KR20180001297A - Project management apparatust - Google Patents

Project management apparatust Download PDF

Info

Publication number
KR20180001297A
KR20180001297A KR1020160080247A KR20160080247A KR20180001297A KR 20180001297 A KR20180001297 A KR 20180001297A KR 1020160080247 A KR1020160080247 A KR 1020160080247A KR 20160080247 A KR20160080247 A KR 20160080247A KR 20180001297 A KR20180001297 A KR 20180001297A
Authority
KR
South Korea
Prior art keywords
project
schedule
unit
work
information
Prior art date
Application number
KR1020160080247A
Other languages
Korean (ko)
Inventor
강동완
김성호
김진환
민수홍
Original Assignee
두산중공업 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 두산중공업 주식회사 filed Critical 두산중공업 주식회사
Priority to KR1020160080247A priority Critical patent/KR20180001297A/en
Publication of KR20180001297A publication Critical patent/KR20180001297A/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to a project management apparatus. According to the present invention, the project management apparatus includes: a schedule planning unit which receives information on a work classification system, a project order, and work instructions from an enterprise resource planning system, compares the received information with a standard schedule stored in a database, and plans an overall schedule and an activity schedule of a project; a work process aggregating unit which collects and aggregates actual work processes of the project; a user interface which provides a user interface screen for a user to request information on the project and displays the requested information; and a delivery delay expecting unit which determines the possibility of a delay by comparing the actual work processes and a project schedule, classifies and groups a determined result into two or more categories, and separately displays the delay result on a screen.

Description

프로젝트 관리 장치{PROJECT MANAGEMENT APPARATUST}[PROJECT MANAGEMENT APPARATUST]

본 발명은 프로젝트 관리 장치에 관한 것으로, 더욱 상세하게는 전사자원관리시스템으로부터 작업분류체계, 프로젝트 발주서에 대한 정보, 및 작업지시에 대한 정보를 전달받아 데이터베이스에 저장되어 있는 표준일정과 비교하여 해당 프로젝트의 전체 일정 및 액티비티 일정을 수립하는 일정수립부; 상기 프로젝트의 실제 작업 공정을 수집하여 집계하는 작업공정 집계부; 사용자 인터페이스 화면을 제공하여 사용자가 프로젝트 관련 내용을 요청할 수 있도록 하고, 요청된 내용을 표시하는 사용자 인터페이스부; 및 상기 실제 작업 공정과 프로젝트 일정을 비교하여 지연가능성 정도를 판단하고, 지연 가능성 정도에 따라 2개 이상으로 분류하여 그룹핑하고, 지연결과가 상기 인터페이스 화면에 구분되어 표시되도록 제어하는 납품지연 예상부;를 포함하는 프로젝트 관리 장치에 관한 것이다. The present invention relates to a project management apparatus, and more particularly, to a project management apparatus that receives information on a work classification system, information on a project order book, and work instruction from an enterprise resource management system and compares the information with a standard schedule stored in a database, A schedule establishing unit for establishing an overall schedule and an activity schedule of the mobile terminal; A work process aggregation unit for collecting and aggregating actual work processes of the project; A user interface unit for providing a user interface screen so that a user can request a project related content and displaying requested contents; A delivery delay estimating unit for comparing the actual work process and a project schedule to determine a degree of delay possibility, grouping the two or more groups according to the degree of delay possibility, and controlling the delay result to be displayed separately on the interface screen; To a project management apparatus.

발전소, 선박건조, 플랜트 등과 같은 대규모 사업에는 많은 세부 공정이 진행되고 프로젝트를 완료하기까지 많은 시간이 소요되므로 작업 공정에 따라 작업을 완료하는 것이 매우 중요하다. In large-scale projects such as power plants, shipbuilding, and plants, it is very important to complete work according to the work process, because many detailed processes are in progress and it takes time to complete the project.

이러한 사업은 설계, 구매, 시공, 시운전, 인도까지 일괄 공급하는 방식으로 이루어 지는데, 이를 EPC(Engineering, Procurement & Construction) 사업이라고 한다. This is done by supplying the design, procurement, construction, commissioning, and delivery in a lump sum, which is called EPC (Engineering, Procurement & Construction) business.

EPC 사업은 공사를 수행할 때 그 계획 과정에서 일정표가 작성되는데, 일반적으로 일정표는 전체 공사의 이정표 일정과 액티비티 정보를 이용하여 작성된다.When the EPC project is carried out, a schedule is prepared in the planning process. Generally, the schedule is created by using the milestone schedule and activity information of the whole construction.

이정표(Milestone)는 공사에 관한 주요 지표로서, 이정표 일정은 전체 공사에서 해당 이정표의 달성이 요구되는 시점을 말한다. 액티비티(Activity)는 공사의 단위 공정을 말하는 것으로서, 액티비티 정보에는 해당 액티비티가 수행되어야 하는 일자, 공기(工期), 타 액티비티와의 상호연관관계 등이 포함된다.Milestone is a key indicator of construction, and the milestone schedule refers to the time when the milestone in the whole construction is required to be achieved. Activity refers to the unit process of the construction. The activity information includes the date on which the activity is to be performed, air (construction period), and interrelationship with other activities.

공사 프로젝트가 대형화되고 공사기간이 장기화될수록 계획업무(Planning)가 중요해지고 있다. 최근에는 EPC 사업을 수행하는 핵심적인 업무들을 통합 관리하는데 EVM 시스템(Erned Value Management System)이 적용되고 있다.As the construction project becomes larger and the construction period becomes longer, planning is becoming more important. In recent years, the EVM system (Erned Value Management System) has been applied to the integrated management of core tasks for EPC business.

상기 EVM 시스템은 건설공사의 원가관리, 견적, 공사관리 등을 유기적으로 연결하여 종합적으로 관리하는 시스템으로서, 실행예산을 평가하고, 추후공정에 대한 예측을 가능하게 함으로써 공사관리의 효율을 향상시키며, 비용과 일정계획 대비 성과를 미리 예측하여 현재 공사수행의 문제분석과 대책을 수립할 수 있다.The EVM system is a system that collectively manages cost management, estimating, and construction management of the construction work by organically linking it. It evaluates the execution budget and makes it possible to forecast future processes, thereby improving the efficiency of construction management. It is possible to analyze the problem of current construction work and establish countermeasures by predicting the cost versus the schedule.

이러한 EVM 시스템을 이용해 건설이나 조선 등의 사업 관리하는 기술의 일 예가 대한민국 특허 등록번호 제10-0927953호(2009년 11월 24일 공고, 이하 '특허문헌 1'이라 함), 대한민국 특허 공개번호 10-2012-0121634호(2012년 11월 6일 공개, 이하 '특허문헌 2'라 함)등에 개시되어 있다.An example of a technology for managing a business such as construction or shipbuilding using the EVM system is disclosed in Korean Patent Registration No. 10-0927953 (published on Nov. 24, 2009, hereinafter referred to as Patent Document 1), Korean Patent Publication No. 10 -2012-0121634 (published on November 6, 2012, hereinafter referred to as "Patent Document 2").

