KR20200114553A - Underground structure with top-down construction method using underground column wall and construction method therefor - Google Patents

Underground structure with top-down construction method using underground column wall and construction method therefor Download PDF

Info

Publication number
KR20200114553A
KR20200114553A KR1020190036501A KR20190036501A KR20200114553A KR 20200114553 A KR20200114553 A KR 20200114553A KR 1020190036501 A KR1020190036501 A KR 1020190036501A KR 20190036501 A KR20190036501 A KR 20190036501A KR 20200114553 A KR20200114553 A KR 20200114553A
Authority
KR
South Korea
Prior art keywords
steel
steel pipe
main column
wall
plate
Prior art date
Application number
KR1020190036501A
Other languages
Korean (ko)
Other versions
KR102210345B1 (en
Inventor
유병훈
Original Assignee
유병훈
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 유병훈 filed Critical 유병훈
Priority to KR1020190036501A priority Critical patent/KR102210345B1/en
Publication of KR20200114553A publication Critical patent/KR20200114553A/en
Application granted granted Critical
Publication of KR102210345B1 publication Critical patent/KR102210345B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/14Sealing joints between adjacent sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

Disclosed are an underground structure manufactured in a top-town method using a column type wall and a construction method thereof, which can construct the column type wall sufficiently securing water-proof performance even when steel pipes are constructed to be spaced apart from each other by using a steel water-stop plate, construct an upper plate structure, both wall structures, and a lower plate structure in the top-down method after excavating the inside of both column type walls, and construct the box-shaped underground structure.

Description

주열식벽체를 이용하여 탑다운 방식으로 제작된 지중구조물 및 그 시공방법{UNDERGROUND STRUCTURE WITH TOP-DOWN CONSTRUCTION METHOD USING UNDERGROUND COLUMN WALL AND CONSTRUCTION METHOD THEREFOR}An underground structure manufactured in a top-down method using a main heat type wall and its construction method {UNDERGROUND STRUCTURE WITH TOP-DOWN CONSTRUCTION METHOD USING UNDERGROUND COLUMN WALL AND CONSTRUCTION METHOD THEREFOR}

본 발명은 주열식벽체를 이용하여 탑다운 방식으로 제작된 지중구조물 및 그 시공방법에 관한 것이다. 더욱 구체적으로 강재지수판을 이용하여 강관을 이격시켜 시공함에도 차수성능을 충분히 확보할 수 있는 주열식벽체를 시공하고, 양 주열식벽체 내측을 굴착한 후, 상판구조물, 양 벽체구조물과 하판구조물을 탑다운 방식으로 시공하여 박스체 형태의 지중구조물을 시공하는 주열식벽체를 이용하여 탑다운 방식으로 제작된 지중구조물 및 그 시공방법에 관한 것이다.The present invention relates to an underground structure manufactured in a top-down manner using a main heat type wall and a construction method thereof. More specifically, construct a main column wall that can sufficiently secure water-repelling performance even when the steel pipes are spaced apart using a steel index plate, and after excavating the inside of both main column walls, the upper plate structure, both wall structures and the lower plate structure are topped. The present invention relates to an underground structure manufactured in a top-down manner using a main column wall that constructs a box-shaped underground structure by using a down method and a construction method thereof.

도 1a는 종래 주열식벽체의 시공도이다.Figure 1a is a construction view of a conventional main heating wall.

즉, 지반을 트렌치 굴착하여 형성된 굴착공간에 강관파일의 측면이 서로 겹쳐지도록 하여 연결 시공하고, 내부에는 철근조립체 또는 철골부재를 삽입한 후, 콘크리트를 강관파일 내부에 충진시키고 있음을 알 수 있다.That is, it can be seen that the side surfaces of the steel pipe piles overlap each other to be connected to the excavation space formed by trench excavation of the ground, and after inserting a reinforcing bar assembly or a steel frame member inside, concrete is filled inside the steel pipe pile.

이에 강관과 강관이 서로 겹쳐져 시공되기 때문에 차수성능을 충분히 확보할 수 있는 반면, 강관을 가공해야 하고, 겹쳐지는 부위가 많아져 다수의 강관을 연결시공함에 있어 겹쳐지는 부위만큼 강관손실이 있을 수 밖에 없어 경제성이 저하 될 수 밖에 없다는 한계가 있게 된다.Therefore, since steel pipes and steel pipes are overlapped with each other, the ordering performance can be sufficiently secured, while steel pipes have to be processed, and there are many overlapping areas, so there will be a loss of steel pipes as much as the overlapping parts when connecting multiple steel pipes. There is a limit that economic feasibility is inevitably lowered.

도 1b는 종래 다른 주열식벽체의 시공도이다.Figure 1b is a construction diagram of another conventional main heating wall.

즉, 강관(10)을 서로 겹쳐지도록 시공하지 않고 강관을 서로 이격 시공하되, 강관 외주면에 연결강재(20)를 추가로 형성시키고 상기 연결강재가 서로 맞물리도록 하여 강관을 서로 이격 시공함에 있어서도 서로 연결될 수 있도록 한 것이다.That is, the steel pipes 10 are not constructed so as to overlap each other, but the steel pipes are spaced apart from each other, but a connecting steel 20 is additionally formed on the outer circumferential surface of the steel pipes, and the connecting steels are meshed with each other so that the steel pipes will be connected to each other in spaced construction I made it possible.

이러한 방식은 도 1a와 달리 강관을 겹쳐서 시공하지 않기 때문에 강관 설치개수를 줄일 수 있어 경제적인 반면 연결강재(20)가 설치되는 부위의 차수성능을 어떻게 확보하느냐 중요하게 된다.Unlike FIG. 1A, this method is economical because it is possible to reduce the number of steel pipes installed because the steel pipes are not overlapped, and how to secure the order performance of the part where the connecting steel 20 is installed becomes important.

이에 도 1b와 같이 강관과 강관은 연결에 용이하도록 다양한 형태의 연결강재(20)를 이용하고 있음을 알 수 있는데, 연결강재가 서로 연결되는 부위(연결부위)는 차수성능 확보를 위해 충진재를 마감재(C)로 사용하고 있음을 알 수 있다.Accordingly, as shown in FIG. 1B, it can be seen that the steel pipe and the steel pipe are using various types of connecting steel 20 to facilitate connection, and the part (connection part) where the connecting steel is connected to each other is finished with a filler to secure water-repellent performance. It can be seen that it is used as (C).

이로서 종래 주열식 벽체는 강관을 서로 이격되도록 지반에 시공하되 연결강재와 충진재를 이용하여 주열식벽체를 시공함으로서 차수성능을 확보하고 있음을 알 수 있으나 시공품질이 확보되지 않으면 차수성능 확보가 어렵다는 문제점이 있었다.As a result, it can be seen that the conventional main-heated wall is constructed on the ground so that the steel pipes are spaced apart from each other, but the water-repelling performance is secured by constructing the main-heated wall using connecting steel and fillers, but it is difficult to secure water-repellent performance unless the construction quality is secured. There was this.

대한민국 공개특허 제 10-1662091호(발명의 명칭: 내부차수재를 이용하여 제작된 차수벽체 및 이를 이용한 구조물 시공방법, 공개일자: 2016년10월05일)Republic of Korea Patent Laid-Open Patent No. 10-1662091 (Name of the invention: a barrier wall manufactured using an inner barrier material and a structure construction method using the same, publication date: October 5, 2016) 대한민국 공개특허 제 10-2015-0051101호(발명의 명칭: 차수벽용 강관, 공개일자: 2015년05월11일)Republic of Korea Patent Publication No. 10-2015-0051101 (Name of the invention: steel pipe for the water wall, publication date: May 11, 2015)

이에 본 발명은 강관을 서로 이격시켜 시공함에도 차수성능을 충분히 확보할 수 있는 주열식벽체를 먼저 시공하고, 탑다운 방식으로 박스체 형태의 지중구조물을 주열식벽체 내측에 신속하게 시공할 수 있는 강재지수판을 이용하여 제작된 지중벽체 및 이를 이용한 지중구조물 시공방법 제공을 해결하고자 하는 기술적 과제로 한다.Accordingly, the present invention is a steel material that can be constructed by first constructing a main heat-type wall that can sufficiently secure water-repelling performance even when the steel pipes are spaced apart from each other, and then quickly construct a box-type underground structure inside the main heat-type wall in a top-down method. It is a technical task to solve the provision of an underground wall manufactured using a water-stop plate and an underground structure construction method using the same.

상기 과제를 달성하기 위한 본 발명의 주열식벽체를 이용하여 제작된 지중굳조물 및 이를 이용한 탑다운 방식의 지중구조물 시공방법은 종방향으로 강관을 가이드관을 이용하여 연결 설치하여 형성된 양 주열식벽체; 및 상기 양 주열식벽체 사이 지표면으로부터 지반을 굴착하여 형성시킨 공간을 이용하여 양 주열식벽체 사이에 거치된 프리캐스트 상판에 상판콘크리트를 타설하여 양 주열식벽체에 일체화되도록 형성된 상판구조물; 상기 상판구조물 하부를 굴착하여 양 주열식벽체 사이에 형성된 하판구조물;와 상판구조물과 하판구조물 사이의 노출된 양 주열식벽체에 형성된 측벽콘크리트에 의하여 형성된 양 측벽체;를 포함하는 지중구조물;을 포함하게 된다.In order to achieve the above task, an underground hardened material manufactured using the main column wall of the present invention and a top-down type underground structure construction method using the same are both column type walls formed by connecting and installing steel pipes in a longitudinal direction using a guide tube. ; And a top plate structure formed to be integrated with both main column walls by pouring top plate concrete on the precast top plate mounted between the two main column walls using a space formed by excavating the ground from the ground surface between the two main column walls. Including; a lower plate structure formed between the two main column walls by excavating the lower part of the upper plate structure; and both side walls formed by side wall concrete formed on both exposed main column walls between the upper plate structure and the lower plate structure; and an underground structure including; Is done.

