KR20200110981A - Electric construction work method with high electricity cost reduction through standby power cut-off - Google Patents

Electric construction work method with high electricity cost reduction through standby power cut-off Download PDF

Info

Publication number
KR20200110981A
KR20200110981A KR1020190030600A KR20190030600A KR20200110981A KR 20200110981 A KR20200110981 A KR 20200110981A KR 1020190030600 A KR1020190030600 A KR 1020190030600A KR 20190030600 A KR20190030600 A KR 20190030600A KR 20200110981 A KR20200110981 A KR 20200110981A
Authority
KR
South Korea
Prior art keywords
power supply
power
supply line
cut
independent
Prior art date
Application number
KR1020190030600A
Other languages
Korean (ko)
Inventor
박병수
이선주
Original Assignee
주식회사 탑기획
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 탑기획 filed Critical 주식회사 탑기획
Priority to KR1020190030600A priority Critical patent/KR20200110981A/en
Publication of KR20200110981A publication Critical patent/KR20200110981A/en

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F17/00Vertical ducts; Channels, e.g. for drainage
    • E04F17/08Vertical ducts; Channels, e.g. for drainage for receiving utility lines, e.g. cables, pipes
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01RELECTRICALLY-CONDUCTIVE CONNECTIONS; STRUCTURAL ASSOCIATIONS OF A PLURALITY OF MUTUALLY-INSULATED ELECTRICAL CONNECTING ELEMENTS; COUPLING DEVICES; CURRENT COLLECTORS
    • H01R13/00Details of coupling devices of the kinds covered by groups H01R12/70 or H01R24/00 - H01R33/00
    • H01R13/73Means for mounting coupling parts to apparatus or structures, e.g. to a wall

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The present invention relates to a method for constructing electric work having a high effect of reducing electricity costs through interrupting standby power. According to the present invention, the method for constructing electric work having a high effect of reducing electricity costs through interrupting standby power divides a power supply line installed in a building into a regular power supply line and an interruptible power supply line and separately installs the same, and installs separate power on/off switches between a main power switch connected to the uppermost portion of the interruptible power supply line and an independent area on the interruptible power supply line which is a lower layer of the main power switch, between the independent area and an independent space which is a lower layer of the independent area, and between the independent space and a line terminal unit or an outlet installed at the lowermost portion of the interruptible power supply line. Therefore, if necessary, the power supplied to a device or electronic product connected to the interruptible power supply line can be simply interrupted by operation of the separate power on/off switches, and as a result, the standby power can be interrupted to minimize power waste.

Description

대기전력차단을 통한 전기료 절감 효과가 높은 전기공사 시공방법{Electric construction work method with high electricity cost reduction through standby power cut-off}Electric construction work method with high electricity cost reduction through standby power cut-off}

본 발명은 전기공사 시공방법에 관한 것으로서, 더 상세하게는 필요시에만 전력이 공급되어야 하는 전자제품들 에서 불필요하게 낭비되는 대기전력을 간단한 스위치 조작만으로 차단이 가능한 대기전력 차단이 용이한 전기공 사 시공방법에 관한 것이다.The present invention relates to an electric construction method, and more specifically, electric construction construction that is easy to cut off standby power, which can cut off standby power unnecessarily wasted in electronic products that need to be supplied with power only when necessary, with a simple switch operation. It's about the method.

일반적으로, 가정집이나 사무실 및 공장 등에는 독립 공간별로 상시 전력이 공급되어야 하는 전자제품들과 필요 시에만 전력이 공급되어야 하는 전자제품들이 공존하고 있다. 따라서, 필요시에만 전력이 공급되어야 하는 전자 제품들에 대한 대기 전력을 차단하기 위해서는, 그 해당 전자제품들(즉, 필요시에만 전력공급이 이루어지는 전 자제품들)의 전원코드를 일일이 콘센트에서 뽑아야 한다. 그러나, 이와 같이 전원코드를 때때마다 일일이 콘센 트에서 뽑는 일은 상당히 번거로운 일이며, 현실적으로 제대로 실행하기 어려운 일이다. 따라서 대기전력을 근 본적으로 차단하는데 큰 어려움이 있으며, 그 결과 불필요한 전력이 낭비되는 문제가 있다.In general, in homes, offices, factories, etc., electronic products that must be supplied with power at all times and electronic products that must be supplied with power only when necessary coexist in each independent space. Therefore, in order to cut off standby power for electronic products that need to be supplied only when necessary, the power cords of the corresponding electronic products (ie, electronic products that supply power only when necessary) must be unplugged from the outlet. do. However, it is very cumbersome to unplug the power cord from the power outlet each time, and in reality, it is difficult to perform properly. Therefore, there is a great difficulty in fundamentally blocking standby power, and as a result, unnecessary power is wasted.