특허문헌 1에는 클라이언트 서버(CS) 기반의 Http Remoting을 이용한 스마트 클라이언트(Smart Client) 방식으로 통합적인 컴퓨터 데이터베이스를 구축하고, 기업에서 시행하고 있거나 시행 계획에 있는 토목분야 건설사업에 대한 공정 공사비를 통합함으로써 예산관리, 일정관리, 물량분개, 하도관리, 기성관리, 진도관리 및 성과분석 등의 정보를 통합적으로 관리하고 경영의 효율화를 기할 수 있는 공정 공사비 통합관리기법(EVM)을 이용한 전사적 프로젝트 통합관리시스템 및 방법이 개시되어 있다.Patent Document 1 discloses an integrated computer database by a smart client method using Http Remoting based on a client server (CS), and integrates the construction cost of the construction work for the civil engineering field in the enterprise (EVM), which can integrate management of information such as budget management, schedule management, quantity indentation, underflow management, off-the-shelf management, progress management and performance analysis, A system and method are disclosed.

특허문헌 2에는 특정 프로젝트(예컨대, 건설공사 등)를 수행함에 있어서 프로젝트에 따른 구조물에 대한 EVMS(Earned Value Management System) 데이터를 설정하는 과정, 구조물의 2차원 도면 데이터로부터 3차원 모델을 생성하는 과정, 3차원 모델을 EVMS 데이터와 연계하는 과정, 3차원 모델을 웹상에서 시뮬레이션을 위해 인터넷 모델로 변환하는 과정을 포함하여 공정과 비용을 웹 기반으로 제공되는 3차원 모델과 연계하여 관리할 수 있는 공정 및 비용 관리를 위한 웹 기반의 BIM 시스템 및 그의 운용 방법이 개시되어 있다. Patent Document 2 describes a process of setting up EVMS (Earned Value Management System) data on a structure according to a project in performing a specific project (for example, construction work), a process of generating a three-dimensional model from two- , The process of linking the 3D model with the EVMS data, the process of converting the 3D model from the web to the Internet model for simulation, and the process that can be managed in connection with the 3D model provided with the web-based process and cost And a web-based BIM system for managing costs and an operation method thereof.

하지만 이러한 종래기술에는 공정 및 비용관리를 일괄적으로 관리하고 있어 공정 정도를 한눈에 파악하기 어렵고, 사용이 복잡하다는 문제점이 있다. However, this prior art has a problem in that it is difficult to grasp the degree of process at a glance and its use is complicated because the process and cost management are managed collectively.

대한민국 특허 등록번호 제10-0927953호Korean Patent Registration No. 10-0927953 대한민국 특허 공개번호 10-2012-0121634호Korean Patent Publication No. 10-2012-0121634

본 발명이 해결하고자 하는 과제는, 단위 작업별 공정 정도를 파악하여 전제 프로젝트의 지연 발생 정도를 시각적으로 표시할 수 있는 작업 공정 관리 장치를 제공하는 것이다. SUMMARY OF THE INVENTION It is an object of the present invention to provide a work process control device capable of visually indicating the degree of delay of a premade project by grasping the degree of process by unit work.

상기와 같은 기술적 과제를 해결하기 위해, 본 발명의 일 실시예에 따른 프로젝트 관리 장치는 전사자원관리시스템으로부터 작업분류체계, 프로젝트 발주서에 대한 정보, 및 작업지시에 대한 정보를 전달받아 데이터베이스에 저장되어 있는 표준일정과 비교하여 해당 프로젝트의 전체 일정 및 액티비티 일정을 수립하는 일정수립부; 상기 프로젝트의 실제 작업 공정을 수집하여 집계하는 작업공정 집계부; 사용자 인터페이스 화면을 제공하여 사용자가 프로젝트 관련 내용을 요청할 수 있도록 하고, 요청된 내용을 표시하는 사용자 인터페이스부; 및 상기 실제 작업 공정과 프로젝트 일정을 비교하여 지연가능성 정도를 판단하고, 지연 가능성 정도에 따라 2개 이상으로 분류하여 그룹핑하고, 지연결과가 상기 인터페이스 화면에 구분되어 표시되도록 제어하는 납품지연 예상부;를 포함할 수 있다. In order to solve the above technical problems, the project management apparatus according to an embodiment of the present invention receives information on a work classification system, information on a project order book, and work instruction from an enterprise resource management system, A schedule establishment unit for establishing an overall schedule and an activity schedule of the project in comparison with the standard schedule; A work process aggregation unit for collecting and aggregating actual work processes of the project; A user interface unit for providing a user interface screen so that a user can request a project related content and displaying requested contents; A delivery delay estimating unit for comparing the actual work process and a project schedule to determine a degree of delay possibility, grouping the two or more groups according to the degree of delay possibility, and controlling the delay result to be displayed separately on the interface screen; . ≪ / RTI >

또한, 본 발명의 일 실시예에 따른 프로젝트 관리 장치에서, 상기 일정수립부는, 상기 전사자원관리 시스템의 구매 정보를 기반으로 상기 프로젝트의 전체 일정을 수립하는 마스터 일정 수립부; 상기 전사자원관리 시스템의 작업지시 정보를 기반으로 생산 액티비티별 일정을 수립하는 생산 일정 수립부; 및 사용자가 입력한 설걔 내용을 기반으로 설계 액티비티별 일정을 수립하는 설계 일정 수립부를 포함할 수 있다. Also, in the project management apparatus according to an embodiment of the present invention, the schedule establishing unit may include a master schedule establishing unit for establishing an overall schedule of the project based on purchase information of the enterprise resource management system; A production schedule establishing unit for establishing a schedule for each production activity based on the work instruction information of the enterprise resource management system; And a design schedule establishing unit for establishing a schedule for each design activity based on the contents of the input by the user.

또한, 본 발명의 일 실시예에 따른 프로젝트 관리 장치에서, 상기 납품지연 예상부는, 상기 프로젝트의 액티비티 일정의 여유기간이 '0'보다 작은 액티비티 공정을 제1 그룹으로 분류하고, 상기 프로젝트의 액티비티 일정의 여유기간이 '0' 이상이고 미리 설정된 기준일 보다 작은 액티비티 공정을 제2 그룹으로 분류하고, 상기 프로젝의 액티비티 일정의 여유기간이 상기 기준일 이상인 액티비티 공정을 제3 그룹으로 분류할 수 있다. Also, in the project management apparatus according to an embodiment of the present invention, the delivery delay estimating unit classifies the activity processes whose free period of the activity schedule of the project is less than 0, into the first group, The activity process having an allowance period of 0 or more and smaller than a preset reference date may be classified into a second group and an activity process in which an allowance period of the activity schedule of the project is equal to or greater than the reference date may be classified into a third group.

또한, 본 발명의 일 실시예에 따른 프로젝트 관리 장치에서, 상기 납품지연 예상부는 상기 그룹핑된 작업 공정이 색상을 달리하여 인터페이스 화면에 표시되도록 제어할 수 있다. In the project management apparatus according to an embodiment of the present invention, the delivery delay estimating unit may control the grouped work processes to display on the interface screen with different colors.

또한, 본 발명의 일 실시예에 따른 프로젝트 관리 장치에서, 상기 프로젝트 관리 장치는, 상기 진행중인 전체 프로젝트를 리스트업하고, 사용자가 전체 프로젝트 리스트 중 어느 하나를 선택하는 경우, 해당 프로젝트와 관련된 하위 작업 일정들이 바 형태로 상기 사용자 인터페이스부에 표시되도록 제어하는 프로젝트 관리부를 더 포함할 수 있다. In addition, in the project management apparatus according to an embodiment of the present invention, when the user selects any one of the entire project list, the project management apparatus lists up the entire project in progress, To be displayed on the user interface unit in the form of a bar.

