KR20190050342A - Construction method for concrete piles - Google Patents

Construction method for concrete piles Download PDF

Info

Publication number
KR20190050342A
KR20190050342A KR1020170145638A KR20170145638A KR20190050342A KR 20190050342 A KR20190050342 A KR 20190050342A KR 1020170145638 A KR1020170145638 A KR 1020170145638A KR 20170145638 A KR20170145638 A KR 20170145638A KR 20190050342 A KR20190050342 A KR 20190050342A
Authority
KR
South Korea
Prior art keywords
casing
cast
place
pile
outer casing
Prior art date
Application number
KR1020170145638A
Other languages
Korean (ko)
Inventor
동원영
Original Assignee
주식회사 세진이씨에스
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 세진이씨에스 filed Critical 주식회사 세진이씨에스
Priority to KR1020170145638A priority Critical patent/KR20190050342A/en
Publication of KR20190050342A publication Critical patent/KR20190050342A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/385Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to a cast-in-place construction method, and more particularly, to a construction method of cast-in place continuous pile using a mold for cast-in-place pile. The cast-in-place construction method comprises: a step (a) for inserting an outer casing, while drilling the ground using a punch; a step (b) for installing a mold for cast-in-place pile inside the installed outer casing; a step (c) for withdrawing the outer casing; a step (d) for inserting the outer casing, while drilling the ground using a punch to be in contact with an interface of the auxiliary casing; a step (e) for installing the mold for cast-in-place pile inside the installed outer casing; a step (f) for withdrawing the outer casing; a step (g) for continuously installing the mold for cast-in-place pile by repeatedly performing the step (d) to the step (f); a step (h) for placing concrete inside the inner casing; and a step (i) for filling concrete inside the inner casing while withdrawing the pre-installed a plurality of mold for cast-in-place piles. According to the present invention, after a cast-in-place construction method is performed in a number of times, an auxiliary casing for forming a connection portion with an adjacent pile is only replaced, and an inner casing can be recycled. Therefore, as compared with the case in which the whole casing is replaced, construction costs can be reduced.

Description

콘크리트 말뚝의 현장 타설 공법 { CONSTRUCTION METHOD FOR CONCRETE PILES }{CONSTRUCTION METHOD FOR CONCRETE PILES}

본 발명은 현장 타설 공법에 관한 것으로, 더욱 상세하게는 현장 타설 말뚝용 거푸집을 이용하여 현장에서 연속말뚝을 타설하는 공법에 관한 것이다.More particularly, the present invention relates to a method of pouring successive piles in a field by using a cast-in-place pile formwork.

CIP공법은 철근콘그리트 기둥을 현장에서 타설 설치하는 것으로서, 기둥설치공을 뚫어 케이싱을 설치하고 케이싱 내부에 철근을 설치한 후 시멘트, 자갈, 모래 등으로 된 몰타르를 충진시켜 기둥으로 고형화시키며, 케이싱을 해제시켜 주되 H파일을 소정의 간격에 위치하는 기둥에 삽입시키는 공법이다. 그러나 CIP공법은 기둥과 기둥 사이가 밀폐 상태로 되지 못하여 누수가 발생하는 문제점이 있었다.The CIP method is to install a reinforced concrete grate column at the site. It installs a casing by drilling a column installation hole, installs a reinforcing bar inside the casing, solidifies it with a column by filling a mortar made of cement, gravel, sand, And the H file is inserted into the column located at a predetermined interval. However, in the CIP method, there is a problem that leakage occurs because the column and the column are not sealed.

최근에는 상기 문제점을 해결하기 위하여, 도 1 및 도 2에 도시된 바와 같이, 각 케이싱(11)의 일면을 길이 방향으로 절개하고 절개면(13)의 내·외면을 뒤집은 상태에서 양측 모서리면을 용접시켜 내접호면(17)을 형성시킨 케이싱을 케이싱 설치공에 삽입하여 설치하되 내접호면(17)이 진행방향으로 향하도록 설치하는 공법이 개발되었다.1 and 2, one surface of each casing 11 is cut in the longitudinal direction, and the inner and outer surfaces of the cut surface 13 are turned upside down, A method has been developed in which a casing in which an internal arc surface 17 is formed by welding is inserted into a casing installation hole so that the internal arc surface 17 is directed in the advancing direction.

그러나 상기한 바와 같은 종래기술에서는 다음과 같은 문제점이 있다.However, the above-described conventional techniques have the following problems.

즉, 상기 절개면(13)의 내·외면을 뒤집은 상태에서 양측모서리면을 용접시켜 내접호면(17)을 형성시킨 케이싱을 사용하는 경우, 용접부(15)가 마모되는 등의 문제가 발생하면 상기 케이싱 전체를 사용할 수 없게 되는 문제점이 있었다.That is, in the case of using the casing in which the inner and outer surfaces of the incision surface 13 are turned upside down and both side edge surfaces are welded to form the inner raceway surface 17, if the welded portion 15 has a problem such as being worn, The entire casing can not be used.

또한, 상기 케이싱을 해제시키는 과정에서 상기 케이싱의 용접부 및 내접호면에 콘크리트가 부착되어 떨어지지 않음으로 인해 콘크리트 말뚝 기둥과 기둥 사이의 내구성이 좋지 못한 문제점이 있었다.Further, in the process of releasing the casing, there is a problem that the durability between the concrete pillar and the column is poor due to the concrete not being attached to the welded portion and the inner surface of the casing.

대한민국 특허등록 제10-0970440호Korean Patent Registration No. 10-0970440

본 발명은 상기와 같은 종래의 문제점을 해결하기 위하여 안출된 것으로, 본 발명의 목적은 현장 타설 공법을 다수 회에 걸쳐 수행한 이후에 보조 케이싱의 용접 부분이 마모되더라도 내부 케이싱을 재활용 할 수 있는 현장 타설 말뚝용 거푸집 및 이를 이용한 현장 타설 공법을 제공하는 것이다.SUMMARY OF THE INVENTION It is an object of the present invention to solve the above-mentioned problems occurring in the prior art, and it is an object of the present invention to provide a field- And to provide a method for casting a pile using the same.

본 발명의 다른 목적은, 원기둥 형태의 케이싱을 사용하여 케이싱을 해제시키는 과정에서 콘크리트가 케이싱의 내측면에 부착되어 떨어지지 않음으로 인해 발생할 수 있는 콘크리트 말뚝의 내구성 불량 문제를 해결할 수 있는 현장 타설 말뚝용 거푸집 및 이를 이용한 현장 타설 공법을 제공하는 것이다.It is another object of the present invention to provide a pile-type pile structure capable of solving the problem of durability of the concrete pile caused by the fact that the concrete is attached to the inner surface of the casing during the process of releasing the casing by using the cylindrical casing. And to provide a method of casting using the mold.

