrete hollow slab reinforcing device | |
KR200254651Y1 (en) | Prestressed composite beam | |
KR200222325Y1 (en) | Connection structure of PS beam using connecting plate and connecting rebar | |
FR2724680B1 (en) | IMPROVEMENTS ON A PANEL FORMING LOST FORMWORK FOR THE CONSTRUCTION OF WORKS OF CIVIL ENGINEERING, AND PARTICULARLY POOLS, AND METHOD OF IMPLEMENTING SUCH PANELS | |
CN110205943A (en) | The construction method of prefabricated freely-supported small box girder end floor beam | |
JP3047817B2 (en) | Method of placing concrete so that it can be separated | |
CN217812367U (en) | Template is exempted from to punch and can be had enough to meet need small-size template anchor clamps | |
KR200229731Y1 (en) | The structure system of composite girder with partial slab concrete and the time casting the rest slab concrete | |
KR100437258B1 (en) | Rehabilitating method of rahman hinged-joint bridge | |
KR101389819B1 (en) | Continuous prestressed concrete girder structure and construction method thereof | |
KR960034617A (en) | Method for manufacturing prestressed composite beam by abdominal reinforcement | |
KR950032906A (en) | Bridge construction method | |
JPH05306543A (en) | Device for joining precast reinforced concrete column and beam | |
KR100529140B1 (en) | The method of construction and a structure for simple composite girder | |
KR200394381Y1 (en) | Prestressed concrete girder structure with projected section above the top flange | |
JPS5930842B2 (en) | How to build a long concrete bridge | |
JPH0665979A (en) | Filling method of hole of concrete slab | |
SU975869A1 (en) | Method for reconstructing reinforced concrete ribbed girder span structure of bridge | |
JP3062871B2 (en) | Floor slab construction method | |
NO144430B (en) | CONNECTION FOR CONCRETE ELEMENTS. | |
KR100286614B1 (en) | Continuous process of pcs beam by weight |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20100720 Year of fee payment: 13 |
|
LAPS | Lapse due to unpaid annual fee |