또한, 본 발명의 일 실시예에 따른 프로젝트 관리 장치에서, 상기 프로젝트 관리부는 진행중인 전체 프로젝트 중, 설계 단계인 프로젝트와 생산단계인 프로젝트를 구분하여 상기 인터페이스부에 표시되도록 제어할 수 있다. Also, in the project management apparatus according to an embodiment of the present invention, the project management unit may divide a project, which is a design stage, from a project, which is a production stage, and control the display to be displayed on the interface unit.

또한, 본 발명의 일 실시예에 따른 프로젝트 관리 장치에서, 상기 프로젝트 관리 장치는, 여러 프로젝트에 대한 정보를 취합하여 리스트업하거나 통계 정보를 생성하여 상기 인터페이스 화면에 표시되도록 제어할 수 있다. In addition, in the project management apparatus according to an embodiment of the present invention, the project management apparatus can collect information on various projects and list up or generate statistical information to be displayed on the interface screen.

본 발명에 의한 프로젝트 관리 장치에 의하면, 프로젝트 일정을 통합하여 관리할 수 있으며 납기 지연이 예상되는 프로젝트를 쉽게 파악할 수 있다. According to the project management apparatus of the present invention, it is possible to integrate and manage the project schedule, and it is possible to easily grasp the project whose delivery delay is expected.

또한, 본 발명에 의한 프로젝트 관리 장치에 의하면, 설계도면, 구매 /입고, 직영 제작, 외주 제작, 출하까지의 통합 일정을 온라인에서 실시간으로 확인 가능하다. Further, according to the project management apparatus according to the present invention, it is possible to check the integration schedule from design drawing, purchase / receipt, direct production, outsourced production, and shipment on-line in real time.

또한, 본 발명에 의한 프로젝트 관리 장치에 의하면, 타 부서와의 커뮤니케이션을 증대시킬 수 있다. Further, according to the project management apparatus of the present invention, communication with other departments can be increased.

또한, 본 발명에 의한 프로젝트 관리 장치에 의하면, 일정을 통합하여 관리하고 회의를 통해서 납기일을 선행 관리하여 리스크를 줄일 수 있다. Further, according to the project management apparatus of the present invention, the schedule can be integrated and managed, and the risk can be reduced by pre-managing the delivery date through the meeting.

도 1은 본 발명의 일 실시예에 따른 프로젝트 관리 장치를 나타낸 것이다.
도 2는 도 1에 도시된 작업분류체계 데이터베이스의 계층 구조를 나타낸 것이다.
도 3은 도 2에 도시된 퍼실리티 중에서 시공 워크를 산출하는 매트리스를 예시한 나타낸 것이다.
도 4는 본 발명의 일 실시예에 따른 일정 생성의 개념을 도시한 것이다.
도 5는 본 발명의 일 실시예에서 따른 프로젝트 관리 장치에서, 여유 기간에 따라 납품 지연을 표시하는 예시를 나타낸 것이다.
도 6은 본 발명의 일 실시예에 따른 인터페이스 화면을 나타낸 것이다.
도 7은 본 발명의 다른 일 실시예에 따른 인터페이스 화면을 나타낸 것이다.
도 8은 본 발명의 다른 일 실시예에 따른 인터페이스 화면을 나타낸 것이다.
1 illustrates a project management apparatus according to an exemplary embodiment of the present invention.
FIG. 2 shows a hierarchical structure of the work classification system database shown in FIG. 1. FIG.
Fig. 3 is an illustration of a mattress that produces a construction work among facilities shown in Fig. 2. Fig.
4 illustrates a concept of schedule creation according to an embodiment of the present invention.
FIG. 5 illustrates an example in which a delivery delay is displayed according to an allowance period in a project management apparatus according to an exemplary embodiment of the present invention.
6 illustrates an interface screen according to an embodiment of the present invention.
7 illustrates an interface screen according to another embodiment of the present invention.
FIG. 8 illustrates an interface screen according to another embodiment of the present invention.

본 발명은 다양한 변경을 가할 수 있고 여러가지 실시예를 가질 수 있는바, 특정 실시예들을 도면에 예시하고 상세한 설명에 상세하게 설명하고자 한다. 그러나, 이는 본 발명을 특정한 실시 형태에 대해 한정하려는 것이 아니며, 본 발명의 사상 및 기술범위에 포함되는 모든 변경, 균등물 내지 대체물을 포함하는 것으로 이해되어야 한다.While the invention is susceptible to various modifications and alternative forms, specific embodiments thereof are shown by way of example in the drawings and will herein be described in detail. It should be understood, however, that the invention is not intended to be limited to the particular embodiments, but includes all modifications, equivalents, and alternatives falling within the spirit and scope of the invention.

도면들에 있어서, 본 발명의 실시 예들은 도시된 특정 형태로 제한되는 것이 아니며 명확성을 기하기 위하여 과장된 것이다. 본 명세서에서 특정한 용어들이 사용되었으나. 이는 본 발명을 설명하기 위한 목적에서 사용된 것이며, 의미 한정이나 특허 청구 범위에 기재된 본 발명의 권리 범위를 제한하기 위하여 사용된 것은 아니다.In the drawings, embodiments of the present invention are not limited to the specific forms shown and are exaggerated for clarity. Although specific terms are used herein, It is to be understood that the same is by way of illustration and example only and is not to be taken by way of limitation of the scope of the appended claims.

본 명세서에서 ‘및/또는’이란 표현은 전후에 나열된 구성요소들 중 적어도 하나를 포함하는 의미로 사용된다. 또한, ‘연결되는/결합되는’이란 표현은 다른 구성요소와 직접적으로 연결되거나 다른 구성요소를 통해 간접적으로 연결되는 것을 포함하는 의미로 사용된다. 본 명세서에서 단수형은 문구에서 특별히 언급하지 않는 한 복수형도 포함한다. 또한, 명세서에서 사용되는 ‘포함한다’또는 ‘포함하는’으로 언급된 구성요소, 단계, 동작 및 소자는 하나 이상의 다른 구성요소, 단계, 동작 및 소자의 존재 또는 추가를 의미한다.The expression " and / or " is used herein to mean including at least one of the elements listed before and after. Also, the expression " coupled / connected " is used to mean either directly connected to another component or indirectly connected through another component. The singular forms herein include plural forms unless the context clearly dictates otherwise. Also, as used herein, "comprising" or "comprising" means to refer to the presence or addition of one or more other components, steps, operations and elements.

또한, '제1, 제2' 등과 같은 표현은, 복수의 구성들을 구분하기 위한 용도로만 사용된 표현으로써, 구성들 사이의 순서나 기타 특징들을 한정하지 않는다.Also, the expressions such as 'first, second', etc. are used only to distinguish between plural configurations, and do not limit the order or other features among the configurations.

실시예들의 설명에 있어서, 각 층(막), 영역, 패턴 또는 구조물들이 기판, 각 층(막), 영역, 패드 또는 패턴들의 "상/위(on)"에 또는 "하/아래(under)"에 형성된다는 기재는, 직접(directly) 또는 다른 층을 개재하여 형성되는 것을 모두 포함한다. 각 층의 상/위 또는 하/아래에 대한 기준은 도면을 기준으로 설명한다.In the description of the embodiments, it is to be understood that each layer (film), area, pattern or structure may be referred to as being "on" or "under / under" Quot; includes all that is formed directly or through another layer. The criteria for top / bottom or bottom / bottom of each layer are described with reference to the drawings.

