KR950013840B1 - Automatic servetance unit and operation method of overload of in service control - Google Patents

Automatic servetance unit and operation method of overload of in service control Download PDF

Info

Publication number
KR950013840B1
KR950013840B1 KR1019930004194A KR930004194A KR950013840B1 KR 950013840 B1 KR950013840 B1 KR 950013840B1 KR 1019930004194 A KR1019930004194 A KR 1019930004194A KR 930004194 A KR930004194 A KR 930004194A KR 950013840 B1 KR950013840 B1 KR 950013840B1
Authority
KR
South Korea
Prior art keywords
overload
local
processor
slp
monitoring
Prior art date
Application number
KR1019930004194A
Other languages
Korean (ko)
Other versions
KR940022947A (en
Inventor
김윤희
이경휴
임덕빈
Original Assignee
한국전기통신공사
조백제
재단법인한국전자통신연구소
양승택
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한국전기통신공사, 조백제, 재단법인한국전자통신연구소, 양승택 filed Critical 한국전기통신공사
Priority to KR1019930004194A priority Critical patent/KR950013840B1/en
Publication of KR940022947A publication Critical patent/KR940022947A/en
Application granted granted Critical
Publication of KR950013840B1 publication Critical patent/KR950013840B1/en

Links

Classifications

    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01QANTENNAS, i.e. RADIO AERIALS
    • H01Q1/00Details of, or arrangements associated with, antennas

Landscapes

  • Debugging And Monitoring (AREA)
  • Computer And Data Communications (AREA)

Abstract

an OA having a response time measuring unit for measuring a treatment time through a time of the input from that of the output of transaction of a first measuring unit for measuring the used amount of a CPU; a measuring unit for measuring the amount of the transaction that is not treated in the real time and is at the standby state; a CCP overload check reference value storing part for storing an overload check reference value under connection with the CCP overload watching and local check processing unit; a double-structured CCP having a CCP overload local controlling unit for controlling the overload corresponding to an overload control level of a corresponding processor under connection with the CCP overload watching and local check processing unit; a SLP overload watching and local check processing unit for collecting data from each measuring unit by being connected thereto; a SLP overload check reference value storing part for storing an overload check reference value under connection with the SLP overload watching and local check processing unit; a double-structured SLP having a SLP overload local controlling unit for controlling the overload corresponding to an overload control level of a corresponding processor under connection with the SLP overload watching and local check processing unit; an overload synthesis check processing unit for the overload degree of the all systems according to the local overload state of the processor; a system overload degree displaying unit for displaying the overload degree to an operator under connection with the overload synthesis check processing unit; an overload synthesis controlling unit for controlling the overload by being connected to the overload synthesis check processing unit; and a system process obstacle watching unit for watching the obstacle within the system.

Description

지능망 서비스 제어용 분산형 과부하 자동 감시 장치 및 그 운용 방법Distributed overload automatic monitoring device for intelligent network service control and its operation method

제 1 도는 본 발명이 적용되는 지능망 서비스 제어용 트랜잭션 처리 시스팀의 개략도.1 is a schematic diagram of an intelligent network service control transaction processing system to which the present invention is applied.

제 2 도는 본 발명에 지능망 서비스 제어용 트랜잭션 처리 시스팀의 상세 블럭 구성도.2 is a detailed block diagram of a transaction processing system for intelligent network service control according to the present invention.

제 3 도는 본 발명에 따른 과부하 감시 및 국부 판단 처리 방법에 대한 전체 흐름도.3 is an overall flowchart of the overload monitoring and local determination processing method according to the present invention.

제 4 도는 본 발명에 따른 과부하 종합 판단 처리기의 처리흐름도.4 is a flow chart of the overload comprehensive determination processor according to the present invention.

* 도면의 주요부분에 대한 부호의 설명* Explanation of symbols for main parts of the drawings

11, 21 : 응답시간 측정기 12, 22, 51, 61 : CPU 사용량 측정기11, 21: response time meter 12, 22, 51, 61: CPU usage meter

13, 23, 52, 62 : 트랜잭션 대기량 측정기13, 23, 52, 62: Transaction Wait Meter

14, 24 : CCP 과부하 국부 제어기14, 24: CCP overload local controller

15, 25: CCP 과부하 감시 및 국부 판단 처리기15, 25: CCP Overload Monitoring and Local Decision Processor

16, 26 : CCP 과부하 판단 기준값 저장소16, 26: CCP overload judgment reference value store

53, 63 : SLP 과부하 감시 및 국부 판단 처리기53, 63: SLP Overload Monitoring and Local Decision Processor

54, 64 : SLP 과부하 국부 제어기54, 64: SLP overload local controller

55, 65 : SLP 과부하 판단 기준값 저장소55, 65: SLP Overload Judgment Store

71 : 시스팀 각 처리기 장애 감시기 72 : 과부하 종합 판단 처리기71: each processor failure monitor 72: overload comprehensive judgment processor

73 : 시스팀 과부하 정도표시 장치 74 : 과부하 종합 제어기73: system overload degree display device 74: overload integrated controller

본 발명은 지능망 서비스 제어용 분산형 과부하 자동 감시 장치 및 그 운용 방법에 관한 것이다.The present invention relates to a distributed overload automatic monitoring device for intelligent network service control and an operation method thereof.

지능망 서비스 제어는 서비스 수행 교환기로부터 발생하는 서비스호(입력 트랜잭션)를 처리하여 결과(출력 트랜잭션)를 다시 서비스 수행교환기에 전송하는 일을 수행하는데 이때 호의 과량으로 인하여 처리 시스팀의 한계를 넘을 경우 시스팀의 과부하를 발생하게 되고 예측치 못한 비정상적인 동작을 함으로써 본연의 서비스 제어가 불가능하게 되는 경우가 발생한다. 그러므로 이와 같은 현상을 미연에 방지하여 시스팀을 보호하고 시스팀의 신뢰도를 향상시키기 위하여 과부하 관리를 행하여야 한다. 그런데, 이같은 과부하 상태를 판단하기 위하여 종래에 사용되는 과부하 상태 판단 처리방법은 시스팀의 과부하 상태를 판단하는 처리기가 중앙집중적으로 OAP(Operation and Administration Processor)에만 존재하여 일률적으로 과부하 상태를 결정하게 되는 중앙집중적 처리구조를 가지고 있으므로 시스팀의 변화에 대한 능동적인 대처가 어려우며, 모든 프로세서에 대해서 동일한 기준으로 판단을 행하게 되므로써 각 프로세서의 다양한 특성에 대한 적절한 과부하 판단 기준값을 결정하는 것이 어려운 문제점이 있다.The intelligent network service control processes the service call (input transaction) originating from the service execution exchange and sends the result (output transaction) back to the service execution exchange. When the excess of the call exceeds the limit of the processing system, Overloading and unexpected abnormal operation can lead to inadequate service control. Therefore, overload management should be carried out to prevent such a phenomenon and protect the system and improve the reliability of the system. However, in the conventional overload state determination processing method for determining such an overload state, a processor for determining the overload state of the system is centrally located in the OAP (Operation and Administration Processor) to determine the overload state uniformly. Because of the intensive processing structure, it is difficult to proactively cope with changes in the system, and it is difficult to determine an appropriate overload judgment reference value for various characteristics of each processor by making the same criteria for all processors.