상기한 바와 같은 목적을 달성하기 위한 본 발명의 특징에 따르면, 본 발명은 중공관으로 형성되는 내부 케이싱과, 상기 내부 케이싱의 외측 일면에 구비되고 인접한 말뚝과의 연결부분을 형성하는 보조 케이싱을 포함하여 구성된다.According to an aspect of the present invention for achieving the above object, the present invention includes an inner casing formed of a hollow tube, and an auxiliary casing provided on an outer surface of the inner casing to form a connection portion between adjacent piles .

이때, 상기 보조 케이싱은 상기 내부 케이싱의 측면으로 연장되어 형성되는 한 쌍의 측면부와, 상기 측면부의 단부를 연결하고 인접 말뚝과 접하도록 곡면으로 형성되는 연접부를 포함하여 구성될 수 있다.The auxiliary casing may include a pair of side portions extending from the side surface of the inner casing and a connecting portion connecting ends of the side portions and forming a curved surface contacting the adjacent piles.

그리고 상기 한 쌍의 측면부는 상기 내부 케이싱과 접하는 내측 단부 사이의 거리가 외측 단부 사이의 거리보다 길도록 형성될 수 있다.And the pair of side portions may be formed to be longer than the distance between the inner ends thereof in contact with the inner casing is longer than the distance between the outer ends.

한편, 본 발명은 중공관으로 형성되는 내부 케이싱과, 상기 내부 케이싱의 외측면에 구비되고 인접한 말뚝과의 연결부분을 형성하는 보조 케이싱, 그리고 상기 내부 케이싱과 상기 보조 케이싱이 내접하는 중공관으로 형성되는 외부 케이싱을 포함하여 구성될 수 있다.According to another aspect of the present invention, there is provided an air conditioner comprising: an inner casing formed of a hollow tube; an auxiliary casing provided on an outer surface of the inner casing to form a connection portion between adjacent piles; and a hollow tube in which the inner casing and the auxiliary casing are in contact with each other And an outer casing which is made of a metal.

이때, 상기 보조 케이싱은 상기 내부 케이싱의 측면으로 연장되어 형성되는 한 쌍의 측면부와, 상기 측면부의 단부를 연결하고, 인접 말뚝과 접하도록 곡면으로 형성되는 연접부를 포함하여 구성될 수 있다.The auxiliary casing may include a pair of side portions extending from the side surface of the inner casing, and a connecting portion connecting ends of the side portions and forming a curved surface contacting the adjacent piles.

또한, 상기 보조 케이싱의 연접부는 상기 외부 케이싱의 곡률과 동일한 곡률 반경을 갖도록 형성될 수 있다.The connecting portion of the auxiliary casing may be formed to have a radius of curvature equal to the curvature of the outer casing.

그리고 상기 측면부는 상기 연접부의 내측면이 상기 내부 케이싱의 외주연에 접하도록 하는 길이로 형성될 수 있다.And the side portion may be formed to have a length such that the inner side surface of the connecting portion is in contact with the outer circumference of the inner casing.

이때, 상기 한 쌍의 측면부는 상기 내부 케이싱과 접하는 내측 단부 사이의 거리가 외측 단부 사이의 거리보다 길도록 형성될 수 있다.At this time, the pair of side portions may be formed to be longer than the distance between the inner ends of the inner casing and the outer casing.

한편, 본 발명은 (a)천공기를 이용하여 지반을 천공하면서, 외부 케이싱을 삽입하는 단계, (b)설치된 외부 케이싱의 내부에 현장 타설 말뚝용 거푸집을 설치하는 단계, (c)상기 외부 케이싱을 인출하는 단계, (d)상기 내부 케이싱 내부에 콘크리트를 타설하는 단계, (e)상기 현장 타설 말뚝용 거푸집을 인출하면서, 상기 내부 케이싱 내부에 콘크리트를 보충하는 단계를 포함할 수 있다.(A) inserting an outer casing while piercing the ground using a perforator, (b) installing a casting for piling into the interior of the installed outer casing, (c) (D) pouring concrete into the inner casing; and (e) replenishing concrete in the inner casing while withdrawing the dock for the cast-in-place pile.

이때, 상기 내부 케이싱 내부에 콘크리트를 타설하는 단계 이전에, 상기 현장 타설 말뚝용 거푸집 주변의 지반을 다짐 작업하는 단계를 포함할 수 있다.At this time, before the concrete is poured into the inner casing, it may include a step of compaction of the ground around the mold for the cast-in-place pile.

그리고 상기 (e)단계 이후 기 설치된 콘크리트 말뚝에 연접한 지반에 대하여 상기 (a)단계 내지 (e)단계를 반복 수행할 수 있다.The step (a) to (e) may be repeated for the ground connected to the concrete pile installed after the step (e).

한편, 본 발명은 (a)천공기를 이용하여 지반을 천공하면서, 외부 케이싱을 삽입하는 단계, (b)설치된 외부 케이싱의 내부에 현장 타설 말뚝용 거푸집을 설치하는 단계, (c)상기 외부 케이싱을 인출하는 단계, (d)상기 보조 케이싱의 연접부에 접하도록 천공기를 이용하여 지반을 천공하면서, 외부 케이싱을 삽입하는 단계, (e)설치된 상기 외부 케이싱 내부에 상기 현장 타설 말뚝용 거푸집을 설치하는 단계, (f)상기 외부 케이싱을 인출하는 단계, (g)상기 (d)단계 내지 (f)단계를 반복 실시하여 상기 현장 타설 말뚝용 거푸집을 연속 설치하는 단계, (h)상기 내부 케이싱 내부에 콘크리트를 타설하는 단계, (i)상기 기 설치된 복수 개의 현장 타설 말뚝용 거푸집을 인출하면서, 상기 내부 케이싱 내부에 콘크리트를 보충하는 단계를 포함한다.(A) inserting an outer casing while piercing the ground using a perforator, (b) installing a casting for piling into the interior of the installed outer casing, (c) (D) inserting an outer casing while piercing the ground using a perforator so as to contact with the connecting portion of the auxiliary casing, (e) installing the casting for piling into the inside of the outer casing installed (D) repeating the steps (d) to (f) so as to continuously install the cast-in-place pile formwork, (h) Casting the concrete; (i) replenishing concrete inside the inner casing while withdrawing the plurality of cast-in-place piles for piling.