이하, 첨부된 도면을 참조하여 본 발명의 실시예에 따른 프로젝트 관리 장치 및 방법을 상세히 설명한다. Hereinafter, an apparatus and method for managing a project according to an embodiment of the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 발명의 일 실시예에 따른 프로젝트 관리 장치(30) 및 이와 관련된 시스템을 도시한 블럭도이다. FIG. 1 is a block diagram illustrating a project management apparatus 30 and a system related thereto according to an embodiment of the present invention.

도 1을 참조하면, 상기 시스템은 데이터베이스(10), 전사자원관리 시스템(Enterprise Resource Planning, ERP, 20), 및 프로젝트 관리 장치(30)를 포함할 수 있다. Referring to FIG. 1, the system may include a database 10, an Enterprise Resource Planning (ERP) 20, and a project management device 30.

상기 데이터베이스(10)는 현장 시공 중심으로 분류되어 작업분류체계(Work Breakdown Structure, WBS) 및 그에 따른 표준화된 일정을 저장한다. The database 10 is classified as a site construction center and stores a work breakdown structure (WBS) and a standardized schedule accordingly.

상기 데이터베이스(10)에 저장되는 작업분류체계는 도 2에 도시된 바와 같이, 프로젝트(Project), 유닛(unit), 페이즈(phase), 퍼실리티(facility), 워크(works)(또는 워크 패키지) 및 액티비티(Activity)의 6단계로 표준화된 계층(hierarchy) 구조로 구성될 수 있으며 각각의 계층 레벨에는 표준 일정이 저장되어 있다.The task classification scheme stored in the database 10 may include a project, a unit, a phase, a facility, a work (or a work package), and a task It can be configured as a hierarchical structure that is standardized in six stages of activity, and standard schedules are stored at each hierarchical level.

이를 위해, 데이터베이스(10)는 각 레벨별 데이터를 저장하는 프로젝트, 유닛, 페이즈, 퍼실리티, 워크 및 액티비티 데이터베이스(11 내지 16)를 포함하는 표준화된 데이터베이스 구조로 구축될 수 있다.To this end, the database 10 may be constructed in a standardized database structure including a project, a unit, a phase, a facility, a work and an activity database 11 to 16 for storing data for each level.

상세하게 설명하면, 데이터베이스(10)에 저장되는 작업분류체계는 현장 시공을 중심으로 퍼실리티와 워크 패키지를 표준화하여 전체 구조를 구성하고, 프로젝트의 설계, 구매, 시공 각 페이즈별로 동일한 명칭의 설비 및 공사를 적용한 하위 데이터베이스로 구축되고, 각 페이즈별 표준 공정 일정이 저장될 수 있다.In detail, the work classification system stored in the database 10 includes a standard structure of facilities and work packages, centering on field construction, and constitutes an overall structure. The system includes a facility having the same name for each design, purchase, , And a standard process schedule for each phase can be stored.

데이터베이스(10)의 계층 구조를 상세하게 설명하면 다음과 같다.The hierarchical structure of the database 10 will be described in detail as follows.

제1 레벨인 프로젝트를 저장하는 프로젝트 데이터베이스(11)는 시설물의 개념을 갖는 명칭으로 프로젝트를 설정하고, 제2 레벨인 유닛을 저장하는 유닛 데이터베이스(12)는 프로젝트의 성격에 따라 사업에 필요한 유닛이 있는 경우에 프로젝트 하위 레벨에 유닛을 설정해서 저장한다. 만약, 유닛이 없는 경우에는 생략될 수 있다.A project database 11 for storing a project of a first level sets a project in a name having a concept of a facility and a unit database 12 for storing a unit of a second level includes units necessary for a business according to the nature of the project If there is, set the unit at the lower level of the project and save it. If there is no unit, it can be omitted.

제3 레벨인 페이즈를 저장하는 페이즈 데이터베이스(13)는 설계(Engineering), 구매(Procurement), 시공(Construction)과 스타트업(start-up)을 페이즈 명 및 각각의 페이즈에 대한 표준 공정 일정이 저장될 수 있다. The phase database 13 storing the phase of the third level stores the phase name and the standard process schedule for each phase in the order of design, engineering, procurement, construction, and start- .

제4 레벨인 퍼실리티를 저장하는 퍼실리티 데이터베이스(14)는 도 3에 도시된 바와 같이, 현장 시공 워크를 기반으로 해서 프로젝트를 수행하기 위한 각종 설비나 목적물로 퍼실리티를 설정하고, 각각의 퍼실리티에 대한 표준 공정 일정이 저장될 수 있다. 예를 들어, 발전소 건설 프로젝트인 경우, 퍼실리티는 보일러, 터빈 및 발전기, 스팀 시스템, 워터시스템 등 총 90여 개의 항목으로 표준화되어 설정되며, 각 퍼실리티 항목에는 고유의 코드번호가 부여되어 각각의 퍼실리티에 대한 표준 공정 일정이 저장될 수 있다.As shown in FIG. 3, the facility database 14 for storing facilities at the fourth level is a facility for setting facilities by various facilities or objects for performing a project based on a site construction work, The process schedule can be saved. For example, in the case of a power plant construction project, facilities are standardized with a total of 90 items such as boilers, turbines, generators, steam systems, and water systems. Each facility has its own code number assigned to each facility A standard process schedule can be stored.

이와 같이 표준화된 항목은 현장 시공 워크에 따라 변경이나 삭제 또는 추가될 수 있다.Such standardized items can be changed, deleted or added according to the site construction work.

그리고 퍼실리티 데이터베이스(14)는 계통이나 구역(area), 설비유형(system)을 페이즈로 설정할 수도 있다.And the facility database 14 may set the system, the area, and the facility type in a phase.

예를 들어, 토목/건축 퍼실리티는 관련 퍼실리티 유형의 구역 혹은 해당 빌딩 명으로 설정되고, 기계/전기설비는 설비유형(system)에 따라 설정될 수 있다. 이러한 퍼실리티는 시공 페이즈와 동일하게 설계 및 구매 페이즈에도 동일한 명칭으로 생성될 수 있다.For example, the civil / architectural facility can be set to a zone of the relevant facility type or the name of the building, and the mechanical / electrical facility can be set according to the facility type (system). This facility can be created with the same name in the design and purchase phases as in the construction phase.

제5 레벨인 워크를 저장하는 워크 데이터베이스(15)는 퍼실리티를 구현하기 위한 필요시공 작업인 워크를 토목, 건축, 기계, 전기 워크 관점에서 액티비티의 그룹으로 설정해서 저장할 수 있다. 이와 같이 설정되는 워크는 공정 및 원가 통합관리를 연결하는 역할을 한다. The work database 15 storing the fifth level work can set and store work as a necessary construction work for implementing facilities as a group of activities from the perspective of civil engineering, construction, machinery, and electric work. The work that is set in this way serves to link process and cost integrated management.

예를 들어, 발전소 건설 프로젝트에서는 파일링 워크, 콘크리트 워크, 스틸 워크 등 30여 개의 항목으로 표준화되어 설정되며, 각 워크 항목에는 고유의 코드번호 및 표준 공정 일정이 부여될 수 있다.For example, in a power plant construction project, 30 items such as a piling work, a concrete work, and a steel work are standardized and set, and each work item can be given a unique code number and a standard process schedule.