상기 문제점을 해결하기 위하여 안출된 본 발명은, 과부하를 자동 탐지할 수 있도록 각 프로세서 과부하 상태를 판단하는 국부 판단 처리기를 두어 각 프로세서 과부하 상태를 정확하게 진단한 후 전 시스팀 과부하 상태를 결정하는 과부하 종합 판단 처리기에 통보하여 처리할 수 있도록 한 지능망 서비스 제어용 분산형 과부하 자동 감시 장치 및 방법을 제공하는데 그 목적이 있다.In order to solve the above problems, the present invention has a local determination processor for determining each processor overload state so as to automatically detect the overload. It is an object of the present invention to provide a distributed overload automatic monitoring apparatus and method for intelligent network service control that can notify and process a processor.

상기 목적을 달성하기 위하여 본 발명인 지능망 서비스 제어용 트랜잭션 처리 시스팀은, 트랜잭션의 입력시기부터 출력시기를 측정하여 처리시간 여부에 대한 측정을 하는 응답시간 측정수단, 각 프로세서의 사용량을 측정하는 CPU 사용량 측정수단, 각 프로세서내의 트랜잭션의 흐름상에서 실시간으로 처리하지 못하고 대기하고 있는 트랜잭션의 양을 측정하기 위한 트랜잭션 대기량 측정수단, 상기 각 측정수단에 연결되어 각 측정기로부터의 데이타를 수집하는 CCP 과부하 감시 및 국부 판단 처리수단과, 상기 CCP 과부하 감시 및 국부 판단 처리수단에 연결되어 과부하 판단 기준값을 저장하기 위한 CCP 과부하 판단 기준값 저장소, 상기 CCP 과부하 감시 및 국부 판단 처리수단에 연결되어 해당 프로세서의 과부하 제어 레벨에 따라 해당되는 과부하 제어를 하도록 조치하는 CCP 과부하 국부 제어수단을 구비하여 동일 구조로서 이중화 구조로 되어 있는 제1, 제2CCP와, 프로세서의 사용량을 측정하는 CPU 사용량 측정수단, 각 프로세서내의 트랜잭션의 흐름상에서 실시간으로 처리하지 못하고 대기하고 있는 트랜잭션의 양을 측정하기 위한 트랜잭션 대기량 측정수단, 상기 각 측정수단에 연결되어 각 측정수단으로부터의 데이타를 수집하는 SLP 과부하 감시 및 국부 판단 처리수단, 상기 SLP 과부하 감시 및 국부 판단 처리수단에 연결되어 과부하 판단 기준값을 저장하기 위한 SLP 과부하 판단 기준값 저장소, 상기 SLP 과부하 감시 및 국부 판단 처리수단에 연결되어 해당 프로세서의 과부하 제어 레벨에 따라 해당되는 과부하 제어를 하도록 조치하는 SLP 과부하 국부 제어수단을 구비하여 동일 구조로서 이중화되어 있는 제1, 제2SLP와, 상기 과부하 감시 및 국부 판단 처리수단에 LAN 장치로 연결되어 과부하인 경우 각 프로세서의 국부 과부하 상태 추이에 따라 전 시스팀의 과부하 정도를 결정하는 과부하 종합 판단 처리수단, 상기 과부하 종합 판단 처리수단에 연결되어 운용자가 인식할 수 있도록 표시하기 위한 시스팀 과부하 정도표시장치, 상기 과부하 종합 판단 처리수단에 연결되어 과부하를 제어하여 감소시키도록 하기 위한 과부하 종합 제어수단, 상기 과부하 종합 판단 처리수단에 연결되어 시스팀내 각 처리기의 장애를 감시하는 시스팀 처리기 장애 감시수단을 구비하는 OAP를 구비하는 것을 특징으로 한다.In order to achieve the above object, the present invention provides an intelligent network service control transaction processing system comprising: response time measuring means for measuring whether a processing time is measured from an input time of a transaction and a CPU time measuring means for measuring the usage of each processor; Transaction latency measurement means for measuring the amount of transactions waiting in real time on the flow of transactions in each processor; CCP overload monitoring and local judgment connected to each measurement means to collect data from each measurement instrument; A CCP overload determination reference value storage for storing an overload determination reference value connected to a processing means, the CCP overload monitoring and local determination processing means, and connected to the CCP overload monitoring and local determination processing means according to the overload control level of the processor. Overload control CCP overload local control means, which have the same structure as the first and second CPUs, which have a redundant structure, CPU usage measuring means for measuring processor usage, and cannot process in real time in the flow of transactions in each processor. Transaction latency measurement means for measuring the amount of transactions waiting, SLP overload monitoring and local determination processing means connected to each measurement means for collecting data from each measurement means, and the SLP overload monitoring and local determination processing means An SLP overload determination reference value storage for storing an overload determination reference value, and an SLP overload local control means connected to the SLP overload monitoring and local determination processing means to perform a corresponding overload control according to the overload control level of the processor. Redundant as the same structure Overload comprehensive determination processing means connected to the first and second SLPs and the overload monitoring and local determination processing means to determine the degree of overload of the entire system according to the local overload state trend of each processor in case of overload. A system overload degree display device connected to the overload comprehensive judgment processing unit for displaying by the operator so as to be recognized by the overload comprehensive control unit, an overload comprehensive control unit connected to the overload comprehensive judgment processing unit to control and reduce the overload; And an OAP connected to the processing means and having a system processor failure monitoring means for monitoring a failure of each processor in the system.