이때, 상기 내부 케이싱 내부에 콘크리트를 타설하는 단계 이전에, 상기 현장 타설 말뚝용 거푸집 주변의 지반을 다짐 작업하는 단계를 포함할 수 있다.At this time, before the concrete is poured into the inner casing, it may include a step of compaction of the ground around the mold for the cast-in-place pile.

그리고 상기 (i)단계는 상기 기 설치된 복수 개의 현장 타설 말뚝용 거푸집에 대하여 동시에 수행될 수 있다.The step (i) may be simultaneously performed on the plurality of pre-installed cast-in-place piles.

또한, 상기 (i)단계는 상기 기 설치된 복수 개의 현장 타설 말뚝용 거푸집에 대하여 순차적으로 수행될 수 있다.Also, the step (i) may be sequentially performed on the plurality of pre-installed cast-in-place piles.

이와 같은 본 발명에 의하면, 현장 타설 공법을 다수 회에 걸쳐 수행한 이후에 보조 케이싱의 용접 부분이 마모되더라도 내부 케이싱을 재활용할 수 있어 공사비를 절감할 수 있고, 내부 케이싱이 원형의 단면을 가지므로 콘크리트 현장 타설이 원활하게 이루어질 수 있는 장점이 있다.According to the present invention, since the inner casing can be recycled even if the welded portion of the auxiliary casing is worn after performing the field installation method a plurality of times, the construction cost can be reduced, and the inner casing has a circular cross section There is an advantage that the casting of concrete can be performed smoothly.

이상에서 상세히 설명한 바와 같이 본 발명에 의한 현장 타설 말뚝용 거푸집 및 이를 이용한 현장 타설 공법에 의하면 다음과 같은 효과를 기대할 수 있다.As described above in detail, according to the present invention, the following effects can be expected by using a cast-in-place pile formwork and a cast-in-place method using the same.

즉, 현장 타설 공법을 다수 회 수행한 이후에도 인접한 말뚝과의 연결부분을 형성하는 보조 케이싱만을 교체하고 내부 케이싱을 재활용할 수 있어 케이싱 전체를 교체하여야 하는 경우보다 공사비를 절감할 수 있는 장점이 있다. That is, even after performing the site piling method a plurality of times, it is possible to replace only the auxiliary casing forming the connection portion with the adjacent pile and recycle the internal casing, which is advantageous in that the construction cost can be reduced compared to the case in which the entire casing is replaced.

그리고 본 발명에 의하면, 내부 케이싱의 단면이 원형이므로 콘크리트가 케이싱의 내측면에 부착되어 떨어지지 않음으로 인해 발생할 수 있는 콘크리트 현장 타설 공법의 장애를 예방하여 보다 내구성이 뛰어난 말뚝을 형성할 수 있는 이점이 있다.According to the present invention, since the inner casing has a circular cross-section, the concrete can be prevented from being attached to the inner surface of the casing, have.

도 1은 종래의 현장 타설 말뚝용 거푸집의 구성을 도시한 평면도.
도 2는 종래의 현장 타설 말뚝용 거푸집의 구성을 도시한 사시도.
도 3은 본 발명의 구체적인 실시예에 의한 현장 타설 말뚝용 거푸집의 구성을 도시한 사시도.
도 4a 내지 도 4c는 본 발명의 구체적인 실시예에 의한 현장 타설 말뚝용 거푸집의 구성을 도시한 평면도.
도 5a 내지 도 5f는 본 발명의 구체적인 실시예를 구성하는 현장 타설 말뚝용 거푸집을 연속하여 설치하는 단계를 순차적으로 도시한 평면도.
도 6a 내지 도 6e는 본 발명의 구체적인 실시예를 구성하는 현장 타설 말뚝용 거푸집을 소정 높이만큼 인출하여 보조 케이싱 부분을 보충하는 단계를 순차적으로 도시한 사시도.
도 7은 각을 가진 벽체를 시공하기 위해 본 발명의 구체적인 실시예에 의한 현장 타설 말뚝용 거푸집을 설치한 상태를 도시한 평면도.
1 is a plan view showing a structure of a conventional cast-in-place pile.
BACKGROUND OF THE INVENTION Field of the Invention [0001]
3 is a perspective view showing the construction of a cast-in-place pile formwork according to a specific embodiment of the present invention.
4A to 4C are plan views showing the construction of a mold for a cast-in-place pile according to a specific embodiment of the present invention.
FIGS. 5A to 5F are plan views sequentially showing steps for continuously installing dies for a cast-in-place pile constituting a specific embodiment of the present invention.
FIG. 6A to FIG. 6E are perspective views sequentially showing steps of drawing a form for a cast-in-place pile constituting a concrete embodiment of the present invention by a predetermined height to supplement the auxiliary casing portion.
FIG. 7 is a plan view showing a state in which a cast-in-place pile according to a concrete embodiment of the present invention is installed to construct a wall having an angle; FIG.

이하에서는 상기한 바와 같은 본 발명에 의한 현장 타설 말뚝용 거푸집 및 이를 이용한 현장 타설 공법의 바람직한 실시예를 첨부한 도면을 참고하여 상세하게 설명한다. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, a preferred embodiment of the present invention will be described in detail with reference to the accompanying drawings.

도 4a 내지 도 4c는 본 발명의 구체적인 실시예를 구성하는 내부 케이싱, 상기 내부 케이싱의 외측면에 구비되고 인접한 말뚝과의 연결부분을 형성하는 보조 케이싱, 그리고 상기 내부 케이싱과 상기 보조 케이싱이 구비된 현장 타설 말뚝용 거푸집을 도시한 평면도이다.FIGS. 4A to 4C are cross-sectional views of an inner casing and a sub-casing of the inner casing, respectively, constituting a specific embodiment of the present invention, an auxiliary casing provided on an outer surface of the inner casing and forming a connection portion with adjacent piles, And FIG.

도 4a에 도시된 바와 같이, 내부 케이싱(21)은 단면이 원형인 중공관으로 형성된다. 그리고 도 4b에 도시된 바와 같이 상기 보조 케이싱(23)은 상기 내부 케이싱(21)의 외측면에 길이방향으로 구비되어 인접한 말뚝과의 연결부분을 형성한다. 또한, 도 4c에 도시된 바와 같이 본 발명에 의한 현장 타설 말뚝용 거푸집(25)은 상기 내부 케이싱(21)과 상기 보조 케이싱(23)을 포함하여 구성된다. As shown in FIG. 4A, the inner casing 21 is formed of a hollow tube having a circular cross section. As shown in FIG. 4B, the auxiliary casing 23 is provided on the outer surface of the inner casing 21 in the longitudinal direction to form a connection portion with adjacent piles. As shown in FIG. 4C, the cast-in-place pile formwork 25 according to the present invention includes the inner casing 21 and the auxiliary casing 23.