발명의 주열식벽체는 강재지수판을 이용하여 강관 사이의 차수성능 확보가 가능한 상태에서, 주열식벽체 사이를 굴착하여 프리캐스트 상부구조물을 먼저 신속하게 시공한 후 굴착공간을 복구시켜 차량등 운행이 가능하도록 하기 때문에 지중구조물 시공에 따른 시공성 및 안전성을 확보할 수 있는 가능한 강재지수판을 이용하여 제작된 지중벽체 및 이를 이용한 지중구조물 시공방법 제공이 가능하게 된다. The main column wall of the invention is capable of securing the ordering performance between the steel pipes by using a steel index plate, and the precast superstructure is first quickly constructed by excavating between the main column walls, and then the excavation space is restored to enable the operation of vehicles, etc. Therefore, it is possible to provide an underground wall manufactured using a steel index plate and a method for constructing an underground structure using the same, which can secure constructability and safety according to the construction of the underground structure.

본 발명의 지중구조물 상부는 차량통행이 신속하게 복원될 수 있도록 지중구조물의 상판구조물은 프리캐스트방식으로 제작된 것으로 주열식벽체 사이에 강관지지대를 이용하여 거치식으로 시공하고, 상판구조물 상부 굴착공간을 복구시켜 바로 차량통행등이 가능하도록 하기 때문에 보다 효율적인 지중구조물 시공이 가능한 가능한 강재지수판을 이용하여 제작된 지중벽체 및 이를 이용한 지중구조물 시공방법 제공이 가능하게 된다.The upper part of the underground structure of the present invention is constructed by a precast method so that vehicle traffic can be quickly restored, and it is constructed in a stationary manner using a steel pipe support between the main column walls, and the excavation space above the upper plate structure is It is possible to provide an underground wall manufactured using a steel index plate that enables more efficient underground structure construction and a method for constructing an underground structure using the same because it is restored to enable immediate vehicle passage.

본 발명의 지중구조물에 있어 하판구조물은 현장타설 콘크리트 방식으로 시공하되 하부로부터 침투하는 누수에 의한 피해를 받지 않도록 방수시트를 설치하여 하판구조물으로의 누수문제가 발생하지 않도록 하고, 양 측벽구조물은 마감패널을 이용하여 신속한 시공이 가능하도록 하게 된다.In the underground structure of the present invention, the lower plate structure is constructed in a field-cast concrete method, but a waterproof sheet is installed so as not to be damaged by leakage from the lower part to prevent leakage to the lower plate structure, and both side wall structures are finished. It enables rapid construction using panels.

셋째, 주열식벽체 횡방향간격이 길어질 경우 중간 주열식벽체를 추가로 시공하도록 하되, 상판구조물 상부에 위치한 주열식벽체의 강관은 희생시키지 않고, 분리시켜 회수가 가능하도록 함으로서 보다 경제적인 지중구조물 시공이 가능한 강재지수판을 이용하여 제작된 지중벽체 및 이를 이용한 지중구조물 시공방법 제공이 가능하게 된다.Third, if the lateral spacing of the main column wall becomes longer, an intermediate main column wall should be additionally constructed, but the steel pipe of the main column wall located above the upper plate structure is not sacrificed, and the recovery is possible by separating it. It is possible to provide an underground wall manufactured using this possible steel index plate and a method for constructing an underground structure using the same.

도 1a 및 도 1b는 종래 주열식벽체의 시공도,
도 2는 본 발명의 주열식벽체를 이용하여 제작된 지중구조물의 시공도,
도 3a, 도 3b 및 도 3c는 본 발명의 주열식벽체를 이용하여 제작된 지중구조물의 구성상세도,
도 4a 및 도 4b는 본 발명의 주열식벽체를 이용하여 제작된 지중굳조물을 이용한 탑다운 방식의 지중구조물 시공방법 순서도이다.
1A and 1B are construction views of a conventional main heat type wall,
Figure 2 is a construction view of an underground structure manufactured using the main column wall of the present invention,
3A, 3B and 3C are detailed configuration diagrams of an underground structure manufactured using the main column wall of the present invention,
4A and 4B are a flow chart of a top-down method of constructing an underground structure using an underground hardening material manufactured using the main column wall of the present invention.

아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those of ordinary skill in the art can easily implement the present invention. However, the present invention may be implemented in various different forms and is not limited to the embodiments described herein. In the drawings, parts irrelevant to the description are omitted in order to clearly describe the present invention, and similar reference numerals are assigned to similar parts throughout the specification.

명세서 전체에서, 어떤 부분이 어떤 구성요소를 "포함"한다고 할 때, 이는 특별히 반대되는 기재가 없는 한 다른 구성요소를 제외하는 것이 아니라 다른 구성요소를 더 포함할 수 있는 것을 의미한다.Throughout the specification, when a part "includes" a certain component, it means that other components may be further included rather than excluding other components unless otherwise stated.

[ 주열식벽체를 이용하여 탑다운 방식으로 제작된 지중구조물(300) ][Underground structure (300) manufactured in a top-down manner using main heat type walls]

도 2는 본 발명의 주열식벽체(100)를 이용하여 탑다운 방식으로 제작된 지중구조물(300)의 시공도를 도시한 것이다.Figure 2 shows a construction diagram of an underground structure 300 manufactured in a top-down manner using the main column wall 100 of the present invention.

상기 지중구조물(300)은 도 2와 같이, 먼저 차수성능을 충분히 확보할 수 있도록 가이드관(120)을 이용하여 종방향으로 강관을 연결 시공하여 양 주열식벽체(100)를 서로 횡방향으로 이격시켜 시공함으로서 지중구조물(300)의 양 측벽체(310)를 시공할 수 있도록 하고, 상기 양 주열식벽체(100) 개략 중간에서 중간벽체(200)를 시공하여 지중구조물(300)의 내측벽체(330)를 시공할 수 있도록 하게 되며, 시공된 상판구조물(320) 상부는 차량 통행이 가능하도록 한 상태에서 상판구조물(320) 하부로는 하판구조물(340)를 시공하는 탑-다운방식을 이용하여 시공된다.As shown in FIG. 2, the underground structure 300 is constructed by connecting the steel pipes in the longitudinal direction using a guide pipe 120 so as to sufficiently secure the ordering performance, thereby separating the two main column walls 100 in the transverse direction from each other. It is possible to construct both side walls 310 of the underground structure 300 by performing construction, and the inner wall of the underground structure 300 by installing the intermediate wall 200 in the outline of the both main column walls 100 330) is to be constructed, and the upper structure of the upper plate structure 320 is constructed so that vehicle passage is possible, and a top-down method is used to construct the lower plate structure 340 under the upper plate structure 320. It is constructed.

이에 구체적으로 살펴보면, 지중구조물(300)은 도 2와 같이, 주열식벽체(100), 중간벽체(200) 및 지중구조물(300)을 포함하여 구성됨을 알 수 있다.Looking specifically at this, it can be seen that the underground structure 300 includes a main column wall 100, an intermediate wall 200, and an underground structure 300, as shown in FIG. 2.

먼저 상기 주열식벽체(100)는 강관(110)을 가이드관(120)을 이용하여 서로 종방향으로 이격시켜 시공함으로서 강관을 겹쳐서 시공함에 따른 강관 손실을 방지하면서 인접한 강관 사이에서의 차수성능을 확보할 수 있도록 한 것이다.First, the main column wall 100 is constructed by spaced apart the steel pipes 110 in the longitudinal direction using the guide pipes 120, thereby preventing the loss of steel pipes caused by overlapping steel pipes and securing order performance between adjacent steel pipes. I made it possible to do it.

이에 상기 주열식벽체(100)는 도 2 및 도 3a와 같이, 강관(110), 가이드관(120), 스터드(130), 강관연결판(140), 강관브라켓(150), 강관연결부(160)을 포함하여 구성된다.Accordingly, the main column wall 100 is a steel pipe 110, a guide pipe 120, a stud 130, a steel pipe connection plate 140, a steel pipe bracket 150, a steel pipe connector 160, as shown in FIGS. 2 and 3A. ).

먼저 상기 강관(110)은 도 3a에 의하면 일정한 직경을 가진 원형강관으로서 일측 외주면에는 가이드관(120)의 원통형가이드부(121)가 형성되어 있고, 대향되는 타측 외주면에는 가이드관(120)의 강재지수판(122)이 각각 측방으로 연장되어 있음을 알 수 있다.First, the steel pipe 110 is a circular steel pipe having a constant diameter according to FIG. 3A, and a cylindrical guide part 121 of the guide pipe 120 is formed on one outer circumferential surface, and a steel material of the guide pipe 120 is formed on the opposite outer circumferential surface. It can be seen that each of the water stop plates 122 extends laterally.

