KR900004569Y1 - Hold bilge system for ship - Google Patents

Hold bilge system for ship Download PDF

Info

Publication number
KR900004569Y1
KR900004569Y1 KR2019870002798U KR870002798U KR900004569Y1 KR 900004569 Y1 KR900004569 Y1 KR 900004569Y1 KR 2019870002798 U KR2019870002798 U KR 2019870002798U KR 870002798 U KR870002798 U KR 870002798U KR 900004569 Y1 KR900004569 Y1 KR 900004569Y1
Authority
KR
South Korea
Prior art keywords
bilge
hold
box
center
ship
Prior art date
Application number
KR2019870002798U
Other languages
Korean (ko)
Other versions
KR880017845U (en
Inventor
조덕근
Original Assignee
조덕근
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 조덕근 filed Critical 조덕근
Priority to KR2019870002798U priority Critical patent/KR900004569Y1/en
Publication of KR880017845U publication Critical patent/KR880017845U/en
Application granted granted Critical
Publication of KR900004569Y1 publication Critical patent/KR900004569Y1/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B13/00Conduits for emptying or ballasting; Self-bailing equipment; Scuppers

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Filtration Of Liquid (AREA)

Abstract

내용 없음.No content.

Description

선박의 홀드빌지 시스템Ship's Hold Bilge System

제1도는 본 고안이 설치된 선박의 종단면도.Figure 1 is a longitudinal cross-sectional view of the vessel the present invention is installed.

제2도는 제1도의 A-A 선 단면도.2 is a cross-sectional view taken along the line A-A of FIG.

제3도는 제2도의 B-B 선 단면도.3 is a cross-sectional view taken along the line B-B in FIG.

제4도는 본 고안의 요부 확대 단면도.Figure 4 is an enlarged cross-sectional view of the main part of the present invention.

제5도는 본 고안의 센터홀드빌지박스에 모인 빌지를 배출시키는 상태 확대 단면도.5 is an enlarged cross-sectional view of discharging the bilge collected in the center hold bilge box of the present invention.

제6도는 빌지웰에 빌지가 모이는 상태 확대 단면도.6 is an enlarged cross-sectional view of the bilge gathers in the bilge well.

* 도면의 주요부분에 대한 부호의 설명* Explanation of symbols for main parts of the drawings

4 : 홀드벌크헤드(Hold Bulk Hea)4: Hold Bulk Head

5 : 센터홀드빌지박스(Center Hold Bilge Box)5: Center Hold Bilge Box

6,6' : 빌지웰(Bilge Well)6,6 ': Bilge Well

7,7' : 빌지 도수관7,7 ': bilge water pipe

8 : 빌지로즈박스(Bilge Rose Box)8: Bilge Rose Box

9 : 빌지썩숀파이프(Bilge Suction Pipe)9: Bilge Suction Pipe

11 : 홀드빌지사운딩 파이프(Hold Bilge Sounding Pipe)11: Hold Bilge Sounding Pipe

13,13',13" : 스트레이너(Strainer)13,13 ', 13 ": Strainer

14 : 프로텍숀가드(Protection Guard)14: Protection Guard

본 고안은 홀드 구획이 많은 각종 대형화물선의 홀드빌지시스템에 관한 것이다.The present invention relates to a hold bilge system of various large cargo ships with many hold compartments.

종래에는 각종 발카 콘테이너 캐리어(Bulk Container Carrier), 카 캐리어(Car Carrier), 칩 캐리어(Chip Carrier)등 화물 홀드(Hold)가 많은 화물선의 홀드빌지 박스(Hold Bilge Box)를 홀드후부 양현에 각각 1개씩 설치하여 홀드빌지를 배출하도록 하므로서 홀드빌지를 배출시키는 빌지썩숀파이프(Bilge Suction Pipe)와 빌지사운딩파이프(Bilge Sounding Pipe)등도 각 홀드빌지박스마다 1개씩 설치하여야 하므로 공사 설치비가 많이 들며 홀드크리닝(Hold Cleaning)시 빌지박스(Bilge Box)청소의 시간이 길고, 매일 조석으로 홀드빌지를 검측하는 일상작업의 시간이 길며, 황천(荒天)이 극심한 때에는 사운딩파이프의 위치가 양현측에 치우치게 위치하므로 검측이 불가능한 등의 폐단이 있었다.Conventionally, hold bilge boxes of cargo ships having a lot of hold such as various bulk container carriers, car carriers, chip carriers, etc. Bilge Suction Pipe and Bilge Sounding Pipe, which discharges hold bilges by installing them, must be installed in each hold bilge box. Long cleaning time of bilge box during hold cleaning, long time of daily work to detect hold bilge with tides every day, and the position of sounding pipe is biased on both sides when heavy weather is extreme. As a result, the detection was impossible such as lungs.