이때, 상기 보조 케이싱(23)은 도 4b에 도시된 바와 같이, 연접부(27)와 한 쌍의 측면부(29)로 구성된다. 상기 연접부(27)는 인접한 위치에 삽입될 외부 케이싱(31)과 동일한 곡률 반경을 가진다. 따라서 상기 보조 케이싱(23)의 연접부(27)는 상기 외부 케이싱(31)을 길이 방향으로 절단함으로써 형성될 수 있다. 한편, 상기 한 쌍의 측면부(29)는 상기 연접부(27)와 함께 상기 보조 케이싱(23)을 구성하는 부분으로 상기 내부 케이싱(21)의 측면으로 연장되어 형성되고 상기 내부 케이싱(21)과 상기 연접부(27)를 연결하는 역할을 한다. 이때, 상기 측면부(29)는 다양한 결합방법에 의해 상기 내부 케이싱(21)에 결합될 수 있으나, 바람직하게는 현장 작업이 용이한 용접에 의해 연결된다. 또한 상기 한 쌍의 측면부는 상기 내부 케이싱(21)과 접하는 내측 단부 사이의 거리가 외측 단부 사이의 거리보다 길도록 형성될 수 있다.At this time, as shown in FIG. 4B, the auxiliary casing 23 is composed of a connecting portion 27 and a pair of side portions 29. The connecting portion 27 has the same radius of curvature as the outer casing 31 to be inserted in the adjacent position. Therefore, the connecting portion 27 of the auxiliary casing 23 can be formed by cutting the outer casing 31 in the longitudinal direction. The pair of side portions 29 may be formed as a part of the auxiliary casing 23 together with the connecting portion 27 so as to extend to the side surface of the inner casing 21, And serves to connect the connecting portion 27. At this time, the side portions 29 may be coupled to the inner casing 21 by various joining methods, but they are preferably connected by welding that facilitates field work. Further, the pair of side portions may be formed so that the distance between the inner ends thereof contacting the inner casing 21 is longer than the distance between the outer ends.

그리고 상기 외부 케이싱(31)은 상기 내부 케이싱(21)과 상기 보조 케이싱(23)이 내접하는 중공관으로 형성된다. 상기 현장 타설 말뚝용 거푸집(25)은 상기 내부 케이싱(21)과 상기 보조 케이싱(23)으로 구성되고, 현장 타설 말뚝용 거푸집 유닛(33)은 상기 내부 케이싱(21)과 상기 보조 케이싱(23), 그리고 상기 외부 케이싱(31)으로 구성된다.The outer casing (31) is formed of a hollow tube in which the inner casing (21) and the auxiliary casing (23) are in contact with each other. The shake pile formwork 25 is constituted by the inner casing 21 and the auxiliary casing 23 and the form casting unit 33 for the excavated pile is connected to the inner casing 21 and the auxiliary casing 23, , And the outer casing (31).

한편, 상기 보조 케이싱(23)은 상기 연접부(27)의 내측면이 상기 내부 케이싱(21)의 외주연에 접하도록 구비될 수 있다. 이는 콘크리트를 상기 내부 케이싱(21)에만 타설하되, 기 설치된 현장 타설 말뚝용 거푸집(25)을 인출하여 생긴 빈 공간에 콘크리트가 용이하게 채워지도록 하기 위함이다. 즉, 상기 인출된 현장 타설 말뚝용 거푸집(25)의 보조 케이싱(23) 부분에 의해 생기는 빈 공간의 체적을 작게 하여 상기 빈 공간에 대한 콘크리트의 현장 타설을 원활히 하고, 상기 기 설치된 현장 타설 말뚝용 거푸집(25)을 인출하면서 보충해야 하는 콘크리트의 양을 줄이기 위함이다.Meanwhile, the auxiliary casing 23 may be provided such that the inner surface of the connecting portion 27 is in contact with the outer circumference of the inner casing 21. That is, the concrete is laid only in the inner casing 21, and the concrete is easily filled in the empty space formed by drawing out the pre-installed cast-in-place pile formwork 25. That is, the volume of the empty space created by the extracted portion of the auxiliary casing 23 of the cast-in-place pile formwork 25 is reduced to smoothly put the concrete into the empty space, This is to reduce the amount of concrete to be replenished while withdrawing the form 25.

또한, 상기 보조 케이싱(23)은 상기 연접부(27)와 한 쌍의 측면부(29)로 구성되는데, 상기 한 쌍의 측면부(29)는 상기 내부 케이싱(21)과 접하는 내측 단부 사이의 거리가 외측 단부 사이의 거리보다 길도록 형성될 수 있다. 이는 내부 케이싱(21) 내부에 타설되는 콘크리트가 상기 인출된 현장 타설 말뚝용 거푸집(25)의 보조 케이싱(23) 부분에 의해 생긴 빈 공간을 보충하는 단계에서, 상기 빈 공간에 대한 콘크리트의 현장 타설을 원활하게 하기 위함이다. 즉, 상기 내부 케이싱(21)과 접하는 내측 단부 사이의 거리가 외측 단부 사이의 거리보다 길도록 형성되는 경우가 그러하지 아니한 경우보다 상기 빈 공간으로 콘크리트의 보충이 용이하고 신속하게 이루어질 수 있기 때문이다.The auxiliary casing 23 is constituted by the connecting portion 27 and the pair of side portions 29. The pair of side portions 29 has a distance between the inner end portions in contact with the inner casing 21 May be formed to be longer than the distance between the outer ends. This is because in the step of replenishing the empty space created by the portion of the auxiliary casing 23 of the cast-in-place pile form 25 from which the concrete laid in the inner casing 21 is pulled out, . That is, it is easier and quicker to replenish the concrete to the hollow space than when the distance between the inner end portions contacting with the inner casing 21 is longer than the distance between the outer end portions.

도 5a 내지 도 5f는 본 발명의 구체적인 실시예에 의한 현장 타설 말뚝용 거푸집(25)을 연속하여 설치하는 단계를 순차적으로 도시한 평면도이다.FIGS. 5A to 5F are plan views sequentially showing the step of continuously installing the dies for casting a pile according to a specific embodiment of the present invention.