그리고, 지능망 서비스 제어용 분산형 과부하 자동 감시 장치의 운용 방법은 과부하 감시가 시작되면 각 트랜잭션 처리기(CCP, SLP)가 작동하는가 여부를 판단하는 제 1 단계, 상기 제 1 단계 수행 후, CCP1/2 혹은 SLP1/2가 동시 장애되면 과부하 감시 및 국부 판단 처리기 중지 및 시스팀이 정지하여 종료되도록 하는 제 2 단계, 상기 제 1 단계 수행 후, 각 프로세서가 CCP로 동작할 경우는 CCP내의 측정기를 구동하여 데이타를 발생시키고, CCP의 측정값과 과부하 판단 기준 저장소의 입력 기준값을 수집하여 비교로직으로 이 수집데이타를 테이블화하는 제 3 단계, 상기 제 3 단계 수행 후, 이 두 테이블을 매핑시켜 비교하여 과부하시에는 국부과부하 레벨을 결정하여 과부하 데이타 및 국부과부하 레벨을 과부하 종합판단 처리기에 전달함과 동시에 국부과부하 제어기에 전달하여 국부과부하 제어를 시작하도록 요청하는 제 4 단계, 상기 제 4 단계 수행 후, 비 과부하시에는 전에 과부하 상태였는지를 파악하여 전에 과부하인 경우에는 과부하가 해소된 경우이므로 이를 종합판단기에 통보하고 아닌 경우에는 주기적인 감시 시간대역에서 CCP/SLP 각 측정기를 정지시키고 리턴하는 제 5 단계, 상기 제 1 단계 수행 후, SLP인 경우에는 SLP내의 측정기를 구동하여 데이타를 발생시키고 SLP의 측정값과 과부하 판단 기준 저장소의 입력 기준값을 수집하여 비교로직으로 이 수집데이타를 테이블화하는 제 6 단계, 상기 제 6 단계 수행 후, 이 두 테이블을 매핑시켜 비교하여 과부하시에는 국부과부하 레벨을 결정하여 과부하 데이타 및 국부과부하 레벨을 과부하 종합판단 처리기에 전달함과 동시에 국부과부하 제어기에 전달하여 국부과부하 제어를 시작하도록 요청하는 제 7 단계, 상기 제 7 단계 수행후, 비 과부하시에는 전에 과부하상태였는지를 파악하여 전에 과부하인 경우에는 과부하가 해소된 경우이므로 이를 종합판단기에 통보하고 아닌 경우에는 주기적인 감시 시간대역에서 CCP/SLP 각 측정기를 정지시키고 리턴하는 제 8 단계로 이루어지는 것을 특징으로 한다.In addition, the method of operating the distributed overload automatic monitoring device for intelligent network service control includes the first step of determining whether each transaction processor (CCP, SLP) is operated when the overload monitoring starts, and after performing the first step, CCP1 / 2 or If the SLP1 / 2 fails simultaneously, after overload monitoring and local determination processor stop and the system stops and terminates, after performing the first step, each processor operates the CCP to drive the data in the CCP. After the third step of performing the third step, and after performing the third step to collect the measured value of the CCP and the input reference value of the overload judgment reference repository and the logic to table the collected data, the two tables are mapped and compared The local overload level is determined and the overload data and the local overload level are transmitted to the overload comprehensive judgment processor. After performing step 4 and requesting to start local overload control, it is determined whether the previous overload condition has been performed when the non-overload was performed. If not, the fifth step of stopping and returning each CCP / SLP measuring instrument in the periodic monitoring time band; after performing the first step, in case of SLP, the measuring instrument in the SLP is driven to generate data, and the measured value and overload of the SLP is After performing the sixth step of collecting the input reference value of the judgment reference storage and comparing the logical data with the sixth step, after performing the sixth step, the two tables are mapped and compared to determine the local overload level in case of overload. The local overload level is transmitted to the overload integrated judgment processor and simultaneously to the local overload controller. After performing the seventh step and the seventh step of requesting to start the local overload control, it is determined whether the overload state was previously performed when the non-overload was performed. And an eighth step of stopping and returning each CCP / SLP meter in a periodic monitoring time band.

이하, 첨부된 도면을 참조하여 본 발명의 일 실시예를 상세히 설명한다.Hereinafter, with reference to the accompanying drawings will be described an embodiment of the present invention;

제 1 도는 본 발명이 적용되는 지능망 서비스 제어용 트랜잭션 처리 시스팀의 개략도로서, 도면에서 10, 20는 CCP(Common Channel Signaling Processor), 30, 40는 LAN(Local Area Network)장치, 50, 60은 SLP(Service Logic Processor), 70은 OAP(Operation and Adiministration Processor)를 각각 나타낸다.1 is a schematic diagram of an intelligent network service control transaction processing system to which the present invention is applied, in which, 10 and 20 are Common Channel Signaling Processor (CCP), 30 and 40 are Local Area Network (LAN) devices, and 50 and 60 are SLP ( Service Logic Processor) and 70 represent an Operation and Adiministration Processor (OAP), respectively.

본 발명에 따른 지능망 서비스 제어용 트랜잭션 처리 시스팀은, 서비스 교환기로부터 질의가 입력되면 이에 대한 적절한 응답을 제공하여 각종 통신망 서비스를 제어하는 역할을 하는 시스팀으로 도면에 도시한 바와 같이, 시스팀의 입력은 신호망에 연결된 트랜잭션 입출력 링크장치를 통하여 트랜잭션에 입력되며, 이 트랜잭션은 신호프로토콜 메시지 형태로 되어 있어 전단프로세서인 CCP(10, 20)에서 프로토콜 레이어 처리상의 상호 연결제어 및 트랜잭션 핸들러 처리를 하고, 이 결과는 다시 LAN 장치(30, 40)를 거쳐 후단 프로세서인 SLP(50, 60)에서 프로토콜상의 다이알로그 핸들러 처리하며, 서비스별 관련 응답을 하기 위하여 SLP(50, 60)의 메모리 데이타 베이스에 존재하는 서비스별 로직 데이타에 의해 응답을 생성하기 위하여 다시 역순으로 결과를 전송한다. 여기에서, 이 시스팀이 고성능 및 고신뢰도를 추구하고자 각 처리 장치를 이중화하였으며, 정상적인 상황에서 트랜잭션의 처리는 전후단 전후단 프로세서(10, 20, 50, 60)에서 상호 로드를 균형있게 처리하며 한 요소가 비정상적일 경우는 모든 로드 분담은 정상적인 프로세서가 수행한다. 여기에서 이 시스팀에 트랜잭션 입력량은 사용자의 무제한적인 통신망의 특성상 시스팀의 처리 용량에 무관하게 사용될 수 있다.The transaction processing system for intelligent network service control according to the present invention is a system that controls various communication network services by providing an appropriate response when a query is input from a service exchanger, as shown in the drawing. The transaction is inputted to the transaction through the I / O link device connected to the transaction. The transaction is in the form of a signal protocol message, so that the CCP (10, 20), the front end processor, performs the interconnection control and transaction handler processing in the protocol layer processing. SLP 50, 60, which is a later processor, processes the dialogue handler on the protocol through LAN devices 30, 40, and services per service existing in the memory database of SLP 50, 60 for service-specific responses. The result is then returned in reverse order to generate a response by the logic data. The. Here, the system has duplicated each processing unit in pursuit of high performance and high reliability, and under normal circumstances, the processing of transactions is balanced between mutual loads in the front, back, front and back processors (10, 20, 50, 60). If an element is abnormal, all load sharing is performed by the normal processor. Here, the transaction input amount to this system can be used regardless of the processing capacity of the system due to the nature of the user's unlimited network.

