KR20240001867A - Upper ground settlement-reducing loop steel pipe and pipe loop construction method using the same - Google Patents

Upper ground settlement-reducing loop steel pipe and pipe loop construction method using the same Download PDF

Info

Publication number
KR20240001867A
KR20240001867A KR1020220078690A KR20220078690A KR20240001867A KR 20240001867 A KR20240001867 A KR 20240001867A KR 1020220078690 A KR1020220078690 A KR 1020220078690A KR 20220078690 A KR20220078690 A KR 20220078690A KR 20240001867 A KR20240001867 A KR 20240001867A
Authority
KR
South Korea
Prior art keywords
steel pipe
loop
upper ground
pipe
ground settlement
Prior art date
Application number
KR1020220078690A
Other languages
Korean (ko)
Inventor
유정식
박우진
유병안
유병규
Original Assignee
유정식
박우진
유병안
유병규
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 유정식, 박우진, 유병안, 유병규 filed Critical 유정식
Priority to KR1020220078690A priority Critical patent/KR20240001867A/en
Publication of KR20240001867A publication Critical patent/KR20240001867A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

본 발명은 상부 지반 침하 감소형 루프 강관 및 이를 이용한 파이프 루프 시공 공법에 관한 것으로서, 더 구체적으로는 루프 강관의 상부 양쪽 측면부에 각각 단부 결속형 플랜지를 설치하여 측면부 끼리 서로 연속적으로 결속시켜 파이프 루프가 설치되도록 구성함으로써 상부 지반의 자중과 통행 차량이나 열차의 진동이나 충격 하중에 대하여 단부 결속형 돌출 강판이 탈락되고 변형되어 상부 지반이 침하되는 현상을 방지하고 누수도 방지함으로써 상부 지반을 통과하는 통행 차량이나 열차의 안전성을 확보할 수 있는 상부 지반 침하 감소형 루프 강관 및 이를 이용한 파이프 루프 시공 공법에 관한 것이다.The present invention relates to an upper ground settlement-reducing roof steel pipe and a pipe loop construction method using the same. More specifically, end binding flanges are installed on both upper side surfaces of the loop steel pipe, and the side parts are continuously connected to each other to form a pipe loop. By constructing it so that it is installed, it prevents the upper ground from sinking due to the end-bound protruding steel plate being dislodged and deformed due to the self-weight of the upper ground and the vibration or shock load of passing vehicles or trains, and also prevents water leakage from passing vehicles passing through the upper ground. This relates to an upper ground settlement-reducing loop steel pipe that can ensure the safety of trains and a pipe loop construction method using the same.

Description

상부 지반 침하 감소형 루프 강관 및 이를 이용한 파이프 루프 시공 공법{omitted}Upper ground settlement-reducing loop steel pipe and pipe loop construction method using the same{omitted}

본 발명은 상부 지반 침하 감소형 루프 강관 및 이를 이용한 파이프 루프 시공 공법에 관한 것으로서, 더 구체적으로는 루프 강관의 상부 양쪽 측면부에 각각 단부 결속형 플랜지를 설치하여 측면부 끼리 서로 연속적으로 결속시켜 파이프 루프가 설치되도록 구성함으로써 상부 지반의 자중과 통행 차량이나 열차의 진동이나 충격 하중에 대하여 단부 결속형 돌출 강판이 탈락되고 변형되어 상부 지반이 침하되는 현상을 방지하고 누수도 방지함으로써 상부 지반을 통과하는 통행 차량이나 열차의 안전성을 확보할 수 있는 상부 지반 침하 감소형 루프 강관 및 이를 이용한 파이프 루프 시공 공법에 관한 것이다.The present invention relates to an upper ground settlement-reducing roof steel pipe and a pipe loop construction method using the same. More specifically, end binding flanges are installed on both upper side surfaces of the loop steel pipe, and the side parts are continuously connected to each other to form a pipe loop. By constructing it so that it is installed, it prevents the upper ground from sinking due to the end-bound protruding steel plate being dislodged and deformed due to the self-weight of the upper ground and the vibration or shock load of passing vehicles or trains, and also prevents water leakage from passing vehicles passing through the upper ground. This relates to an upper ground settlement-reducing loop steel pipe that can ensure the safety of trains and a pipe loop construction method using the same.

기존 성토 지반 상에 축조된 도로나 철도의 하부로 횡단하여 지하차도나 보도나 통로를 축조할 경우에는 토피가 얕은 경우가 흔히 존재한다.When constructing an underpass, sidewalk, or passageway by crossing the lower part of a road or railroad built on existing fill ground, the top cover is often shallow.

상기와 같은 경우의 얕은 토피 조건하에서 지하차도나 보도나 통로를 축조할 경우에는 통상적인 파이프 루프를 시공한 후 상기 파이프 루프 내에 본 철근을 배근하여 콘크리트 구조물을 축조하거나 또는 상기 파이프 루프의 하부에 합벽식으로 별도의 콘크리트 구조물을 축조하게 된다.When constructing an underpass, sidewalk, or passage under shallow cover conditions as described above, a concrete structure is constructed by constructing a normal pipe loop and then placing the reinforcing bar within the pipe loop, or attaching it to the lower part of the pipe loop. A separate concrete structure is built as a wall.

상기와 같은 파이프 루프 공법의 경우 종래의 공법으로는 대한민국특허청 등록특허공보 상의 특허등록번호 10-1616505호에 의하면, 식별번호 0025 내지 0026에서 설명되어 있는 바와 같이 첫째로, 기본적으로 강관압입 공법으로 지중구조체를 시공하게 되는데 지중구조체의 상수슬래브는 상재된 하중이 연직방향으로 작용하는 가설체구조체의 상부슬래부는 예컨대 강관이 연속된 합성 슬래브 형식(STS공법)으로 시공하고, 측면토압이 작용하는 측벽체는 상하 병렬로 이격된 측벽강관을 설치하고 측벽강관 사이의 이격된 부분은 엄지말뚝 기능의 토류판지지대를 종방향으로 연직방향으로 이격 설치하여 측벽강관과 토류판지지대를 고정시킨 후, 토류판지지대 사이 사이에는 토류판을 포함하는 흙막이부재를 삽입 설치하여 시공하게 된다.In the case of the pipe loop method as described above, the conventional method is as described in the identification numbers 0025 to 0026 according to patent registration number 10-1616505 in the Korean Intellectual Property Office Registered Patent Gazette. First, it is basically a steel pipe press-in method, which is used in the ground. The structure is constructed, and the upper slab of the temporary structure, where the loaded load acts in the vertical direction, is constructed in the form of a composite slab (STS method) with continuous steel pipes, and the upper slab of the underground structure is constructed in the form of a composite slab (STS method) where the lateral earth pressure acts. Install side wall steel pipes spaced in parallel up and down, and in the spaced part between the side wall steel pipes, earth plate supports with a thumb pile function are installed longitudinally and vertically to fix the side wall steel pipes and earth plate supports. Construction is done by inserting and installing earth retaining members including earth plates.

둘째, 측벽강관과 토류판지지대의 고정은 상부슬래브 시공을 위한 슬래브강관을 포함한 측벽강관의 관내부에 콘크리트를 타설하여 일체화되도록 하고 경화시켜 서로 강결시키도록 구성되어 있다.Second, the fixation of the side wall steel pipe and the earth plate support is done by pouring concrete into the inside of the side wall steel pipe, including the slab steel pipe for upper slab construction, so that it is integrated, and hardened to strengthen each other.

상기 영속된 강관의 경우에는 본 발명의 도1 내지 도2 도시 및 상기 종래의 발명 특허의 식별번호 0039 내지 식별번호 0042에 설명된 바와 같이 상기 상부슬래브(100)는 슬래브강관(110)의 측부가 서로 결합되도록 순차적으로 압입시켜 시공하게 된다.In the case of the permanent steel pipe, the upper slab 100 has a side of the slab steel pipe 110, as shown in Figures 1 and 2 of the present invention and as described in identification numbers 0039 to 0042 of the prior invention patent. Construction is carried out by sequentially press-fitting them so that they are joined together.

예컨대, 상기 슬래브강관(110)은 도 2b와 같이 원형 강관을 이용하게 되며, 슬래브강관(110)의 일측면에 제1 플랜지(111)가 상하로 이격되도록 부착되고, 슬래브강관(110)의 타측면에 제2 플랜지(112)가 상하로 이격되도록 부착된다.For example, the slab steel pipe 110 uses a circular steel pipe as shown in FIG. 2b, and the first flange 111 is attached to one side of the slab steel pipe 110 so as to be spaced vertically, and the other flange of the slab steel pipe 110 A second flange 112 is attached to the side so as to be spaced apart vertically.

또한, 슬래브강관(110)의 일측면(우측) 중앙에는 걸쇠고리(113)가 형성되고, 타측면(좌측) 중앙에는 T자형 걸쇠(114)가 부착된다.In addition, a latch ring 113 is formed in the center of one side (right side) of the slab steel pipe 110, and a T-shaped latch 114 is attached to the center of the other side (left side).

이러한 슬래브강관(110)을 압입수단을 이용하여 지중에 먼저 압입하고, 압입된 슬래브강관(110)의 걸쇠고리(113)에 다른 슬래브강관(110)의 T자형 걸쇠(114)가 삽입되도록 하는 방식으로 강관의 측부가 접하도록 압입 설치하게 된다.A method in which this slab steel pipe 110 is first press-fitted into the ground using a press-fitting means, and the T-shaped clasp 114 of another slab steel pipe 110 is inserted into the clasp 113 of the press-fitted slab steel pipe 110. It is press-fitted and installed so that the sides of the steel pipe come into contact.

상기 종래의 발명 특허의 도시 및 설명된 강관의 경우 본 발명의 도1에 도시된 바와 같이 강관(32)의 양쪽 측면부에 제1 플랜지(31)가 상하로 이격되도록 부착되고, 강관(32)의 타측면에 제2 플랜지(35)가 상하로 이격되도록 부착되도록 설치되며, 도2에 도시된 바와 같이 슬래브강관(110)은 원형 강관을 이용하게 되며, 슬래브강관(110)의 일측면에 제1 플랜지(111)가 상하로 이격되도록 부착되고, 슬래브강관(110)의 타측면에 제2 플랜지(112)가 상하로 이격되도록 부착되도록 구성되어 있다.In the case of the steel pipe shown and described in the above conventional invention patent, as shown in Figure 1 of the present invention, first flanges 31 are attached to both side parts of the steel pipe 32 so as to be spaced apart vertically, and the steel pipe 32 A second flange 35 is installed on the other side to be spaced vertically apart, and as shown in Figure 2, the slab steel pipe 110 uses a circular steel pipe, and a first flange is installed on one side of the slab steel pipe 110. The flange 111 is attached to be spaced apart vertically, and the second flange 112 is attached to the other side of the slab steel pipe 110 to be spaced up and down.

상기 강관(32)의 양쪽 측면부에 부착된 제1 플랜지(31)와 제2 플랜지(35)나, 슬래브강관(110)의 양쪽 측면부에 부착된 제1 플랜지(111)와 제2 플랜지(112)의 경우 공통적으로 플랜지(112)의 끝단부가 각각 캔틸레버식의 자유단으로 구성되어 상부 지반의 자중이나 통행 차량이나 열차의 진동하중이나 충격하중에 대해 구속력이 전혀 없는 결합 구조로서 하향으로 탈락되어 변형될 수 있어서 이렇게 하향으로 탈락되어 변형되는 체적에 해당되는 만큼 상부토사가 흘러내릴 수도 있고 누수도 될 수 있어서 결과적으로는 함몰부(2')의 상부 지반(2) 상을 빠른 속도로 통행하는 차량이나 열차가 전복될 수도 있어서 대형 안전사고를 유발할 수 있는 문제점이 있는 실정이다.A first flange 31 and a second flange 35 attached to both side surfaces of the steel pipe 32, or a first flange 111 and a second flange 112 attached to both side parts of the slab steel pipe 110. In the case of the common case, the end of the flange 112 is each composed of a cantilever-type free end, so it is a combined structure that has no binding force at all against the self-weight of the upper ground or the vibration load or impact load of passing vehicles or trains, so it can be deformed by falling off downward. Therefore, the upper soil may flow down or leak to the extent corresponding to the volume that is deformed by falling off downward, and as a result, vehicles passing at high speed on the upper ground (2) of the depression (2') There is a problem that the train may overturn, causing a major safety accident.

상기한 종래의 발명 특허의 문제점을 본 발명의 도3에서 좀 더 상세하게 설명하면, 상부지반의 자중이나 통행 차량이나 열차의 진동하중이나 충격하중이 작용할 경우 강관(3)의 양쪽 측면부에 부착된 각각의 플랜지(7)의 끝단부가 각각 하향으로 탈락되어 변형된 플랜지(7')로 결속상의 품질이 저하되어 상기 변형된 플랜지(7')의 틈새를 통해 상부 토사가 흘러내릴 수도 있고 누수도 될 수 있어서 결과적으로는 함몰부(2')의 상부 지반(2) 상을 빠른 속도로 통행하는 차량이나 열차가 전복될 수도 있어서 대형 안전사고를 유발할 수 있는 문제점이 있는 실정이다.If the problem of the above-described conventional invention patent is explained in more detail in Figure 3 of the present invention, when the self-weight of the upper ground or the vibration load or impact load of a passing vehicle or train acts, the material attached to both side parts of the steel pipe (3) The end of each flange (7) is separated downward, resulting in a deformed flange (7'), which deteriorates the quality of the binding, so that the upper soil may flow down or leak through the gap of the deformed flange (7'). As a result, vehicles or trains passing at high speed on the ground 2 above the depression 2' may overturn, causing a problem that can cause a large-scale safety accident.