이에 가이드관(120)이 양 측방으로 형성된 강관(110)이 삽입될 수 있는 직경을 가진 천공홀(h)을 미리 지반에 형성시키고, 상기 천공홀에 강관(110)을 삽입한 다음, 먼저 삽입된 강관(110)의 원통형가이드부(121)에 연결 시공되는 강관(110)의 강재지수판(122)이 상부로부터 하강 삽입되어 가이드 되도록 하는 방식으로 강관(110)을 서로 연결 시공하게 된다.Accordingly, a perforated hole (h) having a diameter into which the steel pipe 110 formed in both sides of the guide pipe 120 can be inserted is formed in the ground in advance, and the steel pipe 110 is inserted into the perforated hole, and then inserted first. The steel pipes 110 are connected to each other in a manner such that the steel material index plate 122 of the steel pipe 110 connected to the cylindrical guide part 121 of the steel pipe 110 is inserted downward from the top to be guided.

이에 도 3a에 의하면 상기 가이드관(120)은 원통형가이드부(121) 및 강재지수판(122)으로 구성되어 있음을 알 수 있다.Accordingly, according to FIG. 3A, it can be seen that the guide pipe 120 is composed of a cylindrical guide portion 121 and a steel index plate 122.

상기 원통형가이드부(121)는 강관(110)의 연장길이에 걸쳐 수직판 형태로 형성된 연결플랜지(121a)에 일측이 일체화된 수직중공관(121b)으로 형성되며 수직중공관(121b)의 타측으로 개구부(121c)가 형성되도록 하여 수직중공관(121b) 내측과 개구부(121c)에 후술되는 강재지수판(122)이 상부로부터 하강 삽입되어 가이드 설치될 수 있도록 하게 된다.The cylindrical guide part 121 is formed of a vertical hollow pipe 121b in which one side is integrated with a connection flange 121a formed in the form of a vertical plate over the extended length of the steel pipe 110, and the other side of the vertical hollow pipe 121b The opening 121c is formed so that the steel material index plate 122, which will be described later, is inserted downward from the upper side of the vertical hollow pipe 121b and in the opening 121c to be installed as a guide.

상기 강재지수판(122)은 원통형가이드부(121)와 대향되는 위치에 강관(110)의 외주면에 일체로 역시 수직판 형태로 형성된 연결플랜지(122a)에 충진홀(122b)이 중심으로부터 다수 방사형으로 형성된 수직중공관(122c)이 일체화되도록 형성된다.The steel index plate 122 is integrally formed on the outer circumferential surface of the steel pipe 110 at a position opposite to the cylindrical guide portion 121, and a filling hole 122b is formed in the connection flange 122a in the form of a vertical plate. The formed vertical hollow pipe (122c) is formed to be integrated.

이때 상기 수직중공관(122c)은 외주면에는 수팽창지수재(122d)가 감싸져 있으며, 수팽창지수재(122d)가 감싸진 상태에서 원통형가이드부(121)의 수직중공관(121b)으로 삽입될 수 있도록 크기로 형성된다.At this time, the vertical hollow pipe (122c) is wrapped with a water expansion index material (122d) on the outer circumferential surface, and is inserted into the vertical hollow pipe (121b) of the cylindrical guide part 121 while the water expansion index member (122d) is wrapped It is shaped to be sized.

또한, 수직중공관(122c)에 일체로 형성된 연결플랜지(122a)는 원통형가이드부(121)와 개구부(121c)에 일체로 삽입되도록 하게 된다.In addition, the connection flange 122a integrally formed in the vertical hollow tube 122c is integrally inserted into the cylindrical guide portion 121 and the opening 121c.

이로서 상기 수팽창지수재(122d)에 의하여 물이 침입하면 수팽창지수재(122d)는 팽창하여 가이드관(120)에 의한 강관 배면으로부터의 1차 차수가 가능하게 되며, 상기 수직중공관(122c)에 고압으로 액체방수재를 주입하면 수직중공관(122c)의 충진홀(122b)을 통해 외부로 액체방수재가 주입되면서 추가적인 강관 배면으로부터의 2차 차수가 가능하도록 하게 된다.Thus, when water enters by the water expansion index member 122d, the water expansion index member 122d expands to enable the first order from the rear surface of the steel pipe by the guide pipe 120, and the vertical hollow pipe 122c ), the liquid waterproofing material is injected to the outside through the filling hole 122b of the vertical hollow pipe 122c, thereby enabling a secondary degree from the rear of the steel pipe.

또한 도 3a와 같이, 상기 스터드(130)는 강관 외주면에 전면쪽으로 다수 형성되도록 하여 지중구조물(300)의 양 측벽체(310) 시공 시 숏크리트 또는 측벽콘크리트 타설에 있어 합성성능 확보를 위한 전단연결재로 작용할 수 있도록 하게 된다.In addition, as shown in Fig. 3a, the stud 130 is formed on the outer circumferential surface of the steel pipe toward the front side, so that when constructing the both side walls 310 of the underground structure 300, it is used as a shear connector for securing the composite performance in casting shotcrete or sidewall concrete. To be able to work.

또한 도 3a와 같이 상기 강관연결판(140)은 서로 이격되어 연결 시공된 강관 외주면 사이에 가이드관(120) 보다 전면쪽으로 위치하여 형성된다. 이러한 강관연결판(140)에 의하여 강관 배면으로부터의 3차 차수가 가능하게 된다.In addition, as shown in FIG. 3A, the steel pipe connection plate 140 is formed to be located toward the front side of the guide pipe 120 between the outer circumferential surfaces of the steel pipes connected to each other. The third order from the rear surface of the steel pipe is possible by the steel pipe connection plate 140.

또한, 상기 강관(110) 내부에는 콘크리트가 충전되도록 하여 주열식벽체(100)는 콘크리트 충전 강관으로서 구조적 강성을 확보할 수 있도록 하여 지중구조물(300)의 양 측벽체(310)로 작용할 수 있도록 하게 된다.In addition, the inside of the steel pipe 110 is filled with concrete so that the main column wall 100 is a concrete-filled steel pipe to secure structural rigidity, so that it can act as both side walls 310 of the underground structure 300. do.

콘크리트 충전 깊이는 상판구조물(320) 위쪽으로 후술되는 강관연결부(160)까지만 충진되도록 하여 회수되는 상부 강관(110b)은 충전시키지 않아도 된다.It is not necessary to fill the recovered upper steel pipe 110b by filling the concrete filling depth above the upper plate structure 320 only up to the steel pipe connection 160 to be described later.

또한 도 3a와 같이, 후술되는 프리캐스트 상판(321)의 단부가 지지되도록 하는 위치에 강관(110) 외주면에 전면쪽으로 형성된 강관브라켓(150)이 일체로 더 형성되어 있음을 알 수 있다. In addition, as shown in FIG. 3A, it can be seen that the steel pipe bracket 150 formed toward the front side on the outer circumferential surface of the steel pipe 110 is further integrally formed at a position where the end of the precast upper plate 321 to be described later is supported.

이에 도 3a와 같이 상기 강관브라켓(150)은 수평으로 연장된 상부형강(151)과 상부형강 저면과 강관 외주면 사이의 스티프너판(152)로 형성되어 상부형강(151) 상면에 프리캐스트 상판(321) 단부 저면이 지지될 수 있도록 하게 된다.Accordingly, as shown in FIG. 3A, the steel pipe bracket 150 is formed of a horizontally extended upper section steel 151 and a stiffener plate 152 between the lower surface of the upper section steel and the outer circumferential surface of the steel pipe, and the precast upper plate 321 on the upper surface of the upper section steel 151 ) The bottom of the end can be supported.

도 2와 같이, 강관(110)은 지표면으로부터 지중구조물(300)의 상판구조물(320)까지는 최종 복구에 의하여 매립되기 때문에 지중구조물(300)의 상판구조물(310) 위쪽에 위치한 강관연결부(160)를 형성시키고, 강관연결부(160) 위쪽의 상부 강관(110b)을 회수하게 된다.As shown in FIG. 2, since the steel pipe 110 is buried from the ground surface to the upper plate structure 320 of the underground structure 300 by the final restoration, the steel pipe connection 160 located above the upper plate structure 310 of the underground structure 300 To form, and the upper steel pipe 110b above the steel pipe connector 160 is recovered.

이에 도 3a와 같이 강관연결부(160)를 기준으로 상,하부 강관(110a,110b)은 소켓식으로 겹쳐져 연결시키고, 강관연결부를 관통하는 수평볼트와 너트에 의하여 서로 일체화되어 복구 시 수평볼트를 풀어 상부강관(110a)은 회수가 가능하도록 하게 된다.Accordingly, as shown in Fig. 3a, the upper and lower steel pipes 110a and 110b are connected in a socket manner based on the steel pipe connection 160, and are integrated with each other by a horizontal bolt and a nut penetrating the steel pipe connection, and the horizontal bolts are loosened during recovery. The upper steel pipe 110a is made to be recoverable.