이러한 이유로 다량의 트랜잭션 입력이 발생하였을 경우 시스팀의 과부하로 시스팀 본연의 기능을 처리하지 못하는 경우와 더불어 시스팀의 장애요인을 발생시킬 수 있으므로 이를 사전에 조치해야 하는 기능이 필수적이다. 특히 이 시스팀의 구성이 분산처리 구조식으로 되어 있으므로 각 분산장치인 전후단 프로세서(10, 20, 50, 60)에 따라 과부하의 특성이 다르고, 과부하 상태를 결정하는 기준도 다르게 설정되어질 수 있으므로 프로세서별 과부하 상태를 토대로 시스팀 전체를 종합적으로 판단하여 전 시스팀 차원의 과부하를 감시하여야 한다. 이를 위하여 시스팀의 운용관리 측면의 OAP(70)내에 과부하 종합 판단 장치를 구성하고 시스팀의 과부하에 대한 자동 감시를 수행하는 장치를 분산 장치별로 부여하여 시스팀의 과부하 정도를 감시한다.For this reason, if a large amount of transaction input occurs, the system may be unable to handle its original functions due to the overload of the system, and the system may cause obstacles. In particular, since this system has a distributed processing structure, the characteristics of the overload are different according to the front and rear processors 10, 20, 50, and 60, which are distributed devices, and the criteria for determining the overload state may be set differently. Based on the overload condition, the entire system should be judged comprehensively to monitor overload at the entire system level. To this end, the overload comprehensive determination device is configured in the OAP 70 of the operation management of the system, and a device for performing automatic monitoring of the overload of the system is assigned to each distributed device to monitor the degree of overload of the system.

제 2 도는 본 발명에 따른 지능망 서비스 제어용 트랜잭션 처리 시스팀의 상세 블럭 구성도로서, 도면에서 11, 21은 응답시간 측정기, 12, 22, 51, 61은 CPU 사용량 측정기, 13, 23, 52, 62는 트랜잭션 대기량 측정기, 14, 24는 CCP 과부하 국부 제어기, 15, 25는 CCP 과부하 감시 및 국부 판단 처리기, 16, 26은 CCP 과부하 판단 기준값 저장소, 53, 63은 SLP 과부하 감시 및 국부 판단 처리기, 54, 64는 SLP 과부하 국부 제어기, 55, 65는 SLP 과부하 판단 기준값 저장소, 71은 시스팀 각 처리기 장애 감시기, 72는 과부하 종합 판단 처리기, 73은 시스팀 과부하 정도표시장치, 74는 과부하 종합 제어기를 각각 나타낸다.2 is a detailed block diagram of an intelligent network service control transaction processing system according to the present invention, in which 11, 21 are response time meters, 12, 22, 51, and 61 are CPU usage meters, and 13, 23, 52, and 62 are Transaction Latency Meter, 14, 24 are CCP Overload Local Controllers, 15, 25 are CCP Overload Monitoring and Local Decision Processors, 16 and 26 are CCP Overload Determination Reference Stores, 53, 63 are SLP Overload Monitoring and Local Decision Processors, 54, 64 denotes an SLP overload local controller, 55 and 65 represent an SLP overload judgment reference value store, 71 represents a system fault handler, 72 represents an overload comprehensive judgment processor, 73 represents a system overload degree indicating device, and 74 represents an overload integrated controller.

도면에 도시한 바와 같이, 지능망 서비스 제어용 트랜잭션 처리 시스팀은, CCP(10)내에 트랜잭션의 입력시기부터 출력시기까지의 처리시간 여부에 대한 측정을 행하는 응답시간 측정기(11), 각 프로세서의 사용량을 측정하는 CPU 사용량 측정기(12), 각 프로세서내의 트랜잭션의 흐름상에서 실시간으로 처리하지 못하고 대기하고 있는 트랜잭션의 양을측정하기 위한 트랜잭션 대기량 측정기(13), 상기 각 측정기(11 내지 13)에 연결되어 각 측정기로부터의 데이타를 수집하는 CCP 과부하 감시 및 국부 판단 처리기(15), 상기 CCP 과부하 감시 및 국부 판단 처리기(15)에 연결되어 과부하 판단 기준값을 저장하기 위한 CCP 과부하 판단 기준값 저장소(16), 상기 CCP 과부하 감시 및 국부 판단 처리기(15)에 연결되어 해당 프로세서의 과부하 제어 레벨에 따라 해당되는 과부하 제어를 하도록 조치하는 CCP 과부하 국부 제어기(14)를 구비하고, CCP(20)은 상기 CCP(10)과 동일하게 구성된 이중화 구조이며, SLP(50)는 각 프로세서의 사용량을 측정하는 CPU 사용량 측정기(54), 각 프로세서내의 트랜잭션의 흐름상에서 실시간으로 처리하지 못하고 대기하고 있는 트랜잭션이 양을 측정하기 위한 트랜잭션 대기량 측정기(52), 상기 각 측정기(51, 52)에 연결되어 각 측정기로부터의 데이타를 수집하는 SLP 과부하 감시 및 국부 판단 처리기(53), 상기 SLP 과부하감시 및 국부 판단 처리기(53)에 연결되어 과부하 판단 기준값을 저장하기 위한 SLP 과부하 판단 기준값 저장소(55), 상기 SLP 과부하 감시 및 국부 판단 처리기(53)에 연결되어 해당 프로세서의 과부하 제어 레벨에 따라 해당되는 과부하 제어를 하도록 조치하는 SLP 과부하 국부 제어기(54)를 구비하고, SLP(60)는 상기 SLP(50)와 동일하게 구성된 이중화 구조이며, 상기 과부하 감시 및 국부 판단 처리기(15, 25, 53, 63)에서 과부하인 경우의 각 프로세서의 국부과부하 상태 추이에 따라 전 시스팀의 과부하 정도를 결정하는 과부하 종합 판단 처리기(72), 상기 과부하 종합 판단 처리기(72)에 연결되어 운용자가 인식할 수 있도록 표시하기 위한 시스팀 과부하 정도표시장치(73), 상기 과부하 종합 판단 처리기(72)에 연결되어 과부하를 감소시키도록 하기 위한 과부하 종합 제어기(74), 상기 과부하 종합 판단 처리기(72)에 연결되어 시스팀내 각 처리기의 장애를 감시하는 시스팀 처리기 장애 감시기(71)로 구성된다.As shown in the figure, the transaction processing system for intelligent network service control measures the usage time of each processor and the response time measuring device 11 which measures whether the processing time is from the input time to the output time of the transaction in the CCP 10. CPU usage meter 12, a transaction latency meter 13 for measuring the amount of transactions waiting to be processed in real time on the flow of transactions in each processor, each connected to each of the meter (11 to 13) CCP overload determination reference value storage 16 for storing an overload determination reference value connected to a CCP overload monitoring and local determination processor 15 for collecting data from a meter, the CCP overload monitoring and local determination processor 15, and the CCP Connected to the overload monitoring and local determination processor 15, the corresponding widow according to the overload control level of the processor The CCP overload local controller 14 is configured to take control, and the CCP 20 has a duplex structure configured in the same manner as the CCP 10, and the SLP 50 is a CPU usage meter for measuring the usage of each processor ( 54) is connected to each of the transaction latency measuring device 52 and each of the measuring devices 51 and 52 to measure the amount of transactions waiting in real time on the flow of transactions in each processor. SLP overload determination reference value storage 55 for storing the overload determination reference value connected to the collected SLP overload monitoring and local determination processor 53, the SLP overload monitoring and local determination processor 53, and the SLP overload monitoring and local determination It is provided with an SLP overload local controller 54 that is connected to the processor 53 and measures to perform the corresponding overload control according to the overload control level of the processor. In addition, the SLP 60 has a redundant structure configured in the same manner as the SLP 50, and according to the local overload state transition of each processor when the overload monitoring and local determination processor 15, 25, 53, and 63 are overloaded. An overload comprehensive determination processor 72 for determining the degree of overload of the entire system, a system overload degree display device 73 for displaying to be recognized by an operator so as to be connected to the overload comprehensive determination processor 72, and the overload comprehensive determination processor And a system processor failure monitor 71 connected to the overload comprehensive controller 74 for reducing the overload, and connected to the overload comprehensive determination processor 72 to monitor the failure of each processor in the system. .