또한, 도1 내지 도2에 도시된 바와 같이, 종래 발명의 강관(110)을 전방으로 압입시키는 과정에서 강관(110) 사이와 상·하부 플랜지(111, 112) 사이의 구속된 공간 내에 전방 토사가 연속적으로 채워질 경우에는 구속된 공간 내의 토사와 강관(110) 및 상·하부 플랜지(111, 112) 사이의 주면 마찰력으로 인해서 누적되는 저항력이 발생하게 됨으로써 강관(110)의 추진길이가 감소되거나 압입력이 증가되어 강관(110)에 휨 현상이 발생하여 안전성이 감소되는 문제점이 있으며, 강관(110)의 전면을 통해서 우측부나 좌측부의 강관(110)의 전방부를 포함하여 강관(110) 사이와 상·하부 플랜지(111, 112) 사이의 토사를 굴착할 경우에는 강관(110)을 포함하여 강관(110) 사이와 상·하부 플랜지(111, 112) 사이의 전방부 지표면의 지반(2) 상에 함몰부(2')가 발생되어 결과적으로는 함몰부(2')의 상부 지반(2) 상을 빠른 속도로 통행하는 차량이나 열차가 전복될 수도 있어서 대형 안전사고를 유발할 수 있는 문제점이 있는 실정이다.In addition, as shown in Figures 1 and 2, in the process of press-fitting the steel pipe 110 of the conventional invention forward, soil is deposited forward within the confined space between the steel pipe 110 and the upper and lower flanges 111 and 112. When filled continuously, a cumulative resistance force is generated due to the friction between the earth and sand in the confined space and the main surface of the steel pipe 110 and the upper and lower flanges 111 and 112, so that the propulsion length of the steel pipe 110 is reduced or pressure is increased. There is a problem in that safety is reduced due to an increase in input, which causes bending in the steel pipe 110. In addition, there is a problem that safety is reduced through the front of the steel pipe 110, including the front part of the steel pipe 110 on the right or left side, between and above the steel pipe 110. · When excavating soil between the lower flanges (111, 112), on the ground (2) of the front surface between the steel pipes (110), including the steel pipe (110), and between the upper and lower flanges (111, 112). There is a problem in that a depression (2') is generated and as a result, a vehicle or train passing at high speed on the ground (2) above the depression (2') may overturn, causing a large-scale safety accident. am.

한편, 도1 내지 도2에 도시된 바와 같이, 상기 강관(110)의 내부에도 상·하부 플랜지(111, 112) 사이의 높이만큼만 모르타르나 레미콘을 포함한 내부 채움재가 채워지게 되는 상황이지만 강관(110)의 수직 높이(직경)와 상·하부 플랜지(111, 112)의 높이 차이만큼 휨모멘트 보강에 도움이 되지 않는 굳지 않은 콘크리트를 포함한 내부 채움재가 더 채워져서 재료비 증가에 따른 공사비가 증가되는 문제점이 있는 실정이다.Meanwhile, as shown in Figures 1 and 2, the inside of the steel pipe 110 is filled with an internal filler including mortar or ready-mixed concrete only to the height between the upper and lower flanges 111 and 112, but the steel pipe 110 ) and the height difference between the upper and lower flanges (111, 112) are filled with more internal filler material, including unhardened concrete, which does not help reinforce the bending moment, resulting in an increase in construction costs due to an increase in material costs. There is a situation.

대한민국특허청 등록특허공보 특허등록번호 10-1616505호Korea Intellectual Property Office Registered Patent Gazette Patent Registration No. 10-1616505

상기한 바와 같은 종래의 문제점을 해결하기 위한 본 발명은 상부 지반 침하 감소형 루프 강관의 상·하부 양쪽 측면부에 각각 단부 결속형 플랜지를 설치하여 측면부 끼리 서로 연속적으로 구속된 상태로 결속시켜 탈락이나 변형이 없으면서 전방으로만 압입되어 파이프 루프가 설치되도록 구성함으로써 상부 지반의 자중과 통행 차량이나 열차의 진동이나 충격 하중에 대하여 단부 결속형 플랜지가 탈락되어 변형되지 않도록 구속시켜 상부 지반이 침하되는 현상을 방지하고 누수도 방지함으로써 결과적으로는 상부 지반을 통과하는 통행 차량이나 열차의 안전성을 확보하는데 그 목적이 있다.In order to solve the conventional problems described above, the present invention installs end binding flanges on both the upper and lower side surfaces of the upper ground settlement reduction loop steel pipe, and binds the side parts in a continuous state to each other to prevent separation or deformation. By constructing the pipe loop to be installed by press-fitting only forward, the end binding flange is restrained from falling off and deforming due to the self-weight of the upper ground and the vibration or shock load of passing vehicles or trains, thereby preventing the upper ground from sinking. The purpose is to ensure the safety of passing vehicles and trains passing through the upper ground by preventing water leaks.

또한, 지반 내에 상부 지반 침하 감소형 루프 강관을 전방으로 압입시키는 과정에서 상부 지반 침하 감소형 루프 강관의 외부와 단부 결속형 플랜지 사이의 구속된 공간 내의 지반 토사나 상부 지반 침하 감소형 루프 강관의 외부와 상·하부 강관 병렬 결합형 플랜지 또는 상·하부 단부 결속형 플랜지 사이의 구속된 공간 내의 지반 토사를 수시로 실시간 단위로 배토시킬 수 있는 루프 강관 선도관용 측면공을 더 포함하여 설치하여 구속된 공간 내의 지반 토사와의 주면 마찰력을 실시간 단위로 제거하거나 감소시키도록 구성함으로써 상부 지반 침하 감소형 루프 강관의 추진길이를 증가시키면서도 시공 상의 안전성을 향상시키는데 그 목적이 있다.In addition, in the process of press-fitting the upper ground settlement reduction type loop steel pipe forward into the ground, the ground soil and sand within the confined space between the outside of the upper ground settlement reduction type loop steel pipe and the end binding flange or the outside of the upper ground settlement reduction type loop steel pipe It further includes a side hole for a loop steel pipe conductor that can discharge ground soil in the confined space between the upper and lower steel pipe parallel flange or the upper and lower end bound flanges in real time at any time, so that it is installed within the confined space. The purpose is to increase the propulsion length of the upper ground settlement reduction loop steel pipe and improve safety during construction by configuring it to remove or reduce the friction force between the main surface and soil on a real-time basis.

한편, 상기 상부 지반 침하 감소형 루프 강관의 내부에는 하부의 단부 결속형 플랜지 상부의 높이만큼만 굳지 않은 콘크리트를 포함한 내부 채움재를 채우기 위하여, 상부 지반 침하 감소형 루프 강관의 하부 내부에 하부 단부 결속형 플랜지의 높이 이하 또는 하부 강관 병렬 결합형 플랜지의 높이 이하에 해당되는 높이 정도로 제작된 초생달형 거푸집을 더 포함하여 가설재로 설치함으로써 상부 지반 침하 감소형 루프 강관의 하부에 초생달형 거푸집에 해당되는 체적만큼 굳지 않은 콘크리트를 포함한 내부 채움재가 채워지지 않도록 하여 이에 해당되는 내부 채움재를 절감시킴으로써 재료비의 감소에 따른 공사비를 감소시키는데 그 목적이 있다.Meanwhile, in order to fill the inside of the upper ground settlement-reducing loop steel pipe with an internal filler containing unhardened concrete only to the height of the upper part of the lower end-bound flange, a lower end-bound flange is installed inside the lower part of the upper ground settlement-reducing loop steel pipe. By installing it as a temporary material by further including a crescent-shaped form manufactured to a height of less than or equal to the height of the lower steel pipe parallel joint flange, the lower part of the upper ground settlement reduction loop steel pipe is hardened by a volume corresponding to the crescent-shaped form. The purpose is to reduce construction costs due to a reduction in material costs by preventing internal fillers, including raw concrete, from being filled, thereby reducing the corresponding internal fillers.

본 발명은 상기 목적을 달성하기 위하여, 종래 공법용 강관의 양쪽 플랜지가 변형 플랜지로 탈락이나 변형되기 쉬운 연결 구조를 본 발명에서는 탈락되거나 변형 없이 전방으로 한쪽 방향으로만 이동될 수 있는 결속된 힌지 형태인 단부 결속형 플랜지로 개량하여 상부 지반의 자중과 충격하중이 작용해도 탈락되거나 변형되지 않아서 지상의 상부 지반 표면에 함몰부가 발생되지 않도록 하여 차량 통행상 안전성을 증가시키는 원리를 적용하였다.In order to achieve the above object, the present invention replaces the connection structure in which both flanges of a conventional steel pipe for construction with a deformed flange, which are prone to falling off or being deformed, into a connected hinge form that can be moved forward in only one direction without falling off or deforming. By improving the end-binding flange, it does not fall off or deform even when the self-weight and impact load of the upper ground acts, so the principle of increasing safety in vehicle traffic is applied by preventing depressions from forming on the upper ground surface of the ground.

상기 원리를 본 발명에 적용하기 위하여 파이프 루프용 강관의 제1실시예로서, 소정의 직경과 소정의 길이를 갖는 강관과; 상기 강관의 외면 좌측과 우측의 양쪽 측면부의 정점부로부터 다소 하부에 각각 수평방향으로 소정의 폭과 강관의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관에 접합되고 다른 한쪽 끝단부는 U형의 후크 형태로 결속되도록 설치되는 단부 결속형 플랜지와; 상기 강관의 외면 좌측과 우측의 양쪽 측면부의 저점부로부터 다소 상부에 각각 수평방향으로 소정의 폭과 강관의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관에 접합되고 다른 한쪽 끝단부는 U형의 후크 형태로 상기 U형의 후크에 서로 끼워지도록 배열되어 결속되도록 설치되는 단부 결속형 플랜지와; 로 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관에 관한 것이다.In order to apply the above principle to the present invention, a first embodiment of a steel pipe for a pipe loop includes a steel pipe having a predetermined diameter and a predetermined length; The outer surface of the steel pipe has a predetermined width and a length equal to the length of the steel pipe in a horizontal direction somewhat below the apex of both left and right sides, and one end is joined to the steel pipe, and the other end is in the form of a U-shaped hook. An end binding flange installed to be connected to; The steel pipe has a predetermined width and a length equal to the length of the steel pipe in a horizontal direction slightly above the low point on both left and right sides of the outer surface of the steel pipe, and one end is joined to the steel pipe, and the other end is in the form of a U-shaped hook. End binding flanges arranged to fit into the U-shaped hook and installed to be bound to each other; It relates to an upper ground settlement-reducing loop steel pipe, characterized in that it consists of.

또한, 상기 소정의 직경과 소정의 길이를 갖는 강관과; 상기 강관의 외면 좌측과 우측의 양쪽 측면부의 정점부로부터 다소 하부에 각각 수평방향으로 소정의 폭과 강관의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관에 접합되고 다른 한쪽 끝단부는 U형의 후크 형태로 결속되도록 설치되는 단부 결속형 플랜지와; 상기 강관의 외면 좌측과 우측의 양쪽 측면부의 저점부로부터 다소 상부에 각각 수평방향으로 소정의 폭과 강관의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관에 접합되고 다른 한쪽 끝단부는 U형의 후크 형태로 상기 U형의 후크에 서로 끼워지도록 배열되어 결속되도록 설치되는 단부 결속형 플랜지와; 를 제2실시예로서, 수평적으로 다소 이격되어 평행하게 배열되며 소정의 직경과 소정의 길이를 갖는 한 쌍의 강관과; 상기 이격된 한 쌍의 강관 외면 사이에 강관의 정점부로부터 다소 하부에 수평방향으로 소정의 폭에 강관과 길이와 동일한 길이를 갖도록 강관에 접합된 상태로 설치되는 강관 병렬 결합형 플랜지와; 상기 이격된 한 쌍의 강관 외면 사이에 강관의 저점부로부터 다소 상부에 수평방향으로 소정의 폭에 강관과 길이방향으로 동일한 길이를 갖도록 강관에 접합된 상태로 설치되는 강관 병렬 결합형 플랜지와; 상기 우측 강관 외면의 우측과 좌측 강관 외면의 좌측에 각각 강관의 정점부로부터 다소 하부에 수평방향으로 소정의 폭과 강관의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관에 접합되고 다른 한쪽 끝단부는 U형의 후크 형태로 결속되도록 설치되는 단부 결속형 플랜지와; 상기 우측 강관 외면의 우측과 좌측 강관 외면의 좌측에 각각 강관의 저점부로부터 다소 상부에 수평방향으로 소정의 폭과 강관의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관에 접합되고 다른 한쪽 끝단부는 U형의 후크 형태로 결속되도록 설치되는 단부 결속형 플랜지와; 로 치환되는 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관에 관한 것이다.In addition, a steel pipe having the predetermined diameter and the predetermined length; The outer surface of the steel pipe has a predetermined width and a length equal to the length of the steel pipe in a horizontal direction somewhat below the apex of both left and right sides, and one end is joined to the steel pipe, and the other end is in the form of a U-shaped hook. An end binding flange installed to be connected to; The steel pipe has a predetermined width and a length equal to the length of the steel pipe in a horizontal direction slightly above the low point on both left and right sides of the outer surface of the steel pipe, and one end is joined to the steel pipe, and the other end is in the form of a U-shaped hook. End binding flanges arranged to fit into the U-shaped hook and installed to be bound to each other; As a second embodiment, a pair of steel pipes arranged in parallel and somewhat spaced apart horizontally and having a predetermined diameter and a predetermined length; A steel pipe parallel coupling type flange installed between the outer surfaces of the pair of spaced steel pipes in a horizontal direction slightly below the apex of the steel pipe and joined to the steel pipe to have a predetermined width and a length equal to the length of the steel pipe; a steel pipe parallel coupling type flange installed between the outer surfaces of the pair of spaced steel pipes in a horizontal direction slightly above the low point of the steel pipe and joined to the steel pipe to have a predetermined width and the same length in the longitudinal direction as the steel pipe; On the right side of the outer surface of the right steel pipe and on the left side of the outer surface of the left steel pipe, each has a predetermined width in the horizontal direction somewhat below the apex of the steel pipe and a length equal to the length of the steel pipe, and one end is joined to the steel pipe, and the other end is U. An end binding flange installed to be connected in the form of a hook; On the right side of the outer surface of the right steel pipe and on the left side of the outer surface of the left steel pipe, each has a predetermined width in the horizontal direction slightly above the low point of the steel pipe and a length equal to the length of the steel pipe, and one end is joined to the steel pipe and the other end is U. An end binding flange installed to be connected in the form of a hook; It relates to an upper ground settlement reduction type loop steel pipe, characterized in that it is replaced by .

한편, 상기 제1실시예와 제2실시예 중의 어느 하나에 있어서, 상부와 하부의 강관 병렬 결합형 플랜지 사이 또는 상부와 하부의 단부 결속형 플랜지 사이에 강관의 길이방향으로 소정의 간격마다 소정의 높이의 위치에 강관을 관통하여 소정의 직경을 갖는 보강근 삽입공을 더 포함하여 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관에 관한 것이다.Meanwhile, in any one of the first and second embodiments, a predetermined gap is provided at predetermined intervals in the longitudinal direction of the steel pipe between the upper and lower steel pipe parallel coupling flanges or between the upper and lower end coupling flanges. It relates to an upper ground settlement reduction loop steel pipe, characterized in that it further includes a reinforcing bar insertion hole having a predetermined diameter penetrating the steel pipe at a height position.