제6 레벨인 액티비티를 저장하는 액티비티 데이터베이스(16)는 워크를 구성하는 작업단위인 각 액티비티를 견적서(Bill of Quantities, BOQ)의 내역항목이나 각 페이즈, 즉 설계, 구매, 시공 페이즈의 특성을 반영하여 정의하여 저장할 수 있다. 여기서, 액티비티는 자원(Resource)의 단가 매핑 최저단위이기도 하다. 그리고 각각의 액티비티에 대한 표준 공정 일정이 저장된다. The activity database 16 for storing activity as the sixth level reflects each activity, which is a work unit constituting the work, as a detail item of the bill of quantities (BOQ) or characteristics of each phase, namely, design, purchase, and construction phases Can be defined and stored. Here, the activity is also the minimum unit of unit price mapping of resources. A standard process schedule for each activity is stored.

이와 같이, 데이터베이스(10)는 프로젝트 수행에 필요한 공정을 계층(hierarchy)으로 구성하고, 시공워크를 세분화하여 관리하도록 작업분류체계로 분류하고 각각의 하위 공정(액티비티)별 표준화한 일정을 저장한다. In this manner, the database 10 organizes the processes necessary for project execution in a hierarchy, classifies the construction work into sub-types and manages them, and stores a standardized schedule for each sub-process (activity).

상기 전사자원관리 시스템(20)은 작업분류체계(WBS)를 확정하고, 발주서(purchase order)에 대한 정보, 작업지시(job order)에 대한 정보 및 예산 관련 정보 등 프로젝트 수행에 필요한 다양한 정보를 프로젝트 관리 장치(30)로 전송한다. 이때 공급사 수행 상세 일정과 같은 외주관리 정보도 함께 전송될 수 있다. The enterprise resource management system 20 determines a work classification system (WBS), and various information necessary for project execution such as information on a purchase order, information on a job order, To the management device (30). At this time, the outsourced management information such as the vendor execution detailed schedule can also be transmitted together.

상기 전사자원관리 시스템(20)은 이 외에도 프로젝트의 비용관리, 실적 관리, 외주 진도 관리 등 다양한 정보를 프로젝트 관리 장치로 전송할 수 있다. The enterprise resource management system 20 can also transmit various information such as cost management, performance management, and outsourcing progress management of the project to the project management apparatus.

상기 프로젝트 관리 장치(30)는 사용자 인증부(31), 일정 수립부(32), 작업공정 집계부(33), 납품지연 예측부(34), 사용자 인터페이스부(35), 및 프로젝트 관리부(36)를 포함할 수 있다. The project management apparatus 30 includes a user authentication unit 31, a schedule establishing unit 32, a work process aggregation unit 33, a delivery delay estimating unit 34, a user interface unit 35, and a project management unit 36 ).

상기 사용자 인증부(31)는 사용자 정보를 미리 저장하고 있으며, 아이디 및 비밀번호가 입력되면 미리 저장된 정보와 비교하여 일치하는지 여부를 판단하고, 일치하는 경우 접근을 허용한다. 미리 저장된 사용자 정보는 사내 임직원일 수 있다. 그리고 사용자 인증부는 사용자를 일반 직원과 파트장 또는 팀장으로 구분하여 관리할 수 있다. 하기에서 설명되는 프로젝트 관리부(36)는 사용자가 파트장 또는 팀장인 경우에는 개인 업무와 더불어 파트 또는 팀의 전체 업무가 표시되도록 할 수 있다. The user authentication unit 31 stores the user information in advance. When the user ID and the password are inputted, the user authentication unit 31 compares the information with the previously stored information to determine whether they match or not. Pre-stored user information can be in-house employees. The user authentication unit can manage the user by dividing the user into a general staff member and a part or team leader. The project management unit 36 described below can display the whole work of the part or the team together with the personal work when the user is a part or team leader.

상기 일정수립부(32)는 전사자원관리시스템(10)으로부터 수신한 작업분류체계, 구매정보, 및 작업지시 정보 등 프로젝트와 관련된 정보를 수신하고 이를 기반으로 해당 프로젝트의 일정을 수립한다. 즉, 해당 프로젝트가 작업분류체계상 어디에 해당하는지 판단하고, 데이터베이스에 저장되어 있는 해당 작업분류체계의 표준 일정과 비교하여 수행할 프로젝트의 전체 일정 및 하위 작업 일정(액티비티별 일정)을 수립한다. The schedule establishing unit 32 receives information related to a project, such as a work classification scheme, purchase information, and work instruction information received from the enterprise resource management system 10, and establishes a schedule of the project based on the information. That is, it judges where the project corresponds to the work classification system and compares the total schedule and the sub-work schedule (activity-specific schedule) of the project to be performed by comparing with the standard schedule of the corresponding job classification system stored in the database.

예를 들어 계약 발효일로부터 납품기일까지의 기일이 표준일정보다 긴 경우에는 그에 따라 세부일정도 길게 조정하고 반대의 경우에는 짧게 조정한다. For example, if the expiration date from the effective date of the contract to the delivery date is longer than the standard schedule, adjust the long schedule accordingly and shorten the schedule in the opposite case.

도 4는 일정수립의 과정을 간략히 도시한 것이다. FIG. 4 schematically shows a process of constant establishment.

도 4를 참조하면, 일정수립부(32)는 기본적으로 표준화된 일정을 사용자가 지정한 신규 공사 프로젝트의 공사기간 또는 전사자원관리 시스템(10)에서 수신된 프로젝트 관련 정보에 맞추어 조정 내지 신축하는 방식을 통해 신규 공사 프로젝트의 일정을 생성한다.4, the schedule establishing unit 32 basically adjusts the standardized schedule in accordance with the construction period of the new construction project designated by the user or the project related information received from the enterprise resource management system 10 Create a schedule of new construction projects through.

도 4의 (a)에 도시된 예와 같이 표준 일정에 대응하는 표준공사기간이 신규 공사 프로젝트의 공사기간보다 짧으면 표준 일정을 신장하여 신규 공사 프로젝트의 일정을 만든다.If the standard construction period corresponding to the standard schedule is shorter than the construction period of the new construction project as shown in FIG. 4 (a), the standard schedule is extended to schedule the new construction project.

도 4의 (b)에 도시된 예와 같이 표준 일정에 대응하는 표준공사기간이 신규 공사 프로젝트의 공사기간보다 길면 표준 일정을 단축하여 신규 공사 프로젝트의 일정을 만든다.If the standard construction period corresponding to the standard schedule is longer than the construction period of the new construction project as shown in FIG. 4 (b), the standard schedule is shortened to schedule the new construction project.

다만, 표준 일정이 고정되어 있다고 하더라도 신규 공사 프로젝트의 이정표 일정이나 액티비티 정보가 동일한 비율로 처리되는 않는 경우도 있을 수 있으며, 사용자가 일정의 생성을 더욱 세밀하게 제어할 수도 있다.However, even if the standard schedule is fixed, the milestone schedule or activity information of the new construction project may not be processed at the same rate, and the user may control the generation of the schedule more finely.