도 5a에 도시된 바와 같이, 케이싱 설치공에 상기 외부 케이싱(31)을 설치한다. 다음으로 도 5b에 도시된 바와 같이, 상기 외부 케이싱(31)의 내부에 상기 현장 타설 말뚝용 거푸집(25)을 설치한다. 이때 상기 현장 타설 말뚝용 거푸집(25)은 상기 외부 케이싱(31)에 내접하도록 설치할 수 있다. 이는 상기 외부 케이싱(31)을 인출하였을 때, 빈 공간의 체적을 최대한 작게 하여 주변의 토사가 상기 현장 타설 말뚝용 거푸집(25)과 밀착될 수 있도록 하기 위함이다. 다만, 상기 현장 타설 말뚝용 거푸집(25)은 상기 외부 케이싱(31)에 최대한 내접하게 설치하되, 이후의 단계에서 상기 외부 케이싱(31)이 인출될 수 있도록 약간의 공간을 두어 설치하는 것이 바람직하다.As shown in Fig. 5A, the outer casing 31 is installed in the casing installation hole. Next, as shown in FIG. 5B, the casting 25 for the cast-in-place pile is installed inside the outer casing 31. At this time, the cast-in-place pile formwork (25) can be installed so as to be inscribed in the outer casing (31). This is to minimize the volume of the empty space when the outer casing 31 is taken out, so that the surrounding soil can be brought into close contact with the casting mold 25 for the cast-in-place pile. However, it is preferable that the above-mentioned cast-in-place pile form 25 is installed so as to be in contact with the outer casing 31 as much as possible, and that the outer casing 31 is installed with a slight space to be taken out at a later stage .

이어서 도 5c에 도시된 바와 같이, 기 설치된 상기 외부 케이싱(31)을 인출한다. 다음으로 도 5d에 도시된 바와 같이, 상기 현장 타설 말뚝용 거푸집(25)의 상기 보조 케이싱의 연접부(27)에 접하도록 상기 케이싱 설치공을 뚫고 그 내부에 상기 외부 케이싱(31)을 설치한다. 이어서 도 5e에 도시된 바와 같이, 상기 외부 케이싱(31)의 내부에 상기 현장 타설 말뚝용 거푸집(25)을 설치한다. 다음으로 도 5f에 도시된 바와 같이, 기 설치된 상기 외부 케이싱(31)을 인출한다. Then, as shown in Fig. 5C, the previously installed outer casing 31 is taken out. Next, as shown in FIG. 5D, the casing installation hole is pierced so as to contact the connecting portion 27 of the auxiliary casing of the submerged pile formwork 25, and the outer casing 31 is installed therein . Then, as shown in FIG. 5E, the above-mentioned cast-in-place pile formwork 25 is installed in the outer casing 31. Next, as shown in Fig. 5F, the previously installed outer casing 31 is taken out.

이하에서는, 상기 내부 케이싱 내부에 콘크리트를 타설하여 말뚝을 형성하는 과정을 상세히 살피기로 한다.Hereinafter, a process of forming piles by pouring concrete into the inner casing will be described in detail.

도 6a 내지 도 6e는 본 발명의 구체적인 실시예에 의한 상기 현장 타설 말뚝용 거푸집을 인출하여 상기 내부 케이싱 내부에 타설된 콘크리트가 상기 보조 케이싱 부분의 인출에 의해 생기는 빈 공간을 보충하는 단계를 순차적으로 도시한 사시도이다.6A to 6E illustrate the steps of withdrawing the dies for piling the shots according to a specific embodiment of the present invention and replenishing empty space created by the concrete poured into the interior casing by drawing out the auxiliary casing portions, FIG.

먼저, 도면으로 도시하지는 않았으나 말뚝을 형성하고자 하는 위치의 지반을 천공하면서 외부 케이싱(31)을 삽입하고, 상기 외부 케이싱(31) 내부에 상기 현장 타설 말뚝용 거푸집(25)을 설치한다. 다음으로 설치된 상기 외부 케이싱(31)을 인출하면 도 6a에 도시된 바와 같이 현장 타설 말뚝용 거푸집(25)만이 설치된 상태가 된다. 이때, 설치된 상기 현장 타설 말뚝용 거푸집(25) 주변의 지반을 다지는 작업을 함으로써 상기 외부 케이싱(31)의 인출로써 생기는 빈 공간을 주변의 토사가 보충하여 토사가 상기 현장 타설 말뚝용 거푸집(25)과 밀착되도록 할 수 있다. 이어서, 도면으로 도시하지는 않았으나 설치된 상기 현장 타설 말뚝용 거푸집(25)의 내부 케이싱(21) 내부에 콘크리트를 타설한다. First, an outer casing 31 is inserted while a ground at a position where a pile is to be formed is punctured, though not shown in the drawing, and the cast-in-place pile formwork 25 is installed in the outer casing 31. When the next outer casing 31 is pulled out, only the formwork 25 for the cast-in-place pile is installed as shown in FIG. 6A. At this time, the ground around the form casting pile for casting 25 is refined so that the surrounding space of the empty space formed by the pulling out of the outer casing 31 replenishes the soil, As shown in Fig. Then, although not shown in the figure, concrete is poured into the inner casing 21 of the cast-in-place pile formwork 25 installed.

이때, 상기 내부 케이싱(21) 내부에는 무근 콘크리트, 철근 콘크리트, 고화토(쏘일 시멘트), 시멘트풀, 쉬트 파일 및 H 파일 등과 같은 다양한 충진물이 타설될 수 있다. 이때, 상기 충진물의 종류는 상기 말뚝의 용도, 지지 하중 등에 따라 적절히 선택된다. 이하에서는 설명의 편의상 콘크리트가 타설되는 경우를 예로 들어 설명한다.At this time, a variety of packing materials such as non-woven concrete, reinforced concrete, solidified soil (soil cement), cement paste, sheet pile, and H file can be placed in the inner casing 21. At this time, the type of the filler is appropriately selected depending on the use of the pile, the support load, and the like. Hereinafter, a case where concrete is installed for convenience of explanation will be described as an example.