다음으로 상기 중간벽체(200)는 도 2 및 도 3a와 같이, 양 주열식벽체(100) 횡방향 간격이 커지게 되면 양 주열식벽체(100) 사이에 스트럿(220, 버팀보)을 설치하여 토압에 저항할 수 있도록 할 필요도 있고, 양 주열식벽체(100) 횡방향 간격이 커지게 되면 지중구조물(300)도 횡방향 연장길이가 길어지게 되므로 내측벽체(330)로 상판구조물(320)를 중간 지지할 필요가 있게 된다.Next, as shown in Figs. 2 and 3A, the intermediate wall 200 is formed by installing struts 220 between the two main column walls 100 when the lateral distance between the two main column walls 100 increases. It is also necessary to be able to resist resistance, and when the lateral distance between the two main column walls 100 increases, the underground structure 300 also extends in the transverse direction, so that the upper plate structure 320 is formed as the inner wall 330 There is a need for intermediate support.

이에 상기 중간벽체(200)는 도 2 및 도 3b와 같이, 수직강재(210), 중간브라켓(250)를 포함시켜 형성시키게 된다.Accordingly, the intermediate wall 200 is formed by including a vertical steel material 210 and an intermediate bracket 250 as shown in FIGS. 2 and 3B.

상기 수직강재(210)는 도 3b와 같이, H형 강재빔을 이용하여 강관(110) 시공 시 함께 종방향으로 이격시켜 지반에 삽입시키게 된다. 이격 거리는 프리캐스트 상판(321)을 종방향으로 지지할 수 있도록 정하면 된다.As shown in FIG. 3B, the vertical steel material 210 is inserted into the ground by being separated from each other in the longitudinal direction when the steel pipe 110 is constructed using an H-type steel beam. The separation distance may be determined so as to support the precast upper plate 321 in the longitudinal direction.

이에 수직강재(210)가 삽입될 수 있는 직경을 가진 천공홀(h1)을 형성시키고, 상기 천공홀에 수직강재(210)를 삽입시키고 하부구조물(340)의 하부 지반에 위치한 천공홀에만 콘크리트를 타설 및 양생시켜 하부가 고정되어 시공되도록 하게 된다.Accordingly, a perforated hole (h1) having a diameter into which the vertical steel material 210 can be inserted is formed, and the vertical steel material 210 is inserted into the perforated hole, and concrete is placed only in the perforated hole located in the lower ground of the lower structure 340. By pouring and curing, the lower part is fixed and constructed.

상기 중간브라켓(250)는 도 3b와 같이, 프리캐스트 상판(321) 단부가 지지되도록 하기 위한 받침대로서, 강관(110)에 형성시킨 강관브라켓(150)과 기능은 동일하다.The intermediate bracket 250 is a support for supporting the end of the precast upper plate 321 as shown in FIG. 3B, and has the same function as the steel pipe bracket 150 formed on the steel pipe 110.

예컨대, 양 측방등으로 프리캐스트 상판(321) 단부가 지지되도록 하기 위하여 수직강재 양 측방으로 연장된 h형 강재(251)를 용접등의 방법으로 형성시키고, 미도시된 거푸집을 이용하여 양 측방으로 연장된 h형 강재가 매립되도록 하여 콘크리트 받침대가 구체 형태로 형성되도록 하게 된다.For example, in order to support the ends of the precast top plate 321 on both sides, h-type steels 251 extending in both sides of the vertical steel are formed by welding, etc., and use a formwork not shown in both sides. The extended h-type steel is buried so that the concrete pedestal is formed in a spherical shape.

상기 지중구조물(300)은 도 2 및 도 3과 같이, 앞서 살펴본 주열식벽체(100), 중간벽체(200)를 이용하여 지중에 종방향으로 연속되도록 시공된 박스체 구조물로서 양 측벽체(310), 상판구조물(320), 내측벽체(330) 및 하판구조물(340)로 구성된다.The underground structure 300 is a box body structure constructed to be continuous in the underground in the longitudinal direction using the main column wall 100 and the intermediate wall 200 as described above, as shown in FIGS. 2 and 3, and both side walls 310 ), an upper plate structure 320, an inner wall body 330, and a lower plate structure 340.

이러한 지중구조물(300)은 탑-다운방식으로 시공함으로서 상판구조물(320)만 시공하면 지중구조물(300) 상부로는 차량통행이 가능하도록 할 수 있다.The underground structure 300 is constructed in a top-down manner, so that only the upper plate structure 320 can be constructed so that a vehicle can be passed to the top of the underground structure 300.

이에 상기 양 측벽체(310)는 도 2와 같이, 앞서 살펴본 강관(110) 내부에 콘크리트를 타설하여 주열식벽체(100)를 시공한 후, 서로 횡방향으로 이격 시공된 양 주열식벽체(100) 내측 사이 지반을 먼저 굴착하여 주열식벽체(100)를 노출시킨후, 노출된 주열식벽체에 강관연결판(140)과 강관(110)을 거푸집 삼아 스터드(130)가 매립되도록 측벽콘크리트를 타설하는 방식으로 형성시킨 후, 패널로 마감시켜 형성시키게 된다.Accordingly, as shown in FIG. 2, the two side walls 310 are constructed by pouring concrete into the steel pipe 110 as described above to construct the main column wall 100, and then the two main column walls 100 that are constructed horizontally apart from each other. ) After excavating the ground between the inner side first to expose the main column wall 100, the steel pipe connection plate 140 and the steel pipe 110 are used as formwork on the exposed main column wall, and side wall concrete is poured so that the stud 130 is buried. After forming in such a way that it is formed by finishing with a panel.

이에 콘크리트로 채워진 강관(110)은 지중구조물(300)의 양 측벽체(310)로서 1,2,3차 차수 기능을 가지면서 토압에 저항하게 되며, 상판구조물과 하판구조물이 연결 시공된다.Accordingly, the steel pipe 110 filled with concrete is the both side walls 310 of the underground structure 300, and has a 1, 2, 3 order function and resists earth pressure, and the upper plate structure and the lower plate structure are connected.

상기 상판구조물(320)은 도 3a 및 도 3b와 같이, 탑-다운방식에서는 양 주열식벽체(100)를 시공 한 후, 강관에 강관브라켓(150)을 설치 한 후, 프리캐스트 상판(321) 단부가 지지지도록 한 후, 상기 프리캐스트 상판(321)이 양 주열식벽체(100)와 일체화되도록 상판콘크리트를 타설하여 시공하게 된다.As shown in FIGS. 3A and 3B, the top plate structure 320 is formed by installing both main column walls 100 in the top-down method, and after installing the steel pipe bracket 150 on the steel pipe, the precast top plate 321 After the end is supported, the top plate concrete is poured and constructed so that the precast top plate 321 is integrated with the two main column walls 100.

즉, 현장타설콘크리트만을 사용하지 않고, 프리캐스트 상판(321)를 거치하는 방식으로 설치한 후, 상판콘크리트를 통해 양 주열식벽체(100)와 일체화시키는 방식을 이용하여 신속한 상판구조물 시공이 가능하게 된다.In other words, it is possible to quickly construct a top plate structure by using a method of mounting the precast top plate 321 without using only cast-in-place concrete, and then integrating it with both main column walls 100 through the top plate concrete. do.

이때 상기 양 주열식벽체(100) 사이에 중간벽체(200)가 시공되는 경우에는 수직강재(210)에 형성시킨 중간브라켓(250)과 강관브라켓(150) 사이사이에 프리캐스트 상판(321)을 설치하고, 수직강재가 매립되도록 상판콘크리트(321)를 타설하여 시공하면 된다.At this time, when the intermediate wall 200 is constructed between the two main column walls 100, a precast top plate 321 is placed between the intermediate bracket 250 formed on the vertical steel material 210 and the steel pipe bracket 150. It is installed, and the concrete top plate 321 is poured and constructed so that the vertical steel is buried.

이러한 상판구조물(320)은 탑-다운 방식에서는 상부는 복구시키거나, 복공판을 설치하여 차량 통행이 가능하도록 하고, 하부는 지중구조물(300) 시공이 추가적으로 이루어지기 때문에 프리캐스트 상판과 상판콘크리트를 모두 이용하여 신속하게 시공하고 있음을 알 수 있다.In the top-down method, in the top-down method, both the precast top plate and the top plate concrete are used because the upper part is restored or a retracted plate is installed to enable vehicle passage, and the underground structure 300 is additionally constructed. It can be seen that the construction is being carried out quickly.

상기 내측벽체(330)는 도 2 및 도 3b와 같이, 상판구조물(320)과 하판구조물(340) 사이에 중간벽체(200)의 수직강재(210)가 매설되도록 종방향으로 연속하여 일정한 폭을 가진 콘크리트 벽체로 시공하게 된다.The inner wall 330 has a constant width continuously in the longitudinal direction so that the vertical steel 210 of the intermediate wall 200 is buried between the upper plate structure 320 and the lower plate structure 340, as shown in FIGS. 2 and 3B. It will be constructed with a concrete wall.

상기 하판구조물(340)은 도 2 및 도 3b와 같이, 양 측벽체(310)의 하단 사이에 소정의 두께를 가진 콘크리트 판구조물로 형성시키면 된다.The lower plate structure 340 may be formed of a concrete plate structure having a predetermined thickness between the lower ends of both side walls 310, as shown in FIGS. 2 and 3B.

도 3c는 상판구조물(320), 하판구조물(340)을 시공함에 있어 방수시트(350) 시공도를 도시한 것이다.Figure 3c shows the construction of the waterproof sheet 350 in the construction of the upper plate structure 320 and the lower plate structure 340.