구체적으로 살펴보면, 일정 수립부(32)는 프로젝트 일정은 프로젝트의 전체 일정을 수립하는 마스터 일정 수립부(321), 생산 일정 수립부(322), 및 설계 일정 수립부(323)를 포함할 수 있다. Specifically, the schedule establishing unit 32 may include a master schedule establishing unit 321, a production schedule establishing unit 322, and a design schedule establishing unit 323 for establishing an overall schedule of the project .

상기 마스터 일정 수립부는 구매 정보를 바탕으로 프로젝트의 전체 일정을 수립하고, 상기 생산 일정 수립부는 작업 지시 정보를 바탕으로 생산 액티비티별 일정을 수립하고, 설계 일정 수립부는 사용자가 입력한 설계 내용을 기반으로 설계 액티비티별 일정을 수립한다. The master schedule establishing unit establishes the entire schedule of the project based on the purchase information, the production schedule establishing unit establishes a schedule for each production activity based on the work instruction information, and the design schedule establishing unit Establish a schedule for each design activity.

상기 진도율 집계부(33)는 실제 설계, 구매, 시공의 각 액티비티별 진도율을 집계한다. The progress ratio aggregation unit 33 compiles the progress rate for each activity of actual design, purchase, and construction.

납품지연 예측부(34)는 일정수립부(32)에서 수립된 일정과 진도율 집계부에서 집계된 실제 진도율을 비교하여 납품지연 가능성을 예측한다. 사용자가 지연 가능성을 쉽게 파악할 수 있도록, 프로젝트의 여러 액티비티 중 지연 가능성이 높은 액티비티와 그렇지 않은 액티비티를 그룹핑하여 상기 사용자 인터페이스부(35)에 구분하여 표시하도록 제어한다. The delivery delay estimating unit 34 predicts the delivery delay possibility by comparing the schedule established in the schedule establishing unit 32 with the actual progress rate calculated by the progress rate aggregating unit. In order to allow the user to easily grasp the delay possibility, an activity having high possibility of delay and an activity not likely to be delayed among the various activities of the project are grouped and displayed in the user interface unit 35 in a controlled manner.

도 5는 납품지연 예측 결과를 3가지로 구분하여 표시하는 예를 도시한 것이다. FIG. 5 shows an example in which the delivery delay prediction results are classified into three types and displayed.

도 5를 참조하면, 일정 대비 여유 기간이 '0'보다 작은 경우는 빨간색으로 표시하고, 여유기간이 '0'보다 크거나 같고 '30'일 미만인 경우에는 노란색으로 표시하고, 여유기간이 '30'일 이상인 경우에는 초록색으로 표시할 수 있다. 본 발명에서 여유 기간이란 일정 수립부에서 수립된 일정에서 정해진 납품 기일에서 실제 작업 진도를 뺀 것을 의미한다. Referring to FIG. 5, in the case where the allowance period for schedule comparison is less than 0, it is indicated in red. In the case where the allowance period is greater than or equal to 0 and less than 30 days, yellow is displayed, 'Days, it can be displayed in green. In the present invention, an allowance period means that the actual work progress is subtracted from the delivery date determined in the schedule established in the schedule establishing section.

본 실시예에서는 지연기준을 30일로 설정했지만 필요에 따라 더 짧게 또는 더 길게 설정할 수 있다. 즉, 30일은 여유 기간이 얼마 남지 않아 지연 가능성이 있음을 표시하기 위한 하나의 기준일이고, 이 기준일은 변경가능하다. Although the delay reference is set to 30 days in this embodiment, it can be set shorter or longer as necessary. That is, 30 days is a reference date for indicating that there is a possibility of delay due to a short margin period, and this reference date can be changed.

상기 사용자 인터페이스부(35)는 사용자가 자신의 업무 현황 및 프로젝트 진행 현황을 파악할 수 있도록 다양한 인터페이스 화면을 제공할 수 있다. The user interface unit 35 may provide various interface screens so that the user can grasp his / her work status and project progress status.

도 6은 이러한 인터페이스 화면의 예를 도시한 것이다. 도 6은 사용자 인터페이스의 일 실시예를 도시한 것이고, 인터페이스 화면은 다양한 형태로 변경 가능하다. Fig. 6 shows an example of such an interface screen. FIG. 6 illustrates an embodiment of a user interface, and the interface screen can be changed in various forms.

도 6에 도시된 바와 같이, 인터페이스 화면에는 Main, PJT 일정계획생성, PJT Schedule, 나의 할 일, 프로젝트 일정 확인(PJT Schedule 확인), 리포트(REPORT), PJT 일정 계획 관리, 표준 일정 괸리, 게시판, Workflow, 관리자 등 다양한 탭이 표시될 수 있다. As shown in FIG. 6, the interface screen includes Main, PJT schedule creation, PJT schedule, My task, Project schedule confirmation (PJT schedule confirmation), REPORT, PJT schedule management, Various tabs such as Workflow, Manager, etc. can be displayed.

도 6은 상기 다수의 탭 중 Main탭과 RERPORT탭이 활성화된 예를 도시한 것이다 FIG. 6 illustrates an example in which the Main tab and the RERPORT tab are activated among the plurality of tabs

사용자가 메인탭을 선택하면 표시된 바와 같이 사용자의 업무가 도면 번호 61과 같이 표시되고, 표시된 항목에서 현재 업무(Job To-do)를 클릭하면, 현재 진행중인 업무 리스트가 도면 번호 62와 같이 리스트업된다. 그리고 사용자가 파트장 또는 팀장인 경우에는 개인 일정 뿐만 아니라 전체 일정을 확인할 수 있다. When the user selects the main tab, the task of the user is displayed as indicated by the drawing number 61 as shown, and when the current task (Job To-do) is clicked on the displayed item, the task list currently in progress is listed up as the drawing number 62 . And if the user is a department manager or a team leader, the entire schedule can be checked as well as individual schedule.

앞서 살펴본 바와 같이, 하나의 프로젝트에는 다수의 액티비티가 포함되어 있고, 각 액티비티별 납품 기일이 정해져 있다. 각각의 프로젝트에는 납품 기일에 따른 지연 가능성이 도면번호 63과 같이 색상을 달리하여 신호등 형태로 표시된다. As we have seen, a project contains a number of activities, and the delivery dates for each activity are fixed. In each project, the possibility of delays due to the delivery date is displayed in the form of traffic lights with different colors,

도 5에서 살펴본 바와 같이, 빨간색은 납품기일을 경과하여 여유기간이 '0'보다 적은 경우이고, 노란색은 납품기일이 0과 기준일 사이, 초록색은 납품기일이 기준일 이상인 경우이다. As can be seen from FIG. 5, red is the case when the allowance period is less than '0' after the delivery date, yellow is the case where the delivery date is between 0 and the reference date, and green is the delivery date is the reference date or more.

다시 도 6을 참조하며, 첫번째 프로젝트의 신한울 #1,2 T/G Schedule은 빨간색이 1개, 노란색이 6개, 초록색이 93개인데, 이는 신한울 #1,2 T/G 프로젝트에서 납품기일이 경과한 작업(액티비티)이 1개이고, 여유기간이 기준일보다 적게 남은 작업이 6개이고, 여유기간이 기준일 이상인 작업이 93개임을 표시한 것이다. Referring back to FIG. 6, the first project's Shinhan Wool # 1,2 T / G Schedule has 1 red, 6 yellow and 93 green, which are delivered from Shinhan Wool # 1,2 T / G project This indicates that there are one job (activity) that has passed the expiration date, six jobs that have an allowance period that is less than the reference date, and 93 jobs that have an allowance of more than the reference date.