본 고안은 이러한 점을 감안하여 홀드중앙부위 후두부에 센터홀드빌지박스(Center Hold Bilge Box)하나만 설치하고 종래의 빌지박스가 위치하는 좌, 우현 부위에 소형 빌지웰(Bilge Well)을 각각 1개씩 설치하여 빌지웰에 모인 홀드빌지를 빌지 수도관(Bilge By-Pass)을 통하여 센터홀드빌지박스에 모이게 하므로서 빌지박스에 모인 홀드빌지를 흡출하는 빌지썩숀파이프와 빌지사운딩파이프 등의 설치를 중앙의 빌지박스에만 설치하게 되므로서 종래보다 빌지썩숀파이프와 빌지사운딩파이프의 설치 숫자가 반으로 줄게 되어 공사비를 반으로 줄일 수 있으며 홀드 청소시 빌지박스 청소의 시간을 단축하고 매일 조석으로 홀드빌지를 검축하는 루팅워크(Routine Work)의 시간단축 및 황천시에도 극심한 때가 아니면 사운딩파이프의 위치가 중앙부위에 위치하여 검출이 가능하게 한 등의 효과가 있는 것으로 첨부도면에 의거 상세히 설명하면 다음과 같다.In consideration of this, the present invention installs only one center hold bilge box at the center of the head of the hold and one small bilge well at the left and right side where the conventional bilge box is located. The bilge box and bilge sounding pipe that draw out the hold bilge collected in the bilge box by collecting the hold bilge collected in the bilge well through the bilge water pipe (Bilge By-Pass). Since the installation of the bilge rushon pipe and the bilge sounding pipe is reduced by half, the construction cost can be cut in half, and the time for cleaning the bilge box can be shortened and the hold bilge can be inspected every day. Even if the time is short and the weather is slowing down, the sounding pipe is located at the center of the route. When described in detail according to the accompanying drawings as having the effect such as to enable as follows.

선박의 각 홀드벌크헤드(4)의 중앙부위 후부에 센터홀드빌지박스(5)를 설치하고 좌,우현에 소형의 빌지웰(6)(6')을 설치하여 센터홀드빌지박스(5)와 좌,우현의 빌지웰(6)(6')을 빌지가 배출되기 용이한 경사도를 가진 빌지도수관(7)(7')으로 연결하여서 된 것이다.The center hold bilge box 5 is installed at the rear of the center of each hold bulkhead 4 of the ship, and the small bilge wells 6, 6 'are installed at the left and right sides of the ship. The left and right bilge wells 6 and 6 'are connected to the bilge water pipes 7 and 7' which have an inclination to easily discharge the bilge.

미설명 부호(2)는 카고홀드(cargo hold)(3)은 더블보텀탱크(Double Bottom tank)이고, (12)는 홀드사이드호퍼(Hold Side Hopper), (15)는 스트라이킹 패드(Striking Pad)이다.Reference numeral (2) is a cargo hold (3) is a double bottom tank, (12) is a Hold Side Hopper, (15) a strike pad to be.