또한, 상기 제1실시예와 제2실시예 중의 어느 하나에 있어서, 강관의 길이방향을 기준으로 압입시 전방으로 첫 번째로 설치되는 선도용 강관의 전방으로부터 길이방향으로 다소 이격된 좌측과 우측의 측면부에 각각 직경의 수직방향 중앙부 위치에 소정의 직경을 갖는 원형으로 강관이 천공되는 루프 강관 선도관용 측면공을 더 포함하여 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관에 관한 것이다.In addition, in any one of the first and second embodiments, the left and right sides are slightly spaced apart in the longitudinal direction from the front of the leading steel pipe, which is first installed forward when press-fitting, based on the longitudinal direction of the steel pipe. It relates to an upper ground settlement reduction type loop steel pipe, characterized in that the side hole for the loop steel pipe conductor pipe is perforated in a circular shape with a predetermined diameter at a central position in the vertical direction of each diameter on the side portion.

한편, 상기 제1실시예와 제2실시예 중의 어느 하나에 있어서, 루프 강관 선도관용 측면공의 강관 내측 주위를 둘러싸도록 소정의 폭을 갖는 링 형상의 보강 덧판에 해당되는 측면공 가장자리 보강판을 더 포함하여 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관에 관한 것이다.Meanwhile, in any one of the first and second embodiments, a side hole edge reinforcement plate corresponding to a ring-shaped reinforcement plate having a predetermined width is provided to surround the inner side of the steel pipe of the side hole for the loop steel pipe lead pipe. It relates to an upper ground settlement-reducing loop steel pipe, characterized in that it further includes.

또한, 상기 제1실시예와 제2실시예 중의 어느 하나에 있어서, 강관의 길이방향으로 압입 전방으로 첫 번째로 설치되는 선도용 강관의 전방부 상부에 다소 돌출되도록 강관의 곡률과 동일하며 소정의 폭과 길이를 갖는 상부 지반 침하 방지판을 더 포함하여 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관에 관한 것이다.In addition, in any one of the first and second embodiments, the curvature of the steel pipe is the same as the curvature of the steel pipe so as to slightly protrude above the front portion of the leading steel pipe that is first installed toward the press-fitting front in the longitudinal direction of the steel pipe. It relates to an upper ground settlement-reducing loop steel pipe, characterized in that it further includes an upper ground settlement prevention plate having a width and length.

한편, 통상적인 도로나 철도를 대상으로 얕은 토피의 상태로 지하로 횡단하는 지반 내에 파이프 루프를 시공함에 있어서, 반력 말뚝과 반력벽을 포함하는 통상적인 추진대를 제작하여 설치하는 공정과; 상기 추진대를 제작하여 설치하는 공정 후 상부 지반 침하 감소형 루프 강관의 단부 결속형 플랜지끼리 연속적으로 연결시키면서 압입시켜 파이프 루프를 형성시키고 상부 지반 침하 감소형 루프 강관의 내부와 상부 지반 침하 감소형 루프 강관의 외부와 단부 결속형 플랜지 사이의 구속된 공간 내의 지반 토사를 굴착함과 동시에 상부 지반 침하 감소형 루프 강관을 전방으로 압입시켜 추진하는 공정과; 상기 상부 지반 침하 감소형 루프 강관을 전방으로 압입시켜 추진하는 공정 후 강관의 길이방향을 기준으로 직각방향으로 보강근 삽입공을 통해서 보강근을 설치하는 공정과; 상기 보강근을 설치하는 공정 후 상부지반 침하 감소형 루프 강관의 내부와 상부 지반 침하 감소형 루프 강관의 외부와 단부 결속형 플랜지 사이의 구속된 공간 내부에 채움재를 채워서 양생시키는 공정과; 상기 채움재를 채워서 양생시키는 공정 후 상부 지반 침하 감소형 루프 강관으로 연속적으로 결속시켜 구성된 파이프 루프 내부의 지반 토사를 굴착하는 공정과; 상기 파이프 루프 내부의 지반 토사를 굴착하는 공정 후 파이프 루프 내측면을 대상으로 방수 마감공을 시공하는 공정과; 로 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법에 관한 것이다.On the other hand, in constructing a pipe loop in the ground crossing underground in a shallow top cover for a typical road or railroad, the process includes manufacturing and installing a typical propulsion base including a reaction pile and a reaction wall; After the process of manufacturing and installing the propulsion base, a pipe loop is formed by continuously connecting the end flanges of the upper ground settlement reduction loop steel pipe and press-fitting them, and forming a pipe loop inside the upper ground settlement reduction loop steel pipe and the upper ground settlement reduction loop. A process of excavating ground soil in the confined space between the outside of the steel pipe and the end binding flange and simultaneously pushing the upper ground settlement-reducing loop steel pipe forward and pushing it forward; After the process of press-fitting and propelling the upper ground settlement-reducing roof steel pipe forward, a process of installing reinforcing bars through reinforcing bar insertion holes in a direction perpendicular to the longitudinal direction of the steel pipe; After the step of installing the reinforcing bars, a process of curing the inside of the upper ground settlement reduction type loop steel pipe and the inside of the confined space between the outside of the upper ground settlement reduction type loop steel pipe and the end binding flange with filler; After the process of filling and curing the filler, a process of excavating the soil and soil inside the pipe loop formed by continuously binding the upper ground settlement reduction loop steel pipe; A process of constructing a waterproof finishing hole on the inner surface of the pipe loop after excavating the ground soil inside the pipe loop; It relates to a pipe loop construction method using an upper ground settlement-reducing roof steel pipe, characterized in that it consists of.

또한, 상기 추진대를 제작 설치하는 공정 후 상부 지반 침하 감소형 루프 강관의 단부 결속형 플랜지끼리 연속적으로 연결시키면서 압입시켜 파이프 루프를 형성시키고 상부 지반 침하 감소형 루프 강관의 내부와 상부 지반 침하 감소형 루프 강관의 외부와 단부 결속형 플랜지 사이의 구속된 공간 내의 지반 토사를 굴착함과 동시에 상부 지반 침하 감소형 루프 강관을 전방으로 압입시켜 추진하는 공정과; 를 상부 지반 침하 감소형 루프 강관의 단부 결속형 플랜지끼리 연속적으로 연결시키면서 압입시켜 파이프 루프를 형성시키고 상부 지반 침하 감소형 루프 강관의 내부와 상부지반 침하 감소형 루프 강관의 외부와 상·하부 강관 병렬 결합형 플랜지 및 상·하부 단부 결속형 플랜지 사이의 구속된 공간 내의 지반 토사를 굴착함과 동시에 상부 지반 침하 감소형 루프 강관을 전방으로 압입시켜 추진하는 공정과; 로 치환되는 것을 특징으로 하는 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법에 관한 것이다.In addition, after the process of manufacturing and installing the propulsion base, the end binding flanges of the upper ground settlement reduction type loop steel pipe are continuously connected to each other and press-fitted to form a pipe loop, and the interior and upper ground settlement reduction type of the upper ground settlement reduction type loop steel pipe are formed. A process of excavating ground soil in the confined space between the outside of the loop steel pipe and the end binding flange and simultaneously pushing and pushing the upper ground settlement-reducing loop steel pipe forward; The end binding flanges of the upper ground settlement reduction loop steel pipe are continuously connected and press-fitted to form a pipe loop, and the inside of the upper ground settlement reduction type loop steel pipe and the outside of the upper ground settlement reduction type loop steel pipe are parallel with the upper and lower steel pipes. A process of excavating ground soil in the confined space between the coupling flange and the upper and lower end coupling flanges and simultaneously pushing and pushing the upper ground settlement reduction loop steel pipe forward; It relates to a pipe loop construction method using an upper ground settlement-reducing roof steel pipe, characterized in that it is replaced by .

한편, 상기 파이프 루프 내측면을 대상으로 방수 마감공을 시공하는 공정 후 방수 마감공의 내부에 본체 구조물을 더 포함하여 설치하도록 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법에 관한 것이다.On the other hand, a pipe loop construction method using an upper ground settlement-reducing roof steel pipe, characterized in that a main body structure is further included and installed inside the waterproof finishing hole after the process of constructing a waterproof finishing hole targeting the inner surface of the pipe loop. It's about.

또한, 상기 보강근을 설치하는 공정 이후에 상부 지반 침하 감소형 루프 강관의 하부에 초생달형 거푸집을 더 포함하여 설치하는 공정과; 상기 채움재를 채워서 양생시키는 공정 후 채움재의 하부를 대상으로 하부 단부 결속형 플랜지의 높이 이하 또는 하부 강관 병렬 결합형 플랜지의 높이 이하에 해당되는 높이 정도의 상부 지반 침하 감소형 루프 강관의 하부를 초생달형 거푸집을 포함하여 절단하여 제거시키는 공정과; 를 더 포함하여 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법에 관한 것이다.In addition, after the step of installing the reinforcing bars, a process of installing a crescent-shaped form further included in the lower part of the upper ground settlement reduction type loop steel pipe; After the process of filling and curing the filler, the lower part of the upper ground settlement reduction type loop steel pipe with a height corresponding to less than the height of the lower end binding type flange or less than the height of the lower steel pipe parallel combination type flange is shaped like a crescent moon. A process of cutting and removing, including the formwork; It relates to a pipe loop construction method using an upper ground settlement-reducing roof steel pipe, characterized in that it further includes.

본 발명은 상부 지반 침하 감소형 루프 강관의 상·하부 양쪽 측면부에 각각 단부 결속형 플랜지를 설치하여 측면부 끼리 서로 연속적으로 구속된 상태로 결속시켜 탈락이나 변형이 없으면서 전방으로만 압입되어 파이프 루프가 설치되도록 구성함으로써 상부 지반의 자중과 통행 차량이나 열차의 진동이나 충격 하중에 대하여 단부 결속형 플랜지가 탈락되어 변형되지 않도록 구속시켜 상부지반이 침하되는 현상을 방지하고 누수도 방지함으로써 결과적으로는 상부 지반을 통과하는 통행 차량이나 열차의 안전성을 확보하는 효과가 있다.In the present invention, end binding flanges are installed on both upper and lower sides of the upper ground settlement reduction loop steel pipe, and the side parts are continuously bound to each other, so that the pipe loop is installed by press-fitting only forward without falling off or deforming. By constructing it so that the end binding flange does not fall off and deform due to the self-weight of the upper ground and the vibration or shock load of passing vehicles or trains, it prevents the upper ground from sinking and prevents water leaks, ultimately maintaining the upper ground. It has the effect of ensuring the safety of passing vehicles or trains.

또한, 지반 내에 상부 지반 침하 감소형 루프 강관을 전방으로 압입시키는 과정에서 상부 지반 침하 감소형 루프 강관의 외부와 단부 결속형 플랜지 사이의 구속된 공간 내의 지반 토사나 상부 지반 침하 감소형 루프 강관의 외부와 상·하부 강관 병렬 결합형 플랜지 또는 상·하부 단부 결속형 플랜지 사이의 구속된 공간 내의 지반 토사를 수시로 실시간 단위로 배토시킬 수 있는 루프 강관 선도관용 측면공을 더 포함하여 설치하여 구속된 공간 내의 지반 토사와의 주면 마찰력을 실시간 단위로 제거하거나 감소시키도록 구성함으로써 상부 지반 침하 감소형 루프 강관의 추진 길이를 증가시키면서도 시공 상의 안전성을 향상시키는 효과가 있다.In addition, in the process of press-fitting the upper ground settlement reduction type loop steel pipe forward into the ground, the ground soil and sand within the confined space between the outside of the upper ground settlement reduction type loop steel pipe and the end binding flange or the outside of the upper ground settlement reduction type loop steel pipe It further includes a side hole for a loop steel pipe conductor that can discharge ground soil in the confined space between the upper and lower steel pipe parallel flange or the upper and lower end bound flanges in real time at any time, so that it is installed within the confined space. By configuring it to remove or reduce the friction force between the main surface and soil on a real-time basis, it has the effect of increasing the propulsion length of the upper ground settlement reduction loop steel pipe and improving safety during construction.

한편, 상기 상부 지반 침하 감소형 루프 강관의 내부에는 하부의 단부 결속형 플랜지 상부의 높이만큼만 굳지 않은 콘크리트를 포함한 내부 채움재를 채우기 위하여, 상부 지반 침하 감소형 루프 강관의 하부 내부에 하부 단부 결속형 플랜지의 높이 이하 또는 하부 강관 병렬 결합형 플랜지의 높이 이하에 해당되는 높이 정도로 제작된 초생달형 거푸집을 더 포함하여 가설재로 설치함으로써 상부 지반 침하 감소형 루프 강관의 하부에 초생달형 거푸집에 해당되는 체적만큼 굳지 않은 콘크리트를 포함한 내부 채움재가 채워지지 않도록 하여 이에 해당되는 내부 채움재를 절감시킴으로써 재료비의 감소에 따른 공사비를 감소시키는 효과가 있다.Meanwhile, in order to fill the inside of the upper ground settlement-reducing loop steel pipe with an internal filler containing unhardened concrete only to the height of the upper part of the lower end-bound flange, a lower end-bound flange is installed inside the lower part of the upper ground settlement-reducing loop steel pipe. By installing it as a temporary material by further including a crescent-shaped form manufactured to a height of less than or equal to the height of the lower steel pipe parallel joint flange, the lower part of the upper ground settlement reduction loop steel pipe is hardened by a volume corresponding to the crescent-shaped form. This has the effect of reducing construction costs due to a reduction in material costs by reducing the corresponding internal filler material by preventing the internal filler material, including raw concrete, from being filled.