본 발명은 상기와 같은 사항을 감안하여 창출된 것으로서, 건물의 신축이나 리모델링 작업 시 전기공사를 시공 함에 있어서, 필요시에만 전력이 공급되어야 하는 전자제품들에서 불필요하게 낭비되는 대기전력을 간단한 스위 치 조작만으로 차단할 수 있도록 하는 대기전력차단을 통한 전기료 절감 효과가 높은 전기공사 시공방법을 제공함에 그 목적이 있다.The present invention was created in consideration of the above, and in the construction of electrical work during new construction or remodeling of a building, a simple switch to reduce standby power unnecessarily wasted in electronic products that must be supplied with power only when necessary. Its purpose is to provide a construction method for electric construction with a high effect of reducing electricity costs by blocking standby power that can be blocked only by operation.

상기의 목적을 달성하기 위하여 본 발명에 따른 대기전력차단을 통한 전기료 절감 효과가 높은 전기공사 시공방법은, 건물의 신축이나 리모델링 작업 시 대기전력 차단이 용이하도록 하는 전기공사 시공방법으로서,In order to achieve the above object, the electric construction construction method having a high electric cost reduction effect through blocking standby power according to the present invention is an electric construction construction method that facilitates blocking standby power during new construction or remodeling of a building,

a) 상기 건물 내에 포설되는 전력공급선을 상시 전력공급선과 차단가능 전력공급선으로 이원화하여 분리 포설하 는 단계;a) dividing the power supply line installed in the building into a regular power supply line and a cut-off power supply line, and separately installing the power supply line;

b) 상기 상시 전력공급선의 최상단부에는 건물 내의 메인 전원스위치를 연결하고, 상기 상시 전력공급선의 최말 단부에는 상시 전력이 공급되어야 하는 장치 또는 전자제품을 연결하기 위한 선로 단말부 또는 콘센트를 설비하 는 단계;b) The main power switch in the building is connected to the uppermost end of the constant power supply line, and a line terminal or outlet for connecting devices or electronic products to which constant power must be supplied is installed at the most end of the constant power supply line. step;

c) 상기 차단가능 전력공급선의 최상단부에는 상기 건물 내의 메인 전원스위치를 연결하고, 상기 차단가능 전력 공급선의 최말단부에는 필요시 전력공급 차단이 가능한 장치 또는 전자제품을 연결하기 위한 선로 단말부 또는 콘센트를 설비하는 단계; 및c) A main power switch in the building is connected to the uppermost end of the cut-off power supply line, and a line terminal or outlet for connecting a device or electronic product capable of shutting off the power supply when necessary. Installing; And

d) 상기 차단가능 전력공급선의 최상단부에 연결된 메인 전원스위치와 메인 전원 스위치의 하위 계층인 상기 차 단가능 전력공급선 상의 독립구역 사이에 별도의 전원 온/오프 스위치를 설비하는 단계를 포함하는 점에 그 특 징이 있다.d) installing a separate power on/off switch between the main power switch connected to the uppermost end of the cut-off power supply line and an independent zone on the cut-off power supply line, which is a lower layer of the main power switch. It has its characteristics.

여기서, 바람직하게는 e) 상기 차단가능 전력공급선 상의 상기 독립구역과 그 독립구역의 하위 계층인 독립공간 사이와, 그 독립공간과 상기 차단가능 전력공급선의 최말단부에 설비된 선로 단말부 또는 콘센트 사이에는 별도 의 전원 온/오프 스위치를 각각 설비하는 단계를 더 포함한다.Here, preferably, e) between the independent area on the blockable power supply line and an independent space that is a lower level of the independent area, and between the independent space and a line terminal or outlet installed at the most end of the blockable power supply line. The step of installing separate power on/off switches, respectively, is further included.

또한, 상기 단계 b)에서의 상시 전력이 공급되어야 하는 장치 또는 전자제품은 방범장치, 냉장고, 컴퓨터 시스 템 서버 등을 포함할 수 있다.In addition, the device or electronic product to be supplied with constant power in step b) may include a security device, a refrigerator, and a computer system server.

또한, 상기 단계 c)에서의 상기 필요시 전력공급 차단이 가능한 장치 또는 전자제품은 개인용 컴퓨터, 복사기, 냉난방기기 등을 포함할 수 있다.In addition, the device or electronic product capable of cutting off the power supply when necessary in step c) may include a personal computer, a photocopier, a cooling and heating device, and the like.

이와 같은 본 발명에 의하면, 건물의 전기공사 시공시 상시 전력공급선과 차단가능 전력공급선을 이원화하여 분 리 포설하고, 차단가능 전력공급선로 상의 메인 전원 스위치와 그 하위의 독립구간 사이, 독립구간과 그 하위의 독립공간 사이 및 독립공간과 최종 말단부 콘센트 사이에 각각 별도의 전원 온/오프 스위치를 설비함으로써, 필 요시 이들 별도의 전원 온/오프 스위치의 조작에 의해 차단가능 전력공급선에 연결되어 있는 장치 또는 전자제 품에 공급되는 전원을 간단히 차단할 수 있다. 이에 따라 대기전력을 쉽고 확실하게 차단시킬 수 있으며, 그 결 과 전력낭비를 최소화할 수 있다.According to the present invention as described above, the power supply line and the cut-off power supply line are divided and installed separately during the electric work of the building, and between the main power switch on the cut-off power supply line and the independent section below it, the independent section and its Separate power on/off switches are provided between independent spaces below and between independent spaces and the final outlet, so that they can be cut off by operating these separate power on/off switches when necessary, or devices connected to power supply lines You can simply cut off the power supplied to the electronic product. Accordingly, standby power can be easily and reliably cut off, and as a result, power waste can be minimized.

도 1은 본 발명에 따른 대기전력차단을 통한 전기료 절감 효과가 높은 전기공사 시공방법에 따라 시공된 전기공사의 개요를 보여주는 도면.
도 2는 본 발명에 따른 대기전력차단을 통한 전기료 절감 효과가 높은 전기공사 시공방법의 실행 과정을 보여주는 흐름도.
1 is a view showing an overview of the electric work constructed according to the electric work construction method having a high effect of reducing electricity costs by blocking standby power according to the present invention.
Figure 2 is a flow chart showing the execution process of the electric construction construction method having a high effect of reducing electricity costs by blocking standby power according to the present invention.

이하 첨부된 도면을 참조하여 본 발명의 실시예를 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1 및 도 2는 본 발명에 따른 대기전력차단을 통한 전기료 절감 효과가 높은 전기공사 시공방법을 나타낸 것으로서, 도 1은 그 시공 방법에 따라 시공된 전기공사의 개요를 보여주는 도면이고, 도 2는 전기공사 시공방법의 실행 과정을 보여주는 흐름도이다.1 and 2 are diagrams showing an electrical construction method having a high effect of reducing electricity costs by blocking standby power according to the present invention, and FIG. 1 is a view showing an outline of an electrical work constructed according to the construction method, and FIG. It is a flow chart showing the execution process of the electrical construction method.

도 1 및 도 2를 참조하면, 본 발명에 따른 대기전력차단을 통한 전기료 절감 효과가 높은 전기공사 시공방법은, 건물의 신축이나 리모 델링 작업 시 대기전력 차단이 용이하도록 하는 전기공사 시공방법으로서, 먼저 상기 건물 내에 포설되는 전력 공급선을 상시 전력공급선(도 1에서 실선으로 표시된 부분, 즉 콘센트A(102)와 연결된 선)과 차단가능 전력공급 선(도 1에서 점선으로 표시된 부분, 즉 콘센트B(103)와 연결된 선)으로 이원화하여 분리 포설한다(단계 S201).Referring to Figures 1 and 2, the electric construction construction method having a high electric cost reduction effect through blocking standby power according to the present invention is an electric construction construction method that facilitates blocking standby power during new construction or remodeling of a building, First, the power supply line installed in the building is a constant power supply line (the part indicated by a solid line in FIG. 1, that is, the line connected to the outlet A102) and a cut-off power supply line (the part indicated by a dotted line in FIG. 1, that is, the outlet B ( 103) and separated and installed (step S201).

그런 후, 상기 상시 전력공급선의 최상단부에는 건물 내의 메인 전원스위치(101)를 연결하고, 상기 상시 전력공 급선의 최말단부에는 상시 전력이 공급되어야 하는 장치 또는 전자제품을 연결하기 위한 선로 단말부 또는 콘센 트(콘센트 A)(102)를 설비한다(단계 S202). 여기서, 상시 전력이 공급되어야 하는 장치 또는 전자제품은 방범장 치, 냉장고, 컴퓨터 시스템 서버 등을 포함할 수 있다.Then, the main power switch 101 in the building is connected to the uppermost end of the constant power supply line, and the line terminal for connecting devices or electronic products to which constant power is to be supplied, or A power outlet (outlet A) 102 is installed (step S202). Here, the device or electronic product to be supplied with power at all times may include a security device, a refrigerator, and a computer system server.

그리고, 상기 차단가능 전력공급선의 최상단부에는 상기 건물 내의 메인 전원 스위치(101)를 연결하고, 상기 차 단가능 전력공급선의 최말단부에는 필요시 전력공급 차단이 가능한 장치 또는 전자제품을 연결하기 위한 선로 단말부 또는 콘센트(콘센트 B)(103)를 설비한다(단계 S203). 여기서, 상기 필요시 전력공급 차단이 가능한 장치 또는 전자제품은 개인용 컴퓨터, 복사기, 냉난방기기 등을 포함할 수 있다.In addition, a main power switch 101 in the building is connected to the uppermost end of the cut-off power supply line, and a line for connecting a device or electronic product capable of cutting off the power supply if necessary at the most end of the cut-off power supply line. A terminal unit or an outlet (outlet B) 103 is provided (step S203). Here, the device or electronic product capable of cutting off the power supply when necessary may include a personal computer, a photocopier, and a cooling/heating device.

또한, 상기 차단가능 전력공급선의 최상단부에 연결된 메인 전원 스위치 (101)와 그 메인 전원 스위치(101)의 하위 계층인 상기 차단가능 전력공급선 상의 독립구역(전원스위치)(104) 사이에 별도의 전원 온/오프 스위치 (106)를 설비한다(단계 S204).In addition, a separate power supply between the main power switch 101 connected to the uppermost end of the cut-off power supply line and an independent zone (power switch) 104 on the cut-off power supply line that is a lower layer of the main power switch 101 An on/off switch 106 is provided (step S204).

그리고, 바람직하게는 상기 차단가능 전력공급선 상의 상기 독립구역(전원스위치)(104)과 그 독립구역(전원스위 치)(104)의 하위 계층인 독립공간(105) 사이와, 그 독립공간(105)과 상기 차단가능 전력공급선의 최말단부에 설 비된 선로 단말부 또는 콘센트(콘센트 B)(103) 사이에는 별도의 전원 온/오프 스위치(107)(108)를 각각 더 설비 한다(단계 S205).And, preferably, between the independent area (power switch) 104 on the cut-off power supply line and the independent space 105 that is a lower layer of the independent area (power switch) 104, and the independent space 105 ) And separate power on/off switches 107 and 108 are further provided between the line terminal or outlet (outlet B) 103 installed at the most end of the cut-off power supply line (step S205).

여기서, 이상과 같은 각 단계들은 반드시 위에서와 같은 순서로 진행되어야 하는 것으로 한정되는 것은 아니다. 즉, 위에서의 각 단계들은 전기공사 시공상의 특정 상황이나 현장의 작업 여건 등에 따라 순서가 서로 바뀌어 진행될 수도 있다.Here, each of the steps as described above is not necessarily limited to being performed in the same order as above. That is, each of the above steps may be performed in a different order depending on a specific situation in the construction of an electrical work or work conditions at the site.

또한, 이상과 같은 일련의 과정 및 설명에 있어서, 상기 독립구역(104)은 예를 들면, 아파트의 1세대, 건물의 입주회사 전체공간 등을 말할 수 있다.In addition, in the series of processes and explanations as described above, the independent zone 104 may refer to, for example, a first generation of an apartment, the entire space of a tenant company of a building, and the like.

또한, 상기 독립공간(105)은 예를 들면, 가정집의 방, 주방, 거실 등과, 회사 내의 단위 사무공간, 공장 내의 단위 작업장 등을 들 수 있다.In addition, the independent space 105 may be, for example, a room of a home, a kitchen, a living room, etc., a unit office space within a company, a unit work place within a factory, and the like.

도 1에서 점선으로 표시된 전기선은 온/오프 스위치(106,107,108)에 의해 전력공급을 임의로 차단할 수 있다. 그리고, 점선에 연결된 콘센트(콘센트 B) (103)에는 전술한 바와 같이, 대기전력을 차단시킬 전자제품(개인용 컴퓨터, 복사기, 냉난방기 등)을 연결한다. 따라서, 사무 공간, 공장 등의 퇴근 시 건물 전체 또는 공간별 온/ 오프 스위치의 오프(off)를 통해 대기전력 차단 대상인 모든 전자제품에 공급되는 전력을 차단시킬 수 있으며, 이에 따라 대기전력을 즉시 차단시킬 수 있다.The electric wire indicated by the dotted line in FIG. 1 can be arbitrarily cut off the power supply by the on/off switches 106, 107, and 108. In addition, electronic products (personal computers, copiers, air conditioners, etc.) to cut off standby power are connected to the outlet (outlet B) 103 connected to the dotted line as described above. Therefore, when the office space, factory, etc. leave the office, the power supplied to all electronic products to be blocked by standby power can be cut off by turning off the entire building or the on/off switch for each space, and accordingly, standby power is immediately cut off. I can make it.

또한, 실선인 전기선에 연결된 콘센트(콘센트 A)(102)에는 전술한 바와 같이, 전기가 상시 공급되어야 하는 전 자제품(서버, 팩스기기, 냉장고, 방범장치 등)을 연결한다. 따라서, 대기전력을 차단하기 위해 온/오프 스위치 (106,107,108)를 오프(off) 시켜도 이들 전자제품에는 관계없이 전력이 공급된다.In addition, as described above, electronic products (servers, fax machines, refrigerators, security devices, etc.) to which electricity must be supplied at all times are connected to the outlet (outlet A) 102 connected to the solid electric line. Therefore, even if the on/off switches 106, 107, and 108 are turned off to cut off standby power, power is supplied regardless of these electronic products.

한편, 건물의 메인 전원 스위치(101)와 독립구역 전원 스위치(104) 사이의 온/오프 스위치(106)와 독립구역 전 원 스위치(104)와 독립공간(105) 사이의 온/오프 스위치(107)에 조명기구를 연결하면 건물 내부, 구역 내부의 조명기구의 대기전력까지 모두 차단할 수 있다.On the other hand, the on/off switch 106 between the main power switch 101 of the building and the power switch 104 in the independent area and the on/off switch 107 between the power switch 104 and the independent space 105 ), you can cut off the standby power of the lighting equipment inside the building and the area.

즉, 가정집에서의 외출 시나, 회사 전체의 퇴근 시에 독립구역의 온/오프 스위치(107) 또는 건물의 온/오프 스 위치(106)를 오프(off) 시킴으로써 집안 내부의 조명기구 포함 모든 대기전력을 한꺼번에 차단할 수 있으며, 이 때 상시 전력이 공급되는 실선에 연결된 방범장치, 냉장고 등에는 이상 없이 전력이 공급된다.That is, all standby power including lighting equipment inside the house by turning off the on/off switch 107 of the independent area or the on/off switch 106 of the building when going out from the house or when the entire company leaves work. The power can be cut off all at once, and at this time, power is supplied to security devices and refrigerators connected to the solid line where power is always supplied.

또한, 공장 등의 작업종료, 휴가 시에 건물의 온/오프 스위치(106)를 오프시킴으로써 공장 내부의 모든 대기전 력을 차단할 수 있고, 특정 단위작업장만 가동시에는 해당 독립구역을 제외한 다른 독립구역의 온/오프 스위치 (107)를 오프시킴으로써 가동 외의 타작업장의 대기전력만 차단시킬수 있다.In addition, all standby power inside the factory can be cut off by turning off the on/off switch 106 of the building at the end of work at the factory or on vacation. When only a specific unit work place is operated, other independent areas excluding the corresponding independent area By turning off the on/off switch 107, only standby power in other workplaces other than the operation can be cut off.

이상의 설명에서와 같이, 본 발명에 따른 대기전력차단을 통한 전기료 절감 효과가 높은 전기공사 시공방법은, 건물의 전기공사 시공 시 상시 전력공급선과 차단가능 전력공급선을 이원화하여 분리 포설하고, 차단가능 전력공급선로 상의 메인 전 원 스위치와 그 하위의 독립구간 사이, 독립구간과 그 하위의 독립공간 사이 및 독립공간과 최종 말단부 콘센트 사이에 각각 별도의 전원 온/오프 스위치를 설비함으로써, 필요시 이들 별도의 전원 온/오프 스위치의 조작에 의해 차단가능 전력공급선에 연결되어 있는 장치 또는 전자제품에 공급되는 전원을 간단히 차단할 수 있다. 이 에 따라 대기전력을 쉽고 확실하게 차단시킬 수 있으며, 그 결과 전력낭비를 최소화할 수 있는 장점이 있다.As described above, the electric construction construction method having a high electric cost reduction effect through the standby power cut-off according to the present invention is to separate and install a regular power supply line and a cut-off power supply line during the electric work construction of a building, and Separate power on/off switches are installed between the main power switch on the supply line and its sub-independent section, between the independent section and its sub-independent space, and between the independent space and the final terminal outlet. Can be cut off by operating the power on/off switch The power supplied to the device or electronic product connected to the power supply line can be simply cut off. Accordingly, standby power can be easily and reliably cut off, and as a result, there is an advantage of minimizing power waste.

이상, 바람직한 실시예를 통하여 본 발명에 관하여 상세히 설명하였으나, 본 발명은 이에 한정되는 것은 아니며, 본 발명의 기술적 사상을 벗어나지 않는 범위 내에서 다양하게 변경, 응용될 수 있음은 당업자에게 자 명하다. 따라서, 본 발명의 진정한 보호 범위는 다음의 청구범위에 의하여 해석되어야 하며, 그와 동등한 범위 내에 있는 모든 기술적 사상은 본 발명의 권리 범위에 포함되는 것으로 해석되어야 할 것이다.As described above, the present invention has been described in detail through preferred embodiments, but the present invention is not limited thereto, and it is apparent to those skilled in the art that various changes and applications can be made without departing from the technical spirit of the present invention. Therefore, the true scope of protection of the present invention should be interpreted by the following claims, and all technical ideas within the scope equivalent thereto should be interpreted as being included in the scope of the present invention.

101 건물 메인 전원 스위치
102 콘센트 A
103 콘센트 B
104 독립구역(전원스위치)
105 독립공간
106,107,108 온/오프 스위치
101 building main power switch
102 outlet A
103 outlet B
104 Independent area (power switch)
105 Independent space
106,107,108 on/off switch

Claims (4)

건물의 신축이나 리모델링 작업 시 대기전력 차단이 용이하도록 하는 전기공사 시공방법으로서,
a) 상기 건물 내에 포설되는 전력공급선을 상시 전력공급선과 차단가능 전력공급선으로 이원화하여 분리 포설하 는 단계;
b) 상기 상시 전력공급선의 최상단부에는 건물 내의 메인 전원스위치를 연결하고, 상기 상시 전력공급선의 최말 단부에는 상시 전력이 공급되어야 하는 장치 또는 전자제품을 연결하기 위한 선로 단말부 또는 콘센트를 설비하 는 단계;
c) 상기 차단가능 전력공급선의 최상단부에는 상기 건물 내의 메인 전원스위치를 연결하고, 상기 차단가능 전력 공급선의 최말단부에는 필요시 전력공급 차단이 가능한 장치 또는 전자제품을 연결하기 위한 선로 단말부 또는 콘센트를 설비하는 단계; 및
d) 상기 차단가능 전력공급선의 최상단부에 연결된 메인 전원스위치와 메인 전원 스위치의 하위 계층인 상기 차 단가능 전력공급선 상의 독립구역 사이에 별도의 전원 온/오프 스위치를 설비하는 단계를 포함하는 대기전력 차 단이 용이한 전기공사 시공방법.
As an electrical construction method that makes it easy to cut off standby power during new construction or remodeling of buildings,
a) dividing the power supply line installed in the building into a regular power supply line and a cut-off power supply line, and separately installing the power supply line;
b) The main power switch in the building is connected to the uppermost end of the constant power supply line, and a line terminal or outlet for connecting devices or electronic products to which constant power must be supplied is installed at the most end of the constant power supply line. step;
c) A main power switch in the building is connected to the uppermost end of the cut-off power supply line, and a line terminal or outlet for connecting a device or electronic product capable of shutting off the power supply when necessary. Installing; And
d) Standby power including the step of installing a separate power on/off switch between the main power switch connected to the uppermost end of the cut-off power supply line and an independent zone on the cut-off power supply line that is a lower layer of the main power switch. Electrical work construction method that is easy to block.
제1항에 있어서,
e) 상기 차단가능 전력공급선 상의 상기 독립구역과 그 독립구역의 하위 계층인 독립공간 사이와, 그 독립공간 과 상기 차단가능 전력공급선의 최말단부에 설비된 선로 단말부 또는 콘센트 사이에는 별도의 전원 온/오프 스 위치를 각각 설비하는 단계를 더 포함하는 대기전력차단을 통한 전기료 절감 효과가 높은 전기공사 시공방법.
The method of claim 1,
e) Separate power on between the independent area on the cut-off power supply line and the independent space that is a lower level of the independent area, and between the independent space and the line terminal or outlet installed at the end of the cut-off power supply line. Electric construction construction method with high effect of reducing electricity costs through standby power cutoff, further comprising installing each of the /off switches.
제1항에 있어서,
상기 단계 b)에서의 상시 전력이 공급되어야 하는 장치 또는 전자제품은 방범장치, 냉장고, 컴퓨터 시스템 서버 중 적어도 하나를 포함하는 대기전력차단을 통한 전기료 절감 효과가 높은 전기공사 시공방법.
The method of claim 1,
The device or electronic product to be supplied with constant power in step b) includes at least one of a security device, a refrigerator, and a computer system server.
제1항에 있어서,
상기 단계 c)에서의 상기 필요시 전력공급 차단이 가능한 장치 또는 전자제품은 개인용 컴퓨터, 복사기, 냉난방 기기 중 적어도 하나를 포함하는 대기전력차단을 통한 전기료 절감 효과가 높은 전기공사 시공방법.
The method of claim 1,
In the step c), the device or electronic product capable of cutting off the power supply when necessary includes at least one of a personal computer, a photocopier, and a cooling/heating device.
KR1020190030600A 2019-03-18 2019-03-18 Electric construction work method with high electricity cost reduction through standby power cut-off KR20200110981A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190030600A KR20200110981A (en) 2019-03-18 2019-03-18 Electric construction work method with high electricity cost reduction through standby power cut-off