사용자가 REPORT탭을 선택하면 프로젝트 납기 현황이나 프로젝트 진행 상황을 리스트 또는 그래프 형태로 볼 수 있다. 도면 번호 64는 리프트의 예를 도시한 것이다. When the user selects the REPORT tab, the project delivery status or project progress can be viewed in a list or graph form. Reference numeral 64 denotes an example of a lift.

도면번호 65는 리프트시에 작성될 수 있는 다른 형태의 통계 데이터를 표시한것으로, 착수일 준수일 및 완료일 준수일을 나타낸 그래프이다. Drawing No. 65 is a graph showing other types of statistical data that can be created at the time of lifting, that is, the date of adherence to the start date and adherence to the completion date.

또한, 상기 사용자 인터페이스부(35)는 프로젝트 일정 작성 및 실적 입력하는 인터페이스 화면을 더 포함할 수 있다. In addition, the user interface unit 35 may further include an interface screen for creating a project schedule and inputting an achievement.

상기 프로젝트 관리부(36)는 사용자 인터페이스부(35)를 통해 입력되는 사용자 입력 정보에 따라 프로젝트 정보를 필요한 형식으로 가공하여 상기 인터페이스부(35)에 표시되도록 제어한다. The project management unit 36 processes the project information into a required format according to the user input information input through the user interface unit 35 and controls the interface unit 35 to display the processed project information.

예를 들어, 도 7에 도시된 바와 같이, 사용자가 인터페이스 화면에서 프로젝트탭(PROJECT, 61))을 선택하면, 현재 진행중인 프로젝트가 도면 번호 62와 같이 리스트업되도록 제어하고, 사용자가 리스트 중 하나를 선택하면 선택된 프로젝트에 대한 하위 공정에 대한 일정이 도면 번호 63과 같이 바(bar) 형태로 표시되도록 제어할 수 있다. For example, as shown in FIG. 7, when the user selects a project tab (PROJECT, 61) on the interface screen, the current project is controlled to be listed up as indicated by reference numeral 62, The schedule for the sub-process for the selected project can be controlled to be displayed in the form of a bar as shown in FIG.

또한, 상기 프로젝트 관리부(35)는 사용자 인터페이스 화면에서 사용자가 리포트탭(REPORT)을 선택하면 프로젝트 진행 상황에 대한 리스트 또는 통계 현황을 작성하여 디스플레이도록 제어할 수 있다. In addition, when the user selects a report tab on the user interface screen, the project management unit 35 can control to create and display a list of project progress status or statistical status.

도 8은 프로젝트 일정 확인탭(PJT Schedule 확인)의 인터페이스 화면을 나타낸 것이다. 8 shows an interface screen of the project schedule confirmation tab (PJT schedule confirmation).

도 8을 참조하면, 프로젝트 리스트와 상세 정보리스트가 표시되어 있다. Referring to FIG. 8, a project list and a detailed information list are displayed.

도면번호 81은 구매 상세정보를 나타낸 것이고, 도면번호 82는 설계 상세 정보를 나타낸 것이고, 도면 번호 83은 프로젝트 세부 일정을 나타낸 것이고, 도면번호 84는 프로젝트 일정을 바 형태로 표시한 것이다. Reference numeral 81 denotes purchasing detailed information, reference numeral 82 denotes design detailed information, reference numeral 83 denotes a project detailed schedule, and reference numeral 84 denotes a project schedule in bar form.

상기와 같은 인터페이스 화면을 제공함으로써 프로젝트 및 아이템별로 고객 납기, 일정, 실 제작 일정을 그래프로 일자 및 그래프로 확인 가능하다. 또한, 설계, 생산, 구매, 외주 상세 현황도 한 화면에서 조회 가능하므로 타 업무 부서와의 커뮤니케이션을 증대시킬 수 있다. By providing the above-mentioned interface screen, it is possible to check the customer's delivery schedule, schedule, and actual production schedule for each project and item by graph and date and graph. In addition, the details of design, production, purchasing, and subcontracting details can be viewed from a single screen, so communication with other business units can be increased.

상기 인터페이스 화면은 프로젝트 관리부(36)의 제어에 의해 표시될 수 있다. The interface screen may be displayed under the control of the project management unit 36.

이상에서 본 발명에 따른 실시예들이 설명되었으나, 이는 예시적인 것에 불과하며, 당해 분야에서 통상적 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 범위의 실시예가 가능하다는 점을 이해할 것이다. 따라서, 본 발명의 진정한 기술적 보호 범위는 다음의 특허청구범위에 의해서 정해져야 할 것이다.While the invention has been shown and described with reference to certain preferred embodiments thereof, it will be understood by those skilled in the art that various changes and modifications may be made without departing from the spirit and scope of the invention as defined by the appended claims. Accordingly, the true scope of the present invention should be determined by the following claims.

10 : 데이터베이스
20 : 전사자원관리 시스템
30 : 프로젝트 관리 장치
10: Database
20: Enterprise resource management system
30: Project management device

Claims (7)