다음으로 도 6b에 도시된 바와 같이, 콘크리트를 타설하고 소정 시간 이후에 상기 현장 타설 말뚝용 거푸집(25)을 소정 높이만큼 인출한다. 도 6b는 상기 현장 타설 말뚝용 거푸집(25)을 인출한 직후의 상태를 도시한 도면이다. 따라서 상기 현장 타설 말뚝용 거푸집(25)이 인출된 소정 높이 이하 부분의 콘크리트는 아직 원기둥의 형태를 나타낸다. Next, as shown in FIG. 6B, the concrete is poured, and after a predetermined period of time, the form 25 for the cast-in-place pile is drawn out by a predetermined height. FIG. 6B is a view showing a state immediately after drawing the mold 25 for the cast-in-place pile. Therefore, the concrete in the portion below the predetermined height from which the dies 25 for the cast-in-place piles are taken out still shows a shape of a cylinder.

이어서 도 6c에 도시된 바와 같이, 콘크리트가 인출된 상기 현장 타설 말뚝용 거푸집(25)의 보조 케이싱(27) 부분에 의해 생기는 빈 공간을 보충한다. 따라서 상기 현장 타설 말뚝용 거푸집(25)의 인출은 상기 타설된 콘크리트가 완전히 고체 상태로 되기 이전에 이루어져야 한다.Subsequently, as shown in FIG. 6C, an empty space created by the portion of the auxiliary casing 27 of the cast-in-place pile form 25 from which the concrete is drawn out is supplemented. Therefore, the withdrawal of the cast-in-place pile formwork 25 must be performed before the poured concrete is completely solidified.

다음으로, 도 6d에 도시된 바와 같이, 상기 현장 타설 말뚝용 거푸집(25)을 다시 소정 높이만큼 인출한다. 도 6d도 도 6b와 마찬가지로 상기 현장 타설 말뚝용 거푸집(25)을 다시 소정 높이만큼 인출한 직후의 상태를 도시한 도면이다. 따라서 상기 현장 타설 말뚝용 거푸집(25) 바로 아래 부분의 콘크리트는 아직 원기둥의 형태를 나타낸다. Next, as shown in FIG. 6D, the cast-in-place pile formwork 25 is drawn out again by a predetermined height. FIG. 6D is a view showing a state immediately after the above-mentioned cast-in-place pile form 25 is taken out again by a predetermined height as in FIG. 6B. Therefore, the concrete just below the cast-in-place pile form 25 still shows the shape of a cylinder.

이어서, 도 6e에 도시된 바와 같이, 콘크리트가 상기 소정 높이만큼 인출된 보조 케이싱(27)에 의해 생기는 빈공간을 보충한다. 이와 같은 단계를 반복 수행하여 상기 내부 케이싱(21) 내부에 타설한 콘크리트가 상기 내부 케이싱(21) 부분뿐만 아니라 콘크리트를 타설하지 않은 상기 보조 케이싱(23) 부분까지도 채우게 된다. 따라서 콘크리트 현장 타설에 의해 말뚝이 상기 현장 타설 말뚝용 거푸집(25)과 동일한 형상이 되도록 할 수 있다.Subsequently, as shown in FIG. 6E, the concrete replenishes the empty space created by the auxiliary casing 27 drawn out by the predetermined height. By repeating the above steps, the concrete laid in the inner casing 21 is filled not only with the inner casing 21 but also with the auxiliary casing 23 where no concrete is laid. Therefore, by pouring the concrete into the concrete, the pile can have the same shape as that of the cast-in-place pile form 25.

이때 상기 보조 케이싱(27) 부분을 보충하는데 소비된 콘크리트는 상기 단계의 반복 수행 중에 상기 내부 케이싱(21) 내부로 콘크리트를 추가로 타설하여 보충할 수 있다.At this time, the concrete consumed for supplementing the portion of the auxiliary casing 27 can be supplemented by further pouring concrete into the inner casing 21 during the repetition of the above steps.

도 5a 내지 도 6e를 참고하면, 상기 현장 타설 말뚝용 거푸집(25)을 이용한 연속적인 콘크리트 말뚝의 현장 타설 방법은 다음과 같은 단계에 의하여 구성된다. 5A to 6E, a method of casting a continuous concrete pile using the cast-in-place pile formwork 25 is as follows.

먼저 천공기를 이용하여 지반을 천공하면서, 상기 외부 케이싱(31)을 삽입한다. 이어서 상기 외부 케이싱(31)의 내부에 상기 현장 타설 말뚝용 거푸집(25)을 설치한다. 이때, 상기 보조 케이싱(23)이 말뚝 시공의 진행방향을 향하도록 상기 현장 타설 말뚝용 거푸집(25)을 설치하여 인접하는 말뚝이 접하도록 할 수 있다.First, the outer casing 31 is inserted while perforating the ground using a perforator. Then, the above-mentioned cast-in-place pile formwork 25 is installed in the outer casing 31. At this time, the casting mold 25 for the cast-in-place pile may be provided so that the auxiliary casing 23 faces the proceeding direction of the pile construction, so that adjacent piles can be brought into contact with each other.

다음으로 상기 외부 케이싱(31)을 인출하고, 인접한 지반에 상기 보조 케이싱의 연접부(27)와 동일한 곡률 반경을 가지는 케이싱 설치공을 뚫고 상기 외부 케이싱(31)을 설치한다. 이어서 상기 외부 케이싱(31) 내부에 현장타설 말뚝용 거푸집(25)을 상기 보조 케이싱(23)이 말뚝 시공의 진행방향을 향하도록 설치한다. Next, the outer casing 31 is taken out, and a casing installation hole having the same radius of curvature as that of the connecting portion 27 of the auxiliary casing is drilled in the adjacent ground, and the outer casing 31 is installed. Subsequently, a die (25) for a casting pile is installed in the outer casing (31) so that the auxiliary casing (23) faces the direction of the pile construction.

다음으로 상기와 동일한 방법을 반복 실시하여 상기 현장 타설 말뚝용 거푸집(25)을 연속 설치하고, 상기 현장 타설 말뚝용 거푸집(25)이 소정 개수만큼 설치되면 상기 내부 케이싱(21) 내부에 콘크리트를 타설한다. Then, the same method as described above is repeated to continuously install the cast-in-place pile formwork 25, and when a predetermined number of the cast-in-place pile formwork 25 is installed, concrete is poured into the inside casing 21 do.

마지막으로 소정 시간 이후에 상기 복수 개의 현장 타설 말뚝용 거푸집(25)을 인출하면서, 상기 내부 케이싱(21) 내부에 콘크리트를 추가로 타설한다. 이때 콘크리트를 추가로 타설하는 이유는 상기 내부 케이싱(21) 내부의 콘크리트가 상기 보조 케이싱(23)에 의한 빈 공간을 보충하기 때문이다.Finally, concrete is additionally installed in the inner casing 21 while withdrawing the plurality of cast-in-place piles 25 after a predetermined time. At this time, the reason why the concrete is further laid is that the concrete inside the inner casing 21 replenishes the empty space by the auxiliary casing 23.