즉, 상판구조물(320), 하판구조물(340)의 양 단부는 양 주열식벽체(100)와 연결되기 때문에 시공 시기에 차이가 있어 시공이음이 발생하게 되고 이를 통해 누수가 발생할 수 있다.That is, since both ends of the upper plate structure 320 and the lower plate structure 340 are connected to the two main column walls 100, there is a difference in construction time, so that a construction joint may occur, and water leakage may occur through this.

이에 도 3c와 같이 상판구조물(320)의 경우에는Therefore, in the case of the upper plate structure 320 as shown in Figure 3c

상판구조물 상면에 보호층(351)을 일정한 두께로 형성시키고, 보호층(351) 상면에 시트방수재(352)를 포설하고, 시트방수재(352) 상면에 프라이머프를 도포 한후, 보호몰탈(353)을 일정두께로 형성시키되, 양 주열식벽체(100)의 강관(110)과 접하는 부위는 시트방수재(352)가 상,하로 겹쳐지도록 배치하되, 상부 시트방수재(352a) 하부에는 러버가 채워진 U형절곡부가 형성된 보강플레이트(354)가 하부 시트방수재(352b)에 연결되도록 하여 하부 시트방수재(352b)가 주열실벽체(100)와 접하고, 하부 시트방수재(352b) 상부에 상부 시트방수재(352a)가 위치하며, 상부 시트방수재(352a)는 하부 시트방수재(352b)와 겹쳐지지도록 하고, 하부 시트방수재(352b)는 러버가 채워진 U형절곡부가 형성된 보강플레이트(354)와 서로 연결되면서, 유수경로가 연장되면서 러버가 채워진 U형절곡부에 의한 지수가 가능하도록 하고 있음을 알 수 있다.A protective layer 351 is formed on the upper surface of the upper plate structure to have a certain thickness, a sheet waterproofing material 352 is installed on the upper surface of the protective layer 351, and a primer plate is applied to the upper surface of the sheet waterproofing material 352, and then the protective mortar 353 Is formed to a certain thickness, but the portion in contact with the steel pipe 110 of both main column walls 100 is arranged so that the sheet waterproofing material 352 overlaps up and down, and the upper sheet waterproofing material 352a is a U-shaped bottom filled with rubber. The reinforcing plate 354 formed with the bent portion is connected to the lower sheet waterproofing material 352b so that the lower sheet waterproofing material 352b is in contact with the main heat chamber wall 100, and the upper sheet waterproofing material 352a is placed on the lower sheet waterproofing material 352b. And the upper sheet waterproofing material 352a overlaps the lower sheet waterproofing material 352b, and the lower sheet waterproofing material 352b is connected to each other with the reinforcing plate 354 formed with a U-shaped bent part filled with rubber, and the flow path is It can be seen that the index is made possible by the U-shaped bent part filled with rubber as it is extended.

다음으로 도 3c와 같이 하판구조물(340)의 경우에는Next, in the case of the lower plate structure 340 as shown in Figure 3c

버림콘크리트 상면에 보호몰탈(353)을 일정두께로 형성시키고, 프라이머를 도포한 후, 시트방수재(352)를 포설하고, 보호층(351)을 형성시킨 후, 상기 보호층(351) 상면에 하판구조물(340)이 형성되도록 하되, 양 주열식벽체(100)의 강관(110)과 접하는 부위는 시트방수재(352)가 상,하로 겹쳐지도록 배치하되, 상부 시트방수재(352a) 하부에는 러버가 채워진 U형절곡부가 형성된 보강플레이트(354)가 하부 시트방수재(352b)에 연결되도록 하여 유수경로가 연장되면서 러버에 의한 지수가 가능하도록 하고 있음을 알 수 있다.A protective mortar 353 is formed on the upper surface of the discarded concrete to a certain thickness, and after applying a primer, a sheet waterproofing material 352 is installed, and a protective layer 351 is formed, and the lower plate is placed on the upper surface of the protective layer 351. The structure 340 is formed, but the portion in contact with the steel pipe 110 of both main column walls 100 is arranged so that the sheet waterproofing material 352 overlaps up and down, and the lower part of the upper sheet waterproofing material 352a is filled with rubber. It can be seen that the reinforcing plate 354 in which the U-shaped bent portion is formed is connected to the lower sheet waterproofing material 352b so that the water flow path is extended and the water index by the rubber is possible.

[ 주열식벽체를 이용하여 탑다운 방식으로 제작된 지중구조물 시공방법 ][Construction method of underground structure manufactured in top-down method using main heat type wall]

도 4a 및 도 4b는 본 발명의 주열식벽체(100)를 이용하여 제작된 지중구조물(300)을 이용한 탑다운 방식의 지중구조물 시공방법 순서도를 도시한 것이다.4A and 4B show a flow chart of a top-down method of constructing an underground structure using an underground structure 300 manufactured using the main column wall 100 of the present invention.

상기 시공방법은 양 주열식벽체(100)와 중간벽체(200)를 시공한 후, 양 주열식벽체(100) 사이의 지반을 하방 굴착하고, 상판구조물(320)을 시공한 후, 상판구조물(320) 상부 굴착된 공간을 차량통행 가능하도록 하고, 상판구조물(320) 아래 지반을 계속 굴착하여 하판구조물(340)과 양 측벽체(310)와 내측벽체(330)를 마감시키는 방법이다.The above construction method is after constructing both the main column wall body 100 and the intermediate wall body 200, excavating the ground between the both column wall body 100, and after installing the top plate structure 320, the top plate structure ( 320) This is a method of closing the lower plate structure 340, both side walls 310 and the inner wall body 330 by allowing the vehicle to pass through the upper excavated space and continuously excavating the ground under the upper plate structure 320.

이에 먼저 도 4a에 의하면,First, according to FIG. 4A,

양 주열식벽체(100) 및 중간벽체(200) 시공을 위하여 천공홀(h)을 3개 횡방향으로 이격시켜 시공하고 있음을 알 수 있다.It can be seen that three perforated holes h are spaced apart from each other in the transverse direction for the construction of both the main column wall body 100 and the intermediate wall body 200.

이에 좌측 및 우측 천공홀(h)에는 양 주열식벽체(100) 시공을 위한 강관(110)을 종방향으로 연결시공하게 되며, 내부에는 콘크리트를 충전시키되 강관연결부(160) 아래까지만 충전시키고, 중간 천공홀(h)에는 수직강재(210)을 삽입한 후, 하판구조물(340)의 하부로만 콘크리트를 충전시키고 있음을 알 수 있다.Accordingly, the left and right perforation holes (h) are connected to the steel pipe 110 for the construction of both main column walls 100 in the longitudinal direction, and the concrete is filled inside, but filled only up to the bottom of the steel pipe connector 160, and the middle After inserting the vertical steel material 210 into the perforated hole h, it can be seen that concrete is filled only in the lower part of the lower plate structure 340.

다음으로는 양 주열식벽체(100) 사이의 지반을 굴착하면서 스트럿(220, 버팀보)을 설치하여 굴착에 의한 붕괴위험을 방지하면서 양 주열식벽체(100)와 중간벽체(200)의 강관(110)과 수직강재(210)가 노출되도록 하게 된다.Next, while excavating the ground between the two main column walls 100, struts (220, braces) are installed to prevent the risk of collapse due to excavation, and the steel pipe 110 of the both main column walls 100 and the intermediate wall 200 ) And the vertical steel material 210 is exposed.

이에 노출된 강관(110)과 수직강재(210)의 강관브라켓(150)과 중간브라켓(250)을 각각 형성시킨 후, 프리캐스트 상판(321)의 단부가 강관브라켓(150)과 중간브라켓(250) 상면에 지지되도록 거치시키게 된다.After forming the steel pipe bracket 150 and the intermediate bracket 250 of the steel pipe 110 and the vertical steel material 210 exposed thereto, the ends of the precast top plate 321 are the steel pipe bracket 150 and the intermediate bracket 250 ) It is mounted to be supported on the upper surface.

다음으로 도 4b에 의하면,Next, according to FIG. 4B,

양 주열식벽체(100)와 프리캐스트 상판(321) 사이 공간에 철근을 배근하고 및 상부에 상부콘크리트를 타설하여 프리캐스트 상판(321)을 양 주열식벽체(100)와 일체화시켜 상판구조물(310)을 먼저 시공하게 된다.Reinforcing bars are laid in the space between the two main column walls 100 and the precast top plate 321, and upper concrete is poured on the top, so that the precast top plate 321 is integrated with both the main column walls 100, and the top plate structure 310 ) Will be constructed first.

이때, 상판구조물 상부에 양 주열실벽체(100)와 중간벽체(200)의 두부에 복공판을 추가로 설치하여 차량통행이 가능하도록 할 수 있다.At this time, by additionally installing a double-hole plate on the heads of both the main heat chamber wall 100 and the intermediate wall 200 on the upper plate structure to enable vehicle passage.

다음으로는 상판구조물(330) 하부 지반을 추가 굴착하여 하판구조물(340)을 시공하게 된다. 물로 상판구조물(320), 하판구조물(340) 시공시 방수시트(350)를 함께 시공하게 된다.Next, the lower plate structure 340 is constructed by additional excavation of the lower ground of the upper plate structure 330. When constructing the upper plate structure 320 and the lower plate structure 340 with water, the waterproof sheet 350 is installed together.