이와같이 된 본 고안은 센터홀드빌지박스(5)의 좌,우현의 설치된 빌지웰(6)(6')에 모인 빌지는 빌지도수관(7)(7')을 통해 센터홀드빌지박스(5)에 모이게 되는데 센터홀드빌지박스(5)는 종래의 좌, 우현에 각각 1개씩 설치한 빌지박스의 용적과 거의 동일하게 만들고 빌지웰(6)(6')은 스트레이너(13')(13")의 크기를 적당하게 만들어 빌지가 잘 빠지도록 배치하고 빌지웰(6)(6')의 청소가 용이하도록 빌지수도관(7)(7')의 외경 2배내외의 깊이로 설치하게 된다.The bilge gathered in the left and right bilge wells (6) (6 ') of the center hold bilge box (5) is assembled to the center hold bilge box (5) through the bilge water pipe (7) (7'). The center hold bilge box 5 is almost the same as the volume of the bilge box installed in the left and right starboards respectively, and the bilge wells 6 and 6 'are made of the strainer 13' and 13 ". The size of the bilge is arranged so that the bilge is easily removed and the bilge wells 6, 6 'are installed at a depth of about twice the outer diameter of the bilge water pipes 7 and 7'.

빌지도수관(7)(7')의 경사도는 선박이 좌,우로 로링시에도 센터홀드 빌지박스(5)에 모인 빌지가 역류되지 않을 정도의 적당한 경사도를 유지시켜 빌지웰(6)(6')에 모인 빌지가 센터 홀드빌지박스(5)에 잘 유입되도록 설치하게 되며 센터홀드빌지박스(5)의 좌, 우현에 빌지웰(6)(6')을 소형으로 설치하는 것은 센터홀드빌지박스(5)의 상부에 있는 스트레이너(13)만으로는 항해중 선박이 로링할 때 빌지의 이동속도가 빠르고 스트레이너(13)를 덮어 화물을 싣게 되는 마포(Barlap)의 장애로 센터홀드빌지박스(5)에 빌지의 누수 낙하가 느리며 정박 또는 항해중 선체의 리스트(LIST) 즉 횡 경사시에는 빌지가 한쪽 현으로 몰리므로 빌지의 낙하배출이 용이하지 않아 홀드내의 빌지 유동으로 화물 손상의 우려를 방지하기 위해 홀드 양현에 소형 빌지웰(6)(6')을 설치하여 빌지도수관(7)(7')을 통해 센터홀드 빌지박스(5)로 빌지가 모이게 하는 것이다.The slope of the bilge water pipes (7) (7 ') is maintained so that the bilge collected in the center hold bilge box (5) does not flow back even when the ship is rolling left or right. The bilge collected in the center is installed to flow into the center hold bilge box (5) well, and the small bilge well (6, 6 ') is installed at the left and right sides of the center hold bilge box (5). 5) Only the strainer 13 at the top of the bilge bilge in the center hold bilge box (5) due to the obstacle of barlap that the bilge moving speed is fast and the load is covered by the strainer 13 when the ship is roaring while sailing The leakage of water is slow and the list of hulls during berthing or voyage, ie the bilge is driven to one string during lateral inclination, so it is not easy to discharge the bilge, so the hold spool to prevent the risk of cargo damage by the bilge flow in the hold. Small bilge wells (6) (6 ') Dosugwan to gather in the bilge (7) (7 ') hold bilge center box (5) through.

이렇게 센터홀드빌지박스(5)와 빌지웰(6)(6')을 덮고 있는 스트레이너(13)(13')(13")를 통해 카고홀드(2)내의 곡물등의 화물은 빠지지 않고 빌지만이 빌지박스(5)에 모이면 일정시간마다 프로텍숀가드(14)를 통해 하단이 빌지박스(5)내에 삽입된 홀드빌지사운딩파이프(11)를 꺼내어 센터홀드빌지박스(5)내에 빌지의 양을 측정하여 센터홀드빌지박스(5)내의 빌지의 양이 일정량이 되면 빌지썩숀파이프(9)로 빌지를 배출시키게 되는데 빌지썩숀파이프(9)의 일단이 연결된 빌지로즈박스(8)는 천공된 세공에 의해 센터홀드빌지박스(5)내의 빌지중 찌꺼기가 빌지썩숀파이프(9)로 유입되지 않도록 찌꺼기를 걸러주게 되고 찌꺼기가 걸러진 빌지만이 빌지로즈박스(8)로 유입되어 빌지썩숀파이프(9)를 통해 배출되는 것이다.Through the strainers 13, 13 ', and 13 "covering the center hold bilge box 5 and the bilge well 6, 6', cargoes such as grains in the cargo hold 2 are not drained. When the bilge box 5 is gathered, the hold bilge sounding pipe 11 inserted at the lower end of the bilge box 5 through the protection guard 14 at regular intervals is taken out. When the amount of bilge in the center hold bilge box (5) is measured, the amount of the bilge is discharged into the bilge rotshon pipe (9). The bilge filters the wastes from the bilge in the center hold bilge box (5) to prevent them from flowing into the bilge rotshon pipe (9). Is discharged through).