제 3 도는 본 발명에 따른 각 과부하 감시 및 국부 판단 처리 방법에 대한 전체 흐름도로서 프로세서별 과부하 감시방법과 국부과부하 레벨 결정 방법을 제시한다.3 is a flowchart illustrating a method for monitoring an overload and a method for determining a local overload level for each processor as a general flow chart for each overload monitoring and local determination processing method according to the present invention.

먼저, 과부하 감시가 시작되면 각 트랜잭션 처리기(CCP, SLP)가 작동하는가 여부를 판단(301)하여 시스팀의 특징상 CCP1/2 혹은 SLP1/2가 동시 장애되면 트랜잭션처리가 되지 않으므로 과부하 감시 및 국부 판단 처리기(15, 25, 53, 63) 중지 및 시스팀이 정지하여 종료된다(304). 이때는 시스팀을 재기동하여 원상복귀하도록 한다.상기 판단(301) 결과 각 프로세서가 CCP-SLP로 동작할 경우는 트랜잭션처리를 하는 경우로 CCP내의 측정기(11 내지 13)를 구동하여 데이타를 발생시키고(302), SLP인 경우에는 SLP내의 측정기(51, 52)를 구동하여 데이타를 발생시킨다(303).First, when overload monitoring starts, it is determined whether each transaction processor (CCP, SLP) is operating (301). If CCP1 / 2 or SLP1 / 2 is simultaneously failed due to the characteristics of the system, transaction processing is not performed. The processor 15, 25, 53, 63 stops and the system stops and ends (304). In this case, the system is restarted and returned to its original state. As a result of the determination 301, when each processor operates as a CCP-SLP, it executes transaction processing to generate data by driving the measuring devices 11 to 13 in the CCP (302). In the case of SLP, the measuring devices 51 and 52 in the SLP are driven to generate data (303).

그리고, CCP의 측정값을 수집하여 비교로직으로 이 수집데이타를 테이블화한다(305).Then, the measured values of the CCPs are collected and the collected data is tabulated (305).

이어서 과부하 판단기준저장소(16,26)의 입력기준값을 역시 같은 방식으로 테이블화하고(306) 이 두 테이블을 매핑시켜 비교한다(307).Subsequently, the input reference values of the overload judgment reference stores 16 and 26 are also tabulated in the same manner (306), and the two tables are mapped and compared (307).

상기 비교(307)결과, 과부하시에는 국부과부하 레벨을 결정하여(308) 과부하 데이타 및 국부과부하 레벨을 과부하 종합 판단 처리기에 전달하고(309) 함과 동시에 국부과부하 제어기에 전달하여 국부과부하 제어를 시작하도록 요청하고(309), 비 과부하시에는 전에 과부하상태였는지를 파악하여(310) 근처에 과부하인 경우에는 과부하가 해소된 경우이므로 이를 종합판단기(14)에 통보하고 아닌 경우에는 주기적인 감시 시간대역에서 CCP1,2 각 측정기를 정지시키고 리턴(311)함으로써 다음 감시 시간대역에 도달하면 위와 같은 절차에 의거 CCP 과부하 감시를 반복 수행하여 연속적으로 진행한다.As a result of the comparison (307), in case of overload, the local overload level is determined (308), and the overload data and the local overload level are transmitted to the overload comprehensive determination processor (309), and at the same time, the local overload controller is started to control the local overload. In case of overloading, 310 is notified that the overload is resolved since the overload is resolved. When the next monitoring time band is reached by stopping and returning each of the CCP1 and 2 measuring devices in the band, the CCP overload monitoring is repeatedly performed according to the above procedure to proceed continuously.

또한, SLP의 측정값을 수집하여 비교로직으로 이 수집데이타를 테이블화한다(312).In addition, the measured value of the SLP is collected and the collected data is tabulated (312).

이어서 과부하 판단기준저장소의 입력기준값을 역시 같은 방식으로 테이블화하고(313) 이 두 테이블을 매핑시켜 비교한다(314).Then, the input reference values of the overload judgment reference store are also tabulated in the same manner (313) and the two tables are mapped and compared (314).

상기 비교(314)결과 과부하시에는 국부과부하 레벨을 결정하여(315) 과부하 데이타 및 국부과부하 레벨을 과부하 종합 판단 처리기에 전달하고(319) 함과 동시에 국부과부하 제어기에 전달하여 국부과부하 제어를 시작하도록 요청하고(316), 비 과부하시에는 전에 과부하상태였는지를 파악하여(317) 전에 과부하인 경우에는 과부하가 해소된 경우이므로 이를 종합판단기에 통보하고 아닌 경우에는 주기적인 감시 시간대역에서 SLP1, 2 각 측정기를 정지시키고 리턴(318)함으로써 다음 감시 시간대역에 도달하면 위와 같은 절차에 의거 SLP 과부하 감시를 반복 수행하여 연속적으로 진행함으로써 CCP/SLP 모두 과부하 감시를 반복 수행하여 연속적으로 진행하게 된다.As a result of the comparison (314), when the overload is determined (315), the local overload level is determined (315), and the overload data and the local overload level are transmitted to the overload comprehensive determination processor (319). In case of non-overloading, it is checked whether it was in overload before (317), and if it is in case of overload before, it is notified that the overload is resolved. When the next monitoring time band is reached by stopping the measuring instrument and returning 318, the SLP overload monitoring is repeatedly performed according to the above procedure to continuously execute the overload monitoring by the CCP / SLP.