한편, 상기 복수 개의 현장 타설 말뚝용 거푸집(25)을 인출하면서 상기 내부 케이싱(21) 내부에 콘크리트를 추가로 타설하고 콘크리트가 빈 공간을 보충하도록 하는 단계는 상기 복수 개의 현장 타설 말뚝용 거푸집(25)에 대하여 동시에 수행될 수 있고, 또한 순차적으로 수행될 수도 있다.The step of further pouring concrete into the inner casing 21 while taking out the plurality of pouring dies 25 for piling out the cast-in-place piling device, ), And may also be performed sequentially.

도 7은 각을 가진 벽체를 시공하기 위해 본 발명의 구체적인 실시예에 의한 현장 타설 말뚝용 거푸집을 설치한 상태를 도시한 평면도이다.FIG. 7 is a plan view showing a state in which a cast-in-place pile formwork according to a concrete embodiment of the present invention is installed to construct a wall having an angle.

상기 현장 타설 말뚝용 거푸집(25)을 이용한 연속적인 콘크리트 말뚝의 현장 타설 방법에서 살펴본 바와 마찬가지로 지반을 천공하면서 상기 외부 케이싱(31)을 삽입하고, 상기 외부 케이싱(31) 내부에 상기 현장 타설 말뚝용 거푸집(25)을 상기 보조 케이싱(23)이 말뚝 시공의 진행방향을 향하도록 설치한 뒤 상기 외부 케이싱(31)을 인출하는 단계를 반복하면 상기 현장 타설 말뚝용 거푸집(25)을 도 7에 도시된 바와 같이, 'ㄱ'자 형태의 각을 가진 벽체를 시공하기 위한 현장 타설 말뚝용 거푸집을 설치할 수 있다. 이때, 상기 연접부의 길이는 상기 말뚝이 형성될 방향에 따라 적절하게 결정되어야 한다.As in the method of continuously casting the concrete pile using the cast-in-place pile formwork 25, the outer casing 31 is inserted while piercing the ground, When the mold 25 is installed such that the auxiliary casing 23 faces the proceeding direction of the pile construction and the step of pulling out the outer casing 31 is repeated, the mold 25 for the cast- As described above, it is possible to install a cast-in-place pile formwork for constructing a wall having an 'a' shaped angle. At this time, the length of the connecting portion should be appropriately determined according to the direction in which the pile is to be formed.

이하에서는 상기 말뚝이 형성될 방향이 직각을 갖는 경우를 예를 들어 살펴본다.Hereinafter, a case where the direction in which the pile is formed has a right angle will be described as an example.

만약, 상기 연접부(27) 단면의 길이가 상기 내부 케이싱(21) 단면 원주의 1/4 이하가 아니라면, 상기 현장 타설 말뚝용 거푸집(25)은 도 7에 도시된 바와 같이 'ㄱ'자 형태의 수직으로 꺾인 형상이 될 수 없다. 따라서 말뚝 시공의 진행방향이 'ㄱ'자 형태의 수직으로 꺾인 형상인 경우라면 상기 연접부(27) 단면의 길이는 상기 내부 케이싱(21) 단면 원주의 1/4 이하가 되도록 구비되어야 한다. If the length of the cross section of the connecting portion 27 is not less than 1/4 of the circumferential circumference of the inner casing 21, the mold 25 for the cast-in-place pile may be formed as a ' It can not be a vertically bent shape. Therefore, in the case where the progressing direction of the pile construction is a vertically bent shape of 'a' shape, the length of the end face of the connecting portion 27 should be less than 1/4 of the circumference of the inner casing 21.

살핀 바와 마찬가지로 특정한 각도로 꺾인 벽체를 시공하기 위한 현장 타설 말뚝용 거푸집을 설치하기 위해서는 상기 연접부(27) 단면의 길이가 상기 내부 케이싱(21) 단면 원주의 소정 비율 이하가 되도록 결정하여야 할 필요가 있다.It is necessary to determine the length of the cross section of the connecting portion 27 to be less than a predetermined ratio of the circumferential surface of the inner casing 21 in order to install the cast- have.

본 발명의 권리는 위에서 설명된 실시예에 한정되지 않고 청구범위에 기재된 바에 의해 정의되며, 본 발명의 분야에서 통상의 지식을 가진 자가 청구범위에 기재된 권리범위 내에서 다양한 변형과 개작을 할 수 있다는 것은 자명하다.It is to be understood that the invention is not limited to the disclosed embodiment, but is capable of many modifications and variations within the scope of the appended claims. It is self-evident.

본 발명은 현장 타설 공법에 관한 것으로, 더욱 상세하게는 현장 타설 말뚝용 거푸집을 이용하여 현장에서 연속말뚝을 타설하는 공법에 관한 것으로, 본 발명에 의하면, 본 발명에서는 현장 타설 공법을 다수 회 수행한 이후에도 인접한 말뚝과의 연결부분을 형성하는 보조 케이싱만을 교체하고 내부 케이싱을 재활용할 수 있어 케이싱 전체를 교체하여야 하는 경우보다 공사비를 절감할 수 있는 장점이 있다. More particularly, the present invention relates to a method for pouring successive piles in a field by using a pile formwork, and in the present invention, It is possible to replace only the auxiliary casing which forms the connection part with the adjacent pile and to recycle the internal casing, which is advantageous in that the construction cost can be saved as compared with the case where the entire casing is replaced.