그런데 전술한 바와 같이 홀드벌크헤드(4)의 중앙부위 후부에 센터홀드빌지박스(5)를 설치하고 좌,우현에 소형 빌지웰(6)(6')을 설치하여 빌지도수관(7)(7')으로 연결하는 것은 종래와 같이 홀드벌크헤드(4)의 후부 양현에 각각 1개씩 홀드빌지박스(5)를 2개 설치하게 되면 각각의 홀드빌지박스(5)에 빌지를 흡출하는 빌지썩숀파이프(9)와 빌지의 양을 측정하는 홀드빌지 사운딩 파이프(11) 및 빌지로즈박스(8), 체크밸브(10)등을 홀드빌지박스(5)마다 각각 설치해야 하고 기관실(1)내의 홀드빌지썩숀파이프용 밸브 및 홀드빌지사운딩파이프(11)의 보호용프로텍숀가드(14)도 각 홀드빌지박스(5)마다 각각 설치하게 되어 홀드빌지박스(5)의 숫자만큼 설치하게 되므로 설치공사비가 많이 들게 되는 것으로서 본 고안은 홀드벌크헤드(4) 중앙 후부에 센터홀드빌지박스(5)를 각 1개씩만 설치하게 되어 센터홀드빌지박스(5)의 숫자가 반으로 줄게되고 이에 설치하고 되는 빌지썩숀파이프(9), 홀드빌지사운딩파이프(11), 빌지로즈박스(8), 체크밸브(10)등의 설치 또한 반으로 줄게되므로 총 공사비가 격감되 그에 따른 기자재를 감량 사용하게 되어 신조운항개시부터 폐선시까지 적하량의 증가로 운임 수익을 증대시킬 수 있는 것이다.However, as described above, the center hold bilge box 5 is installed at the rear of the center portion of the hold bulkhead 4, and the small bilge wells 6, 6 'are installed at the left and right sides of the bulge pipes 7 and 7. ') Connects the bilge rush pipe which draws bilge into each hold bilge box 5 when installing two hold bilge boxes 5 one by one on the rear side of the hold bulkhead 4 as in the related art. (9) and hold bilge sounding pipe (11) for measuring the amount of bilge, bilge rose box (8), check valve (10), etc. must be installed for each hold bilge box (5) and hold in engine room (1) The protective protection guard 14 of the bilge shunt pipe and the hold bilge sounding pipe 11 is also installed for each hold bilge box 5, which is installed by the number of the hold bilge box 5. The present invention is to hold a lot of the center of the hold bulkhead (4) center hold bilge box (5) Only one each will be installed so that the number of center hold bilge box (5) is cut in half, and the bilge rotshon pipe (9), hold bilge sounding pipe (11), bilge rose box (8) and check valve Since the installation of (10) is also cut in half, the total cost of construction will be reduced, and equipment and equipment will be reduced accordingly, which can increase freight profits by increasing the amount of cargo from the start of new ship operation to the decommissioning.