도 1은 종래 발명의 제1실시예로서, 강관 양쪽 측면부에 부착된 각각의 플랜지 끝단부가 캔틸레버 형태의 자유단으로 구성되어 상부 지반의 자중이나 통행 차량이나 열차로 인한 충격력에 의해 하향으로 탈락되어 변형되기 쉬운 구성의 사시도.
도 2는 종래 발명의 제2실시예로서, 수평적으로 소정의 간격을 갖는 한 쌍의 강관 양쪽 측면부에 부착된 각각의 플랜지 끝단부가 캔틸레버 형태의 자유단으로 구성되어 상부지반의 자중이나 통행 차량이나 열차로 인한 충격력에 의해 하향으로 탈락되어 변형되기 쉬운 구성의 사시도.
도 3은 종래 발명의 강관 양쪽 측면부에 부착된 각각의 플랜지 끝단부가 캔틸레버 형태의 자유단으로 구성되어 상부 지반의 자중이나 통행 차량이나 열차로 인한 충격력에 의해 하향으로 탈락되어 변형된 상태로서 지반 침하 원인인 지반 함몰부가 발생되는 원리의 단면 개념도.
도 4는 본 발명의 상부 지반 침하 감소형 루프 강관 제1실시예의 단면도.
도 5는 본 발명의 상부 지반 침하 감소형 루프 강관 제2실시예의 단면도.
도 6은 본 발명의 상부 지반 침하 감소형 루프 강관 제1실시예에 보강근 삽입공을 더 포함하여 구성된 상태의 사시도.
도 7은 본 발명의 상부 지반 침하 감소형 루프 강관 제2실시예에 보강근 삽입공을 더 포함하여 구성된 상태의 사시도.
도 8은 본 발명의 상부 지반 침하 감소형 루프 강관 제1실시예의 1본으로서 선도용 강관에 상부 지반 침하 방지판과 루프 강관 선도관용 측면공과 측면공 가장자리 보강판을 각각 더 포함하여 구성된 사시도.
도 9는 본 발명의 상부 지반 침하 감소형 루프 강관 제2실시예의 1본으로서 선도용 강관에 상부 지반 침하 방지판과 루프 강관 선도관용 측면공과 측면공 가장자리 보강판을 각각 더 포함하여 구성된 사시도.
도 10은 본 발명의 상부 지반 침하 감소형 루프 강관 제1실시예에 보강근이 설치되고 채움재가 채워진 상태의 단면도.
도 11은 본 발명의 상부 지반 침하 감소형 루프 강관 제2실시예에 보강근이 설치되고 채움재가 채워진 상태의 단면도.
도 12는 본 발명의 상부 지반 침하 감소형 루프 강관 제1실시예의 하부에 초생달형 거푸집이 설치된 상태를 나타내는 단면도.
도 13은 본 발명의 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법의 단면도.
도 14는 본 발명의 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법 시공시 지반 내 전방으로 상부 지반 침하 감소형 루프 강관의 압입 단면도.
도 15는 본 발명의 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법 시공시 지반 내 전방으로 상부 지반 침하 감소형 루프 강관의 압입 평면도.
도 16은 본 발명의 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법의 시공 공정도.
Figure 1 is a first embodiment of a conventional invention, in which each flange end attached to both side surfaces of a steel pipe is composed of a free end in the form of a cantilever, and is deformed by falling off downward due to its own weight from the upper ground or impact force from a passing vehicle or train. A perspective view of an easy-to-make configuration.
Figure 2 is a second embodiment of the prior invention, in which each flange end attached to both side surfaces of a pair of steel pipes with a predetermined horizontal spacing is composed of a cantilever-shaped free end, so that it can be used for the self-weight of the upper ground or passing vehicles. A perspective view of a configuration that is prone to deformation by falling off downward due to impact force from a train.
Figure 3 shows a state in which each flange end attached to both sides of the steel pipe of the prior invention is composed of a free end in the form of a cantilever, and is deformed and detached downward due to its own weight from the upper ground or impact force from a passing vehicle or train, which is the cause of ground subsidence. A cross-sectional conceptual diagram of the principle by which ground depressions occur.
Figure 4 is a cross-sectional view of the first embodiment of the upper ground settlement reduction type loop steel pipe of the present invention.
Figure 5 is a cross-sectional view of the second embodiment of the upper ground settlement reduction type loop steel pipe of the present invention.
Figure 6 is a perspective view of the first embodiment of the upper ground settlement reduction type loop steel pipe of the present invention in a state in which a reinforcing bar insertion hole is further included.
Figure 7 is a perspective view of the second embodiment of the upper ground settlement-reduced loop steel pipe of the present invention further including a reinforcing bar insertion hole.
Figure 8 is a perspective view of the first embodiment of the upper ground settlement-reducing loop steel pipe of the present invention, which further includes an upper ground settlement prevention plate, a side hole for the loop steel pipe lead pipe, and a side hole edge reinforcement plate on the leading steel pipe, respectively.
Figure 9 is a perspective view of a second embodiment of the upper ground settlement-reducing loop steel pipe of the present invention, which further includes an upper ground settlement prevention plate, a side hole for the loop steel pipe lead pipe, and a side hole edge reinforcement plate on the leading steel pipe, respectively.
Figure 10 is a cross-sectional view of the first embodiment of the upper ground settlement reduction loop steel pipe of the present invention with reinforcing bars installed and filled with filler.
Figure 11 is a cross-sectional view of the second embodiment of the upper ground settlement reduction loop steel pipe of the present invention with reinforcing bars installed and filled with filler.
Figure 12 is a cross-sectional view showing a state in which a crescent-shaped formwork is installed at the lower part of the first embodiment of the upper ground settlement reduction type loop steel pipe of the present invention.
Figure 13 is a cross-sectional view of the pipe loop construction method using the upper ground settlement-reduced loop steel pipe of the present invention.
Figure 14 is a cross-sectional view of the upper ground settlement reduction type loop steel pipe being press-fitted forward into the ground during construction of the pipe loop construction method using the upper ground settlement reduction type loop steel pipe of the present invention.
Figure 15 is a plan view of the upper ground settlement reduction type loop steel pipe being press-fitted forward into the ground during construction of the pipe loop construction method using the upper ground settlement reduction type loop steel pipe of the present invention.
Figure 16 is a construction process diagram of the pipe loop construction method using the upper ground settlement reduction loop steel pipe of the present invention.

본 발명은 다양한 변경을 가할 수 있고 여러 가지 실시 예를 가질 수 있는 바, 특정 실시 예 들을 도면에 예시하고 상세한 설명에 상세하게 설명하고자 한다. 그러나, 이는 본 발명을 특정한 실시 형태에 대해 한정하려는 것이 아니며, 본 발명의 사상 및 기술 범위에 포함되는 모든 변경, 균등물 내지 대체물을 포함하는 것으로 이해되어야 한다.Since the present invention can be modified in various ways and can have various embodiments, specific embodiments will be illustrated in the drawings and described in detail in the detailed description. However, this is not intended to limit the present invention to specific embodiments, and should be understood to include all changes, equivalents, and substitutes included in the spirit and technical scope of the present invention.

본 발명은 이하에서 개시되는 실시 예에 한정되는 것이 아니라 서로 다른 다양한 형태로 구현될 수 있으며, 단지 본 실시 예는 본 발명의 개시가 완전하도록 하며 통상의 지식을 가진 자에게 발명의 범주를 완전하게 알려주기 위하여 제공되는 것이다.The present invention is not limited to the embodiments disclosed below and may be implemented in various different forms, but the present embodiments only serve to complete the disclosure of the present invention and to fully convey the scope of the invention to those skilled in the art. It is provided for information purposes only.

이하, 본 발명의 바람직한 실시 예를 첨부된 도면들을 참조하여 상세히 설명한다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the attached drawings.

또한, 본 발명을 설명함에 있어서, 관련된 공지 구성 또는 기능에 대한 구체적인 설명이 본 고안의 요지를 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명은 생략한다.Additionally, in describing the present invention, if it is determined that a detailed description of a related known configuration or function may obscure the gist of the present invention, the detailed description will be omitted.

도 1은 종래 발명의 제1실시예로서, 강관 양쪽 측면부에 부착된 각각의 플랜지 끝단부가 캔틸레버 형태의 자유단으로 구성되어 상부 지반의 자중이나 통행 차량이나 열차로 인한 충격력에 의해 하향으로 탈락되어 변형되기 쉬운 구성의 사시도이고, 도 2는 종래 발명의 제2실시예로서, 수평적으로 소정의 간격을 갖는 한 쌍의 강관 양쪽 측면부에 부착된 각각의 플랜지 끝단부가 캔틸레버 형태의 자유단으로 구성되어 상부 지반의 자중이나 통행 차량이나 열차로 인한 충격력에 의해 하향으로 탈락되어 변형되기 쉬운 구성의 사시도이며, 도 3은 종래 발명의 강관 양쪽 측면부에 부착된 각각의 플랜지 끝단부가 캔틸레버 형태의 자유단으로 구성되어 상부 지반의 자중이나 통행 차량이나 열차로 인한 충격력에 의해 하향으로 탈락되어 변형된 상태로서 지반 침하 원인인 지반 함몰부가 발생되는 원리의 단면 개념도이고, 도 4는 본 발명의 상부 지반 침하 감소형 루프 강관 제1실시예의 단면도이며, 도 5는 본 발명의 상부 지반 침하 감소형 루프 강관 제2실시예의 단면도이고, 도 6은 본 발명의 상부 지반 침하 감소형 루프 강관 제1실시예에 보강근 삽입공을 더 포함하여 구성된 상태의 사시도이며, 도 7은 본 발명의 상부 지반 침하 감소형 루프 강관 제2실시예에 보강근 삽입공을 더 포함하여 구성된 상태의 사시도이고, 도 8은 본 발명의 상부 지반 침하 감소형 루프 강관 제1실시예의 1본으로서 선도용 강관에 상부 지반 침하 방지판과 루프 강관 선도관용 측면공과 측면공 가장자리 보강판을 각각 더 포함하여 구성된 사시도이며, 도 9는 본 발명의 상부 지반 침하 감소형 루프 강관 제2실시예의 1본으로서 선도용 강관에 상부 지반 침하 방지판과 루프 강관 선도관용 측면공과 측면공 가장자리 보강판을 각각 더 포함하여 구성된 사시도이고, 도 10은 본 발명의 상부 지반 침하 감소형 루프 강관 제1실시예에 보강근이 설치되고 채움재가 채워진 상태의 단면도이며, 도 11은 본 발명의 상부 지반 침하 감소형 루프 강관 제2실시예에 보강근이 설치되고 채움재가 채워진 상태의 단면도이고, 도 12는 본 발명의 상부 지반 침하 감소형 루프 강관 제1실시예의 하부에 초생달형 거푸집이 설치된 상태를 나타내는 단면도이며, 도 13은 본 발명의 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법의 단면도이고, 도 14는 본 발명의 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법 시공시 지반 내 전방으로 상부 지반 침하 감소형 루프 강관의 압입 단면도이며, 도 15는 본 발명의 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법 시공시 지반 내 전방으로 상부 지반 침하 감소형 루프 강관의 압입 평면도이고, 도 16은 본 발명의 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법의 시공 공정도를 나타낸 것이다.Figure 1 is a first embodiment of a conventional invention, in which each flange end attached to both side surfaces of a steel pipe is composed of a free end in the form of a cantilever, and is deformed by falling off downward due to its own weight from the upper ground or impact force from a passing vehicle or train. Figure 2 is a perspective view of an easy-to-use configuration, and Figure 2 is a second embodiment of the prior invention, in which each flange end attached to both side surfaces of a pair of steel pipes with a predetermined horizontal distance is composed of a cantilever-shaped free end, It is a perspective view of a configuration that is prone to deformation by falling off downward due to the ground's own weight or impact force from passing vehicles or trains. Figure 3 shows that each flange end attached to both sides of the steel pipe of the prior invention is composed of a cantilever-shaped free end. It is a cross-sectional conceptual diagram of the principle in which a ground depression, which is the cause of ground subsidence, is generated in a state in which it is deformed and dislodged downward by the self-weight of the upper ground or the impact force from passing vehicles or trains, and Figure 4 is a cross-sectional conceptual diagram of the upper ground subsidence reduction type loop steel pipe of the present invention. It is a cross-sectional view of the first embodiment, and Figure 5 is a cross-sectional view of the second embodiment of the upper ground settlement-reducing loop steel pipe of the present invention, and Figure 6 is a cross-sectional view of the first embodiment of the upper ground settlement-reducing loop steel pipe of the present invention, adding a reinforcing bar insertion hole. Figure 7 is a perspective view of the second embodiment of the upper ground settlement reduction type loop steel pipe of the present invention further including a reinforcing bar insertion hole, and Figure 8 is a perspective view of the upper ground settlement reduction type loop steel pipe of the present invention. As one example of the first embodiment of the loop steel pipe, the leading steel pipe further includes an upper ground settlement prevention plate, a side hole for the loop steel pipe leading pipe, and a side hole edge reinforcement plate, respectively. Figure 9 is a perspective view of the upper ground settlement reduction type of the present invention. As one example of the second embodiment of the loop steel pipe, the leading steel pipe further includes an upper ground settlement prevention plate, a side hole for the loop steel pipe leading pipe, and a side hole edge reinforcement plate, respectively. Figure 10 is a perspective view of the upper ground settlement reduction type of the present invention. It is a cross-sectional view of the first embodiment of the loop steel pipe with reinforcing bars installed and filled with filler, and Figure 11 is a cross-sectional view of the second embodiment of the upper ground settlement reduction loop steel pipe of the present invention with reinforcing bars installed and filled with filler. 12 is a cross-sectional view showing a state in which a crescent-shaped formwork is installed at the lower part of the first embodiment of the upper ground settlement-reducing loop steel pipe of the present invention, and Figure 13 is a cross-sectional view of the pipe loop construction method using the upper ground settlement-reducing loop steel pipe of the present invention. , and Figure 14 is a cross-sectional view of the upper ground settlement reduction type loop steel pipe forward in the ground during construction of the pipe loop construction method using the upper ground settlement reduction type loop steel pipe of the present invention, and Figure 15 is a press-fitting cross-sectional view of the upper ground settlement reduction type loop steel pipe of the present invention. It is a plan view of the upper ground settlement reduction type loop steel pipe being press-fitted forward into the ground during the construction of the pipe loop construction method using a loop steel pipe, and Figure 16 shows the construction process diagram of the pipe loop construction method using the upper ground settlement reduction type loop steel pipe of the present invention. will be.

본 발명은 도1 내지 도3에 도시된 바와 같이 종래 공법용 강관(1)의 양쪽 플랜지(7)가 변형 플랜지(7')로 탈락이나 변형되기 쉬운 연결 구조를 본 발명에서는 도4 내지 도12에 도시된 바와 같이 탈락이나 변형이 없이 전방으로 한쪽 방향으로만 이동될 수 있는 결속된 힌지 형태인 단부 결속형 플랜지(13)로 개량하여 상부 지반(2)의 자중과 충격하중이 작용해도 탈락되거나 변형되지 않아서 지상의 상부 지반(2) 표면에 함몰부(2')가 발생되지 않도록 하여 차량 통행상 안전성을 증가시키는 원리를 적용하였다.As shown in FIGS. 1 to 3, the present invention provides a connection structure in which both flanges 7 of the conventional steel pipe 1 for construction are easily deformed or dislodged by the deformed flange 7'. In the present invention, the connection structure is provided in FIGS. 4 to 12. As shown in , it has been improved to be an end-bound flange (13), which is a type of bound hinge that can only be moved forward in one direction without falling off or deforming, so that it does not fall off even when the self-weight and impact load of the upper ground (2) acts. The principle of increasing safety in vehicle traffic was applied by preventing depressions (2') from forming on the surface of the upper ground (2) because they are not deformed.

상기 원리를 본 발명에 적용하기 위하여 파이프 루프용 강관의 제1실시예로서, 도4 및 도6에 도시된 바와 같이, 소정의 직경과 소정의 길이를 갖는 강관(11)과; 상기 강관(11)의 외면 좌측과 우측의 양쪽 측면부의 정점부로부터 다소 하부에 각각 수평방향으로 소정의 폭과 강관(11)의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관(11)에 접합되고 다른 한쪽 끝단부는 통상적인 U형(또는 "ㄷ"자형)의 후크 형태로 결속되도록 설치되는 단부 결속형 플랜지(13)와; 상기 강관(11)의 외면 좌측과 우측의 양쪽 측면부의 저점부로부터 다소 상부에 각각 수평방향으로 소정의 폭과 강관(11)의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관(11)에 접합되고 다른 한쪽 끝단부는 U형의 후크 형태로 상기 U형의 후크에 서로 끼워지도록 배열되어 결속되도록 설치되는 단부 결속형 플랜지(13)와; 로 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관(9)에 관한 것이다.In order to apply the above principle to the present invention, a first embodiment of a steel pipe for a pipe loop includes, as shown in Figures 4 and 6, a steel pipe 11 having a predetermined diameter and a predetermined length; The outer surface of the steel pipe 11 has a predetermined width and a length equal to the length of the steel pipe 11 in a horizontal direction slightly below the apex of both left and right side surfaces, and one end is joined to the steel pipe 11. The other end includes an end binding flange (13) installed to be fastened in a typical U-shaped (or “ㄷ”-shaped) hook shape; The steel pipe 11 has a predetermined width and a length equal to the length of the steel pipe 11 in a horizontal direction slightly above the low point on both the left and right sides of the outer surface of the steel pipe 11, and one end is joined to the steel pipe 11. The other end is in the form of a U-shaped hook, and an end binding flange (13) is arranged to fit into the U-shaped hook and is installed to be bound; It relates to an upper ground settlement reduction type loop steel pipe (9), characterized in that it consists of.

여기서, 상기 통상적인 강관(11)과 통상적인 강판을 가공하여 제작되는 단부 결속형 플랜지(13)의 접합시에는 통상적인 용접을 사용하는 것이 경제적이고 바람직하다.Here, when joining the conventional steel pipe 11 and the end-binding flange 13 manufactured by processing a conventional steel plate, it is economical and desirable to use conventional welding.

또한, 상기 도4 및 도6에 도시된 바와 같이, 소정의 직경과 소정의 길이를 갖는 강관(11)과; 상기 강관(11)의 외면 좌측과 우측의 양쪽 측면부의 정점부로부터 다소 하부에 각각 수평방향으로 소정의 폭과 강관(11)의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관(11)에 접합되고 다른 한쪽 끝단부는 통상적인 U형의 후크 형태로 결속되도록 설치되는 단부 결속형 플랜지(13)와; 상기 강관(11)의 외면 좌측과 우측의 양쪽 측면부의 저점부로부터 다소 상부에 각각 수평방향으로 소정의 폭과 강관(11)의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관(11)에 접합되고 다른 한쪽 끝단부는 통상적인 U형의 후크 형태로 상기 U형의 후크에 서로 끼워지도록 배열되어 결속되도록 설치되는 단부 결속형 플랜지(13)와; 를 상기 도5 및 도7에 도시된 바와 같이, 제2실시예로서, 수평적으로 다소 이격되어 평행하게 배열되며 소정의 직경과 소정의 길이를 갖는 한 쌍의 강관(11)과; 상기 이격된 한 쌍의 강관(11) 외면 사이에 강관(11)의 정점부로부터 다소 하부에 수평방향으로 소정의 폭에 강관과 길이와 동일한 길이를 갖도록 강관(11)에 접합된 상태로 설치되는 강관 병렬 결합형 플랜지(17)와; 상기 이격된 한 쌍의 강관(11) 외면 사이에 강관(11)의 저점부로부터 다소 상부에 수평방향으로 소정의 폭에 강관(11)과 길이방향으로 동일한 길이를 갖도록 강관(11)에 접합된 상태로 설치되는 강관 병렬 결합형 플랜지(17)와; 상기 우측 강관(11) 외면의 우측과 좌측 강관(11) 외면의 좌측에 각각 강관(11)의 정점부로부터 다소 하부에 수평방향으로 소정의 폭과 강관(11)의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관(11)에 접합되고 다른 한쪽 끝단부는 통상적인 U형의 후크 형태로 결속되도록 설치되는 단부 결속형 플랜지(13)와; 상기 우측 강관(11) 외면의 우측과 좌측 강관(11) 외면의 좌측에 각각 강관(11)의 저점부로부터 다소 상부에 수평방향으로 소정의 폭과 강관(11)의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관(11)에 접합되고 다른 한쪽 끝단부는 통상적인 U형의 후크 형태로 결속되도록 설치되는 단부 결속형 플랜지(13)와; 로 치환되는 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관(15)에 관한 것이다.In addition, as shown in FIGS. 4 and 6, a steel pipe 11 having a predetermined diameter and a predetermined length; The outer surface of the steel pipe 11 has a predetermined width and a length equal to the length of the steel pipe 11 in a horizontal direction slightly below the apex of both left and right side surfaces, and one end is joined to the steel pipe 11. The other end includes an end binding flange (13) installed to be fastened in the form of a typical U-shaped hook; The steel pipe 11 has a predetermined width and a length equal to the length of the steel pipe 11 in a horizontal direction slightly above the low point on both the left and right sides of the outer surface of the steel pipe 11, and one end is joined to the steel pipe 11. The other end is in the form of a typical U-shaped hook, and an end binding flange (13) is arranged to fit into the U-shaped hook and is installed to be bound; As shown in FIGS. 5 and 7, in the second embodiment, a pair of steel pipes 11 arranged in parallel and somewhat spaced apart horizontally and having a predetermined diameter and a predetermined length; It is installed in a state joined to the steel pipe 11 so as to have a predetermined width in the horizontal direction somewhat below the apex of the steel pipe 11 between the outer surfaces of the pair of spaced steel pipes 11 and have a length equal to the length of the steel pipe 11. A steel pipe parallel coupling flange (17); Between the outer surfaces of the pair of spaced steel pipes 11, a steel pipe 11 is joined to a predetermined width in the horizontal direction slightly above the low point of the steel pipe 11 and has the same length in the longitudinal direction as the steel pipe 11. A steel pipe parallel coupling flange (17) installed in a state; On the right side of the outer surface of the right steel pipe 11 and on the left side of the outer surface of the left steel pipe 11, each has a predetermined width in the horizontal direction somewhat below the apex of the steel pipe 11 and a length equal to the length of the steel pipe 11. An end binding flange (13) installed at one end to be joined to the steel pipe (11) and at the other end to be fastened in the form of a typical U-shaped hook; On the right side of the outer surface of the right steel pipe 11 and on the left side of the outer surface of the left steel pipe 11, each has a predetermined width in the horizontal direction slightly above the low point of the steel pipe 11 and a length equal to the length of the steel pipe 11. An end binding flange (13) installed at one end to be joined to the steel pipe (11) and at the other end to be fastened in the form of a typical U-shaped hook; It relates to an upper ground settlement reduction type loop steel pipe (15), characterized in that it is replaced with .

여기서, 상기 강관 병렬 결합형 플랜지(17)는 통상적인 강판으로서 상기 강관(11)과의 접합은 통상적인 용접을 사용함이 경제적이고 바람직하다.Here, the steel pipe parallel coupling flange 17 is a conventional steel plate, and it is economical and desirable to join it with the steel pipe 11 using conventional welding.

한편, 상기 제1실시예와 제2실시예 중의 어느 하나에 있어서, 도6과 도7에 도시된 바와 같이, 상부와 하부의 강관 병렬 결합형 플랜지(17) 사이 또는 상부와 하부의 단부 결속형 플랜지(13) 사이에 강관(11)의 길이방향으로 소정의 간격마다 소정의 높이의 위치에 강관(11)을 관통하여 소정의 직경을 갖는 보강근 삽입공(19)을 더 포함하여 구성된 것을 특징으로 하는 상부지반 침하 감소형 루프 강관(9, 15)에 관한 것이다.Meanwhile, in any one of the first and second embodiments, as shown in Figures 6 and 7, between the upper and lower steel pipe parallel coupling flanges 17 or the upper and lower end coupling type Characterized in that it further includes a reinforcing bar insertion hole 19 having a predetermined diameter that penetrates the steel pipe 11 at a predetermined height at predetermined intervals in the longitudinal direction of the steel pipe 11 between the flanges 13. It relates to a roof steel pipe (9, 15) with reduced upper ground settlement.

여기서, 상기 보강근 삽입공(19)은 통상적인 강관(11)이나 강판의 레이저 천공 방법을 이용하여 천공함이 바람직하고, 강관(11)의 내부와 상부와 하부의 단부 결속형 플랜지(13) 사이와 상부와 하부의 강관 병렬 결합형 플랜지(17) 사이의 공간에 통상적인 철근을 포함한 보강근(25)을 끼워 넣은 후 그 공간의 내부에 통상적인 굳지 않은 콘크리트를 포함한 채움재(27)를 채워 넣어 양생시켜서 직접 경제적인 본체 구조물로 사용하기 위한 것이다.Here, the reinforcing bar insertion hole 19 is preferably drilled using a laser drilling method of a conventional steel pipe 11 or steel plate, and is located between the inside of the steel pipe 11 and the upper and lower end binding flanges 13. Insert reinforcing bars (25) containing conventional reinforcing bars into the space between the upper and lower steel pipe parallel joint flanges (17), and then fill the space with filler (27) containing conventional unhardened concrete for curing. It is intended to be used directly as an economical main body structure.

또한, 상기 제1실시예와 제2실시예 중의 어느 하나에 있어서, 도8 내지 도9에 도시된 바와 같이, 강관(11)의 길이방향을 기준으로 압입시 전방으로 첫 번째로 설치되는 선도용 강관(11)의 전방으로부터 길이방향으로 다소 이격된 좌측과 우측의 측면부에 각각 직경의 수직방향 중앙부 위치에 소정의 직경을 갖는 원형으로 강관이 천공되는 루프 강관 선도관용 측면공(21)을 더 포함하여 구성된 것을 특징으로 하는 상부지반 침하 감소형 루프 강관(9, 15)에 관한 것이다.In addition, in any one of the first and second embodiments, as shown in Figures 8 and 9, a leading pipe is first installed forward when press-fitting with respect to the longitudinal direction of the steel pipe 11. It further includes side holes 21 for loop steel pipe lead pipes in which the steel pipe is perforated in a circular shape with a predetermined diameter at the central portion in the vertical direction of the diameter, respectively, on the left and right side surfaces slightly spaced apart in the longitudinal direction from the front of the steel pipe 11. It relates to a roof steel pipe (9, 15) with reduced upper ground settlement, characterized in that it is constructed.

여기서, 상기 루프 강관 선도관용 측면공(21)은 통상적인 강관(11)이나 강판의 레이저 천공 방법을 이용하여 천공함이 바람직하다.Here, the side hole 21 for the loop steel pipe conductor is preferably drilled using a laser drilling method of a conventional steel pipe 11 or steel plate.

한편, 상기 제1실시예와 제2실시예 중의 어느 하나에 있어서, 도8 내지 도9에 도시된 바와 같이, 루프 강관 선도관용 측면공(21)의 강관(11) 내측 주위를 둘러싸도록 소정의 폭을 갖는 링 형상의 보강 덧판에 해당되는 측면공 가장자리 보강판(24)을 더 포함하여 구성된 것을 특징으로 하는 상부지반 침하 감소형 루프 강관(9, 15)에 관한 것이다.Meanwhile, in any one of the first and second embodiments, as shown in Figures 8 and 9, a predetermined hole is formed to surround the inside of the steel pipe 11 of the side hole 21 for the loop steel pipe leading pipe. It relates to an upper ground settlement reduction type loop steel pipe (9, 15), characterized in that it further includes a side hole edge reinforcement plate (24) corresponding to a ring-shaped reinforcement plate having a width.

여기서, 상기 측면공 가장자리 보강판(24)은 곡률이 동일한 통상적인 강관(11)을 절단하여 사용하거나, 통상적인 강판의 레이저 천공 겸 절단 방법을 이용하는 것이 바람직하다.Here, it is preferable to use the side hole edge reinforcement plate 24 by cutting a conventional steel pipe 11 with the same curvature, or to use a conventional laser drilling and cutting method of a steel sheet.

또한, 상기 제1실시예와 제2실시예 중의 어느 하나에 있어서, 도8 내지 도9에 도시된 바와 같이, 강관(11)의 길이방향을 기준으로 첫 번째로 설치되는 선도용 강관(11)의 전방부 상부에 다소 돌출되도록 강관(11)의 곡률과 동일하며 소정의 폭과 길이를 갖는 상부 지반 침하 방지판(23)을 더 포함하여 구성된 것을 특징으로 하는 상부지반 침하 감소형 루프 강관(9, 15)에 관한 것이다.In addition, in any one of the first and second embodiments, as shown in Figures 8 and 9, the leading steel pipe 11 is installed first based on the longitudinal direction of the steel pipe 11. The upper ground settlement reduction loop steel pipe (9) is characterized in that it further includes an upper ground settlement prevention plate (23) having the same curvature of the steel pipe (11) and having a predetermined width and length so as to slightly protrude from the upper part of the front part of the steel pipe (9). , 15).

여기서, 상기 상부지반 침하 방지판(23)은 강관(11)과 동일한 곡률을 갖도록 통상적인 강관(11)을 절단하고 용접하여 사용하는 것이 바람직하다.Here, the upper ground subsidence prevention plate 23 is preferably used by cutting and welding a typical steel pipe 11 to have the same curvature as the steel pipe 11.

한편, 도13 내지 도16에 도시된 바와 같이, 통상적인 도로나 철도를 대상으로 얕은 토피의 상태로 지하로 횡단하는 지반 내에 파이프 루프를 시공함에 있어서, 반력 말뚝(47)과 반력벽(33)을 포함하는 통상적인 추진대를 제작하여 설치하는 공정과; 상기 추진대를 제작하여 설치하는 공정 후 상부 지반 침하 감소형 루프 강관(9)의 단부 결속형 플랜지(13)끼리 연속적으로 연결시키면서 압입시켜 1련 ""형 또는 2련 ""형 등으로 파이프 루프(31)를 형성시키고 상부 지반 침하 감소형 루프 강관(9)의 내부와 상부 지반 침하 감소형 루프 강관(9)의 외부와 단부 결속형 플랜지(13) 사이의 구속된 공간 내의 지반(2) 토사를 굴착함과 동시에 상부 지반 침하 감소형 루프 강관(9)을 전방으로 압입시켜 추진하는 공정과; 상기 상부 지반 침하 감소형 루프 강관(9)을 전방으로 압입시켜 추진하는 공정 후 강관(11)의 길이방향을 기준으로 직각방향으로 보강근 삽입공(19)을 통해서 보강근(25)을 설치하는 공정과; 상기 보강근(25)을 설치하는 공정 후 상부 지반 침하 감소형 루프 강관(9)의 내부와 상부 지반 침하 감소형 루프 강관(9)의 외부와 단부 결속형 플랜지(13) 사이의 구속된 공간 내부에 채움재(27)를 채워서 양생시키는 공정과; 상기 채움재(27)를 채워서 양생시키는 공정 후 상부 지반 침하 감소형 루프 강관(9)으로 연속적으로 결속시켜 구성된 파이프 루프(31) 내부의 지반(2) 토사를 굴착하는 공정과; 상기 파이프 루프(31) 내부의 지반(2) 토사를 굴착하는 공정 후 파이프 루프(31) 내측면을 대상으로 통상적인 방수 마감공(51)을 시공하는 공정과; 로 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법에 관한 것이다.Meanwhile, as shown in Figures 13 to 16, when constructing a pipe loop in the ground crossing underground in a shallow top cover for a typical road or railway, the reaction pile 47 and the reaction wall 33 A process of manufacturing and installing a typical propulsion unit including; After the process of manufacturing and installing the propulsion base, the end binding flanges (13) of the upper ground settlement-reducing roof steel pipe (9) are continuously connected to each other and press-fitted to form a series of " "Brother or couplet " A pipe loop (31) is formed using a shape, etc., and a confined space is formed between the inside of the upper ground settlement reduction type loop steel pipe (9) and the outside of the upper ground settlement reduction type loop steel pipe (9) and the end binding flange (13). A process of excavating soil and sand within the ground (2) and simultaneously pushing the upper ground settlement reduction type loop steel pipe (9) forward and pushing it forward; A process of pushing the upper ground settlement reduction type loop steel pipe (9) forward and pushing it forward; A process of installing reinforcing bars 25 through reinforcing bar insertion holes 19 in a direction perpendicular to the longitudinal direction of the steel pipe 11; After the process of installing the reinforcing bars 25, an upper ground settlement reduction loop steel pipe ( A process of curing the inside of 9) and the confined space between the outside of the upper ground settlement-reducing loop steel pipe 9 and the end binding flange 13 with filler 27; filling the filler 27; After the curing process, a process of excavating the ground (2) inside the pipe loop (31) constructed by continuously binding with the upper ground settlement reduction loop steel pipe (9); The ground (2) inside the pipe loop (31) After the process of excavating the soil, a process of constructing a conventional waterproof finishing hole (51) on the inner surface of the pipe loop (31); A pipe loop construction method using an upper ground settlement reduction loop steel pipe, which consists of the following: It's about.

여기서, 상기 반력 말뚝(47)은 도14에 도시된 바와 같이, 통상적인 H빔을 사용하고, 반력벽(33)은 통상적인 성토 재료를 포함하여 콘크리트 재료를 사용하는 것이 바람직하다.Here, as shown in Figure 14, the reaction pile 47 uses a typical H beam, and the reaction wall 33 preferably uses a concrete material including a typical embankment material.

상기 반력벽(33)의 반력은 상부 지반 침하 감소형 루프 강관(9) 압입시의 압입 추력 이상을 지지하도록 계획하여야 하며, 지반(2) 조건과 압입용 상부 지반 침하 감소형 루프 강관(9)의 관경과 연장길이 등에 따라 차이가 있으나, 통상적으로 수 백 톤 정도의 큰 반력을 갖도록 시공되어야 한다.The reaction force of the reaction wall (33) should be planned to support more than the indentation thrust when injecting the upper ground settlement reduction type loop steel pipe (9), and the ground (2) condition and the upper ground settlement reduction type loop steel pipe (9) for indentation. There are differences depending on the pipe diameter and extension length, but usually it must be constructed to have a large reaction force of several hundred tons.

또한, 상기 반력벽(33)을 설치한 후 반력벽(33)의 전방부와 성토 지반(13) 상에 도 14 내지 도 15에 도시된 바와 같이 대차(35) 상에 직진성 압입행정(43)과 복귀 행정(45)을 되풀이 하여 수행하는 피스톤이 장착된 유압실린더(41)로 구성된 통상적인 강관압입장치의 전방부에는 현장 여건에 따라 평형 레일(49)을 설치한다.In addition, after installing the reaction wall 33, a straight pressing stroke 43 is performed on the bogie 35 as shown in FIGS. 14 and 15 on the front part of the reaction wall 33 and the embankment ground 13. A balance rail (49) is installed at the front of a typical steel pipe pressing device consisting of a hydraulic cylinder (41) equipped with a piston that repeats the and return strokes (45) according to field conditions.

여기서, 상기 강관압입장치의 하부에는 통상적인 H빔 골조로 구성된 거치대가 설치되고, 평형 레일(49)은 원 지반(2)을 포함한 성토 지반(2)에 압입될 상부 지반 침하 감소형 루프 강관(9)의 중심 위치를 고려한 높이로 설정하여 고정시키는 것이 바람직하다.Here, a stand composed of a typical H-beam frame is installed at the lower part of the steel pipe press-in device, and the balance rail 49 is an upper ground settlement-reduced loop steel pipe to be press-fitted into the embankment ground 2 including the original ground 2 ( 9) It is desirable to set and fix the center position at a height that takes into account the height.

상기 강관압입장치와 평형 레일(49)을 설치한 후 강관압입장치의 전방부인 평형 레일(49)의 상부에 통상적인 크레인을 사용하여 선도용 상부 지반 침하 감소형 루프 강관(9)을 포함하여 후속용 상부 지반 침하 감소형 루프 강관(9)을 배열시킨다.After installing the steel pipe press-in device and the balance rail (49), a conventional crane is used on the upper part of the balance rail (49), which is the front part of the steel pipe press-in device, and a leading upper ground settlement reduction type loop steel pipe (9) is installed for subsequent operations. Arrange the upper ground settlement-reducing loop steel pipe (9).

또한, 상기 선도용 상부 지반 침하 감소형 루프 강관(9)을 포함하여 후속용 상부 지반 침하 감소형 루프 강관(9)을 배열시킨 후 성토 지반(2)을 관통하여 소정의 길이 단위로 전진시켜 1회차 선도용 상부 지반 침하 감소형 루프 강관(9)을 압입시킨다.In addition, after arranging the following upper ground settlement reduction type loop steel pipes (9), including the leading upper ground settlement reduction type loop steel pipe (9), they are advanced by a predetermined length unit through the embankment ground (2) to form 1 The upper ground settlement reduction loop steel pipe (9) for leading the turn is press-fitted.

여기서, 상기 선도용 상부 지반 침하 감소형 루프 강관(9)은 피스톤을 전진시켜 성토 지반(2)에 압입시키게 되며, 피스톤의 통상적인 행정은 1m이므로 6m짜리 압입용 상부 지반 침하 감소형 루프 강관(9)을 성토 지반(2)에 완전히 압입시키려면 피스톤은 이론상 최소한 6회의 압입 행정(43)을 되풀이해야 하고, 피스톤의 행정이 제한되어 있기 때문에 피스톤의 압입 행정(43)으로는 부족한 5m를 보완해 줄 수 있는 보조밀대(39)를 사용하며, 일종의 관상 블록으로서 길이는 피스톤의 행정과 동일한 1m의 길이로 형성되고, 전방부와 후방부에는 피스톤의 전방부 또는 전·후방부의 보조밀대(39)끼리 연직방향으로 연결시키는데 필요한 통상적인 체결나사가 형성되어 있으며, 압입용 상부 지반 침하 감소형 루프 강관(9) 1본의 경우에는 최소한 작업자 1인이 진입하거나 통상적인 토사 반출장비를 진입하여 강관(11) 내부의 지반(2) 토사를 제거할 작업공간이 확보된 중·대구경관이며, 통상적인 직경은 800~1,500mm 이상이고, 길이는 6m 정도이다.Here, the leading upper ground settlement reduction type loop steel pipe (9) is pressed into the embankment ground (2) by advancing the piston, and since the normal stroke of the piston is 1 m, a 6m upper ground settlement reduction type loop steel pipe for press fit ( In order to completely press-fit 9) into the embankment ground (2), the piston must repeat the press-fit stroke (43) at least 6 times in theory, and since the stroke of the piston is limited, the press-fit stroke (43) of the piston must compensate for the insufficient 5 m. It uses an auxiliary push bar (39), which is a type of tubular block with a length of 1 m, which is the same as the stroke of the piston, and the auxiliary push bar (39) is attached to the front and rear parts of the piston. Typical fastening screws required to connect the two in the vertical direction are formed, and in the case of one upper ground settlement-reducing loop steel pipe (9) for press-in, at least one worker enters or uses normal earth and sand removal equipment to secure the steel pipe ( 11) Internal ground (2) It is a medium-to-large diameter pipe with secured work space to remove soil. The typical diameter is 800~1,500mm or more and the length is about 6m.

상기 1회차 압입용 선도용 상부 지반 침하 감소형 루프 강관(9)을 압입시킨 후 1회차 피스톤을 후진하여 복귀시킨다.After the upper ground settlement reduction type loop steel pipe (9) for the first press-fit is press-fitted, the first-round piston is moved backward and returned.

또한, 상기 1회차 피스톤을 후진하여 복귀시킨 후 피스톤의 전방부에 보조밀대(39)를 삽입한 상태에서 그 후방부를 피스톤의 전방부에 체결시킨다.In addition, after the first piston is moved backward and returned, the auxiliary pusher 39 is inserted into the front part of the piston and the rear part is fastened to the front part of the piston.

상기 피스톤의 전방부에 보조밀대(39)를 삽입한 상태에서 그 후방부를 피스톤의 전방부에 체결시킨 후 피스톤을 재차 소정의 길이 단위로 전진시켜 2회차 압입용 상부 지반 침하 감소형 루프 강관(9)을 압입시킨다.With the auxiliary push bar (39) inserted into the front part of the piston, the rear part of the piston is fastened to the front part of the piston, and then the piston is advanced again by a predetermined length unit to form an upper ground settlement reduction loop steel pipe (9) for the second press fit. ) is press-fitted.

여기서, 상기 보조밀대(39)의 1개 당 길이는 압입용 상부 지반 침하 감소형 루프 강관(9)을 1m씩 전진 압입시킬 경우를 예를 들면, 1m 규격 제품, 2m 규격 제품, 3m 규격 제품 등으로 구분하여 조합시켜 사용하면 특정 규격 제품만을 일률적으로 사용하는 것에 비해서 효율적이고 바람직하다.Here, the length per piece of the auxiliary push bar 39 is, for example, 1m standard product, 2m standard product, 3m standard product, etc. when pressing the upper ground settlement reduction loop steel pipe 9 for press-fitting forward by 1m. Using them separately and in combination is more efficient and preferable than uniformly using only specific standard products.

한편, 상기 피스톤을 재차 소정의 길이 단위로 전진시켜 2회차 압입용 상부 지반 침하 감소형 루프 강관(9)을 압입시킨 후 2회차 피스톤의 압입력을 제거하는 후진력 상태로 후진하여 복귀시킨다.Meanwhile, the piston is advanced again in predetermined length units to press-fit the upper ground settlement-reducing loop steel pipe 9 for the second press-in, and then returns to a backward force state to remove the press-in force of the second-round piston.

또한, 상기 2회차 피스톤을 후진하여 복귀시킨 후 3회차부터는 반복해서 피스톤을 전진 및 후진시키면서 통상적으로 6m짜리 압입용 상부 지반 침하 감소형 루프 강관(9)의 압입을 종료한다.In addition, after the piston is moved backwards and returned in the second round, the piston is repeatedly moved forward and backward from the third round to complete the press-fitting of the 6 m upper ground settlement reduction loop steel pipe 9 for press-fitting.

한편, 상기 압입용 상부 지반 침하 감소형 루프 강관(9)의 압입을 종료한 후 압입된 상부 지반 침하 감소형 루프 강관(9) 내의 지반(2) 토사를 외부로 제거한다.Meanwhile, after the press-fitting of the upper ground settlement reduction type loop steel pipe 9 is completed, the ground 2 soil within the press-fitted upper ground settlement reduction type loop steel pipe 9 is removed to the outside.

여기서, 상기 압입된 상부 지반 침하 감소형 루프 강관(9) 내의 지반(2) 토사 제거작업은 통상적인 인력 또는 통상적인 토사 반출장비를 사용하여 반출한다.Here, the work of removing soil from the ground (2) within the press-fitted upper ground settlement reduction loop steel pipe (9) is carried out using normal manpower or normal soil removal equipment.

또한, 상기 압입용 상부 지반 침하 감소형 루프 강관(9) 내의 지반(2) 토사를 외부로 반출한 후 1회차 압입용 상부 지반 침하 감소형 루프 강관(9, 15)의 후방부에 맞대어 또 다른 2회차 압입용 상부 지반 침하 감소형 루프 강관(9)을 용접하여 연결시킨다.In addition, after carrying out the soil (2) of the ground (2) in the upper ground settlement reduction type loop steel pipe (9) for the first press fit, another upper ground settlement reduction type loop steel pipe (9, 15) is butted against the rear part of the first press fit. The upper ground settlement reduction loop steel pipe (9) for the second press fit is welded and connected.

한편, 상기 1회차 압입용 상부 지반 침하 감소형 루프 강관(9)의 후방부에 맞대어 또 다른 2회차 압입용 상부 지반 침하 감소형 루프 강관(9)을 용접하여 연결시킨 후 3회차 이후부터는 1, 2회차와 동일하게 반복하여 전체적인 상부 지반 침하 감소형 루프 강관(9) 압입 시공을 실시한다.On the other hand, after welding and connecting another upper ground settlement reduction type roof steel pipe (9) for the second press fit against the rear part of the upper ground settlement reduction type loop steel pipe (9) for the first press fit, from the third time onwards, 1, Repeat as in the second round to press-fit the entire upper ground subsidence-reducing loop steel pipe (9).

상기 3회차 이후부터는 1, 2회차와 동일하게 반복하여 전체적인 상부 지반 침하 감소형 루프 강관(9) 압입 시공을 실시한다.From the 3rd time onwards, the same process as the 1st and 2nd times is repeated to perform press-fitting construction of the overall upper ground settlement-reducing loop steel pipe (9).

또한, 상기 추진대를 제작 설치하는 공정 후 상부 지반 침하 감소형 루프 강관(9)의 단부 결속형 플랜지(13)끼리 연속적으로 연결시키면서 압입시켜 파이프 루프(31)를 형성시키고 상부 지반 침하 감소형 루프 강관(9)의 내부와 상부 지반 침하 감소형 루프 강관(9)의 외부와 단부 결속형 플랜지(13) 사이의 구속된 공간 내의 지반(2) 토사를 굴착함과 동시에 상부 지반 침하 감소형 루프 강관(9)을 전방으로 압입시켜 추진하는 공정과; 를 상부 지반 침하 감소형 루프 강관(15)의 단부 결속형 플랜지(13)끼리 연속적으로 연결시키면서 압입시켜 파이프 루프(31)를 형성시키고 상부 지반 침하 감소형 루프 강관(15)의 내부와 상부 지반 침하 감소형 루프 강관(15)의 외부와 상·하부 강관 병렬 결합형 플랜지(17) 및 상·하부 단부 결속형 플랜지(13) 사이의 구속된 공간 내의 지반(2) 토사를 굴착함과 동시에 상부 지반 침하 감소형 루프 강관(15)을 전방으로 압입시켜 추진하는 공정과; 로 치환되는 것을 특징으로 하는 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법에 관한 것이다.In addition, after the process of manufacturing and installing the propulsion base, the end binding flanges 13 of the upper ground settlement reduction type loop steel pipe 9 are continuously connected and press-fitted to form a pipe loop 31, and the upper ground settlement reduction type loop is formed. While excavating the soil (2) in the confined space between the inside of the steel pipe (9) and the outside of the upper ground settlement-reducing loop steel pipe (9) and the end binding flange (13), the upper ground settlement-reducing loop steel pipe A process of pushing and pushing (9) forward; The end binding flanges 13 of the upper ground settlement reduction loop steel pipe 15 are continuously connected and press-fitted to form a pipe loop 31, and the interior and upper ground settlement of the upper ground settlement reduction loop steel pipe 15 is formed. The ground (2) within the confined space between the outside of the reduced loop steel pipe (15) and the upper and lower steel pipe parallel coupling flanges (17) and the upper and lower end coupling flanges (13) is excavated and the upper ground at the same time. A process of pushing and pushing the sinkage-reducing loop steel pipe (15) forward; It relates to a pipe loop construction method using an upper ground settlement-reducing roof steel pipe, characterized in that it is replaced by .

여기서, 상기 상부 지반 침하 감소형 루프 강관(15)의 외부와 단부 결속형 플랜지(13) 사이의 구속된 공간 내의 지반(2) 토사를 굴착하는 경우와 상부 지반 침하 감소형 루프 강관(15)의 외부와 상·하부 강관 병렬 결합형 플랜지(17) 및 상·하부 단부 결속형 플랜지(13) 사이의 구속된 공간 내의 지반(2) 토사를 굴착하는 경우에는 공통적으로 강관(11)의 측면에 설치된 루프 강관 선도관용 측면공(21)을 통해서 통상적인 지반(2) 토사 굴착장치나 인력으로 굴착하는 것이 바람직하다.Here, in the case of excavating the soil (2) in the confined space between the outside of the upper ground settlement reduction type loop steel pipe 15 and the end binding flange 13 and the upper ground settlement reduction type loop steel pipe 15 When excavating the ground (2) soil within the constrained space between the outside and the upper and lower steel pipe parallel combination type flange (17) and the upper and lower end connection type flange (13), it is commonly installed on the side of the steel pipe (11). It is desirable to excavate through the side hole (21) for the loop steel pipe lead pipe using a conventional ground (2) soil excavator or manpower.

한편, 상기 파이프 루프(31) 내측면을 대상으로 방수 마감공(51)을 시공하는 공정 후 방수 마감공(51)의 내부에 본체 구조물(53)을 더 포함하여 설치하도록 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법에 관한 것이다.On the other hand, after the process of constructing the waterproof finishing hole 51 on the inner surface of the pipe loop 31, the upper part is configured to further include and install a main body structure 53 inside the waterproof finishing hole 51. This relates to a pipe loop construction method using ground settlement-reducing loop steel pipe.

여기서, 상기 방수 마감공(51)이나 본체 구조물(53)은 통상적인 것이고, 본체 구조물(53)은 통상적인 철근 콘크리트 구조물로서 파이프 루프(31) 내측면에 합벽으로 시공함이 바람직하다.Here, the waterproof finishing hole 51 or the main body structure 53 is a typical structure, and the main structure 53 is a typical reinforced concrete structure and is preferably constructed as a composite wall on the inner side of the pipe loop 31.

또한, 도12에 도시된 바와 같이, 상기 보강근(25)을 설치하는 공정 이후에 상부 지반 침하 감소형 루프 강관(9, 15)의 하부에 초생달형 거푸집(29)을 더 포함하여 설치하는 공정과; 상기 채움재(27)를 채워서 양생시키는 공정 후 채움재(27)의 하부를 대상으로 하부 단부 결속형 플랜지(13)의 높이 이하 또는 하부 강관 병렬 결합형 플랜지(17)의 높이 이하에 해당되는 높이 정도의 상부 지반 침하 감소형 루프 강관(9, 15)의 하부를 초생달형 거푸집(29)을 포함하여 절단하여 제거시키는 공정과; 를 더 포함하여 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법에 관한 것이다.In addition, as shown in Figure 12, after the process of installing the reinforcing bars 25, a process of installing a crescent-shaped formwork 29 at the lower part of the upper ground settlement reduction loop steel pipes 9 and 15; ; After the process of filling and curing the filler 27, a height corresponding to the lower part of the filler 27 is lower than the height of the lower end binding flange 13 or lower than the height of the lower steel pipe parallel coupling flange 17. A process of cutting and removing the lower part of the upper ground settlement reduction loop steel pipe (9, 15), including the crescent-shaped formwork (29); It relates to a pipe loop construction method using an upper ground settlement-reducing roof steel pipe, characterized in that it further includes.

여기서, 상기 초생달형 거푸집(29)은 통상적인 목재나 합판이나 합성 거푸집으로 구성되며, 통상적인 전동 또는 수동 컷터를 사용하여 상부 지반 침하 감소형 루프 강관(9, 15)의 하부를 초생달형 거푸집(29)을 포함하여 절단하는 것이 바람직하다.Here, the crescent-shaped formwork (29) is composed of conventional wood, plywood, or synthetic formwork, and the lower part of the upper ground settlement reduction loop steel pipe (9, 15) is cut into the crescent-shaped formwork ( 29) It is desirable to cut it including.

본 발명은 이상에서 살펴본 바와 같이 바람직한 실시 예를 들어 도시하고 설명하였으나, 상기한 실시 예에 한정되지 아니하며 본 발명의 정신을 벗어나지 않는 범위 내에서 당해 발명이 속하는 기술분야에서 통상의 지식을 가진 자에 의해 본 발명의 기술사상과 아래에 기재될 특허청구범위의 균등범위 내에서 다양한 수정 및 변형이 가능함은 물론이다.Although the present invention has been illustrated and described with preferred embodiments as discussed above, it is not limited to the above-described embodiments and is intended to be used by those skilled in the art without departing from the spirit of the invention. Of course, various modifications and variations are possible within the scope of equivalence of the technical idea of the present invention and the scope of the patent claims described below.

1 : 종래 공법용 강관 2 : 지반
2' : 함몰부 7 : 플랜지
7' : 변형 플랜지
9 : 상부 지반 침하 감소형 루프 강관(제1실시예)
11 : 강관 13 : 단부 결속형 플랜지
15 : 상부 지반 침하 감소형 루프 강관(제2실시예)
17 : 강관 병렬 결합형 플랜지 19 : 보강근 삽입공
21 : 루프 강관 선도관용 측면공 23 : 상부 지반 침하 방지판
24 : 측면공 가장자리 보강판 25 : 보강근
27 : 채움재 29 : 초생달형 거푸집
31 : 파이프 루프 33 : 반력벽
35 : 대차 39 : 보조 밀대
41 : 유압실린더 43 : 압입 행정
45 : 복귀 행정 47 : 반력 말뚝
49 : 평형 레일 51 : 방수 마감공
53 : 본체 구조물
1: Steel pipe for conventional construction methods 2: Ground
2': depression 7: flange
7': modified flange
9: Upper ground settlement reduction loop steel pipe (first embodiment)
11: Steel pipe 13: End binding flange
15: Upper ground settlement reduction loop steel pipe (second embodiment)
17: Steel pipe parallel combination flange 19: Reinforcing bar insertion hole
21: Side hole for loop steel pipe lead pipe 23: Upper ground settlement prevention plate
24: Side hole edge reinforcement plate 25: Reinforcement bar
27: Filler 29: Crescent-shaped mold
31: pipe loop 33: reaction wall
35: Bogie 39: Auxiliary pusher
41: Hydraulic cylinder 43: Pressing stroke
45: return stroke 47: reaction pile
49: Flat rail 51: Waterproof finish hole
53: main body structure

Claims (10)

파이프 루프용 강관에 있어서,
소정의 직경과 소정의 길이를 갖는 강관과;
상기 강관의 외면 좌측과 우측의 양쪽 측면부의 정점부로부터 다소 하부에 각각 수평방향으로 소정의 폭과 강관의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관에 접합되고 다른 한쪽 끝단부는 U형의 후크 형태로 결속되도록 설치되는 단부 결속형 플랜지와;
상기 강관의 외면 좌측과 우측의 양쪽 측면부의 저점부로부터 다소 상부에 각각 수평방향으로 소정의 폭과 강관의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관에 접합되고 다른 한쪽 끝단부는 U형의 후크 형태로 상기 U형의 후크에 서로 끼워지도록 배열되어 결속되도록 설치되는 단부 결속형 플랜지와;
로 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관.
In the steel pipe for pipe loop,
A steel pipe having a predetermined diameter and a predetermined length;
The outer surface of the steel pipe has a predetermined width and a length equal to the length of the steel pipe in a horizontal direction somewhat below the apex of both left and right sides, and one end is joined to the steel pipe, and the other end is in the form of a U-shaped hook. An end binding flange installed to be connected to;
The steel pipe has a predetermined width and a length equal to the length of the steel pipe in a horizontal direction slightly above the low point on both left and right sides of the outer surface of the steel pipe, and one end is joined to the steel pipe, and the other end is in the form of a U-shaped hook. End binding flanges arranged to fit into the U-shaped hook and installed to be bound to each other;
An upper ground settlement-reducing loop steel pipe, characterized in that it consists of.
제1항에 있어서,
상기 소정의 직경과 소정의 길이를 갖는 강관과;
상기 강관의 외면 좌측과 우측의 양쪽 측면부의 정점부로부터 다소 하부에 각각 수평방향으로 소정의 폭과 강관의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관에 접합되고 다른 한쪽 끝단부는 U형의 후크 형태로 결속되도록 설치되는 단부 결속형 플랜지와;
상기 강관의 외면 좌측과 우측의 양쪽 측면부의 저점부로부터 다소 상부에 각각 수평방향으로 소정의 폭과 강관의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관에 접합되고 다른 한쪽 끝단부는 U형의 후크 형태로 상기 U형의 후크에 서로 끼워지도록 배열되어 결속되도록 설치되는 단부 결속형 플랜지와; 를
수평적으로 다소 이격되어 평행하게 배열되며 소정의 직경과 소정의 길이를 갖는 한 쌍의 강관과;
상기 이격된 한 쌍의 강관 외면 사이에 강관의 정점부로부터 다소 하부에 수평방향으로 소정의 폭에 강관과 길이와 동일한 길이를 갖도록 강관에 접합된 상태로 설치되는 강관 병렬 결합형 플랜지와;
상기 이격된 한 쌍의 강관 외면 사이에 강관의 저점부로부터 다소 상부에 수평방향으로 소정의 폭에 강관과 길이방향으로 동일한 길이를 갖도록 강관에 접합된 상태로 설치되는 강관 병렬 결합형 플랜지와;
상기 우측 강관 외면의 우측과 좌측 강관 외면의 좌측에 각각 강관의 정점부로부터 다소 하부에 수평방향으로 소정의 폭과 강관의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관에 접합되고 다른 한쪽 끝단부는 U형의 후크 형태로 결속되도록 설치되는 단부 결속형 플랜지와;
상기 우측 강관 외면의 우측과 좌측 강관 외면의 좌측에 각각 강관의 저점부로부터 다소 상부에 수평방향으로 소정의 폭과 강관의 길이와 동일한 길이를 갖으면서 한쪽 끝단부는 강관에 접합되고 다른 한쪽 끝단부는 U형의 후크 형태로 결속되도록 설치되는 단부 결속형 플랜지와;
로 치환되는 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관.
According to paragraph 1,
a steel pipe having the predetermined diameter and the predetermined length;
The outer surface of the steel pipe has a predetermined width and a length equal to the length of the steel pipe in a horizontal direction somewhat below the apex of both left and right sides, and one end is joined to the steel pipe, and the other end is in the form of a U-shaped hook. An end binding flange installed to be connected to;
The steel pipe has a predetermined width and a length equal to the length of the steel pipe in a horizontal direction slightly above the low point on both left and right sides of the outer surface of the steel pipe, and one end is joined to the steel pipe, and the other end is in the form of a U-shaped hook. End binding flanges arranged to fit into the U-shaped hook and installed to be bound to each other; cast
a pair of steel pipes arranged in parallel and somewhat spaced apart horizontally and having a predetermined diameter and a predetermined length;
A steel pipe parallel coupling type flange installed between the outer surfaces of the pair of spaced steel pipes in a horizontal direction slightly below the apex of the steel pipe and joined to the steel pipe to have a predetermined width and a length equal to the length of the steel pipe;
a steel pipe parallel coupling type flange installed between the outer surfaces of the pair of spaced steel pipes in a horizontal direction slightly above the low point of the steel pipe and joined to the steel pipe to have a predetermined width and the same length in the longitudinal direction as the steel pipe;
On the right side of the outer surface of the right steel pipe and on the left side of the outer surface of the left steel pipe, each has a predetermined width in the horizontal direction somewhat below the apex of the steel pipe and a length equal to the length of the steel pipe, and one end is joined to the steel pipe, and the other end is U. An end binding flange installed to be connected in the form of a hook;
On the right side of the outer surface of the right steel pipe and on the left side of the outer surface of the left steel pipe, each has a predetermined width in the horizontal direction slightly above the low point of the steel pipe and a length equal to the length of the steel pipe, and one end is joined to the steel pipe and the other end is U. An end binding flange installed to be connected in the form of a hook;
An upper ground settlement-reducing loop steel pipe, characterized in that it is replaced by .
제1항 내지 제2항 중의 어느 하나에 있어서,
상기 상부와 하부의 강관 병렬 결합형 플랜지 사이 또는 상부와 하부의 단부 결속형 플랜지 사이에 강관의 길이방향으로 소정의 간격마다 소정의 높이의 위치에 강관을 관통하여 소정의 직경을 갖는 보강근 삽입공을 더 포함하여 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관.
According to any one of claims 1 and 2,
Between the upper and lower steel pipe parallel coupling flanges or between the upper and lower end coupling flanges, a reinforcing bar insertion hole having a predetermined diameter is formed through the steel pipe at a predetermined height at a predetermined interval in the longitudinal direction of the steel pipe. An upper ground settlement-reducing loop steel pipe, characterized in that it further includes.
제1항 내지 제2항 중의 어느 하나에 있어서,
상기 강관의 길이방향을 기준으로 압입시 전방으로 첫 번째로 설치되는 선도용 강관의 전방으로부터 길이방향으로 다소 이격된 좌측과 우측의 측면부에 각각 직경의 수직방향 중앙부 위치에 소정의 직경을 갖는 원형으로 강관이 천공되는 루프 강관 선도관용 측면공을 더 포함하여 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관.
According to any one of claims 1 and 2,
Based on the longitudinal direction of the steel pipe, a circular shape with a predetermined diameter is formed at the center position in the vertical direction of the diameter on the left and right side sides slightly spaced in the longitudinal direction from the front of the leading steel pipe, which is first installed forward when press-fitting, based on the longitudinal direction of the steel pipe. An upper ground settlement-reducing loop steel pipe, characterized in that it further includes a side hole for the loop steel pipe lead pipe through which the steel pipe is perforated.
제1항 내지 제2항 중의 어느 하나에 있어서,
루프 강관 선도관용 측면공의 강관 내측 주위를 둘러싸도록 소정의 폭을 갖는 링 형상의 보강 덧판에 해당되는 측면공 가장자리 보강판을 더 포함하여 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관.
According to any one of claims 1 and 2,
An upper ground settlement-reducing loop steel pipe, characterized in that it further includes a side hole edge reinforcing plate corresponding to a ring-shaped reinforcing plate having a predetermined width to surround the inner side of the steel pipe of the side hole for the loop steel pipe leading pipe.
제1항 내지 제2항 중의 어느 하나에 있어서,
강관의 길이방향으로 압입 전방으로 첫 번째로 설치되는 선도용 강관의 전방부 상부에 다소 돌출되도록 강관의 곡률과 동일하며 소정의 폭과 길이를 갖는 상부 지반 침하 방지판을 더 포함하여 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관.
According to any one of claims 1 and 2,
It is characterized in that it further includes an upper ground settlement prevention plate having a predetermined width and length and having the same curvature as the steel pipe so as to slightly protrude from the upper part of the front part of the leading steel pipe, which is first installed forward of the steel pipe in the longitudinal direction of the steel pipe. Upper ground settlement-reducing loop steel pipe.
통상적인 도로나 철도를 대상으로 얕은 토피의 상태로 지하로 횡단하는 지반 내에 파이프 루프를 시공함에 있어서,
반력 말뚝과 반력벽을 포함하는 통상적인 추진대를 제작하여 설치하는 공정과;
상기 추진대를 제작하여 설치하는 공정 후 상부 지반 침하 감소형 루프 강관의 단부 결속형 플랜지끼리 연속적으로 연결시키면서 압입시켜 파이프 루프를 형성시키고 상부 지반 침하 감소형 루프 강관의 내부와 상부 지반 침하 감소형 루프 강관의 외부와 단부 결속형 플랜지 사이의 구속된 공간 내의 지반 토사를 굴착함과 동시에 상부 지반 침하 감소형 루프 강관을 전방으로 압입시켜 추진하는 공정과;
상기 상부 지반 침하 감소형 루프 강관을 전방으로 압입시켜 추진하는 공정 후 강관의 길이방향을 기준으로 직각방향으로 보강근 삽입공을 통해서 보강근을 설치하는 공정과;
상기 보강근을 설치하는 공정 후 상부 지반 침하 감소형 루프 강관의 내부와 상부 지반 침하 감소형 루프 강관의 외부와 단부 결속형 플랜지 사이의 구속된 공간 내부에 채움재를 채워서 양생시키는 공정과;
상기 채움재를 채워서 양생시키는 공정 후 상부 지반 침하 감소형 루프 강관으로 연속적으로 결속시켜 구성된 파이프 루프 내부의 지반 토사를 굴착하는 공정과;
상기 파이프 루프 내부의 지반 토사를 굴착하는 공정 후 파이프 루프 내측면을 대상으로 방수 마감공을 시공하는 공정과;
로 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법.
In constructing a pipe loop in the ground crossing underground in a shallow top cover for a typical road or railroad,
A process of manufacturing and installing a conventional propulsion table including a reaction pile and a reaction wall;
After the process of manufacturing and installing the propulsion base, a pipe loop is formed by continuously connecting the end flanges of the upper ground settlement reduction loop steel pipe and press-fitting them, and forming a pipe loop inside the upper ground settlement reduction loop steel pipe and the upper ground settlement reduction loop. A process of excavating ground soil in the confined space between the outside of the steel pipe and the end binding flange and simultaneously pushing the upper ground settlement-reducing loop steel pipe forward and pushing it forward;
After the process of press-fitting and propelling the upper ground settlement-reducing roof steel pipe forward, a process of installing reinforcing bars through reinforcing bar insertion holes in a direction perpendicular to the longitudinal direction of the steel pipe;
After the step of installing the reinforcing bars, a process of curing the inside of the upper ground settlement reduction type loop steel pipe and the inside of the confined space between the outside of the upper ground settlement reduction type loop steel pipe and the end binding flange with filler;
After the process of filling and curing the filler, a process of excavating the soil and soil inside the pipe loop formed by continuously binding the upper ground settlement reduction loop steel pipe;
A process of constructing a waterproof finishing hole on the inner surface of the pipe loop after excavating the ground soil inside the pipe loop;
A pipe loop construction method using an upper ground settlement-reducing loop steel pipe, characterized in that it consists of.
제7항에 있어서,
상기 추진대를 제작 설치하는 공정 후 상부 지반 침하 감소형 루프 강관의 단부 결속형 플랜지끼리 연속적으로 연결시키면서 압입시켜 파이프 루프를 형성시키고 상부 지반 침하 감소형 루프 강관의 내부와 상부 지반 침하 감소형 루프 강관의 외부와 단부 결속형 플랜지 사이의 구속된 공간 내의 지반 토사를 굴착함과 동시에 상부 지반 침하 감소형 루프 강관을 전방으로 압입시켜 추진하는 공정과; 를
상부 지반 침하 감소형 루프 강관의 단부 결속형 플랜지끼리 연속적으로 연결시키면서 압입시켜 파이프 루프를 형성시키고 상부 지반 침하 감소형 루프 강관의 내부와 상부 지반 침하 감소형 루프 강관의 외부와 상·하부 강관 병렬 결합형 플랜지 및 상·하부 단부 결속형 플랜지 사이의 구속된 공간 내의 지반 토사를 굴착함과 동시에 상부 지반 침하 감소형 루프 강관을 전방으로 압입시켜 추진하는 공정과;
로 치환되는 것을 특징으로 하는 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법.
In clause 7,
After the process of manufacturing and installing the propulsion base, the end binding flanges of the upper ground settlement reduction type loop steel pipe are continuously connected and press-fitted to form a pipe loop, and the inside of the upper ground settlement reduction type loop steel pipe and the upper ground settlement reduction type loop steel pipe are formed. A process of excavating ground soil within the confined space between the outside of the and the end binding flanges and simultaneously pushing the upper ground settlement-reducing loop steel pipe forward and pushing it forward; cast
The ends of the upper subsidence-reducing loop steel pipe are connected to each other continuously to form a pipe loop by press-fitting the flanges, and the inside of the upper subsidence-reducing loop steel pipe and the outside of the upper subsidence-reducing loop steel pipe are combined in parallel with the upper and lower steel pipes. A process of excavating ground soil in the confined space between the mold flange and the upper and lower end binding flanges and simultaneously pushing and pushing the upper ground settlement reduction type loop steel pipe forward;
A pipe loop construction method using an upper ground settlement-reducing roof steel pipe, characterized in that it is replaced by .
제7항 내지 제8항 중의 어느 하나에 있어서,
상기 파이프 루프 내측면을 대상으로 방수 마감공을 시공하는 공정 후 방수 마감공의 내부에 본체 구조물을 더 포함하여 설치하도록 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법.
According to any one of claims 7 to 8,
A pipe loop construction method using an upper ground settlement reduction roof steel pipe, characterized in that a main body structure is further included and installed inside the waterproof finishing hole after the process of constructing a waterproof finishing hole targeting the inner surface of the pipe loop.
제7항 내지 제8항 중의 어느 하나에 있어서,
상기 보강근을 설치하는 공정 이후에 상부 지반 침하 감소형 루프 강관의 하부에 초생달형 거푸집을 더 포함하여 설치하는 공정과;
상기 채움재를 채워서 양생시키는 공정 후 채움재의 하부를 대상으로 하부 단부 결속형 플랜지의 높이 이하 또는 하부 강관 병렬 결합형 플랜지의 높이 이하에 해당되는 높이 정도의 상부 지반 침하 감소형 루프 강관의 하부를 초생달형 거푸집을 포함하여 절단하여 제거시키는 공정과; 를
더 포함하여 구성된 것을 특징으로 하는 상부 지반 침하 감소형 루프 강관을 이용한 파이프 루프 시공 공법.
According to any one of claims 7 to 8,
A process of installing a crescent-shaped form further included in the lower part of the upper ground settlement reduction loop steel pipe after the process of installing the reinforcing bar;
After the process of filling and curing the filler, the lower part of the upper ground settlement reduction type loop steel pipe with a height corresponding to less than the height of the lower end binding type flange or less than the height of the lower steel pipe parallel combination type flange is shaped like a crescent moon. A process of cutting and removing, including the formwork; cast
A pipe loop construction method using an upper ground settlement-reducing loop steel pipe, characterized in that it further includes.
KR1020220078690A 2022-06-28 2022-06-28 Upper ground settlement-reducing loop steel pipe and pipe loop construction method using the same KR20240001867A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020220078690A KR20240001867A (en) 2022-06-28 2022-06-28 Upper ground settlement-reducing loop steel pipe and pipe loop construction method using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020220078690A KR20240001867A (en) 2022-06-28 2022-06-28 Upper ground settlement-reducing loop steel pipe and pipe loop construction method using the same

Publications (1)

Publication Number Publication Date
KR20240001867A true KR20240001867A (en) 2024-01-04

Family

ID=89543838

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020220078690A KR20240001867A (en) 2022-06-28 2022-06-28 Upper ground settlement-reducing loop steel pipe and pipe loop construction method using the same

Country Status (1)

Country Link
KR (1) KR20240001867A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101616505B1 (en) 2015-07-27 2016-04-29 원화코퍼레이션(주) Side wall structure using retaining member and sub-concrete structure construction method therewith

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101616505B1 (en) 2015-07-27 2016-04-29 원화코퍼레이션(주) Side wall structure using retaining member and sub-concrete structure construction method therewith

Similar Documents

Publication Publication Date Title
KR101324173B1 (en) Construction method for underground tunnel using guiding shape steel
KR101582173B1 (en) The structure assembly for building a tunnel and building method thereof
KR100968048B1 (en) A retaining panel structure and construction method
KR101258807B1 (en) Tunnel installation method and tunnel installation structure of crossing railroad
CN113294166B (en) Oblique starting method for large-section rectangular jacking pipe
KR200415268Y1 (en) Tubular arch tunnel for underground tunnelling
CN104847380A (en) Tunnel lining structure internal force reducing structure and construction method thereof
CN106014446A (en) Strengthening method for improving stability of high-ground-stress soft rock tunnel inverted arch structure
KR20090114863A (en) Parallelly connected iron tube and construction method for underground structure using the same
KR100712593B1 (en) Construction method of pipe roof structures
KR100805189B1 (en) Construction method of underground structure characterized by going side by side wall construction and excavation
CN215057406U (en) Extension structure is originated in rectangle push pipe slant
KR101479267B1 (en) Method for constructing tunnel by using pipe
KR100815568B1 (en) The tunel execution method and the using fabric
KR101255515B1 (en) The tunel execution method
JP2006214269A (en) Erected girder
KR100784201B1 (en) Method for construction of tunnel
CN110230238B (en) Railway line protection device and protection method
CN108930544A (en) A kind of broken ground underground large space method of construction
KR20240001867A (en) Upper ground settlement-reducing loop steel pipe and pipe loop construction method using the same
JP2003193495A (en) Underground structure constructing method
JP4136959B2 (en) "How to build underground structures and installation girder"
KR101022383B1 (en) Octopus tubular roof method
CN210561510U (en) Railway line protection device
KR20200024679A (en) Apparatus and method for constructing non-open cut structure