제 4 도는 본 발명에 따른 과부하 종합 판단 처리방법에 대한 흐름도이다.4 is a flowchart of the overload comprehensive determination processing method according to the present invention.

서비스 제어용 트랜잭션 처리 시스팀의 각 장애 상태를 먼저 검토하여(401), CCP/SLP쌍으로 된 경우에만 각 처리기의 과부하 감시 및 국부 판단 처리기 결과를 수신하고(402 내지 405), CCP/SLP쌍으로 되지않고 동시장애가 발생한 경우에는 전 시스팀이 정지된다(406). 그리고 모두 중앙 수집된 과부하 감시 및 국부 판단 처리기(15, 25, 53, 63) 결과를 비교 매핑시킬 수 있는 테이블을 형성하고(407), 그 테이블에서 시스팀의 과부하 추이를 예측하여 긴급 처리 프로세서를 결정하고(408), 제어할 과부하 종합 레벨을 결정한다(409). 이 최종 결정된 결과는 시스팀 과부하 표시장치(73)에 표시하고 과부하 종합 제어기(74)에 구동 신호를 전달하여 과부하 레벨 및 주요 과부하 위치 정보를 동시에 송신함으로써 전 시스팀의 과부하를 결정한다(410).Each failure status of the transaction processing system for service control is first reviewed (401), and the overload monitoring and local decision processor results of each processor are received only when the CCP / SLP pair is used (402 to 405), and the CCP / SLP pair is returned. If a simultaneous failure occurs, the entire system is stopped (406). In addition, all the centrally-collected overload monitoring and local determination processor (15, 25, 53, 63) form a table that can be compared and mapped the results (407), from the table to predict the overload trend of the system to determine the emergency processing processor (408), and determine the overload overall level to control (409). The final determined result is displayed on the system overload display device 73 and transmits a drive signal to the overload integrated controller 74 to transmit the overload level and the main overload position information simultaneously to determine the overload of the entire system (410).

따라서, 본 발명은 트랜잭션 입력 장치의 다량 및 불규칙 입력의 트랜잭션 처리일 경우 및 처리 구조가 전후단 분리의 쌍으로 이완 결합 구조로 구성된 응용 시스팀에 적용되어질 수 있으며, 특히 통신망에서 서비스 제어용으로 적용되어질 수 있다. 이를 적용함으로써 운용자가 시스팀의 복잡한 내부 상태를 인식하지 않아도 시스팀이 과부하인지의 여부를 자동 통보되어 알 수 있으며 과부하 제어기로 구성되어 과부하로 인한 시스팀의 비정상을 사전에 방지할 수 있다. 또한 이 방식을 데이타화하여 분석함으로써 처리 시스팀의 장애 처리 능력의 보강에 적용하여 설비 엔지니어링 차원에도 적용시킬 수 있는 효과가 있다.Therefore, the present invention can be applied to a transaction processing of a large amount and irregular input of a transaction input device and to an application system in which a processing structure is composed of a loosely coupled structure in pairs of front and rear separation, and particularly, for service control in a communication network. have. By applying this, even if the operator does not recognize the complex internal state of the system, the system can be automatically notified whether the system is overloaded or not, and it is composed of the overload controller to prevent the abnormality of the system due to the overload in advance. In addition, this method can be applied to the engineering of the facility by applying the data to the analysis to reinforce the fault handling capability of the treatment system.

Claims (3)

트랜잭션의 입력시기부터 출력시기를 측정하여 처리시간 여부에 대한 측정을 하는 응답시간 측정수단(11), 각 프로세서의 사용량을 측정하는 CPU 사용량 측정수단(12), 각 프로세서내의 트랜잭션의 흐름상에서 실시간으로 처리하지 못하고 대기하고 있는 트랜잭션의 양을 측정하기 위한 트랜잭션 대기량 측정수단(13), 상기 각 측정수단(11 내지 13)에 연결되어 각 측정기로부터의 데이타를 수집하는 CCP 과부하 감시 및 국부 판단 처리수단(15)과, 상기 CCP 과부하 감시 및 국부 판단 처리수단(15)에 연결되어 과부하 판단 기준값을 저장하기 위한 CCP 과부하 판단 기준값 저장소(16), 상기 CPP 과부하 감시 및 국부 판단 처리수단(15)에 연결되어 해당 프로세서의 과부하 제어 레벨에 따라 해당되는 과부하 제어를 하도록 조치하는 CCP 과부하 국부 제어수단(14)을 구비하여 동일 구조로서 이중화 구조로 되어 있는 CPP(20, 30)와, 프로세서의 사용량을 측정하는 CPU 사용량 측정수단(54), 각 프로세서내의 트랜잭션의 흐름상에서 실시간으로 처리하지 못하고 대기하고 있는 트랜잭션이 양을 측정하기 위한 트랜잭션 대기량 측정수단(52), 상기 각 측정수단(51, 52)에 연결되어 각 측정수단으로부터의 데이타를 수집하는 SLP 과부하 감시 및 국부 판단 처리수단(53), 상기 SLP 과부하 감시 및 국부 판단 처리수단(53)에 연결되어 과부하 판단 기준값을 저장하기 위한 SLP 과부하 판단 기준값 저장소(55), 상기 SLP 과부하 감시 및 국부 판단 처리수단(53)에 연결되어 해당 프로세서의 과부하 제어 레벨에 따라 해당되는 과부하 제어를 하도록 조치하는 SLP 과부하 국부 제어수단(54)을 구비하여 동일 구조로서 이중화 되어 있는 SLP(50, 60)와, 상기 과부하 감시 및 국부 판단 처리 수단(15, 53)에 LAN 장치로 연결되어 과부하인 경우 각 프로세서의 국부과부하 상태 추이에 따라 전 시스팀의 과부하 정도를 결정하는 과부하 종합 판단 처리수단(72), 상기 과부하 종합 판단 처리수단(72)에 연결되어 운용자가 인식할 수 있도록 표시하기 위한 시스팀 과부하 정도표시장치(73), 상기 과부하 종합 판단 처리수단(72)에 연결되어 과부하를 제어하여 감소시키도록 하기 위한 과부하 종합 제어수단(74), 상기 과부하 종합 판단 처리수단(72)에 연결되어 시스팀내 각 처리기의 장애를 감시하는 시스팀 처리기 장애 감시수단(71)을 구비하는 OA(70)을 구비하는 것을 특징으로 하는 지능망 서비스 제어용 분산형 과부하 자동 감시 장치.Response time measuring means (11) for measuring whether the processing time from the input time of the transaction to measure the processing time, CPU usage measuring means (12) for measuring the usage of each processor, in real time on the flow of transactions in each processor Transaction latency measuring means 13 for measuring the amount of transactions waiting to be processed and CCP overload monitoring and local judgment processing means connected to the respective measuring means 11 to 13 to collect data from each measuring instrument. (15), the CCP overload determination reference value storage 16 for storing the overload determination reference value connected to the CCP overload monitoring and local determination processing means 15, and the CPP overload monitoring and local determination processing means 15 And a CCP overload local control means 14 for taking control of the overload control according to the overload control level of the processor. CPPs 20 and 30, which have a redundant structure as the same structure, CPU usage measuring means 54 for measuring processor usage, and transactions waiting in real time on the flow of transactions in each processor, Transaction latency measurement means 52 for measurement, SLP overload monitoring and local determination processing means 53 connected to the respective measurement means 51 and 52 to collect data from each measurement means, and the SLP overload monitoring and SLP overload determination reference value storage 55 for storing the overload determination reference value, connected to the local determination processing means 53, and connected to the SLP overload monitoring and local determination processing means 53 according to the overload control level of the corresponding processor. SLP (50, 60) having the same structure and redundant SLP overload local control means (54) to take overload control, Overload comprehensive determination processing means 72 for determining the degree of overload of the entire system according to the local overload state trend of each processor in case of overload connected to the load monitoring and local determination processing means 15 and 53 as a LAN device. A system overload degree display device 73 for displaying the operator so that it can be recognized by the decision processing means 72, and an overload synthesis for reducing and controlling the overload connected to the overload comprehensive determination processing means 72 Intelligent network characterized in that it comprises an OA (70) having a system processor failure monitoring means (71) connected to the control means (74), said overload comprehensive determination processing means (72) for monitoring the failure of each processor in the system. Distributed overload automatic monitoring device for service control. 응답시간 측정기(11, 21), CPU 사용량 측정기(12, 22, 51, 61), 트랜잭션 대기량 측정기(13, 23, 52, 62), CCP 과부하 국부 제어기(14, 24), CPP 과부하 감시 및 국부 판단 처리기(15, 25), CPP 과부하 판단 기준값 저장소(16, 26), SLP 과부하 감시 및 국부 판단 처리기(53, 63), SLP 과부하 국부 제어기(54, 64), SLP 과부하 판단 기준값 저장소(55, 65), 시스팀 각 처리기 장애 감시기(71), 과부하 종합 판단 처리기(72), 시스팀 과부하 정도표시장치(73), 과부하 종합 제어기(74)를 구비하는 지능망 서비스 제어용 분산형 과부하 자동 감시 장치의 운용 방법에 있어서 ; 과부하 감시가 시작되면 각 트랜잭션 처리기(CCP, SLP)가 작동하는가 여부를 판단하는 제 1 단계(301), 상기 제 1 단계(301) 수행 후, CCP1/2 혹은 SLP1/2가 동시 장애되면 과부하 감시 및 국부 판단 처리기(15, 25, 53, 63) 중지 및 시스팀이 정지하여 종료되도록 하는 제 2 단계(304), 상기 제 1 단계(301) 수행 후, 각 프로세서가 CCP로 동작할 경우는 CCP내의 측정기(11 내지 13, 21 내지 23)를 구동하여 데이타를 발생시키고, CCP의 측정값과 과부하 판단 기준 저장소의 입력 기준값을 수집하여 비교로직으로 이 수집데이타를 테이블화하는 제 3 단계(305, 306), 상기 제 3 단계(305, 306) 수행후, 이 두 테이블을 매핑시켜 비교하여 과부하시에는 국부과부하 레벨을 결정하여 과부하 데이타 및 국부과부하 레벨을 과부하 종합 판단 처리기에 전달함과 동시에 국부과부하 제어기에 전달하여 국부과부하 제어를 시작하도록 요청하는 제 4 단계(307 내지 309, 319), 상기 제 4 단계(307 내지 309, 319) 수행 후, 비 과부하시에는 전에 과부하상태였는지를 파악하여(310) 전에 과부하인 경우에는 과부하가 해소된 경우이므로 이를 종합 판단기에 통보하고 아닌 경우에는 주기적인 감시 시간대역에서 CCP/SLP 각 측정기를 정시키고 리턴하는 제 5 단계(310, 311, 319), 상기 제 1 단계(301) 수행 후, SLP인 경우에는 SLP내의 측정기(51, 52, 25, 26)를 구동하여 데이타를 발생시키고 SLP의 측정값과 과부하 판단 기준 저장소의 입력 기준값을 수집하여 비교로직으로 이 수집데이타를 테이블화하는 제 6 단계(312, 313), 상기 제 6 단계(312, 313) 수행 후, 이 두 테이블을 매핑시켜 비교하여 과부하시에는 국부과부하 레벨을 결정하여 과부하 데이타 및 국부과부하 레벨을 과부하 종합 판단 처리기에 전달함과 동시에 국부과부하 제어기에 전달하여 국부과부하 제어를 시작하도록 요청하는 제 7 단계(314 내지 316, 319), 상기 제 7 단계(314 내지 316, 319) 수행 후, 비 과부하시에는 전에 과부하상태였는지를 파악하여 전에 과부하인 경우에는 과부하가 해소된 경우이므로 이를 종합판단기에 통보하고 아닌 경우에는 주기적인 감시 시간대역에서 CCP/SLP 각 측정기를 정지시키고 리턴하는 제 8 단계(317 내지 319)로 이루어지는 것을 특징으로 하는 지능망 서브시 제어용 분산형 과부하 자동 감시 장치의 운용방법.Response Time Meters (11, 21), CPU Usage Meters (12, 22, 51, 61), Transaction Latency Meters (13, 23, 52, 62), CCP Overload Local Controllers (14, 24), CPP Overload Monitoring and Local judgment processor 15, 25, CPP overload judgment reference value storage 16, 26, SLP overload monitoring and local judgment processor 53, 63, SLP overload local controller 54, 64, SLP overload judgment reference value store 55 , 65), operation of distributed overload automatic monitoring device for intelligent network service control having a system each processor failure monitor 71, a comprehensive overload determination processor 72, a system overload degree indicating device 73, and an overload integrated controller 74; In the method; When the overload monitoring starts, after performing the first step 301 for determining whether each transaction processor (CCP, SLP) is operating or after performing the first step 301, if the CCP1 / 2 or SLP1 / 2 is simultaneously interrupted, the overload monitoring And stopping each local decision processor 15, 25, 53, and 63 and causing the system to stop and terminate, after performing the second step 304 and the first step 301, when each processor operates as a CCP. Third steps (305, 306) of generating the data by driving the measuring devices (11 to 13, 21 to 23), collecting the measured values of the CCP and the input reference values of the overload judgment reference storage and tabulating the collected data with comparative logic. After performing the third step (305, 306), the two tables are mapped and compared to determine the local overload level at the time of overload, and transfers the overload data and the local overload level to the overload comprehensive decision processor, and at the same time, the local overload controller Delivering to After performing the fourth step (307 to 309, 319) and the fourth step (307 to 309, 319) for requesting to start local overload control, it is determined whether the overload state was previously overloaded (310). In this case, since the overload is eliminated, a fifth step (310, 311, 319) and the first step (301) of determining and returning each CCP / SLP meter in the periodic monitoring time band are notified to the comprehensive judgment device. After performing SLP, in the case of SLP, it operates the measuring devices 51, 52, 25, and 26 in SLP to generate data, collects the measured values of SLP and the input reference value of overload judgment reference storage, and compares the collected data with a table. After performing the sixth steps 312 and 313 and the sixth steps 312 and 313, the two tables are mapped and compared to determine the local overload level during overload, and to overload the overload data and the local overload level. After the seventh step (314 to 316, 319) and the seventh step (314 to 316, 319) requesting to transmit to the local processor and the local overload controller to start the local overload control, The eighth step (317 to 319) to stop and return each CCP / SLP measuring instrument in the periodic monitoring time zone is notified to the comprehensive judge if the previous overload is resolved. Method for operating a distributed overload automatic monitoring device for intelligent network sub time control, characterized in that consisting of. 제 2 항에 있어서, 상기 과부하 종합 판단 처리 방법에 있어서 ; 서비스 제어용 트랜잭션 처리 시스팀의 각 장애 상태를 먼저 검토하는 단계(401), 상기 단계(401) 수행 후, CCP/SLP쌍으로 된 경우에만 각 처리기의 과부하 감시 및 국부판단 처리기 결과를 수신하고, CCP/SLP쌍으로 되지 않고 동시장애가 발생한 경우에는 전 시스팀이 정지하는 단계(402 내지 406), 상기 단계(402 내지 406) 수행 후, 중앙 수집된 과부하 감시 및 국부 판단 처리기 결과를 비교 매핑시킬 수 있는 테이블을 형성하고, 그 테이블에서 시스팀의 과부하 추이를 예측하여 긴급 처리 프로세서를 결정하는 단계(407, 408), 상기 단계(407, 408) 수행 후, 제어할 과부하 종합 레벨을 결정하고 과부하 종합 제어기에 구동 신호를 전달하여 과부하 레벨 및 주요 과부하 위치 정보를 동시에 송신함으로써 전 시스팀의 과부하를 결정하는 단계(409, 410)로 이루어지는 것을 특징으로 하는 지능망 서비스 제어용 분산형 과부하 자동 감시 장치의 운용 방법.The method according to claim 2, further comprising: in the overload comprehensive judgment processing method; Step 401 of reviewing each failure state of the transaction processing system for service control, after performing step 401, receiving the overload monitoring and local decision processor results of each processor only in the case of CCP / SLP pairs, and receiving CCP / When the simultaneous failure occurs without the SLP pair, the entire system stops (402 to 406), and after performing the steps (402 to 406), a table for comparing and mapping the centrally collected overload monitoring and local decision processor results is provided. Determining the emergency processing processor by predicting the overload trend of the system in the table (step 407 and 408), and after performing the steps 407 and 408, the overload comprehensive level to be controlled is determined and a drive signal is sent to the overload comprehensive controller. Determining the overload of the entire system by simultaneously transmitting the overload level and the main overload location information (409, 410). How the operation of automatic monitoring system for controlling intelligent network services in a distributed overload.
KR1019930004194A 1993-03-18 1993-03-18 Automatic servetance unit and operation method of overload of in service control KR950013840B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1019930004194A KR950013840B1 (en) 1993-03-18 1993-03-18 Automatic servetance unit and operation method of overload of in service control