다음으로는 상판구조물(320), 하판구조물(340) 사이의 상,하 공간에 양 주열식벽체(100) 노출면에 벽체콘크리트를 타설하고, 노출된 수직강재에 중간벽체 콘크리트를 타설하게 된다. 이로서 양 측벽체(310), 내측벽체(330)가 완성되어 지중구조물(300) 시공이 완성된다.Next, wall concrete is poured on the exposed surfaces of both main columned walls 100 in the upper and lower spaces between the upper plate structure 320 and the lower plate structure 340, and intermediate wall concrete is poured on the exposed vertical steel material. As a result, both side walls 310 and inner walls 330 are completed, and the construction of the underground structure 300 is completed.

이때 미도시 하였지만 상판구조물과 하판구조물 사이가 깊어질 경우에는 양 주열식벽체 사이에 스트럿을 추가로 설치하고 하판구조물을 시공한 후, 양 주열식벽체(100) 노출면에 벽체콘크리트를 타설하고, 노출된 수직강재에 중간벽체 콘크리트를 타설한 후, 상기 스트럿을 제거하는 방식으로도 시공할 수 있다.At this time, although not shown, in the case of deepening between the upper plate structure and the lower plate structure, additional struts are installed between both main column walls and the lower panel structure is constructed, and then wall concrete is poured on the exposed surfaces of both main column walls 100, After pouring the intermediate wall concrete on the exposed vertical steel, it can be constructed by removing the strut.

이에 상판구조물(320) 상부 복공판등을 제거하고, 강관에 형성시킨 강관브라켓(150)의 연결볼트를 풀고, 굴착공간을 복구시킨 후, 다짐이전에 양 주열식벽체(100)의 상부강관을 제거하고, 수직강재(210)도 함께 상부강관의 길이 정도로 제거하여 회수하게 된다. 이에 최종 복구된 지반을 다짐하고 표면에 포장층을 형성시키게 된다.Accordingly, the upper plate structure 320 is removed, the connection bolts of the steel pipe bracket 150 formed on the steel pipe are loosened, the excavation space is restored, and the upper steel pipes of the two main column walls 100 are removed before compaction. And, the vertical steel material 210 is also removed and recovered by the length of the upper steel pipe. Accordingly, the final restored ground is compacted and a pavement layer is formed on the surface.

전술한 본 발명의 설명은 예시를 위한 것이며, 본 발명이 속하는 기술분야의 통상의 지식을 가진 자는 본 발명의 기술적 사상이나 필수적인 특징을 변경하지 않고서 다른 구체적인 형태로 쉽게 변형이 가능하다는 것을 이해할 수 있을 것이다. 그러므로 이상에서 기술한 실시예들은 모든 면에서 예시적인 것이며 한정적이 아닌 것으로 이해해야만 한다. 예를 들어, 단일형으로 설명되어 있는 각 구성 요소는 분산되어 실시될 수도 있으며, 마찬가지로 분산된 것으로 설명되어 있는 구성 요소들도 결합된 형태로 실시될 수 있다.The above description of the present invention is for illustrative purposes only, and those of ordinary skill in the art to which the present invention pertains will be able to understand that other specific forms can be easily modified without changing the technical spirit or essential features of the present invention will be. Therefore, it should be understood that the embodiments described above are illustrative in all respects and not limiting. For example, each component described as a single type may be implemented in a distributed manner, and similarly, components described as being distributed may also be implemented in a combined form.

본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is indicated by the claims to be described later rather than the detailed description, and all changes or modified forms derived from the meaning and scope of the claims and their equivalent concepts should be interpreted as being included in the scope of the present invention. do.

100: 주열식벽체
110,100a,100b: 강관, 상부강관, 하부강관
120: 가이드관 121: 원통형 가이드부
121a: 연결플랜지 121b: 수직중공관
121c: 개구부
122: 강재지수판 122a: 연결플랜지
122b: 충진홀 122c: 수직중공관
122d: 수팽창지수재
130: 스터드 140: 강관연결판
150: 강관브라켓
151: 상부형강 152: 스티프너판
160: 강관연결부
200: 중간벽체
210: 수직강재 220: 스트럿
250: 중간브라켓
300: 지중구조물
310: 양 측벽체 320: 상판구조물
321: 프리캐스트 상판 330: 내측벽체
340: 하판구조물
100: main heating wall
110,100a,100b: steel pipe, upper steel pipe, lower steel pipe
120: guide tube 121: cylindrical guide portion
121a: connecting flange 121b: vertical hollow pipe
121c: opening
122: steel index plate 122a: connecting flange
122b: filling hole 122c: vertical hollow pipe
122d: water expansion index material
130: stud 140: steel pipe connection plate
150: steel pipe bracket
151: upper section steel 152: stiffener plate
160: steel pipe connection
200: intermediate wall
210: vertical steel 220: strut
250: middle bracket
300: underground structure
310: both side walls 320: upper plate structure
321: precast top plate 330: inner wall
340: lower plate structure

Claims (10)