이와같이 홀드벌크헤드(4)의 중앙 후부에 센터홀드빌지박스(5)를 각각 1개씩만 설치하므로서 공사비가 절감되 운임수익을 증대시키며 홀드 청소시간단축 및 홀드빌지 배출작업을 단순화시키면서도 센터홀드빌지박스(5) 및 각 빌지웰(6)(6')에 덮어 설치되는 3개의 스트레이너(13)(13')(13")로 곡물등의 화물을 빠지지 않고 빌지만 배출되므로 빌지의 낙하배출을 용이하게 하고 선박의 로링시에 빌지로 인한 화물의 손상을 방지하는 효과가 있는 고안인 것이다.In this way, by installing only one center hold bilge box 5 at the center rear of the hold bulkhead 4, construction cost is reduced, thereby increasing freight revenue, reducing the time for holding cleaning, and simplifying the hold bilge discharge work. (5) and three strainers (13) (13 ') (13 ") which are installed over each of the bilge wells (6) and (6') so that cargo such as grains are drained without being drained, thereby making it easier to discharge the bilge. It is designed to have the effect of preventing damage to the cargo caused by bilge during roiling of the ship.

Claims (1)

선박의 각 홀드벌크헤드(4)의 중앙부의 후부에 센터홀드빌지박스(5)를 설치하고 그 좌,우현에 소형의 빌지웰(6)(6')을 설치하여 센터홀드빌지박스(5)와 좌,우현의 빌지웰(6)(6')을 빌지가 배출되기 용이한 경사도를 갖는 빌지도수관(7)(7')으로 연결시켜서 된 것을 특징으로 하는 선박의 홀드빌지 시스템.A center hold bilge box 5 is installed at the rear of the center of each hold bulkhead 4 of the ship, and a small bilge well 6, 6 'is installed at the left and right sides of the ship. Hold bilge system of the ship characterized in that by connecting the bilge well (6) (6 ') of the left and right sides with a bildo water pipe (7) (7') having an inclination to discharge the bilge.
KR2019870002798U 1987-03-05 1987-03-05 Hold bilge system for ship KR900004569Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2019870002798U KR900004569Y1 (en) 1987-03-05 1987-03-05 Hold bilge system for ship

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2019870002798U KR900004569Y1 (en) 1987-03-05 1987-03-05 Hold bilge system for ship

Publications (2)

Publication Number Publication Date
KR880017845U KR880017845U (en) 1988-10-27
KR900004569Y1 true KR900004569Y1 (en) 1990-05-25

Family

ID=19260301

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2019870002798U KR900004569Y1 (en) 1987-03-05 1987-03-05 Hold bilge system for ship

Country Status (1)

Country Link
KR (1) KR900004569Y1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20180055451A (en) * 2016-11-17 2018-05-25 삼성중공업 주식회사 Apparatus for bilge treating

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20180055451A (en) * 2016-11-17 2018-05-25 삼성중공업 주식회사 Apparatus for bilge treating

Also Published As

Publication number Publication date
KR880017845U (en) 1988-10-27

Similar Documents

Publication Publication Date Title
US4595030A (en) Fuel tank for a water craft
CN101468715B (en) Apparatus for collecting and separating water surface oil stain
KR101119492B1 (en) System for recovery operation oil floating type
KR19990021962A (en) How to retrofit your tanker
US3938457A (en) Tanker hull modification
KR900004569Y1 (en) Hold bilge system for ship
US4105554A (en) Oil spill retrieval system
US4178247A (en) Oil spill retrieval system
US2039399A (en) Vessel
ES2075779B1 (en) OIL TANKER FOR THE PREVENTION OF THE OIL CARGO SPILL.
CA1114750A (en) Floating skimming barrier assemblies
SE466146B (en) TANKERS, SPECIFICALLY BEFORE TRANSPORTING OIL OR OTHER WASHERS LETTERS IN THE WATER
Noerager et al. Oil tracking, containment, and recovery during the Exxon Valdez response
EP1499524A1 (en) Vessel
CN207180771U (en) A kind of oil discharge monitoring and control system peculiar to vessel
IE781247L (en) Tanker.
CN212447956U (en) Marine hidden tye
EP0863835B1 (en) A method and arrangement for decreasing the risk for sinking of a ship
JPS6058373A (en) Removing device for water immersion of floating roof type storage tank
US4468323A (en) Method and apparatus for cleaning up surface water
CN207374608U (en) A kind of binary overflow oil recovering ship
JPS6233680Y2 (en)
CN109515626B (en) Bank side scratch-proof prompting device for port logistics basic channel
JPH0127516Y2 (en)
JP2982114B2 (en) Race boat pits at a racetrack

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 19941125

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee