KR20190135591A KR1020180060783A KR20180060783A KR20190135591A KR 20190135591 A KR20190135591 A KR 20190135591A KR 1020180060783 A KR1020180060783 A KR 1020180060783A KR 20180060783 A KR20180060783 A KR 20180060783A KR 20190135591 A KR20190135591 A KR 20190135591A
Authority
KR
South Korea
Prior art keywords
demand
unit
inventory
period
time
Prior art date
Application number
KR1020180060783A
Other languages
Korean (ko)
Other versions
KR102064384B1 (en
Inventor
정동오
박명국
김윤국
강성한
우성수
박한기
우효근
Original Assignee
대한민국(육군참모총장)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 대한민국(육군참모총장) filed Critical 대한민국(육군참모총장)
Priority to KR1020180060783A priority Critical patent/KR102064384B1/en
Publication of KR20190135591A publication Critical patent/KR20190135591A/en
Application granted granted Critical
Publication of KR102064384B1 publication Critical patent/KR102064384B1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/08Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
    • G06Q10/087Inventory or stock management, e.g. order filling, procurement or balancing against orders
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment

Abstract

According to the present invention, a material inventory prediction system comprises: a claim result generation unit to generate claim result data of a material in a preset time unit based on claim details of the material; a consumption result generation unit to generate consumption result data of the material in the preset time unit based on consumption details of the material; a lead time calculation unit to calculate a lead time which is the time from a time of claiming the material to a time of receiving and securing the material; a demand prediction unit to predict a demand of the material by applying a statistical technique to the claim result and consumption result data generated by the claim result generation unit and the consumption result generation unit; a material list selection unit to use information predicted by the demand prediction unit to select a list for inventory prediction; a dissemination day designation unit to indicate a level for securing in advance to maintain as inventory in preparation for a demand expected in the future in a day unit; and an inventory prediction unit to predict the inventory of the material based on the demand of the material calculated by the demand prediction unit, the lead time calculated in the lead time calculation step, and dissemination days. Accordingly, the inventory of the material can be predicted.

Description

자재 재고 예측 시스템 및 이를 이용한 방법{COMPONENTS  DEMAND FORECASTING SYSTEM AND METHOD FOR THEREOF}Material inventory prediction system and method using the same {COMPONENTS DEMAND FORECASTING SYSTEM AND METHOD FOR THEREOF}

본 발명은 자재의 적정한 재고를 유지하기 위한 자재의 재고 예측 시스템 및 이를 이용한 방법으로 보다 구체적으로는 장비의 고장에 대비하여 장비의 정비에 필요한 자재의 보관 및 관리를 용이하게 하기 위해 적정한 재고량을 예측하는 시스템 및 그 방법이다. The present invention is a material inventory prediction system and a method using the same to maintain a proper inventory of the material more specifically predicts the appropriate inventory amount to facilitate the storage and management of materials necessary for the maintenance of the equipment in preparation for the failure of the equipment System and method thereof.

장비의 고장이 발생할 경우 각 편성(정비부대) 및 시설별(창고)로 장비를 정비하기 위해 자재를 재고로 확보하고 있다. 이를 위해서는 충분한 자재를 확보해야 하나 예산 상 제약이 발생하게 되고 현실적으로 재고량이 제한된다. In the event of a failure of the equipment, materials are stocked to maintain the equipment in each organization (maintenance unit) and each facility (warehouse). To do this, sufficient materials must be secured, but budgetary constraints and inventories are limited.

일부 자재의 경우 재고가 고갈되어 적시에 공급하지 못하는 문제가 발생한다. 또한 다른 품목의 경우 자재의 재고를 과다하게 보유하는 문제도 발생한다. Some materials run out of stock and fail to deliver on time. Another problem arises for other items, such as excessive inventory of materials.

이와 같은 문제점이 발생하는 원인은 일정기간 동안 사용할 수리부속에 대한 수요예측 정확도가 부정확하기 때문이다. 따라서 수요예측이 정확하다면 수요예측한 기간이 지나고 나면 남아있는 재고는 없어야 한다. 그러나 장비의 고장은 언제 발생할지 모르는 상황에서 장비고장이 예년에 비해 더 발생했다면 장비는 일정기간 동안(1년) 불가동 상태가 될 것이고 예년에 비해 덜 발생했다면 수리부속은 초과자산이 발생하게 될 것이다. 따라서 장비의 불가동 상태를 예방하기 위하여 미리 확보해야할 예비부품의 목록을 예측하고 예측된 목록을 바탕으로 각 부대별 확보하여야 할 물량을 또한 예측하여야 한다. 하지만 자재의 수요를 예측하는 집계자료는 기존의 자재를 청구한 실적이므로 청구실적에 의한 수요예측의 현실태는 특정품목 청구 후 미사용 품목 과다, 가수요 발생 가능 등 왜곡된 자료를 기반으로 재고를 예측 하므로 재고 과다 예측의 문제점이 발생하고 있다.This problem is caused by the inaccuracy of demand forecasting for repair parts to be used for a certain period of time. Therefore, if the demand forecast is accurate, there should be no inventory remaining after the demand forecast period has passed. However, if the equipment failure occurred more than the previous year in a situation where the failure of the equipment occurred, the equipment would be inactive for a period of time (one year), and if it occurred less than the previous year, the repair parts would have excess assets. will be. Therefore, the list of spare parts to be secured in advance should be predicted to prevent equipment downtime and the quantity to be secured for each unit based on the predicted list. However, since the aggregate data predicting the demand for materials is the result of claiming existing materials, the reality of demand forecasting based on the billing performance predicts inventory based on distorted data such as excessive unused items and the possibility of demand for demand after requesting a specific item. There is a problem with overstock forecasts.

자재의 수요 집계 자료가 왜곡되면 집계 자료를 기반으로 수행하는 수요의 예측값이 왜곡될 것이고, 수요의 예측값을 기반으로 재고를 예측하는 재고예측 또한 왜곡되기 때문에 이러한 문제를 방지하기 위해서는 수요 집계 방식의 개선이 필요하다. If the demand aggregate data of the material is distorted, the forecast of demand based on the aggregate data will be distorted, and the inventory forecast that forecasts the stock based on the forecast of the demand will be distorted. This is necessary.

본 발명이 해결하고자 하는 과제는 자재의 실제 소모 실적과 각 부대에서 청구한 청구 실적을 조합하여 수요의 왜곡이 적은 자료를 바탕으로 자재의 수요예측과 재고량을 예측하는 것이다.The problem to be solved by the present invention is to predict the demand and inventory of the material on the basis of the data less distortion of demand by combining the actual consumption of the material and the billing performance billed from each unit.

본 발명의 일 실시예에 따른 자재 재고 예측 시스템은 자재의 청구 내역을 기반으로 하여 기 설정된 기간 단위로 자재의 청구 실적 자료를 생성하는 청구 실적 생성부, 자재의 소모 내역을 기반으로 하여 기 설정된 기간 단위로 자재의 소모 실적 자료를 생성하는 소모 실적 생성부, 자재를 청구한 시점으로부터 자재를 수령하여 확보한 시점까지의 기간인 소요 기간을 산정하는 소요 기간 산정부, 상기 청구 실적 생성부와 상기 소모 실적 생성부에서 생성한 청구 실적과 소모 실적 자료를 통계적 기법을 적용하여 자재의 수요를 예측하는 수요 예측부 및 상기 수요 예측부에서 산출한 자재의 수요예측값과 상기 소요 기간 산정 단계에서 산정한 소요 기간 및 보급 일수를 기반으로 자재의 재고량을 예측하는 재고 예측부를 포함하는 것을 특징으로 한다. Material inventory prediction system according to an embodiment of the present invention is a billing performance generation unit for generating a billing performance data of the material in a predetermined period unit based on the billing history of the material, a predetermined period based on the consumption history of the material Consumption performance generation unit for generating consumption performance data of the material in units, time period calculation for calculating the period required from the time of claiming the material to the time of receiving and securing the material, the billing performance generation unit and the consumption The demand forecasting unit which predicts the demand of the material by applying a statistical technique to the billing performance and consumption performance data generated by the performance generating unit, and the demand forecasting value of the material calculated by the demand forecasting unit and the required time period calculated in the calculation period And an inventory predicting unit predicting an inventory amount of the material based on the number of days of supply.

본 발명의 다른 실시예에 따른 자재 재고 예측 시스템의 소요 기간 산정부는 예측 대상인 자재의 계약 형태에 따라서 소요 기간을 회계 연도 1월 1일부터 자재를 수령하여 확보한 시점까지의 기간 혹은 자재를 청구한 시점으로부터 자재를 수령하여 확보한 시점 중 하나를 선택하여 산정하는 것을 특징으로 한다.According to another embodiment of the present invention, the calculation period of the material stock prediction system according to the contract type of the material to be predicted claims the period or material from January 1 of the fiscal year to the time when the material is received and secured. It is characterized by selecting and calculating one of the points obtained by receiving the material from the point in time.

본 발명의 다른 실시예에 따른 자재 재고 예측 시스템의 수요 예측부는 상기 수요집계된 자료가 과거실적이 있는지 확인하고, 상기 소요 기간 산정부에서 산정한 소요 기간을 기 설정된 기간과 비교하여, 상기 소요 기간을 기 설정된 기간과 비교한 결과에 따라 기 설정된 기간 단위의 청구 실적과 소모 실적 자료를 조합하고 상기 조합한 청구 실적과 소모 실적을 통계적 기법을 적용하여 자재의 수요를 예측하는 것을 특징으로 한다.The demand forecasting unit of the material inventory prediction system according to another embodiment of the present invention checks whether the demand aggregated data is in the past, and compares the required period calculated by the required period calculation unit with a predetermined period, wherein the required period According to the result of comparing with the predetermined period, characterized in that the billing performance and consumption performance data of the predetermined period unit is combined and the combined billing performance and consumption performance by applying a statistical technique to predict the demand of the material.

본 발명의 다른 실시예에 따른 자재 재고 예측 시스템의 수요 예측부는 과거 청구실적과 소모실적이 있는 경우, 예측을 수행하려는 기간의 회계연도 일수에 해당하는 과거의 청구 실적 자료와 그 이전의 소모 실적 자료를 조합하는 것을 특징으로 한다.If the demand forecasting unit of the material inventory prediction system according to another embodiment of the present invention has past billing performance and consumption performance, the past billing performance data corresponding to the number of days in the fiscal year of the period to be forecasted and the previous consumption data It characterized in that the combination.

본 발명의 다른 실시예에 따른 자재 재고 예측 시스템의 상기 수요 예측부는 과거 사용실적은 있으나, 최근 일정기간 동안 사용실적이 없는 경우, 예측을 수행하려는 기간의 회계연도 일수와 소요기간에 따라 과거의 청구 실적 자료와 그 이전의 소모 실적 자료를 조합하는 것을 특징으로 한다.The demand forecasting unit of the material inventory prediction system according to another embodiment of the present invention has past usage history, but if there is no usage history for a certain period of time, past claims are made according to the number of days and the period of the fiscal year of the period for which the forecast is to be performed It is characterized by combining the performance data and the previous consumption performance data.

본 발명의 다른 실시예에 따른 자재 재고 예측 방법의 재고목록 선정부는 예측 대상인 모든 자재를 대상으로 자재를 예측하는 것이 아니라 필수품목 및 수요집계 자료를 기반으로 누적수요율이 일정 범위 안에(예를 들면, 누적수요율 85%이내)포함되는 품목을 편성 및 시설별로 환경적 요소, 품목별 특성 등을 고려하는 자재 목록 선정부를 더 포함하는 것을 특징으로 한다. The inventory selection unit of the material inventory prediction method according to another embodiment of the present invention does not predict the material for all the materials to be predicted, but the cumulative demand rate is within a certain range based on the required items and the aggregated demand data (for example, It is characterized in that it further includes a material list selection unit that considers the environmental factors, characteristics of each item, and the like to include the items included in the cumulative demand of 85%).

본 발명의 다른 실시예에 따른 자재 재고 예측 방법의 보급일수 지정부는 재고로 확보 운영되어야 할 물량을 계산하기 위한 사전작업으로 며칠분에 해당되는 물량이란 의미로 일수 단위로 부대유형별 보급일수를 지정할 수 있는 보급일수 지정부를 더 포함하는 것을 특징으로 한다. The supply days designation part of the material inventory prediction method according to another embodiment of the present invention may specify the supply days for each incident type in units of days, which means a quantity corresponding to several days as a preliminary operation for calculating the quantity to be secured and operated as inventory. Characterized in that it further comprises a spread day designation.

본 발명의 다른 실시예에 따른 자재 재고 예측 시스템은 상기 재고 예측부에서 예측한 재고 예측량을 수정할 수 있는 재고 예측 수정부를 더 포함하는 것을 특징으로 한다.Material inventory prediction system according to another embodiment of the present invention is characterized in that it further comprises a stock prediction correction unit that can modify the inventory forecast amount predicted by the stock prediction unit.

본 발명의 일 실시예에 따른 자재 재고 예측 방법은 자재의 청구 내역을 기반으로 하여 기 설정된 기간 단위로 자재의 청구 실적 자료를 생성하는 청구 실적 생성 단계, 자재의 소모 내역을 기반으로 하여 기 설정된 기간 단위로 자재의 소모 실적 자료를 생성하는 소모 실적 생성 단계, 자재를 청구한 시점으로부터 자재를 수령하여 확보한 시점까지의 기간인 소요 기간을 산정하는 소요 기간 산정 단계, 상기 청구 실적 생성부와 상기 소모 실적 생성부에서 생성한 청구 실적과 소모 실적 자료를 통계적 기법을 적용하여 자재의 수요를 예측하는 수요 예측 단계, 및 상기 수요 예측 단계에서 산출한 자재의 수요예측값과 상기 소요 기간 산정 단계에서 산정한 소요 기간 및 보급 일수를 기반으로 자재의 재고량을 예측하는 재고 예측 단계를 포함하는 것을 특징으로 한다.Material inventory prediction method according to an embodiment of the present invention is a billing performance generation step of generating a billing performance data of the material in a predetermined period unit based on the billing history of the material, a predetermined period based on the consumption history of the material A consumption history generation step of generating consumption performance data of the material in units, a time period calculation step of calculating a time period that is a period from when the material is claimed to when the material is received and secured, the billing performance generation unit and the consumption The demand calculated in the step of calculating the demand forecast value and the required duration of the demand forecasting step of predicting the demand of the material by applying a statistical technique to the billing performance and consumption performance data generated by the performance generating unit and the demand forecasting step To include an inventory forecasting step that estimates the stock of a material based on periods and days of supply. It features.

본 발명의 다른 실시예에 따른 자재 재고 예측 방법의 소요 기간 산정 단계는 예측 대상인 자재의 계약 형태에 따라서 소요 기간을 회계 연도 1월 1일부터 자재를 수령하여 확보한 시점까지의 기간 혹은 자재를 청구한 시점으로부터 자재를 수령하여 확보한 시점 중 하나를 선택하여 산정하는 것을 특징으로 한다.According to another embodiment of the present invention, the step of calculating the required time period of the material stock prediction method claims a period or material from January 1 of the fiscal year to the time when the required time is obtained according to the contract type of the material to be predicted. It is characterized by selecting and calculating one of the points of time when the material is received and secured from a point in time.

본 발명의 다른 실시예에 따른 자재 재고 예측 방법의 수요 예측 단계는 상기 수요집계된 자료가 과거실적이 있는지 확인하는 단계 및 상기 소요 기간 산정단계에서 산정한 소요 기간을 기 설정된 기간과 비교하는 단계, 상기 소요 기간을 기 설정된 기간과 비교하는 단계를 수행한 결과에 따라 기 설정된 기간 단위의 청구 실적과 소모 실적 자료를 조합하는 단계 및 상기 조합한 청구 실적과 소모 실적을 통계적 기법을 적용하여 자재의 수요를 예측하는 단계를 포함하는 것을 특징으로 한다. In the demand forecasting step of the material inventory prediction method according to another embodiment of the present invention, the step of confirming whether the aggregated data is historically performed and comparing the required periods calculated in the required periods calculation step with a preset period, Combining the billing performance and consumption performance data of a predetermined period unit according to a result of comparing the required period with the preset period, and applying the statistical technique to the combined billing performance and consumption performance It characterized in that it comprises a step of predicting.

본 발명의 다른 실시예에 따른 자재 재고 예측 방법은 상기 청구 실적과 소모 실적을 조합하는 단계는 예측을 수행하려는 시점으로부터 수 개의 청구 실적 혹은 소모 실적 자료를 조합하되, 과거 청구실적과 소모실적이 있는 경우, 예측을 수행하려는 기간의 회계연도 일수에 과거의 청구 실적 자료와 그 이전의 소모 실적 자료를 조합하는 것을 특징으로 한다. In the material inventory prediction method according to another embodiment of the present invention, in the step of combining the billing performance and the consumption performance, the billing performance or the consumption performance data may be combined from the time point at which the prediction is to be performed. In this case, the past billing performance data and the previous consumption data are combined with the fiscal day days of the period in which the forecast is to be performed.

본 발명의 다른 실시예에 따른 자재 재고 예측 방법은 상기 청구 실적과 소모 실적을 조합하는 단계는 예측을 수행하려는 시점으로부터 수 개의 청구 실적 혹은 소모 실적 자료를 조합하되, 과거 사용실적은 있으나, 최근 일정기간 동안 사용실적이 없는 경우, 예측을 수행하려는 기간의 회계연도 일수와 소요기간에 따라 예측을 수행하려는 시점으로부터 기 설정된 기간 이전에 해당하는 과거의 청구 실적 자료와 그 이전의 소모 실적 자료를 조합하는 것을 특징으로 한다.In the material inventory prediction method according to another embodiment of the present invention, the step of combining the billing performance and the consumption performance combines several billing performance or consumption performance data from the time point at which the prediction is to be performed, but there are past usage records, but recent schedules If there is no historical performance during the period, the historical billing performance data for the period during which the forecast is to be performed and the previous consumption performance data for the period prior to the preset period from the point at which the forecast is to be performed are combined. It is characterized by.

본 발명의 다른 실시예에 따른 자재 재고 예측 방법의 재고목록 선정단계는 예측 대상인 모든 자재를 대상으로 자재를 예측하는 것이 아니라 필수품목 및 수요집계 자료를 기반으로 누적수요율이 일정 범위 안에(예를 들면, 누적수요율 85%이내)포함되는 품목을 편성 및 시설별로 환경적 요소, 품목별 특성 등을 고려하는 자재 목록 선정단계를 더 포함하는 것을 특징으로 한다. In the inventory selection step of the material inventory prediction method according to another embodiment of the present invention, the cumulative demand rate is not within a certain range (for example, based on essential items and aggregated demand data) instead of predicting the material for all the materials to be predicted. It includes the step of selecting a list of materials to consider the environmental factors, the characteristics of each item, etc. to organize the items included, cumulative demand within 85%).

본 발명의 다른 실시예에 따른 자재 재고 예측 방법의 보급일수 지정단계는 재고로 확보 운영되어야 할 물량을 계산하기 위한 사전작업으로 며칠분에 해당되는 물량이란 의미로 일수 단위로 부대유형별 보급일수를 지정할 수 있는 보급일수 지정 단계를 더 포함하는 것을 특징으로 한다. The supply days designation step of the material inventory prediction method according to another embodiment of the present invention is a preliminary operation for calculating the quantity to be secured and operated as the inventory, which means that the number of days of supply per unit type is specified in units of days. Characterized in that it further comprises the step of designating the number of dissemination days.

본 발명의 다른 실시예에 따른 자재 재고 예측 방법은 상기 재고 예측 단계에서 예측한 재고 예측량을 수정할 수 있는 재고 예측 수정 단계를 더 포함하는 것을 특징으로 한다.Material inventory prediction method according to another embodiment of the present invention is characterized in that it further comprises a stock forecast correction step that can modify the inventory forecast amount predicted in the inventory prediction step.

본 발명은 자재의 소모 실적과 청구 실적을 조합하여 수요를 집계함으로써 수요예측 및 재고 예측의 정확도를 향상시켜 장비의 가동률을 유지하는데 기여하는 효과를 제공할 수 있다. The present invention can provide the effect of contributing to maintaining the utilization rate of the equipment by improving the accuracy of demand prediction and inventory forecasting by combining demand consumption and billing performance of materials.

도 1은 본 발명의 일 실시예에 따른 자재 재고 예측 시스템의 구성도이다.
도 2는 본 발명의 일 실시예에 따른 자재 재고 예측 방법의 순서도이다.
도 3은 본 발명의 일 실시예에 따른 자재 재고 예측 방법 중 소요 기간 산정 단계의 순서도이다.
도 4는 본 발명의 일 실시예에 따른 자재 재고 예측 방법 중 수요 예측 단계의 순서도이다.
1 is a block diagram of a material inventory prediction system according to an embodiment of the present invention.
2 is a flow chart of a material inventory prediction method according to an embodiment of the present invention.
Figure 3 is a flow chart of the required period calculation step of the material inventory prediction method according to an embodiment of the present invention.
Figure 4 is a flow chart of the demand forecasting step of the material inventory prediction method according to an embodiment of the present invention.

이하, 첨부된 도면을 참조하여 본 발명(present invention)을 설명한다. 본 발명은 다양한 변경을 가할 수 있고 여러 가지 실시예를 가질 수 있는 바, 특정 실시예들이 도면에 예시되고 관련된 상세한 설명이 기재되어 있다. 그러나, 이는 본 발명을 특정한 실시 형태에 대해 한정하려는 것이 아니며, 본 발명의 사상 및 기술 범위에 포함되는 모든 변경 및/또는 균등물 내지 대체물을 포함하는 것으로 이해되어야 한다. 도면의 설명과 관련하여, 유사한 구성요소에 대해서는 유사한 참조 부호가 사용되었다. 본 발명 가운데 사용될 수 있는 “포함한다” 또는 “포함할 수 있다” 등의 표현은 발명된 해당 기능, 동작 또는 구성요소 등의 존재를 가리키며, 추가적인 하나 이상의 기능, 동작 또는 구성요소 등을 제한하지 않는다. 또한, 본 발명에서, "포함하다" 또는 "가지다" 등의 용어는 명세서상에 기재된 특징, 숫자, 단계, 동작, 구성요소, 부품 또는 이들을 조합한 것이 존재함을 지정하려는 것이지, 하나 또는 그 이상의 다른 특징들이나 숫자, 단계, 동작, 구성요소, 부품 또는 이들을 조합한 것들의 존재 또는 부가 가능성을 미리 배제하지 않는 것으로 이해되어야 한다. 본 발명의 다양한 실시예는 “또는” 등의 표현은 함께 나열된 단어들의 어떠한, 그리고 모든 조합을 포함 할 수 있다. 예를 들어, “A 또는 B”는, A를 포함할 수도, B를 포함할 수도, 또는 A 와 B 모두를 포함할 수도 있다. 본 발명 가운데 “제 1,”“제2,”“첫째,”또는“둘째,”등의 표현들이 본 발명의 다양한 구성요소들을 수식할 수 있지만, 해당 구성요소들을 한정하지 않는다. 예를 들어, 상기 표현들은 해당 구성요소들의 순서 및/또는 중요도 등을 한정하지 않는다. 상기 표현들은 한 구성요소를 다른 구성요소와 구분 짓기 위해 사용될 수 있다. 예를 들어, 제1 사용자 기기와 제 2 사용자 기기는 모두 사용자 기기이며, 서로 다른 사용자 기기를 나타낸다. 예를 들어, 본 발명의 권리 범위를 벗어나지 않으면서 제1 구성요소는 제2 구성요소로 명명될 수 있고, 유사하게 제2 구성요소도 제1 구성요소로 명명될 수 있다. 어떤 구성요소가 다른 구성요소에 "연결되어" 있다거나 "접속되어" 있다고 언급된 때에는, 그 다른 구성요소에 직접적으로 연결되어 있거나 또는 접속되어 있을 수도 있지만, 중간에 다른 구성요소가 존재할 수도 있다고 이해되어야 할 것이다. 반면에, 어떤 구성요소가 다른 구성요소에 "직접 연결되어" 있다거나 "직접 접속되어" 있다고 언급된 때에는, 중간에 다른 구성요소가 존재하지 않는 것으로 이해될 수 있어야 할 것이다. 본 발명의 다양한 실시예는 사용한 용어는 단지 특정한 실시예를 설명하기 위해 사용된 것으로, 본 발명의 다양한 실시예를 한정하려는 의도가 아니다. 단수의 표현은 문맥상 명백하게 다르게 뜻하지 않는 한, 복수의 표현을 포함 할 수 있다. 다르게 정의되지 않는 한, 기술적이거나 과학적인 용어를 포함해서 여기서 사용되는 모든 용어들은 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자에 의해 일반적으로 이해되는 것과 동일한 의미를 가지고 있다. 일반적으로 사용되는 사전에 정의되어 있는 것과 같은 용어들은 관련 기술의 문맥 상 가지는 의미와 일치하는 의미를 가지는 것으로 해석되어야 하며, 본 발명의 다양한 실시예는 명백하게 정의하지 않는 한, 이상적이거나 과도하게 형식적인 의미로 해석되지 않는다.Hereinafter, the present invention will be described with reference to the accompanying drawings. As the invention allows for various changes and numerous embodiments, particular embodiments will be illustrated in the drawings and described in detail. However, this is not intended to limit the present invention to specific embodiments, it should be understood to include all modifications and / or equivalents and substitutes included in the spirit and scope of the present invention. In the description of the drawings, similar reference numerals are used for similar elements. The expression "comprise" or "comprise" and the like that can be used in the present invention indicates the existence of the corresponding function, operation, or component invented, and does not limit the additional one or more functions, operations or components, and the like. . In addition, in the present invention, the terms "comprise" or "have" are intended to indicate that there is a feature, number, step, operation, component, part, or combination thereof described in the specification, and one or more. It is to be understood that it does not exclude in advance the possibility of the presence or addition of other features or numbers, steps, operations, components, components or combinations thereof. Various embodiments of the present invention may include any and all combinations of words listed together, such as "or". For example, "A or B" may include A, may include B, or may include both A and B. Expressions such as "first," "second," "first," or "second," etc. in the present invention may modify various elements of the present invention, but do not limit the corresponding elements. For example, the above expressions do not limit the order and / or importance of the corresponding elements. The expressions may be used to distinguish one component from another. For example, both a first user device and a second user device are user devices and represent different user devices. For example, without departing from the scope of the present invention, the first component may be referred to as the second component, and similarly, the second component may also be referred to as the first component. When a component is said to be "connected" or "connected" to another component, it may be directly connected to or connected to that other component, but it may be understood that another component may be present in the middle. Should be. On the other hand, when a component is referred to as being "directly connected" or "directly connected" to another component, it should be understood that there is no other component in between. Various embodiments of the present invention are used to describe specific embodiments only, and are not intended to limit the various embodiments of the present invention. Singular expressions may include plural expressions unless the context clearly indicates otherwise. Unless defined otherwise, all terms used herein, including technical or scientific terms, have the same meaning as commonly understood by one of ordinary skill in the art. Terms such as those defined in the commonly used dictionaries should be construed as having meanings consistent with the meanings in the context of the related art, and various embodiments of the invention, unless expressly defined, are ideal or overly formal It is not interpreted in the sense.

도 1은 본 발명의 일 실시예에 따른 자재 재고 예측 시스템의 구성도이다. 본 발명의 일 실시예에 따른 자재 재고 예측 시스템은 제어부, 데이터베이스부 및 통신부를 포함할 수 있다.1 is a block diagram of a material inventory prediction system according to an embodiment of the present invention. Material inventory prediction system according to an embodiment of the present invention may include a control unit, a database unit and a communication unit.

자재 재고 예측 시스템의 데이터베이스부는 예측 대상 자재에 관한 정보가 기록되어 있을 수 있다. 구체적으로 데이터베이스부에는 각 자재의 청구 내역, 소모 내역, 조달 형태, 소요 기간, 보급 일수, 단가 등에 관한 정보가 기록될 수 있다.The database unit of the material inventory prediction system may record information about the material to be predicted. In detail, the database unit may record information on billing history, consumption history, procurement type, required period, supply days, and unit price of each material.

일반적으로 장비가 고장 났을 경우 장비를 운용하는 부대에서 자재를 소모하여 장비를 수리한다. 각 부대는 정비에 필요한 자재를 보유하고 있는 경우 상기 자재를 소모하여 장비를 수리할 수 있으며, 그러하지 않을 경우 상급 부대에 상기 자재를 요구하는 정비지시서를 작성하여 청구할 수 있다. 그 외에도 각 부대에서 보유하고 있는 자재가 시간이 경과함에 따라 노후화하여 교체가 필요한 경우가 있다. 이러한 경우 각 부대는 상급 부대에 교체에 필요한 자재를 청구할 수 있다. In general, when equipment breaks down, the unit operating the equipment consumes the material and repairs the equipment. Each unit may repair the equipment by consuming the material if it has the necessary materials for maintenance. Otherwise, the unit may prepare and claim a maintenance instruction requesting the material. In addition, materials held by each unit may age and require replacement. In such cases, each unit may bill the superior unit for the materials needed for replacement.

각 부대에서 장비 등을 수리하거나 교체하기 위해 상급 부대 등에 자재를 청구한 내역이 청구 내역이다. The billing details are the details of each unit's request for materials to a senior unit to repair or replace equipment.

각 부대에서 자재를 소모하여 수리하거나 자재를 교체하여 기존 자재를 소모한 내역을 소모 내역이라 한다. The consumption of materials used by each unit for repair or replacement of materials is consumed.

상기 청구 내역과 소모 내역은 자재별로 데이터베이스부에 기록될 수 있다. The billing history and consumption history may be recorded in the database unit for each material.

자재 재고 예측 시스템의 제어부는 데이터베이스부로부터 자료를 수신하여 자재의 수요량 및 재고량을 예측할 수 있다. 도 1을 참조하면 상기 제어부는 청구 실적 생성부, 소모 실적 생성부, 소요 기간 산정부, 수요 예측부, 재고 예측부 및 재고 예측 수정부를 포함할 수 있다. The control unit of the material inventory prediction system may receive data from the database unit to predict the demand and inventory of the material. Referring to FIG. 1, the controller may include a billing performance generation unit, a consumption performance generation unit, a time period calculation unit, a demand forecasting unit, a stock prediction unit, and a stock prediction correction unit.

청구 실적 생성부는 데이터베이스부에 기록된 예측 대상 자재의 청구 내역을 일정 기간 단위로 분류할 수 있다. 또한 청구 실적 생성부는 상기 분류된 청구 내역을 기반으로 예측 대상 자재의 청구 실적 자료를 생성하는 청구 실적 생성단계를 수행할 수 있다. 본 발명의 일 실시예에 따르면 청구 실적 생성부는 데이터베이스부에 기록된 상기 청구 내역을 바탕으로 자재별 청구 실적을 월 단위 혹은 연 단위로 청구 실적을 집계할 수 있다. The billing performance generation unit may classify the billing details of the predicted material recorded in the database unit in a predetermined period. In addition, the billing history generation unit may perform a billing history generation step of generating billing history data of the predicted material based on the classified billing details. According to an exemplary embodiment of the present invention, the billing performance generation unit may aggregate billing performance on a monthly or annual basis based on the billing history recorded in the database.

소모 실적 생성부는 데이터베이스부에 기록된 예측 대상 자재의 소모 내역을 일정 기간 단위로 분류할 수 있다. 또한 소모 실적 생성부는 상기 분류된 소모 내역을 기반으로 예측 대상 자재의 소모 실적 자료를 생성하는 소모 실적 생성 단계를 수행할 수 있다. 본 발명의 일 실시예에 따르면 소모 실적 생성부는 데이터베이스부에 기록된 상기 소모 내역의 정보를 바탕으로 자재별 소모 실적을 월 단위 혹은 연 단위로 소모 실적을 집계할 수 있다. The consumption history generation unit may classify the consumption history of the predicted material recorded in the database unit in a predetermined period. In addition, the consumption history generation unit may perform a consumption history generation step of generating consumption history data of the material to be predicted based on the classified consumption history. According to an embodiment of the present invention, the consumption history generation unit may calculate the consumption history by material or monthly consumption based on the consumption history information recorded in the database unit.

소요 기간 산정부는 예측 대상 자재를 청구한 시점으로부터 상기 자재를 수령하여 확보한 시점까지의 기간인 소요 기간을 산정하는 소요 기간 산정단계를 수행할 수 있다. The required period calculation unit may perform a required period calculation step of calculating a required period, which is a period from the time of claiming the predicted material to the time of receiving and securing the material.

도 3은 본 발명의 일 실시예에 따른 자재 재고 예측 방법 중 소요 기간 산정 단계의 순서도이다. 상기 소요 기간 산정부는 예측 대상 자재의 조달 형태에 따라 소요 기간을 산정할 수 있다.Figure 3 is a flow chart of the required period calculation step of the material inventory prediction method according to an embodiment of the present invention. The required time calculation unit may calculate the required time period according to the procurement type of the material to be predicted.

상기 자재의 조달 형태로는 방위사업청에서 조달하는 중앙 조달 방식, 각 부대에서 조달하는 부대 조달 방식, 국외조달의 일반 경쟁계약을 통한 상업 확정 방식, 수량과 가격 및 인도 예정일을 명시하는 지정 발주 방식, 불규칙한 자재에 대하여 소요 발생 시 수시로 청구하는 한도액 계약 방식, 품목별 연간 소요 물량을 일괄적으로 계약하여 수시로 청구하는 총괄 구매 방식, 조달청에서 조달하는 조달청 계약 방식 등이 있을 수 있다. As the procurement form of the above materials, the central procurement method procured by the National Defense Agency, the unit procurement method procured by each unit, the commercial confirmation method through the general competitive contract of foreign procurement, the designated order method specifying the quantity and price, and the scheduled delivery date For example, there may be a limit contract method, which is often billed for irregular materials, a general purchase method that is often billed by collectively contracting annual requirements for each item, and a Procurement Agency contract method procured by the Public Procurement Service.

본 발명의 일 실시예에 따르면 상기 소요 기간 산정부는 데이터베이스부로부터 예측 대상 자재의 조달 형태에 관한 정보를 불러올 수 있다. 상기 소요 기간 산정부는 상기 자재의 조달 형태에 따라 소요 기간의 기산일을 다르게 설정할 수 있다. According to an embodiment of the present invention, the required period calculating unit may retrieve information regarding a procurement type of the predicted material from the database unit. The calculation period calculation period may set the date of calculation of the required period differently depending on the type of procurement of the material.

예측 대상 자재의 조달 형태가 중앙 조달, 부대 조달, 상업 확정, 지정 발주 방식 중 하나인 경우 소요 기간 산정부는 예측 대상 자재의 소요 기간의 기산일을 회계 연도의 1월 1일로 설정할 수 있다. 소요 기간 산정부는 상기 기산일로부터 상기 자재가 납품된 날짜까지의 기간을 소요 기간으로 산정할 수 있다. If the procurement type of the forecasted material is one of the following methods: central procurement, incidental procurement, commercial confirmation, or designated order, the lead period calculation may set the expected date of the required period of the forecasted material to be January 1 of the fiscal year. The required calculation period may calculate the period from the date of the calculation to the date the material is delivered as the required period.

예측 대상 자재의 조달 형태가 한도액 계약, 총괄 구매, 조달청 계약 방식 중 하나인 경우 소요 기간 산정부는 예측 대상 자재의 소요 기간의 기산일을 예측 대상 자재의 청구일로 설정할 수 있다. 소요 기간 산정부는 상기 기산일로부터 상기 자재가 납품된 날짜까지의 기간을 소요 기간으로 산정할 수 있다. If the procurement type of the predicted material is one of the following methods: limit contract, general purchase, and procurement agency contract, the calculation period may set the date of calculation of the required period of the predicted material as the billing date of the predicted material. The required calculation period may calculate the period from the date of the calculation to the date the material is delivered as the required period.

상기 제어부는 소요 기간 산정 단계에서 산정된 소요 기간을 데이터베이스부에 기록할 수 있다. The controller may record the required duration calculated in the required duration calculation step in the database unit.

수요 예측부는 상기 청구 실적 생성부에서 생성한 청구 실적자료를 통계적 기법을 적용하여 예측 대상 자재의 수요를 예측하는 수요 예측 단계를 수행할 수 있다. The demand forecaster may perform a demand forecasting step of predicting the demand of the material to be predicted by applying a statistical technique to the billing performance data generated by the billing performance generator.

수요 예측부는 상기 소모 실적 생성부에서 생성한 소모 실적자료를 통계적 기법을 적용하여 예측 대상 자재의 수요를 예측하는 수요 예측 단계를 수행할 수 있다. The demand prediction unit may perform a demand prediction step of predicting the demand of the material to be predicted by applying a statistical technique to the consumption performance data generated by the consumption performance generation unit.

수요 예측부는 상기 청구 실적 생성부와 상기 소모 실적 생성부에서 생성한 청구 실적과 소모 실적 자료를 조합한 후 상기 조합된 자료를 통계적 기법을 적용하여 예측 대상 자재의 수요를 예측하는 수요 예측 단계를 수행할 수 있다. The demand prediction unit combines the billing performance generated by the billing performance generating unit and the consumption history generating unit with the consumption performance data, and then performs a demand forecasting step of predicting the demand of the material to be predicted by applying a statistical technique to the combined data. can do.

도 4는 본 발명의 일 실시예에 따른 자재 재고 예측 방법 중 수요 예측 단계의 순서도이다. 도 4를 참고한 본 발명의 일 실시예에 따른 자재의 재고 예측 시스템 상의 수요 예측부는 소요 기간 산정부에서 산정한 소요 기간에 따라 청구 실적과 소모 실적 자료를 조합하는 단계와 상기 조합된 청구 실적과 소모 실적을 통계적 기법을 적용하는 단계를 수행할 수 있다. 예측 대상 자재의 소요 기간 동안에는 실제 수요가 소모 실적에 반영되지 않기 때문에 상기 소요 기간을 기준으로 청구 실적과 소모 실적을 조합할 수 있다.Figure 4 is a flow chart of the demand forecasting step of the material inventory prediction method according to an embodiment of the present invention. The demand forecasting unit on the material inventory forecasting system according to an embodiment of the present invention with reference to FIG. 4 includes the steps of combining billing performance and consumption performance data according to the time period calculated by the calculation period. Steps to apply statistical techniques to consumption performance can be performed. Since the actual demand is not reflected in the consumption performance during the required period of the material to be predicted, the billing performance and the consumption performance can be combined based on the required period.

본 발명의 일 실시예에 따르면, 청구실적과 소모실적을 조합하여 최적의 수요를 예측할 수 있다. 예를 들어, 상기 수요집계된 5개년의 자료를 기반으로 수요를 예측할 경우 최근 1개년은 청구실적으로 4개년은 소모실적을 조합하여 수요를 예측할 수 있다.According to an embodiment of the present invention, the optimal demand can be predicted by combining the billing performance and the consumption performance. For example, when the demand is predicted based on the data collected for the five years, the demand may be predicted by combining the consumption performance of the last one year and the four years.

본 발명의 일 실시예에 따르면, 과거 사용실적이 있으나, 최근 일정기간 동안 사용실적이 없는 예측 대상 자재의 소요 기간이 회계연도 일수(1년 365)를 초과하지 않으면 수요 예측부는 예측을 수행하려는 시점으로부터의 상기 자재의 최근 2개년의 청구 실적과 그 이전 3개년의 소모 실적을 조합할 수 있다.According to an embodiment of the present invention, the demand forecasting unit is a point in time when the demand forecasting unit attempts to perform the forecast if the required period of the material to be used in the past for a certain period does not exceed the number of days in the fiscal year (365 a year). The billing performance of the material from the last two years and the consumption history of the previous three years can be combined.

예측 대상 자재의 소요 기간이 365일(1년) 이하인 경우, 최근 2개년의 소모 실적은 최근 발생한 소요를 반영하지 않기 때문에, 이 경우 통제기간 포함 최근 2개년의 청구 실적이 보다 유효한 정보가 된다.If the forecast period is less than 365 days (one year), the consumption performance of the last two years does not reflect the recent occurrence, so in this case, the billing performance of the last two years, including the control period, becomes more valid information.

본 발명의 일 실시예에 따르면, 과거 사용실적이 있으나, 최근 일정기간 동안 사용실적이 없는 예측 대상 자재의 소요 기간이 회계연도 일수보다 크고 다음연도 회계연도 일수보다 작을 경우 수요 예측부는 예측을 수행하려는 시점으로부터의 상기 자재의 최근 3개년의 청구 실적과 그 이전 2개년의 소모 실적을 조합할 수 있다.According to an embodiment of the present invention, the demand forecasting unit attempts to perform a forecast when the required period of the target material for which the past use record is used, but the use record for the past period has been larger than the fiscal year days and less than the next fiscal year days. The billing performance of the last three years of the material from the point in time can be combined with the consumption performance of the previous two years.

예측 대상 자재의 소요 기간이 1년 이상 2년 이하인 경우, 최근 3개년의 소모 실적은 최근 발생한 소요를 반영하지 않기 때문에, 이 경우 통제기간 포함 최근 3개년의 청구 실적이 보다 유효한 정보가 된다.If the required period of the predicted material is 1 year or more and 2 years or less, since the consumption performance of the last three years does not reflect the recent occurrence, the billing performance of the last three years including the control period becomes more effective information.

본 발명의 일 실시예에 따르면, 과거 사용실적이 있으나, 최근 일정기간 동안 사용실적이 없는 예측 대상 자재의 소요 기간이 다음연도 회계연도 일수(2년 730)를 초과하는 경우 수요 예측부는 예측을 수행하려는 시점으로부터의 상기 자재의 최근 4개년의 청구 실적과 그 이전 1개년의 소모 실적을 조합할 수 있다.According to an embodiment of the present invention, the demand forecasting unit performs prediction when the required period of the predicted material having a past use history but no use history for the latest period exceeds the number of days of the next fiscal year (two years 730). It is possible to combine the billing performance of the last four years of the material from the point in time to the consumption history of the previous one year.

예측 대상 자재의 소요 기간이 730일(2년)을 초과하는 경우, 최근 4개년의 소모 실적은 최근 발생한 소요를 반영하지 않기 때문에, 이 경우 통제기간 포함 최근 4개년의 청구 실적이 보다 유효한 정보가 된다.If the forecasted material's lead-time exceeds 730 days (two years), the last four years' consumption does not reflect the recent occurrence, so in this case, the billing performance of the last four years, including the control period, is more effective. do.

예측 대상 자재의 청구 실적과 소모 실적을 조합하는 방식은 상기 실시예에 한정되는 것이 아니며 품목별 특성에 맞게 다양한 방법으로 조합하는 것이 가능하다. 또한 과거 청구실적과 소모실적이 없는 경우는 청구실적만으로 수요를 예측할 수 있으며 그 외 소모실적 만으로도 수요를 예측할 수 있다.The method of combining the billing performance and the consumption performance of the predicted material is not limited to the above embodiment, and may be combined in various ways according to the characteristics of each item. In addition, if there is no past charges and consumption, only demand can be used to predict demand.

수요 예측부는 상기 청구 실적과 소모 실적의 조합 자료를 이용하여 향후 예측 대상 자재의 수요를 예측하는 단계를 수행할 수 있다. 수요 예측부는 통계적 기법을 활용하여 상기 소모 실적과 청구 실적이 조합된 자료를 시계열적으로 분석할 수 있다. The demand prediction unit may perform a step of predicting the demand of the future target material using the combination of the billing performance and the consumption performance. The demand forecaster may analyze the data combining the consumption performance and the billing performance in time series using a statistical technique.

본 발명의 일 실시예에 따른 수요 예측 단계과정은 다음과 같다. The demand forecasting step process according to an embodiment of the present invention is as follows.

자재의 수요 예측을 실시하기 위하여 수요 예측부는 기존의 소모 실적과 최근 청구 실적이 조합된 자료 등을 활용할 수 있다. 수요 예측부는 통계적 기법을 적용하여 추세선을 산출할 수 있다. 수요 예측부는 상기 추세선을 활용하여 예측 대상 자재의 수요를 예측할 수 있다. In order to perform a demand forecast of the material, the demand forecasting unit may utilize data including a combination of existing consumption performance and recent billing performance. The demand forecaster may calculate a trend line by applying statistical techniques. The demand prediction unit may predict the demand of the material to be predicted by using the trend line.

상기 수요 예측부는 수요 예측 단계를 수행할 때 산술평균법, 이동평균법, 최소자승법, ARIMA 등의 통계적 기법을 활용할 수 있다. 그 외의 통상의 기술자에게 용이한 통계적 기법을 적용하는 것 역시 가능하다. The demand forecaster may use statistical techniques such as arithmetic mean, moving average, least squares, and ARIMA when performing the demand forecasting step. It is also possible to apply statistical techniques that are easy for the skilled person.

수요 예측부는 수요 예측 단계를 수행할 때 상기 예측된 수요예측 결과를 바탕으로 어떤 기법을 적용하여 수요를 예측한 것이 최적의 예측치인지를 자동 선정하여 제공할 수 있다. 구체적으로 수요의 점을 연결한 수요선을 통하여 추세선을 구하고 추세선의 기울기 값을 분석하고 수요선과 편차를 검토하여 수요 예측의 최적의 통계기법을 제공할 수 있다. When the demand forecaster performs the demand forecasting step, the demand forecaster may automatically select and provide a method of predicting demand based on the predicted demand forecasting result. Specifically, it is possible to provide an optimal statistical technique for demand forecasting by obtaining trend lines, analyzing slope values of trend lines, and examining demand lines and deviations through demand lines connecting demand points.

예를 들어 상기 수요 예측부는 추세선의 기울기가 +- 1 이내이면 산술평균법을 적용할 수 있으며, 최소자승법 적용 결과 예측치가 -값인 경우 이동평균법을 적용할 수 있다. 상기 수요 예측부는 추세선의 기울기가 +- 1을 초과하며 편차가 +- 0.2 이내이면 최소자승법을 적용하며 그 외는 이동평균법을 적용할 수 있다. 수요 예측부는 위와 같은 방식으로 통계량을 분석하여 최적의 수요예측 결과를 제공할 수 있다.For example, the demand forecaster may apply an arithmetic mean method when the slope of the trend line is within + −1, and may apply a moving average method when the predicted value is -value as a result of applying the least square method. The demand forecasting unit may apply a least square method when the slope of the trend line exceeds + −1 and the deviation is within + −0.2, and may apply a moving average method. The demand forecaster can provide the optimal demand forecasting results by analyzing statistics in the same way.

상기 통계적 기법을 선택하는 기준 및 방식은 위 예시에 한정되지 아니한다는 것은 자명할 것이다. It will be apparent that the criteria and method of selecting the statistical technique are not limited to the above examples.

자재목록 선정부는 ASL/PL선정(Authorized Stockage List 인가저장품목 / Prescribed Load 규정 휴대량)을 통해 정비부대 및 시설부대에 저장하도록 인가한 인가저장 목록상의 품목으로써 각급 보급부대에서 현 보급을 지속하고 장차 예측되는 소요를 충당하기 위하여 향상 저장 유지하도록 인가된 보급품 목록으로, 편성 및 시설부대에서 목록을 선정할 수 있다. The list of materials selected by the ASL / PL (Authorized Stockage List Authorized Storage Items / Prescribed Load Regulation Carrying Volume) is stored on maintenance and facility units. As a list of supplies approved to maintain, store, and upgrade to meet the requirements, the list may be selected by the organization and facility.

자재목록 선정부의 ASL/PL목록선정은, 재고로 확보해야 할 품목을 선정하기 위한 작업으로, 상기 청구실적 생성부, 소모실적 생성부, 조합하여 수요집계된 자료를 기반으로 일정기간동안 수요가 있었던 품목을 선택하여 각 부대별 ASL/PL목록을 선정 할 수 있고, 선정되지 않은 기타 품목을 비인가저장품목(Non Authorized Storge List)이라 할 수 있다. The ASL / PL list selection of the material list selector is a task for selecting items to be secured in stock, and has been in demand for a certain period of time based on the data gathered and demanded by the claim record generation unit and the consumption record generation unit. ASL / PL list for each unit can be selected by selecting items, and other items that are not selected can be referred to as Non Authorized Storge List.

자재목록 선정부는 데이터베이스부에 기록된 예측 대상 자재의 수요집계된 내역을 기반으로 일정 기간 단위로 선정할 수 있다. 또한 자재목록 선정부는 상기 집계된 수요집계 내역을 기반으로 예측 대상 자재의 자재목록를 생성하는 자재 목록 선정단계를 수행할 수 있다. 본 발명의 일 실시예에 따르면 자재목록 생성부는 데이터베이스부에 기록된 상기 수요집계된 자료를 바탕으로 자재별 목록을 연 단위로 선정할 수 있다. The material list selection unit may select the unit based on the demand aggregated details of the predicted materials recorded in the database unit for a predetermined period. In addition, the material list selection unit may perform a material list selection step of generating a material list of the material to be predicted based on the aggregated demand aggregate details. According to an embodiment of the present invention, the material list generation unit may select a material list on a yearly basis based on the demand aggregated data recorded in the database unit.

보급 일수 지정부는 각 부대 유형별로 향후 예상되는 수요에 대비하여 사전에 확보하여 재고로 유지하도록 하는 수준을 일단위로 나타낸 것이다. The number of days of supply designation indicates the level of day-by-day unit for each unit type to secure in advance in preparation for anticipated demand.

보급일수 지정부는 데이터베이스부에 기록된 부대별 유형에 따라 일정 기간 단위로 변경 적용할 수 있다. 또한 보급일수 지정부는 상기 지정된 보급일수를 기반으로 예측대상 자재의 보급일수를 선정하는 보급일수 지정단계를 포함할 수 있다.The day of supply designation may be changed and applied in units of a certain period according to the types of units recorded in the database. In addition, the supply day designation unit may include a supply day designation step of selecting a supply day of the predicted material based on the specified supply day.

본 발명의 일 실시예에 따르면 보급일수 지정부는 데이터베이스부에 기록된 상기 보급일수를 정책적인 판단에 의거 변경할 수 있다.  According to an embodiment of the present invention, the spreading day designation unit may change the spreading day recorded in the database unit based on a policy decision.

상기 보급 일수는 수송 지연 시에도 재고고갈 없이 계속적으로 운영하기 위한 안전 수준(Safety Level, SL), 정상적인 여건 하에서 일정 기간 동안 추가적으로 수령하지 않아도 운영을 지속할 수 있는 운영 수준(Operation Level, OL), 청구를 수행한 날로부터 분배가 가능할 때까지 경과된 시간적 간격인 발주 및 수송 시간(Order and Shipping Time, OST), 현재의 운영을 지속하고 향후 예상되는 수요를 충족하기 위하여 보유하고 있거나 발주 중에 있는 수량인 청구 목표(Requisitioning Objective, RO) 등으로 구분할 수 있다. 상기 보급 일수는 자재를 확보하는 시설의 유형에 따라 서로 상이하게 설정할 수 있다. 보급일수는 예를 들면 대분배 계통(최상위 시설 창고)의 운영수준 일수를 30으로 지정할 수 있고, 소분배 계통(대분배 계통을 제외한 편성 및 시설창고)의 부대 유형에 따라 안전수준 일수를 0 등으로 지정할 수 있고, 운영수준 일수를 10내지 30 등으로 지정할 수 있으며, 발주 및 수송 일수는 10 내지 15 등으로 지정할 수 있다. The number of supply days is a safety level (SL) for continuous operation without inventory depletion even in case of delay in transportation, an operation level (OL) that can continue to operate without additional receipt for a certain period of time under normal conditions, Order and Shipping Time (OST), which is the time interval elapsed from the date the claim is issued until distribution is possible, the quantity held or ordered to continue current operations and to meet future anticipated demand. It can be divided into Requisitioning Objective (RO), etc. The replenishment days may be set differently from each other depending on the type of facility for securing the material. The number of days of dissemination can be specified as 30 operating level days of a large distribution system (top-level facility warehouse), and 0 days of safety level depending on the type of units in a small distribution system (organization and facility warehouse except large distribution system). The number of days of operation can be specified as 10 to 30, and the ordering and transport days can be specified as 10 to 15.

상기 지정된 보급일수를 기반으로 부대별 품목별로 SL, OL, OST를 각각 계산하고 RO는 SL, OL. OST의 합으로 계산되는 재고를 예측할 수 있다.The SL, OL, and OST are calculated for each item on the basis of the specified supply days, and RO is SL, OL. Predict the inventory that is calculated as the sum of the OSTs.

보급일수를 지정하는 방식은 상기 실시예에 한정되는 것이 아니며 부대별 유형에 따라 다양한 방법으로 지정하는 것이 가능하다. The manner of designating the day of dissemination is not limited to the above embodiment and may be specified in various ways according to the type of each unit.

상기 보급 일수는 각 자재별로 데이터베이스부에 기록될 수 있다. The replenishment days may be recorded in the database for each material.

재고 예측부는 상기 수요 예측부에서 산출한 자재의 수요와 상기 소요 기간 산정 단계에서 산정한 예측 대상 자재의 소요 기간 및 보급일수 지정부에서 지정된 예측대상 자재의 보급일수를 기반으로 자재의 재고량을 예측하는 재고 예측 단계를 수행할 수 있다. The inventory forecasting unit predicts the stock quantity of the material based on the demand of the material calculated by the demand forecasting unit and the required supply period of the predicted material specified by the required period of the target material and the supplying date designation calculated in the required period calculating step. Inventory forecasting steps can be performed.

재고 예측 단계는 상기 수요 예측 단계에서 산출한 자재의 수요와 상기 소요 기간 산정 단계에서 산정한 소요 기간 및 보급일수 지정단계에서 지정된 보급 일수를 기반으로 자재의 재고량을 예측할 수 있다.The inventory forecasting step may predict the inventory of the material based on the demand of the material calculated in the demand forecasting step and the supply days specified in the designation of the required period and the supplying date calculated in the required period calculating step.

제어부는 데이터베이스부로부터 수요 예측값, 소요 기간, 보급 일수 등의 정보를 입력받을 수 있고 상기 재고 예측부는 상기 입력 받은 정보를 이용하여 자재의 재고 예측을 수행할 수 있다.The control unit may receive information such as a demand prediction value, a required period, and supply days from a database unit, and the inventory prediction unit may perform inventory prediction of materials using the received information.

본 발명의 일 실시예 따르면 재고 예측부는 다음 수식을 이용하여 대분계 계통(최상위 시설 창고)에 해당하는 예측 대상 자재의 청구목표(

Figure pat00001
) 재고량을 예측할 수 있다. According to an embodiment of the present invention, the inventory prediction unit uses the following equation to calculate the billing target of the material to be predicted corresponding to the grand system system (top-level facility warehouse) (
Figure pat00001
) Inventory can be estimated.

Figure pat00002
Figure pat00002

(

Figure pat00003
: 부대,
Figure pat00004
: 자재,
Figure pat00005
:
Figure pat00006
: 부대
Figure pat00007
자재에 대한 연간수요량(수요예측), (
Figure pat00003
: army unit,
Figure pat00004
: material,
Figure pat00005
:
Figure pat00006
: army unit
Figure pat00007
Annual demand for materials (demand forecast),

Figure pat00008
: 안전수준 일수,
Figure pat00009
: 소요 기간 일수)
Figure pat00008
: Days of safety level,
Figure pat00009
: Days required)

위 수식은 상기 자재목록 선정부에서 선정된 목록을 대상으로 일정기간 동안 상기 수요예측부에서 예측된 예측값인 연간 수요량 값에 상기 보급일수 지정부의 안전수준 일수 및 상기 소요기간 산정부에서 산정한 소요기간 일수를 고려해서 일정기간 동안 필요한 자재의 전체 재고량을 예측하기 위한 수식이다.The above formula is calculated based on the safety level days of the supply days designation part and the required period calculation period for the annual demand value, which is a forecast value predicted by the demand forecasting part, for the list selected by the material list selecting part. It is a formula for estimating the total inventory of materials needed for a certain period in consideration of the number of days.

본 발명의 일 실시예 따르면 재고 예측부는 다음 수식을 이용하여 소분계 계통(대분배 계통을 제외한 편성 및 시설창고)에 해당하는 예측 대상 자재의 안전수준(

Figure pat00010
) 재고량을 예측할 수 있다. According to an embodiment of the present invention, the inventory prediction unit uses the following formula to determine the safety level of the predicted material corresponding to the subdivision system (organization and facility warehouse except the large distribution system) (
Figure pat00010
) Inventory can be estimated.

Figure pat00011
Figure pat00011

(

Figure pat00012
: 부대,
Figure pat00013
: 자재,
Figure pat00014
:
Figure pat00015
부대
Figure pat00016
자재에 대한 연간수요량(수요예측), (
Figure pat00012
: army unit,
Figure pat00013
: material,
Figure pat00014
:
Figure pat00015
army unit
Figure pat00016
Annual demand (demand forecast) for the material,

Figure pat00017
:
Figure pat00018
부대 안전수준 일수)
Figure pat00017
:
Figure pat00018
Unit safety level days)

위 수식은 상기 자재목록 선정부에서 선정된 목록을 대상으로 일정기간 동안 소분배 계통(편성 및 시설창고)의 각 부대별 품목별 상기 수요예측부에서 예측된 예측값인 연간 수요량 값에 상기 보급일수 지정부의 안전수준일수 값을 고려해서 재고량을 예측하기 위한 수식이다. The above formula is the supply day designation part in the annual demand value value, which is a forecast value predicted by the demand forecasting part for each unit of the small distribution system (organization and facility warehouse) for a certain period for the list selected by the material list selecting part. Is a formula for estimating the inventory level considering the safety level days value.

본 발명의 일 실시예 따르면 재고 예측부는 다음 수식을 이용하여 소분계 계통(대분배 계통을 제외한 편성 및 시설창고)에 해당하는 예측 대상 자재의 운영수준(

Figure pat00019
) 재고량을 예측할 수 있다. According to an embodiment of the present invention, the inventory prediction unit uses the following formula to operate the predicted materials corresponding to the subdivision system (organization and facility warehouse except the large distribution system) (
Figure pat00019
) Inventory can be estimated.

Figure pat00020
Figure pat00020

(

Figure pat00021
: 부대,
Figure pat00022
: 자재,
Figure pat00023
:
Figure pat00024
부대
Figure pat00025
자재에 대한 연간수요량(수요예측), (
Figure pat00021
: army unit,
Figure pat00022
: material,
Figure pat00023
:
Figure pat00024
army unit
Figure pat00025
Annual demand for materials (demand forecast),

Figure pat00026
:
Figure pat00027
부대 운영수준 일수)
Figure pat00026
:
Figure pat00027
Unit operating level days)

위 수식은 상기 자재목록 선정부에서 선정된 목록을 대상으로 일정기간 동안 소분배 계통(편성 및 시설창고)의 각 부대별 품목별 상기 수요예측부에서 예측된 예측값인 연간 수요량 값에 상기 보급일수 지정부의 운영수준일수 값을 고려해서 재고량을 예측하기 위한 수식이다. The above formula is the supply day designation part in the annual demand value value, which is a forecast value predicted by the demand forecasting part for each unit of the small distribution system (organization and facility warehouse) for a certain period for the list selected by the material list selecting part. The formula for estimating the inventory level by considering the operating level days value of.

본 발명의 일 실시예 따르면 재고 예측부는 다음 수식을 이용하여 소분계 계통(대분배 계통을 제외한 편성 및 시설창고)에 해당하는 예측 대상 자재의 발주 및 수송시간(

Figure pat00028
) 재고량을 예측할 수 있다.According to an embodiment of the present invention, the stock predicting unit orders and transports time of the predicted material corresponding to the subdivision system (organization and facility warehouse except the large distribution system) using the following formula (
Figure pat00028
) Inventory can be estimated.

Figure pat00029
Figure pat00029

(

Figure pat00030
: 부대,
Figure pat00031
: 자재,
Figure pat00032
:
Figure pat00033
부대
Figure pat00034
자재에 대한 연간수요량(수요예측), (
Figure pat00030
: army unit,
Figure pat00031
: material,
Figure pat00032
:
Figure pat00033
army unit
Figure pat00034
Annual demand for materials (demand forecast),

Figure pat00035
:
Figure pat00036
부대 발주 및 수송시간 일수)
Figure pat00035
:
Figure pat00036
Unit ordering and transport time days)

위 수식은 상기 자재목록 선정부에서 선정된 목록을 대상으로 일정기간 동안 소분배 계통(편성 및 시설창고)의 각 부대별 품목별 상기 수요예측부에서 예측된 예측값인 연간 수요량 값에 상기 보급일수 지정부의 발주 및 수송시간 일수 값을 고려해서 재고량을 예측하기 위한 수식이다.The above formula is the supply day designation part in the annual demand value value, which is a forecast value predicted by the demand forecasting part for each unit of the small distribution system (organization and facility warehouse) for a certain period for the list selected by the material list selecting part. Is a formula for estimating inventory considering the ordering and transit time days.

본 발명의 일 실시예 따르면 재고 예측부는 다음 수식을 이용하여 소분계 계통(대분배 계통을 제외한 편성 및 시설창고)에 해당하는 예측 대상 자재의 청구목표(

Figure pat00037
) 재고량을 예측할 수 있다. According to an embodiment of the present invention, the inventory prediction unit uses the following formula to calculate the billing target of the target material corresponding to the subdivision system (organization and facility warehouse except the large distribution system)
Figure pat00037
) Inventory can be estimated.

Figure pat00038
Figure pat00038

위 수식은 상기 자재목록 선정부에서 선정된 목록을 대상으로 일정기간 동안 소분배 계통(편성 및 시설창고)의 각 부대별 품목별 상기 재고예측된 안전수준, 운영수준, 발주 및 수송시간 수량을 합한 값으로 최종 목표 재고예측 수량이다. The above formula is the sum of the estimated safety level, operation level, ordering and transport time quantity for each item of each sub-distribution system (organization and facility warehouse) for a certain period for the list selected by the material list selector. This is the final target inventory forecast quantity.

재고 예측부는 데이터베이스부로부터 자재의 재고를 보관하기 위한 편성 및 시설별 보급 일수 정보를 불러올 수 있으며, 이를 이용하여 각 편성 및 시설별 재고량을 산출할 수 있다. Inventory forecasting unit can retrieve the information on the organization and facility days to store the inventory of the material from the database unit, it can be used to calculate the inventory for each organization and facility.

상기 제어부는 상기 재고 예측량을 데이터베이스부에 저장할 수 있다.The controller may store the inventory forecast amount in a database unit.

재고 예측 수정부는 상기 재고 예측부에서 산출한 재고 예측량을 수정하는 재고 예측 수정 단계를 수행할 수 있다. The inventory prediction correction unit may perform an inventory prediction correction step of correcting the inventory prediction amount calculated by the inventory prediction unit.

재고 예측 수정부는 상기 재고 예측 단계에서 예측한 재고 예측량을 추가하거나 수정할 수 있다. 상기 재고 예측 수정 단계상에서 재고 예측 수정부는 안전 수준, 운영 수준, 발주 및 수송 시간 및 청구 목표 등의 정보를 수정할 수 있다.The inventory forecast correcting unit may add or modify the inventory forecast amount predicted in the inventory forecasting step. In the inventory prediction correction step, the inventory prediction correction unit may modify information such as safety level, operation level, ordering and transportation time, and billing target.

재고 예측 수정부는 예측 대상 자재를 보관할 시설이 추가될 경우 해당 시설을 추가하여 예측 대상 자재의 재고 예측량을 수정할 수 있다. 재고 예측 수정부는 예측 대상 자재를 보관할 시설이 폐쇄된 경우 해당 시설을 삭제하여 예측 대상 자재의 재고량을 수정할 수 있다. 또한 예측 대상 자재의 관리를 전환할 필요가 있는 경우 재고 예측 수정부는 각 시설별 재고 예측량을 수정할 수 있다. The inventory forecast correction unit may modify the inventory forecast amount of the forecasted material by adding the facility when additional facilities to store the forecasted material are added. The inventory forecast correction unit may modify the inventory of the forecast material by deleting the facility when the facility to store the forecast material is closed. In addition, if it is necessary to switch the management of the material to be predicted, the inventory forecast correction unit may modify the inventory forecast for each facility.

재고 예측 수정부는 수정 사항을 입력받으면, 그에 따라 재고 예측 단계를 다시 수행하여 수정된 재고 예측량을 산출할 수 있다.When the inventory prediction correction unit receives the correction, the inventory prediction step may be performed accordingly to calculate the revised inventory forecast amount.

본 발명에 따른 자재 재고 예측 방법 및 시스템은 다양한 디바이스를 통하여 수행될 수 있는 프로그램 명령 형태로 구현되어 디바이스 판독 가능 매체에 기록될 수 있다. 상기 디바이스 판독 가능 매체는 프로그램 명령, 데이터 파일, 데이터 구조 등을 단독으로 또는 조합하여 포함할 수 있다. 상기 매체에 기록되는 프로그램 명령은 본 발명을 위하여 특별히 설계되고 구성된 것들이거나 소프트웨어 당업자에게 공지되어 사용 가능한 것일 수도 있다. 디바이스 판독 가능 기록 매체의 예에는 하드 디스크, 플로피 디스크 및 자기 테이프와 같은 자기 매체(magnetic media), CD-ROM, DVD와 같은 광기록 매체(optical media), 플롭티컬 디스크(floptical disk)와 같은 자기-광 매체(magneto-optical media), 및 롬(ROM), 램(RAM), 플래시 메모리 등과 같은 프로그램 명령을 저장하고 수행하도록 특별히 구성된 하드웨어 장치가 포함된다. 프로그램 명령의 예에는 컴파일러에 의해 만들어지는 것과 같은 기계어 코드뿐만 아니라 인터프리터 등을 사용해서 컴퓨터에 의해서 실행될 수 있는 고급 언어 코드를 포함한다. 상기된 하드웨어 장치는 본 발명의 동작을 수행하기 위해 하나 이상의 소프트웨어 모듈로서 작동하도록 구성될 수 있으며, 그 역도 마찬가지이다.Material inventory prediction method and system according to the present invention can be implemented in the form of program instructions that can be executed through a variety of devices can be recorded on the device readable medium. The device readable medium may include program commands, data files, data structures, and the like, alone or in combination. Program instructions recorded on the media may be those specially designed and constructed for the present invention, or they may be of the kind well-known and available to those having skill in the software arts. Examples of device-readable recording media include magnetic media such as hard disks, floppy disks, and magnetic tape, optical media such as CD-ROMs, DVDs, and magnetic disks such as floppy disks. Magneto-optical media, and hardware devices specifically configured to store and execute program instructions, such as ROM, RAM, flash memory, and the like. Examples of program instructions include not only machine code generated by a compiler, but also high-level language code that can be executed by a computer using an interpreter or the like. The hardware device described above may be configured to operate as one or more software modules to perform the operations of the present invention, and vice versa.

100 - 자재 재고 예측 시스템
110 - 제어부
111 - 청구 실적 생성부
112 - 소모 실적 생성부
113 - 소요 기간 산정부
114 - 수요 예측부
115 - 재고 예측부
116 - 자재 목록 선정부
117 - 보급 일수 지정부
118 - 재고 예측 수정부
120 - 데이터베이스부
130 - 통신부
211 - 청구 실적 생성 단계
212 - 소모 실적 생성 단계
213 - 소요 기간 산정 단계
214 - 수요 예측 단계
215 - 재고 예측 단계
216 - 자재 목록 선정 단계
217 - 보급 일수 지정 단계
218 - 재고 예측 수정 단계
100-Material Stock Prediction System
110-control unit
111-Billing Performance Generator
112-Consumption Performance Generator
113-Lead Time
114-demand forecast
115-Inventory Prediction
116-Material List Selection
117-Supply Days Assignment
118-Inventory prediction correction
120-Database
130-Communications Department
211-Generate billing performance step
212-Stage consumption generation
213-Estimated lead time step
214-Demand forecasting stage
215-Inventory forecast step
216-Material List Selection Step
217-Stages of Supply Days
218-Modify inventory forecast step

Claims (11)

자재의 청구 내역을 기반으로 하여 기 설정된 기간 단위로 자재의 청구 실적 자료를 생성하는 청구 실적 생성부;
자재의 소모 내역을 기반으로 하여 기 설정된 기간 단위로 자재의 소모 실적 자료를 생성하는 소모 실적 생성부;
자재를 청구한 시점부터 자재를 수령하여 확보한 시점까지의 기간인 소요 기간을 산정하는 소요 기간 산정부;
상기 소요 기간에 따라 기 설정된 기간 단위의 청구 실적과 소모 실적 자료를 조합하고 상기 조합한 청구 실적과 소모 실적을 통계적 기법을 적용하여 자재의 수요를 예측하는 수요 예측부; 및
상기 수요 예측부에서 산출한 자재의 수요와 상기 소요 기간 산정부에서 산정한 소요 기간 및 보급 일수를 기반으로 자재의 재고량을 예측하는 재고 예측부;를 포함하는 것을 특징으로 하는 자재 재고 예측 시스템
A billing performance generation unit for generating billing performance data of materials on a predetermined period basis based on billing details of materials;
A consumption history generation unit configured to generate consumption history data of the material on a predetermined period basis based on the consumption history of the material;
A calculation period for calculating a time period from the time of claiming the material to the time of receiving and securing the material;
A demand prediction unit for combining the billing performance and consumption performance data of a predetermined period unit according to the required period and predicting the demand of materials by applying a statistical technique to the combined billing performance and consumption performance; And
And a stock forecasting unit predicting a stock amount of the material based on the demand of the material calculated by the demand forecasting unit and the required period and supply days calculated by the required period calculating unit.
제 1항에 있어서,
상기 소요 기간 산정부는 예측 대상인 자재의 계약 형태에 따라서 소요 기간을 회계 연도 1월 1일부터 자재를 수령하여 확보한 시점까지의 기간 혹은 자재를 청구한 시점으로부터 자재를 수령하여 확보한 시점 중 하나를 선택하여 산정하는 것을 특징으로 하는 자재 재고 예측 시스템
The method of claim 1,
According to the contract type of the material to be predicted, the required period calculation period shall determine whether the required period is from January 1, fiscal year until the receipt of the material, or when the material is received from the point of claiming the material. Material inventory prediction system, characterized in that the selection and calculation
제 1항에 있어서,
상기 자재의 수요집계를 기반으로 재고예측 목록을 선정하기 위한 자재 목록선정부;를 더 포함하는 것을 특징으로 하는 자재 재고 예측 시스템
The method of claim 1,
Material inventory prediction system further comprises; a material inventory selection for selecting a inventory prediction list based on the demand aggregate of the material
제 1항에 있어서,
상기 자재의 향후 예상되는 수요에 대비하여 편성 및 시설별로 사전에 확보하여 재고로 유지하도록 일단위로 인가 지시된 보급일수 지정부; 를 더 포함하는 것을 특징으로 하는 자재 재고 예측 시스템
The method of claim 1,
A supply day designation unit instructed on a daily basis so as to secure in advance for each organization and facility in preparation for future expected demand of the material; Material inventory prediction system further comprises a
제 1항에 있어서,
상기 재고 예측부에서 예측한 재고 예측량을 수정할 수 있는 재고 예측 수정부를 더 포함하는 것을 특징으로 하는 자재 재고 예측 시스템
The method of claim 1,
Material inventory prediction system further comprises a stock forecast correction unit for modifying the inventory forecast amount predicted by the stock prediction unit
자재의 청구 내역을 기반으로 하여 기 설정된 기간 단위로 자재의 청구 실적 자료를 생성하는 청구 실적 생성 단계;
자재의 소모 내역을 기반으로 하여 기 설정된 기간 단위로 자재의 소모 실적 자료를 생성하는 소모 실적 생성 단계;
자재를 청구한 시점부터 자재를 수령하여 확보한 시점까지의 기간인 소요 기간을 산정하는 소요 기간 산정 단계;
상기 소요 기간에 따라 기 설정된 기간 단위의 청구 실적과 소모 실적 자료를 조합하고, 상기 조합한 청구 실적과 소모 실적을 통계적 기법을 적용하여 자재의 수요를 예측하는 수요 예측 단계; 및
상기 수요 예측 단계에서 산출한 자재의 수요와 상기 소요 기간 산정 단계에서 산정한 소요 기간 및 보급 일수를 기반으로 자재의 재고량을 예측하는 재고 예측 단계;를 포함하는 것을 특징으로 하는 자재 재고 예측 방법
A billing performance generation step of generating billing performance data of the material on a predetermined period basis based on the billing history of the material;
A consumption history generation step of generating consumption history data of the material on a predetermined period basis based on the consumption history of the material;
Calculating a time period for calculating a time period from the time of claiming the material to the time of receiving and securing the material;
A demand prediction step of combining billing performance and consumption performance data of a predetermined period based on the required period, and predicting demand of materials by applying a statistical technique to the combined billing performance and consumption performance; And
And a stock forecasting step of predicting a stock amount of the material based on the demand of the material calculated in the demand forecasting step and the required period and the supply days calculated in the required period calculating step.
제 6항에 있어서,
상기 소요 기간 산정 단계는 예측 대상인 자재의 계약 형태에 따라서 소요 기간을 회계 연도 1월 1일부터 자재를 수령하여 확보한 시점까지의 기간 혹은 자재를 청구한 시점으로부터 자재를 수령하여 확보한 시점 중 하나를 선택하여 산정하는 것을 특징으로 하는 자재 재고 예측 방법
The method of claim 6,
The calculation of the required time period may include one of the time periods from the first January of the fiscal year to the time of receipt of the material or the time of receipt of the material from the time of claiming the material according to the contract type of the material to be predicted. Material inventory prediction method, characterized in that the calculation by selecting
제 6항에 있어서,
상기 자재의 수요집계를 기반으로 재고예측 목록을 선정하기 위한 자재 목록 선정 단계;를 더 포함하는 것을 특징으로 하는 자재 재고 예측 방법
The method of claim 6,
Material inventory selection method for selecting a inventory forecast list based on the demand aggregate of the material; material stock prediction method further comprising
제 6항에 있어서,
상기 자재의 향후 예상되는 수요에 대비하여 편성 및 시설별로 사전에 확보하여 재고로 유지하도록 일단위로 인가 지시된 보급일수 지정 단계; 를 더 포함하는 것을 특징으로 하는 자재 재고 예측 방법
The method of claim 6,
A supply day designation step instructed on a daily basis so as to secure in advance for each organization and facility in preparation for future expected demand of the material; Material inventory prediction method further comprises a
제 6항에 있어서,
상기 재고 예측 단계에서 예측한 재고 예측량을 수정할 수 있는 재고 예측 수정 단계를 더 포함하는 것을 특징으로 하는 자재 재고 예측 방법
The method of claim 6,
The stock forecasting method further comprises a stock forecast correcting step of modifying the stock forecast amount predicted in the stock forecasting step.
제 6항 내지 제 10항 중 어느 한 항의 방법을 실행하기 위한 프로그램이 기록되어 있는 것을 특징으로 하는 디바이스에서 판독 가능한 기록 매체
A recording medium readable by a device, characterized in that a program for executing the method of any one of claims 6 to 10 is recorded.
KR1020180060783A 2018-05-29 2018-05-29 Components demand forecasting system and method for thereof KR102064384B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020180060783A KR102064384B1 (en) 2018-05-29 2018-05-29 Components demand forecasting system and method for thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020180060783A KR102064384B1 (en) 2018-05-29 2018-05-29 Components demand forecasting system and method for thereof

Publications (2)

Publication Number Publication Date
KR20190135591A true KR20190135591A (en) 2019-12-09
KR102064384B1 KR102064384B1 (en) 2020-01-09

Family

ID=68837766

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020180060783A KR102064384B1 (en) 2018-05-29 2018-05-29 Components demand forecasting system and method for thereof

Country Status (1)

Country Link
KR (1) KR102064384B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113919687A (en) * 2021-10-08 2022-01-11 国网江苏省电力有限公司镇江供电分公司 Electric energy metering material inventory distribution method

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102401677B1 (en) 2021-06-16 2022-06-29 황현승 Construction material management system
KR102554580B1 (en) 2023-04-19 2023-07-12 뉴통 주식회사 Method, device and system for providing order alarm serveice and estimating safety inventory in warehouse through pattern analysis of order history regarding distribustion of food materials and subsidiary materials based on artificial intelligence model

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015108976A (en) * 2013-12-04 2015-06-11 三菱重工業株式会社 Part ordering assist system and part ordering assist method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113919687A (en) * 2021-10-08 2022-01-11 国网江苏省电力有限公司镇江供电分公司 Electric energy metering material inventory distribution method
CN113919687B (en) * 2021-10-08 2024-03-08 国网江苏省电力有限公司镇江供电分公司 Electric energy metering material stock distribution method

Also Published As

Publication number Publication date
KR102064384B1 (en) 2020-01-09

Similar Documents

Publication Publication Date Title
Li et al. Enhancement of supply chain resilience through inter-echelon information sharing
US11093893B2 (en) Apparatus and method of maintaining accurate perpetual inventory information
Jin et al. Planning performance based contracts considering reliability and uncertain system usage
US7921061B2 (en) System and method for simultaneous price optimization and asset allocation to maximize manufacturing profits
US7418307B2 (en) System and process for supply management for the assembly of expensive products
US6415195B1 (en) Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
US7921030B1 (en) Profit optimization system for supply chains with limited parts availability
Cohen et al. Achieving breakthrough service delivery through dynamic asset deployment strategies
van Jaarsveld et al. Improving spare parts inventory control at a repair shop
Kusumastuti et al. Redesigning closed-loop service network at a computer manufacturer: A case study
KR102064384B1 (en) Components demand forecasting system and method for thereof
US20070299748A1 (en) System and method for analyzing service loss within a rotable supply chain
Barros et al. A systematic literature review about dimensioning safety stock under uncertainties and risks in the procurement process
JP4023101B2 (en) Electricity supply and demand control method and apparatus
Qin et al. Repairable spare parts provisioning for multiregional expanding fleets of equipment under performance-based contracting
US20100076806A1 (en) Inventory management tool using a criticality measure
Driessen et al. Maintenance spare parts planning and control: A framework for control and agenda for future research
KR101995832B1 (en) Repair parts demand forecasting system and method for thereof
US20100049587A1 (en) System and Method for Using Lifecycle Telecommunications Expense Management (TEM) Data to Predict the Outcome of Changes to Telecommunications Infrastructure
Rafke et al. Simulating fleet procurement in an Indonesian logistics company
US6397118B1 (en) Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
US20090299806A1 (en) Method and apparatus for demand and/or skill hedging
Mo et al. Revamping NetApp’s service parts operations by process optimization
US7783533B1 (en) System and method for entity selection optimization
Jing et al. A Risk‐based Approach to Managing Performance‐based Maintenance Contracts

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right