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190030600A KR20200110981A (en) 2019-03-18 2019-03-18 Electric construction work method with high electricity cost reduction through standby power cut-off

Publications (1)

Publication Number Publication Date
KR20200110981A true KR20200110981A (en) 2020-09-28

Family

ID=72800941

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190030600A KR20200110981A (en) 2019-03-18 2019-03-18 Electric construction work method with high electricity cost reduction through standby power cut-off

Country Status (1)

Country Link
KR (1) KR20200110981A (en)

Similar Documents

Publication Publication Date Title
US11024474B1 (en) Circuit breakers with integrated safety, control, monitoring, and protection features
US20210164227A1 (en) Modular pre-wired dwelling panel design
JP5260072B2 (en) Air conditioning system and address setting method
KR101137453B1 (en) Improved ventilation system by the unit type in apartment houses
BRPI0808869B1 (en) NEMA SMART OUTLETS AND ASSOCIATED NETWORKS.
US9966206B1 (en) Circuit breakers with integrated safety, control, monitoring, and protection features
US9483067B2 (en) Controlling intelligent powered devices
US11795689B2 (en) Multi-head prefabricated wall panel fire sprinkler
KR20200110981A (en) Electric construction work method with high electricity cost reduction through standby power cut-off
KR20200138619A (en) Electric construction work method with high electricity cost reduction through standby power cut-off
JP6158548B2 (en) Power supply system
KR101296548B1 (en) Execution method for electric works capable of easily breaking standby power
US20220120081A1 (en) Prefabricated multi-conduit building panel design
US20220120082A1 (en) Prefabricated above-door cavity conduit routing
US10270237B2 (en) Interruptible universal wall box and methods of use thereof
JP2015027079A (en) Data transmitter using earth wire
KR20040104282A (en) Outlet connected with wire and switch for saving standby power
KR101048904B1 (en) Power control device for outlets and electrical equipment using power line communication
CN104113445A (en) Device and method of realizing network equipment hard restart
Johnson et al. Module 04: Electrical Plans
JP7502909B2 (en) Air conditioner management device and management method
CN204240560U (en) Indoor unit and casing thereof
Burrough Heat Pump Only as Good As Its Installation
US10362709B2 (en) Vent-free and fan-less preconfigured information networking system
AU2015243116B2 (en) Reduced power consumption in air conditioners