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019930004194A KR950013840B1 (en) 1993-03-18 1993-03-18 Automatic servetance unit and operation method of overload of in service control

Publications (2)

Publication Number Publication Date
KR940022947A KR940022947A (en) 1994-10-22
KR950013840B1 true KR950013840B1 (en) 1995-11-16

Family

ID=19352388

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019930004194A KR950013840B1 (en) 1993-03-18 1993-03-18 Automatic servetance unit and operation method of overload of in service control

Country Status (1)

Country Link
KR (1) KR950013840B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100545608B1 (en) * 1999-03-25 2006-01-25 유티스타콤코리아 유한회사 Data Acquisition System with Parallel Distributed Structure

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5943232A (en) * 1997-10-29 1999-08-24 Lucent Technologies Inc. Autonomous overload control for distributed real time systems
KR100381375B1 (en) * 1999-10-08 2003-04-23 엘지전자 주식회사 Method of Predicting Overload in the Home Location Register

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100545608B1 (en) * 1999-03-25 2006-01-25 유티스타콤코리아 유한회사 Data Acquisition System with Parallel Distributed Structure

Also Published As

Publication number Publication date
KR940022947A (en) 1994-10-22

Similar Documents

Publication Publication Date Title
US7941810B2 (en) Extensible and flexible firmware architecture for reliability, availability, serviceability features
JPH01134641A (en) Performance measurement for computer system
JP2721294B2 (en) Online monitoring system for computer systems
KR950013840B1 (en) Automatic servetance unit and operation method of overload of in service control
CN109639755B (en) Associated system server decoupling method, device, medium and electronic equipment
JP3248485B2 (en) Cluster system, monitoring method and method in cluster system
KR940009753B1 (en) Automatic monitoring mehtod of overwork for intelligence network service in transaction processing system
JP3412725B2 (en) Remote maintenance equipment for distributed systems
JP2531351B2 (en) Manager inclusion tree construction method for network management system
KR100216573B1 (en) Method for managing state of multiple processors using dynamic monitoring period in ATM switch
KR0175470B1 (en) Alarm processing device and method in intelligent network service control / management system
JP2993083B2 (en) Polling monitoring control method
JPH0877119A (en) Method for service processing function monitor and device therefor
KR940007832B1 (en) Method of measuring process load on real time system
KR940001697B1 (en) Overload control system of electronic exchange
JPH11122815A (en) Supervisory controller for power system and medium recording its program
KR0140302B1 (en) Apparatus for integrated testing the packet in the full electronic switching system and method thereof1 h 04 l 12/56
KR970007275B1 (en) Respondent in pipelined bus stystem
KR960001053B1 (en) Error detection method in the communication of packet level
JPH0582614B2 (en)
KR100246606B1 (en) A method of alarm and fault statistic using system log file
JPH0414150A (en) Field fault control system for electronic computer system
JPH11249924A (en) Network server diagnostic system
JPS62217336A (en) Remote collector for preventive maintenance data
JP2000187649A (en) Method and device for controlling command in parallel processing type on-line system

Legal Events

Date Code Title Description
A201 Request for examination
N231 Notification of change of applicant
G160 Decision to publish patent application
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 19980929

Year of fee payment: 4

LAPS Lapse due to unpaid annual fee