11: 케이싱 13: 절개면
15: 용접부 17: 내접호면
21: 내부 케이싱 23: 보조 케이싱
25: 현장 타설 말뚝용 거푸집 27: 보조 케이싱의 연접부
29: 보조 케이싱의 측면부 31: 외부 케이싱
33: 현장 타설 말뚝용 거푸집 유닛
11: casing 13: incision surface
15: welding portion 17: inner surface
21: inner casing 23: auxiliary casing
25: Formwork for piling in the field 27: Concatenation of auxiliary casing
29: side portion of the auxiliary casing 31: outer casing
33: Formwork unit for cast-in-place piles

Claims (5)

(a) 천공기를 이용하여 지반을 천공하면서, 외부 케이싱을 삽입하는 단계;
(b) 설치된 외부 케이싱의 내부에 현장 타설 말뚝용 거푸집을 설치하는 단계;
(c) 상기 외부 케이싱을 인출하는 단계;
(d) 상기 보조 케이싱의 연접부에 접하도록 천공기를 이용하여 지반을 천공하면서, 외부 케이싱을 삽입하는 단계;
(e) 설치된 상기 외부 케이싱 내부에 상기 현장 타설 말뚝용 거푸집을 설치하는 단계;
(f) 상기 외부 케이싱을 인출하는 단계;
(g) 상기 (d)단계 내지 (f)단계를 반복 실시하여 상기 현장 타설 말뚝용 거푸집을 연속 설치하는 단계;
(h) 상기 내부 케이싱 내부에 콘크리트를 타설하는 단계; 그리고
(i) 상기 기 설치된 복수 개의 현장 타설 말뚝용 거푸집을 인출하면서, 상기 내부 케이싱 내부에 콘크리트를 보충하는 단계를 포함하는 것을 특징으로 하는 콘크리트 말뚝의 현장 타설 방법.
(a) inserting an outer casing while drilling a ground using a perforator;
(b) installing a cast-in-place pile formwork into the installed outer casing;
(c) withdrawing the outer casing;
(d) inserting an outer casing while piercing the ground using a perforator so as to contact the connecting portion of the auxiliary casing;
(e) installing the cast-in-place pile formwork into the installed outer casing;
(f) withdrawing the outer casing;
(g) repeating the steps (d) to (f) to continuously install the cast-in-place pile formwork;
(h) pouring concrete into the inner casing; And
(i) replenishing concrete in the inner casing while withdrawing a plurality of the cast-in-place piles for the pile installed therein.
제 1 항에 있어서,
상기 내부 케이싱 내부에 콘크리트를 타설하는 단계 이전에, 상기 현장 타설 말뚝용 거푸집 주변의 지반을 다짐 작업하는 단계를 포함하는 것을 특징으로 하는 콘크리트 말뚝의 현장 타설 방법.
The method according to claim 1,
The method of claim 1, further comprising the step of compaction of the ground around the formwork piles prior to pouring concrete into the inner casing.
제 1 항 또는 제 2 항에 있어서,
상기 (i)단계는 상기 기 설치된 복수 개의 현장 타설 말뚝용 거푸집에 대하여 동시에 수행됨을 특징으로 하는 콘크리트 말뚝의 현장 타설 방법.
3. The method according to claim 1 or 2,
Wherein the step (i) is simultaneously performed on the plurality of pre-installed cast-in-place piles.
제 1 항 또는 제 2 항에 있어서,
상기 (i)단계는 상기 기 설치된 복수 개의 현장 타설 말뚝용 거푸집에 대하여 순차적으로 수행됨을 특징으로 하는 콘크리트 말뚝의 현장 타설 방법.
3. The method according to claim 1 or 2,
Wherein the step (i) is sequentially performed on the plurality of pre-installed cast-in-place piles.
제 1 항 또는 제 2 항에 있어서,
상기 보조 케이싱은,
상기 내부 케이싱의 측면으로 연장되어 형성되는 한 쌍의 측면부와;
상기 측면부의 단부를 연결하고, 인접 말뚝과 접하도록 곡면으로 형성되는 연접부를 포함하여 구성됨을 특징으로 하는 콘크리트 말뚝의 현장 타설 방법.
3. The method according to claim 1 or 2,
The sub-
A pair of side portions extending from the side surface of the inner casing;
And a connecting portion connecting the ends of the side portions and being curved to contact the adjacent piles.
KR1020170145638A 2017-11-03 2017-11-03 Construction method for concrete piles KR20190050342A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020170145638A KR20190050342A (en) 2017-11-03 2017-11-03 Construction method for concrete piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020170145638A KR20190050342A (en) 2017-11-03 2017-11-03 Construction method for concrete piles

Publications (1)

Publication Number Publication Date
KR20190050342A true KR20190050342A (en) 2019-05-13

Family

ID=66582136

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020170145638A KR20190050342A (en) 2017-11-03 2017-11-03 Construction method for concrete piles

Country Status (1)

Country Link
KR (1) KR20190050342A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20220123896A (en) 2021-03-02 2022-09-13 주신건기(주) Construction method of cast in place concrete pile

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100970440B1 (en) 2009-12-03 2010-07-15 대한기초엔지니어링 주식회사 Beam penetrating after lower part casting type cast-in-place pile method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100970440B1 (en) 2009-12-03 2010-07-15 대한기초엔지니어링 주식회사 Beam penetrating after lower part casting type cast-in-place pile method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20220123896A (en) 2021-03-02 2022-09-13 주신건기(주) Construction method of cast in place concrete pile

Similar Documents

Publication Publication Date Title
KR101676814B1 (en) CFT pile Construction Method and the Shoring Method using the same file
KR100850028B1 (en) Construction method using concrete mould for concrete piles cast in position
KR101018282B1 (en) Method for constructing fabric for undergound tunnel
KR20180124795A (en) An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same
KR101840226B1 (en) The guide holes of the form for soil auger dredges
JP5742058B2 (en) Method for increasing horizontal resistance of precast concrete pile foundation
KR20070002328A (en) Construction method of pipe roof structures
KR20190050342A (en) Construction method for concrete piles
KR102239089B1 (en) Underaround continued wall structure using casing and pile continuous connection and method therefor
JP3829319B2 (en) Construction method of underground hollow structure and its underground hollow structure
JP4440497B2 (en) Construction method of underground continuous wall and construction method of underground structure
KR20190083898A (en) Method for constructing continuous retaining wall having overlap array structure
KR102299540B1 (en) Construction method of cross-sectional expansion type columnar barrier wall
KR102325623B1 (en) Construction method of retaining wall
KR101153314B1 (en) Construction method for underground watertight wall
KR102124772B1 (en) Self-supporting retaining wall and construction method using it
KR101960499B1 (en) Underground column wall construction method using waterstop rubber and waterstop housing, and underground column wall therewith
KR20090001890U (en) Concrete mould for concrete piles cast in position and its construction method
JPH09324422A (en) Cast-in-place compound pile and building method therefor
JP2009068276A (en) Shield tunnel widening method
JP2009203690A (en) Earth anchor and method of removing the same
KR20080097960A (en) Concrete mould for concrete piles cast in position and its construction method
JP6767542B1 (en) Construction method of support pile
JPH07268867A (en) Cast-in-place concrete pile and method for fabricating the same
KR101964718B1 (en) Soil retaining wall construction method and soil retaining wall constructed by this

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application