전사자원관리시스템으로부터 작업분류체계, 프로젝트 발주서에 대한 정보, 및 작업지시에 대한 정보를 전달받아 데이터베이스에 저장되어 있는 표준일정과 비교하여 해당 프로젝트의 전체 일정 및 액티비티 일정을 수립하는 일정수립부;
상기 프로젝트의 실제 작업 공정을 수집하여 집계하는 작업공정 집계부;
사용자 인터페이스 화면을 제공하여 사용자가 프로젝트 관련 내용을 요청할 수 있도록 하고, 요청된 내용을 표시하는 사용자 인터페이스부; 및
상기 실제 작업 공정과 프로젝트 일정을 비교하여 지연가능성 정도를 판단하고, 지연 가능성 정도에 따라 2개 이상으로 분류하여 그룹핑하고, 지연결과가 상기 인터페이스 화면에 구분되어 표시되도록 제어하는 납품지연 예상부; 를 포함하는 프로젝트 관리 장치.
A scheduling unit that receives information on a work classification system, information on a project order book, and information on a work order from an enterprise resource management system and establishes an overall schedule and activity schedule of the project in comparison with a standard schedule stored in the database;
A work process aggregation unit for collecting and aggregating actual work processes of the project;
A user interface unit for providing a user interface screen so that a user can request a project related content and displaying requested contents; And
A delivery delay estimating unit for comparing the actual work process and the project schedule to determine the degree of delay possibility, grouping the two or more groups according to the degree of delay possibility, and controlling the delay result to be displayed separately on the interface screen; The project management device comprising:
제1항에서, 상기 일정수립부는,
상기 전사자원관리 시스템의 구매 정보를 기반으로 상기 프로젝트의 전체 일정을 수립하는 마스터 일정 수립부,
상기 전사자원관리 시스템의 작업지시 정보를 기반으로 생산 액티비티별 일정을 수립하는 생산 일정 수립부, 및
사용자가 입력한 설걔 내용을 기반으로 설계 액티비티별 일정을 수립하는 설계 일정 수립부를 포함하는 프로젝트 관리 장치.
The apparatus of claim 1,
A master schedule establishing unit for establishing an overall schedule of the project based on purchase information of the enterprise resource management system,
A production schedule establishing unit for establishing a schedule for each production activity based on the work instruction information of the enterprise resource management system;
And a design schedule establishing unit for establishing a schedule for each design activity based on the contents of the input inputted by the user.
제2항에 있어서, 상기 납품지연 예상부는,
상기 프로젝트의 액티비티 일정의 여유기간이 '0'보다 작은 액티비티 공정을 제1 그룹으로 분류하고,
상기 프로젝트의 액티비티 일정의 여유기간이 '0' 이상이고 미리 설정된 기준일 보다 작은 액티비티 공정을 제2 그룹으로 분류하고,
상기 프로젝의 액티비티 일정의 여유기간이 상기 기준일 이상인 액티비티 공정을 제3 그룹으로 분류하는 프로젝트 관리 장치.
3. The system according to claim 2,
Classifying the activity process in which the allowance period of the activity schedule of the project is less than 0 into the first group,
Classifying the activity processes having an allowance period of the activity schedule of the project equal to or more than 0 and smaller than a predetermined reference date into a second group,
And classifies the activity process in which the allowance period of the activity schedule of the project is equal to or greater than the reference date into the third group.
제2항에 있어서,
상기 납품지연 예상부는 상기 그룹핑된 작업 공정이 색상을 달리하여 인터페이스 화면에 표시되도록 제어하는 프로젝트 관리 장치.
3. The method of claim 2,
Wherein the delivery delay estimating unit controls the grouped work processes to be displayed on an interface screen with different colors.
제1항에 있어서, 상기 프로젝트 관리 장치는,
상기 진행중인 전체 프로젝트를 리스트업하고,
사용자가 전체 프로젝트 리스트 중 어느 하나를 선택하는 경우, 해당 프로젝트와 관련된 하위 작업 일정들이 바 형태로 상기 사용자 인터페이스부에 표시되도록 제어하는 프로젝트 관리부를 더 포함하는 프로젝트 관리 장치.
The system according to claim 1,
List up the entire project in progress,
And a project management unit for controlling the user interface unit to display sub-work schedules related to the selected project in the form of a bar when the user selects one of the entire project list.
제 5항에 있어서,
상기 프로젝트 관리부는 진행중인 전체 프로젝트 중, 설계 단계인 프로젝트와 생산단계인 프로젝트를 구분하여 상기 인터페이스부에 표시되도록 제어하는 프로젝트 관리 장치.
6. The method of claim 5,
Wherein the project management unit classifies a project as a design stage and a project as a production stage among the entire projects in progress and controls the interface unit to display the project.
제5항에 있어서,
상기 프로젝트 관리부는 여러 프로젝트에 대한 정보를 취합하여 리스트업하거나 통계 정보를 생성하여 상기 인터페이스 화면에 표시되도록 제어하는 포함하는 프로젝트 관리 장치.
6. The method of claim 5,
Wherein the project management unit collects information on various projects and generates list information or generates statistical information and controls the information to be displayed on the interface screen.
KR1020160080247A 2016-06-27 2016-06-27 Project management apparatust KR20180001297A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020160080247A KR20180001297A (en) 2016-06-27 2016-06-27 Project management apparatust

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020160080247A KR20180001297A (en) 2016-06-27 2016-06-27 Project management apparatust

Publications (1)

Publication Number Publication Date
KR20180001297A true KR20180001297A (en) 2018-01-04

Family

ID=60998241

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020160080247A KR20180001297A (en) 2016-06-27 2016-06-27 Project management apparatust

Country Status (1)

Country Link
KR (1) KR20180001297A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200107632A (en) * 2019-03-08 2020-09-16 포항공과대학교 산학협력단 Management method and system for detail engineering of plant projects
KR102250353B1 (en) * 2019-11-15 2021-05-11 울산과학기술원 Method and displaying project schedule
CN113256131A (en) * 2021-06-01 2021-08-13 安徽鑫洋信息工程有限公司 Intelligent coordination construction system of prefabricated building
KR102315373B1 (en) * 2021-05-20 2021-10-19 씨제이대한통운 (주) Construction process navigation providing method
US20220277268A1 (en) * 2019-10-01 2022-09-01 Jgc Corporation Project management apparatus, project management method, and recording medium
KR20230065011A (en) * 2021-11-04 2023-05-11 (유)구이앤금우통신 Erp system
CN116681313A (en) * 2023-08-02 2023-09-01 菏泽市国土综合整治服务中心 Land comprehensive renovation project supervision system

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200107632A (en) * 2019-03-08 2020-09-16 포항공과대학교 산학협력단 Management method and system for detail engineering of plant projects
US20220277268A1 (en) * 2019-10-01 2022-09-01 Jgc Corporation Project management apparatus, project management method, and recording medium
KR102250353B1 (en) * 2019-11-15 2021-05-11 울산과학기술원 Method and displaying project schedule
KR102315373B1 (en) * 2021-05-20 2021-10-19 씨제이대한통운 (주) Construction process navigation providing method
CN113256131A (en) * 2021-06-01 2021-08-13 安徽鑫洋信息工程有限公司 Intelligent coordination construction system of prefabricated building
CN113256131B (en) * 2021-06-01 2024-02-02 安徽鑫洋信息工程有限公司 Intelligent coordination construction system of assembled building
KR20230065011A (en) * 2021-11-04 2023-05-11 (유)구이앤금우통신 Erp system
CN116681313A (en) * 2023-08-02 2023-09-01 菏泽市国土综合整治服务中心 Land comprehensive renovation project supervision system
CN116681313B (en) * 2023-08-02 2023-10-10 菏泽市国土综合整治服务中心 Land comprehensive renovation project supervision system

Similar Documents

Publication Publication Date Title
KR20180001297A (en) Project management apparatust
Li et al. A blockchain-and IoT-based smart product-service system for the sustainability of prefabricated housing construction
US7168045B2 (en) Modeling business objects
Aziz et al. Applying lean thinking in construction and performance improvement
US8069071B2 (en) Suite of configurable supply chain infrastructure modules for deploying collaborative e-manufacturing solutions
US7519539B1 (en) Assisted profiling of skills in an enterprise management system
Frantzén et al. A simulation-based scheduling system for real-time optimization and decision making support
US20110145284A1 (en) Presenting skills distribution data for a business enterprise
EP2551807A2 (en) Automated system for digitized product management
US20130085587A1 (en) System and method for controlling the operations of a manufacturing facility
US20240193515A1 (en) Systems and methods for generating construction models for construction projects
Gademann et al. Linear-programming-based heuristics for project capacity planning
JP2003228410A (en) Work commencement management system
KR20140077065A (en) System for engineering procurement construction business management and management method thereof
Rossiti et al. Impacts of lean office applications in the supply sector of a construction company
Neumann et al. Continuous process management
JP6695673B2 (en) Plan generation device and plan generation method
Löfstrand et al. Evaluating availability of functional products through simulation
Zahran et al. The effect of learning on line of balance scheduling: Obstacles and potentials
Taha et al. Overall Cost Overrun Estimate in Residential Projects: A Hybrid Dynamics Approach
Yung et al. A mechanism for the integration of TQM and MRPII
Yang et al. Designing an Industrial Product Service System for Robot-Driven Sanding Processing Line: A Reinforcement Learning Based Approach
WO2023166690A1 (en) Warehouse work management system, warehouse work management method, and program
Papapanagiotou et al. A real-world case study of process and data driven predictive analytics for manufacturing workflows
Sahin et al. The first function of engineering management: Planning