종방향으로 강관(110)을 가이드관(120)을 이용하여 연결 설치하여 형성된 양 주열식벽체(100); 및
상기 양 주열식벽체(100) 사이의 지반을 지표면으로부터 굴착하여 형성시킨 공간을 이용하여 양 주열식벽체 사이에 거치된 프리캐스트 상판(321)에 상판콘크리트를 타설하여 양 주열식벽체에 일체화되도록 형성된 상판구조물(320); 상기 상판구조물 (320) 하부를 굴착하여 양 주열식벽체(100) 사이에 형성된 하판구조물(340);과 상판구조물(320)과 하판구조물(340) 사이의 노출된 양 주열식벽체(100)에 타설하여 형성된 측벽콘크리트에 의하여 형성된 양 측벽체(310);를 포함하는 지중구조물(300);을 포함하는 주열식벽체를 이용하여 탑다운 방식으로 제작된 지중구조물.
Both main column type walls 100 formed by connecting and installing the steel pipe 110 in the longitudinal direction using the guide pipe 120; And
It is formed so as to be integrated with both main column walls by pouring concrete on the precast top plate 321 mounted between both main column walls using a space formed by excavating the ground between the two column walls 100 from the ground surface. A top plate structure 320; The lower plate structure 340 formed between the two main columned walls 100 by excavating the lower part of the upper plate structure 320; and both the exposed main columned wall 100 between the upper plate structure 320 and the lower plate structure 340 Both sidewalls 310 formed by pouring sidewall concrete; an underground structure 300 including; an underground structure manufactured in a top-down manner using a main column type wall including.
제 1항에 있어서,
상기 강관(110)은 일측 외주면에는 가이드관(120)의 원통형가이드부(121)가 형성되어 있고, 대향되는 타측 외주면에는 가이드관(120)의 강재지수판(122)이 각각 측방으로 연장되어,
지반에 형성시킨 천공홀에 상기 강관(110)을 삽입한 다음, 먼저 삽입된 강관(110)의 원통형가이드부(121)에 연결 시공되는 강관(110)의 강재지수판(122)이 상부로부터 하강 삽입되어 가이드 되도록 하는 주열식벽체를 이용하여 탑다운 방식으로 제작된 지중구조물.
The method of claim 1,
The steel pipe 110 has a cylindrical guide portion 121 of the guide pipe 120 formed on one outer circumferential surface, and the steel material index plate 122 of the guide pipe 120 is extended laterally on the opposite outer circumferential surface,
After inserting the steel pipe 110 into the perforated hole formed in the ground, the steel index plate 122 of the steel pipe 110 connected to the cylindrical guide part 121 of the first inserted steel pipe 110 is inserted downward from the top. An underground structure manufactured in a top-down manner using a main column wall to be guided.
제 2항에 있어서,
상기 원통형가이드부(121)는 강관(110)의 연장길이에 걸쳐 수직판 형태로 형성된 연결플랜지(121a)에 일측이 일체화된 수직중공관(121b)으로 형성되며 수직중공관(121b)의 타측으로 개구부(121c)가 형성되도록 하여 수직중공관(121b) 내측과 개구부(121c)에 강재지수판(122)이 상부로부터 하강 삽입되어 가이드 설치될 수 있도록 하는 주열식벽체를 이용하여 탑다운 방식으로 제작된 지중구조물.
The method of claim 2,
The cylindrical guide part 121 is formed of a vertical hollow pipe 121b in which one side is integrated with a connection flange 121a formed in the form of a vertical plate over the extended length of the steel pipe 110, and the other side of the vertical hollow pipe 121b It is manufactured in a top-down manner by using a main column wall that allows the opening 121c to be formed so that the steel index plate 122 is inserted downward from the top and guided into the vertical hollow pipe 121b and the opening 121c. Underground structures.
제 2항에 있어서,
상기 강재지수판(122)은 원통형가이드부(121)와 대향되는 위치에 강관(110)의 외주면에 일체로 역시 수직판 형태로 형성된 연결플랜지(122a)에 충진홀(122b)이 중심으로부터 다수 방사형으로 형성된 수직중공관(122c)이 일체화되도록 형성되며,
상기 수직중공관(122c)은 외주면에는 수팽창지수재(122d)가 감싸진 상태에서 원통형가이드부(121)의 수직중공관(121b)으로 삽입될 수 있도록 크기로 형성되는 주열식벽체를 이용하여 탑다운 방식으로 제작된 지중구조물.
The method of claim 2,
The steel index plate 122 is integrally formed on the outer circumferential surface of the steel pipe 110 at a position opposite to the cylindrical guide portion 121, and a filling hole 122b is formed in the connection flange 122a in the form of a vertical plate. It is formed so that the formed vertical hollow tube (122c) is integrated,
The vertical hollow pipe (122c) uses a main column wall formed in size so that it can be inserted into the vertical hollow pipe (121b) of the cylindrical guide portion (121) while the water expansion index member (122d) is wrapped around the outer circumferential surface. An underground structure manufactured in a top-down method.
제 4항에 있어서,
상기 수팽창지수재(122d)에 의하여 물이 침입하면 수팽창지수재(122d)는 팽창하여 가이드관(120)에 의한 강관 배면으로부터의 1차 차수가 가능하게 되며,
상기 수직중공관(122c)에 고압으로 액체방수재를 주입하면 수직중공관(122c)의 충진홀(122b)을 통해 외부로 액체방수재가 주입되면서 추가적인 강관 배면으로부터의 2차 차수가 가능하도록 하며,
서로 이격되어 연결 시공된 강관 외주면 사이에 가이드관(120) 보다 전면쪽으로 위치하여 형성된 강관연결판(140)에 의하여 강관 배면으로부터의 3차 차수가 가능하도록 하는 주열식벽체를 이용하여 탑다운 방식으로 제작된 지중구조물.
The method of claim 4,
When water enters by the water expansion index member 122d, the water expansion index member 122d expands to enable the first order from the rear surface of the steel pipe by the guide pipe 120,
When the liquid waterproofing material is injected into the vertical hollow pipe 122c at high pressure, the liquid waterproofing material is injected to the outside through the filling hole 122b of the vertical hollow pipe 122c, thereby enabling an additional second order from the rear of the steel pipe,
It is a top-down method by using a main heat type wall that enables a third degree from the rear of the steel pipe by the steel pipe connection plate 140 formed to be positioned toward the front side of the guide pipe 120 between the outer circumferential surfaces of the steel pipes connected to each other. Constructed underground structure.
제 1항에 있어서,
상기 프리캐스트 상판은
수평으로 연장된 상부형강(151)과 상부형강 저면과 강관 외주면 사이의 스티프너판(152)로 형성되어 상부형강(151) 상면에 프리캐스트 상판(321) 단부 저면이 지지될 수 있도록 하는 강관브라켓(150)에 의하여 양 주열식벽체 사이에 거치되도록 하는 주열식벽체를 이용하여 탑다운 방식으로 제작된 지중구조물.
The method of claim 1,
The precast top plate
A steel pipe bracket that is formed of a horizontally extended upper section steel 151 and a stiffener plate 152 between the lower surface of the upper section steel and the outer circumferential surface of the steel pipe so that the upper section of the upper section 151 is supported by the lower end of the precast top plate 321 ( Underground structure manufactured in a top-down manner using main column walls to be mounted between both main column walls by 150).
제 1항에 있어서,
상기 강관(110)에 지중구조물(300)의 상판구조물(310) 위쪽에 위치한 강관연결부(160)를 더 형성시켜 강관을 상부강관(110a) 및 하부강관(110b)으로 구분하여,
강관연결부(160)를 기준으로 상,하부 강관(110a,110b)은 소켓식으로 겹쳐져 연결시키고, 강관연결부를 관통하는 수평볼트와 너트에 의하여 서로 일체화되어 복구 시 수평볼트를 풀어 상부강관(110a)은 회수가 가능하도록 하는 주열식벽체를 이용하여 탑다운 방식으로 제작된 지중구조물.
The method of claim 1,
A steel pipe connection unit 160 located above the upper plate structure 310 of the underground structure 300 is further formed in the steel pipe 110 to divide the steel pipe into an upper steel pipe 110a and a lower steel pipe 110b,
The upper and lower steel pipes 110a and 110b based on the steel pipe connection 160 are connected by overlapping in a socket type, and they are integrated with each other by a horizontal bolt and a nut penetrating the steel pipe connection part, and the upper steel pipe 110a by loosening the horizontal bolt when restoring. An underground structure manufactured in a top-down method using a main column wall that allows silver recovery.
제 1항에 있어서,
상기 양 주열식벽체 사이에는 중간벽체(200)를 더 설치하되, 상기 중간벽체(200)는
수직강재(210)가 삽입될 수 있는 직경을 가진 천공홀(h1)을 형성시키고, 상기 천공홀에 수직강재(210)를 삽입시키고 하부구조물(340)의 하부 지반에 위치한 천공홀에만 콘크리트를 타설 및 양생시켜 하부가 고정되어 형성시키고,
상기 수직강재(210) 양 측방으로 연장된 h형 강재를 형성시키고, 상기 양 측방으로 연장된 h형 강재가 매립되도록 하여 콘크리트 받침대가 구체 형태로 형성되도록 중간브라켓(250)를 설치하여, 프리캐스트 상판(321) 단부가 지지되도록 하며,
상판구조물(320)과 하판구조물(340) 사이에 상기 중간벽체(200)의 수직강재(210)가 매설되도록 종방향으로 연속하여 일정한 폭을 가진 콘크리트 벽체로 내측벽체(330)가 더 형성되도록 하는 주열식벽체를 이용하여 탑다운 방식으로 제작된 지중구조물.
The method of claim 1,
An intermediate wall 200 is further installed between the two main column walls, and the intermediate wall 200 is
A perforated hole h1 having a diameter into which the vertical steel 210 can be inserted is formed, the vertical steel 210 is inserted into the perforated hole, and concrete is poured only into the perforated hole located in the lower ground of the lower structure 340 And curing to form the lower part fixed,
An intermediate bracket 250 is installed to form an h-type steel extending in both sides of the vertical steel 210, and the h-type steel extending in both sides is buried so that the concrete support is formed in a spherical shape, and precast So that the end of the top plate 321 is supported,
The inner wall 330 is further formed with a concrete wall having a constant width continuously in the longitudinal direction so that the vertical steel material 210 of the intermediate wall 200 is buried between the upper plate structure 320 and the lower plate structure 340. An underground structure manufactured in a top-down method using a main column wall.
(a) 종방향으로 강관을 가이드관을 이용하여 연결 설치하여 양 주열식벽체를 시공하는 단계;
(b) 상기 양 주열식벽체 사이 지표면으로부터 지반을 굴착하여 형성시킨 공간을 이용하여 양 주열식벽체 사이에 거치된 프리캐스트 상판에 상판콘크리트를 타설하여 양 주열식벽체에 일체화되도록 상판구조물 형성시키는 단계;
(c) 상기 상판구조물 하부를 굴착하여 양 주열식벽체 사이에 스트럿을 설치하면서 하판구조물을 형성시키는 단계; 및
(d) 상기 상판구조물과 하판구조물 사이의 노출된 양 주열식벽체에 형성된 측벽콘크리트에 의하여 양 측벽체를 형성시켜 지중구조물을 시공하는 단계;를 포함하며,
상기 (b) 단계이 상판구조물(320)을 시공함에 있어 방수시트(350)를 설치하되,
상판구조물에 설치되는 방수시트(350)는
상판구조물(320)의 상면에 보호층(351)을 일정한 두께로 형성시키고, 보호층(351) 상면에 시트방수재(352)를 포설하고, 시트방수재(352) 상면에 프라이머프를 도포 한후, 보호몰탈(353)을 일정두께로 형성시키되, 양 주열식벽체(100)의 강관(110)과 접하는 부위는 시트방수재(352)가 상,하로 겹쳐지도록 배치하되, 상부 시트방수재(352a) 하부에는 러버가 채워진 U형절곡부가 형성된 보강플레이트(354)가 하부 시트방수재(352b)에 연결되도록 하여 하부 시트방수재(352b)가 주열실벽체(100)와 접하고, 하부 시트방수재(352b) 상부에 상부 시트방수재(352a)가 위치하며, 상부 시트방수재(352a)는 하부 시트방수재(352b)와 겹쳐지지도록 하고, 하부 시트방수재(352b)는 러버가 채워진 U형절곡부가 형성된 보강플레이트(354)와 서로 연결되면서, 유수경로가 연장되면서 러버가 채워진 U형절곡부에 의한 지수가 가능하도록 하는 주열식벽체를 이용하여 탑다운 방식으로 제작된 지중구조물 시공방법.
(a) connecting and installing steel pipes in a longitudinal direction using a guide pipe to construct both main column walls;
(b) using a space formed by excavating the ground from the ground surface between the two main column walls, pouring top plate concrete on the precast top plate mounted between the two main column walls to form a top plate structure to be integrated with both main column walls ;
(c) excavating the lower part of the upper plate structure to form a lower plate structure while installing struts between both main column walls; And
(d) constructing an underground structure by forming both side walls by using sidewall concrete formed on both exposed main column walls between the upper plate structure and the lower plate structure, and including,
In the step (b), in the construction of the upper plate structure 320, a waterproof sheet 350 is installed,
The waterproof sheet 350 installed on the upper plate structure
A protective layer 351 is formed on the upper surface of the upper plate structure 320 to have a certain thickness, a sheet waterproofing material 352 is laid on the upper surface of the protective layer 351, and a primer coat is applied on the upper surface of the sheet waterproofing material 352, and then protected. The mortar 353 is formed to have a certain thickness, but the part in contact with the steel pipe 110 of both main column walls 100 is arranged so that the sheet waterproofing material 352 overlaps up and down, but the upper sheet waterproofing material 352a is lower than the rubber The reinforcing plate 354 filled with the U-shaped bent portion is connected to the lower sheet waterproofing material 352b so that the lower sheet waterproofing material 352b contacts the main heat chamber wall 100, and the upper sheet waterproofing material on the upper part of the lower sheet waterproofing material 352b (352a) is located, and the upper sheet waterproofing material 352a overlaps the lower sheet waterproofing material 352b, and the lower sheet waterproofing material 352b is connected to each other with the reinforcing plate 354 formed with a U-shaped bent part filled with rubber. , Underground structure construction method manufactured in a top-down method using a main-heated wall that enables water retention by a rubber-filled U-shaped bend while the running path is extended.
제 9항에 있어서,
상기 (c) 단계의 하판구조물(340)을 시공함에 있어 방수시트(350)를 설치하되,
상판구조물에 설치되는 방수시트(350)는
버림콘크리트 상면에 보호몰탈(353)을 일정두께로 형성시키고, 프라이머를 도포한 후, 시트방수재(352)를 포설하고, 보호층(351)을 형성시킨 후, 상기 보호층(351) 상면에 하판구조물(340)이 형성되도록 하되, 양 주열식벽체(100)의 강관(110)과 접하는 부위는 시트방수재(352)가 상,하로 겹쳐지도록 배치하되, 상부 시트방수재(352a) 하부에는 러버가 채워진 U형절곡부가 형성된 보강플레이트(354)가 하부 시트방수재(352b)에 연결되도록 하여 유수경로가 연장되면서 러버에 의한 지수가 가능하도록 하는 주열식벽체를 이용하여 탑다운 방식으로 제작된 지중구조물 시공방법.
The method of claim 9,
In the construction of the lower plate structure 340 of step (c), a waterproof sheet 350 is installed,
The waterproof sheet 350 installed on the upper plate structure
A protective mortar 353 is formed on the upper surface of the discarded concrete to a certain thickness, and after applying a primer, a sheet waterproofing material 352 is installed, and a protective layer 351 is formed, and the lower plate is placed on the upper surface of the protective layer 351. The structure 340 is formed, but the portion in contact with the steel pipe 110 of both main column walls 100 is arranged so that the sheet waterproofing material 352 overlaps up and down, and the lower part of the upper sheet waterproofing material 352a is filled with rubber. Construction method of an underground structure manufactured in a top-down method by using a main heat type wall that allows the reinforcing plate 354 formed with a U-shaped bent portion to be connected to the lower sheet waterproofing material 352b so that the water flow path is extended and water index by rubber is possible .
KR1020190036501A 2019-03-29 2019-03-29 Underground structure with top-down construction method using underground column wall and construction method therefor KR102210345B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190036501A KR102210345B1 (en) 2019-03-29 2019-03-29 Underground structure with top-down construction method using underground column wall and construction method therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190036501A KR102210345B1 (en) 2019-03-29 2019-03-29 Underground structure with top-down construction method using underground column wall and construction method therefor

Publications (2)

Publication Number Publication Date
KR20200114553A true KR20200114553A (en) 2020-10-07
KR102210345B1 KR102210345B1 (en) 2021-02-01

Family

ID=72883486

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190036501A KR102210345B1 (en) 2019-03-29 2019-03-29 Underground structure with top-down construction method using underground column wall and construction method therefor

Country Status (1)

Country Link
KR (1) KR102210345B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20220093816A (en) 2020-12-28 2022-07-05 권영순 Underground structure using cross-beam support apparatus and construction method thereof
KR20220165042A (en) * 2021-06-07 2022-12-14 송성민 Top-down construction method for uneven-slope site
KR20230108564A (en) * 2022-01-11 2023-07-18 송성민 Underground structure with precast concrete pile and composite diaphragm wall and the construction method thereof

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102392517B1 (en) 2021-07-13 2022-04-29 주식회사 와이앤케이에코 Top-down method using by double beam system

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020064819A (en) * 2001-02-03 2002-08-10 한국도로공사 Socket type steel pipe pile and construction method for connecting thereof
KR200390421Y1 (en) * 2005-03-07 2005-07-25 주식회사 한진중공업 Top-down substructure by deck suspension
KR100951097B1 (en) * 2009-03-13 2010-04-07 (주)한국건설공법 Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket
KR20100105211A (en) * 2009-03-20 2010-09-29 정영수 Improved waterproof sheet, method for constructing waterproof and waterproof structure using the same
KR20150051101A (en) 2013-11-01 2015-05-11 비에이치아이 주식회사 Steel pipe for watertight wall
KR101590032B1 (en) * 2015-02-12 2016-01-29 주식회사 대산시빌테크날러지 Column wall using pile and structure construction method therewith
KR101662091B1 (en) 2016-01-29 2016-10-05 (주)서현컨스텍 Water proofing wallusing internal water proof member and the structure construction method therewith
KR101764390B1 (en) * 2016-09-13 2017-08-02 유한회사 강남이앤씨 3-Layered cutoff wall structure with pile of wall steel pipe and variabld linking body, and construction method of cutoff wall using the same
KR101902791B1 (en) * 2017-04-03 2018-10-01 유병훈 Under ground structure construction method using composite steel pile and under ground structure therewith

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020064819A (en) * 2001-02-03 2002-08-10 한국도로공사 Socket type steel pipe pile and construction method for connecting thereof
KR200390421Y1 (en) * 2005-03-07 2005-07-25 주식회사 한진중공업 Top-down substructure by deck suspension
KR100951097B1 (en) * 2009-03-13 2010-04-07 (주)한국건설공법 Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket
KR20100105211A (en) * 2009-03-20 2010-09-29 정영수 Improved waterproof sheet, method for constructing waterproof and waterproof structure using the same
KR20150051101A (en) 2013-11-01 2015-05-11 비에이치아이 주식회사 Steel pipe for watertight wall
KR101590032B1 (en) * 2015-02-12 2016-01-29 주식회사 대산시빌테크날러지 Column wall using pile and structure construction method therewith
KR101662091B1 (en) 2016-01-29 2016-10-05 (주)서현컨스텍 Water proofing wallusing internal water proof member and the structure construction method therewith
KR101764390B1 (en) * 2016-09-13 2017-08-02 유한회사 강남이앤씨 3-Layered cutoff wall structure with pile of wall steel pipe and variabld linking body, and construction method of cutoff wall using the same
KR101902791B1 (en) * 2017-04-03 2018-10-01 유병훈 Under ground structure construction method using composite steel pile and under ground structure therewith

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20220093816A (en) 2020-12-28 2022-07-05 권영순 Underground structure using cross-beam support apparatus and construction method thereof
KR20220165042A (en) * 2021-06-07 2022-12-14 송성민 Top-down construction method for uneven-slope site
KR20230108564A (en) * 2022-01-11 2023-07-18 송성민 Underground structure with precast concrete pile and composite diaphragm wall and the construction method thereof

Also Published As

Publication number Publication date
KR102210345B1 (en) 2021-02-01

Similar Documents

Publication Publication Date Title
KR102210345B1 (en) Underground structure with top-down construction method using underground column wall and construction method therefor
KR101582173B1 (en) The structure assembly for building a tunnel and building method thereof
KR101331261B1 (en) Underground prefabricated precast concrete rainwater recycling facility using precast concrete continuous wall in strut structure or earth anchor and construction method of the same
KR101173045B1 (en) Earth retaining-cum-retaining wall, and construction method thereof
KR100968048B1 (en) A retaining panel structure and construction method
KR101040066B1 (en) Method of constructing non-excavation type tunnel
JP4881555B2 (en) Construction method of underground structure
KR20090029993A (en) Underground structure and its construction method with retaining wall supported by rigid diaphragm
KR102196532B1 (en) Under ground structure construction method using composite steel pile underground column wall and top-down under ground structure therewith
KR101255515B1 (en) The tunel execution method
KR101902791B1 (en) Under ground structure construction method using composite steel pile and under ground structure therewith
KR20210078779A (en) Underground roadway removed upper structure between upper slab and surface of road after constructing the steel continuous wall in the earth by top-down method and method for constructing the same
KR102292152B1 (en) Top-down construction method with underground utility
JP2018009388A (en) End structure of preceding element and construction method of underground continuous wall
JP5021526B2 (en) Construction method of underpass and connecting structure of superstructure girder and underground wall
JPS61122320A (en) Method of coupling continuous underground wall with underground structure
JP2018053466A (en) Open shield method
KR102153783B1 (en) Underground road using self-supporting pile wall with temporary wall
KR20090078684A (en) Composite wall using angled channel and constructing method thereof
KR101884453B1 (en) Pre-climbing core construction method for top-down construction
JP2579120B2 (en) garage
KR101288602B1 (en) Underpass using precast concrete pile and method for constructing the same
JP6871344B1 (en) Tunnel repair method and repair equipment for existing tunnels
KR101516746B1 (en) Construction method for girder and construction method for underground structure without temporary structure using the same
JP2014015777A (en) Construction method of filling with filler for joint-gap sealing

Legal Events

Date Code Title Description
GRNT Written decision to grant