KR20170055849A - Structure for protecting landslide - Google Patents

Structure for protecting landslide Download PDF

Info

Publication number
KR20170055849A
KR20170055849A KR1020150159143A KR20150159143A KR20170055849A KR 20170055849 A KR20170055849 A KR 20170055849A KR 1020150159143 A KR1020150159143 A KR 1020150159143A KR 20150159143 A KR20150159143 A KR 20150159143A KR 20170055849 A KR20170055849 A KR 20170055849A
Authority
KR
South Korea
Prior art keywords
retaining wall
reinforcing
connecting member
ground
present
Prior art date
Application number
KR1020150159143A
Other languages
Korean (ko)
Inventor
윤태홍
전상현
Original Assignee
윤태홍
전상현
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 윤태홍, 전상현 filed Critical 윤태홍
Priority to KR1020150159143A priority Critical patent/KR20170055849A/en
Publication of KR20170055849A publication Critical patent/KR20170055849A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • E02D5/08Locking forms; Edge joints; Pile crossings; Branch pieces
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/10Prefabricated parts, e.g. composite sheet piles made of concrete or reinforced concrete
    • E02D5/12Locking forms; Edge joints; Pile crossings; Branch pieces

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

According to the present invention, a structure for protecting a landslide comprises: a retaining wall inserted into the inside of an underground; a reinforcing pile installed to be spaced from the rear of the retaining wall at a predetermined distance, and inserted into the inside of the underground at a predetermined distance; and a connection member connected between the retaining wall and the reinforcing pile, and installed to be spaced in a vertical direction at a predetermined distance. According to the present invention, the structure for protecting a landslide installs the reinforcing pile in the rear of the retaining wall, and connects and supports the retaining wall and the reinforcing wall with a plurality of connection members. Therefore, earth pressure can be dispersed, and occurrence of the whole displacement of the structure for protecting a landslide can be restricted.

Description

{STRUCTURE FOR PROTECTING LANDSLIDE}

The present invention relates to a retention structure, and more particularly, to a retention structure provided at the rear of a retention structure to be installed in the ground, wherein the retention structure and the reinforcing pile are connected by a connecting member to be fixed, Thereby minimizing the size of the retaining structure.

A retaining structure refers to a structure such as a wall that resists water pressure such as earth pressure or ground water for the purpose of preventing the collapse of the ground or the ground of the surrounding ground during the crushing of the crushed area for the foundation work.

Conventionally, a strut method, an earth anchor method, a soil nail method, a raker method, and the like have been used as a method of supporting the earth retaining structure.

If the excavation area is increased, the length of the strut is lengthened, so that buckling of the joint and distortion of the strut can cause the surrounding ground to settle down due to the deformation of the retaining structure.

The ground anchor method and the soilless nail method have the problem that ground anchor and sole nail construction can not be done when the underground water level is low and the grouting effect is small and there is not enough room at the boundary of the ground such as the underground floor of the adjacent building have.

In the case of the lacquer method, if the depth of excavation is deep, the buckling problem due to the long-term interaction of the lacquer member occurs, and the possibility of wall displacement and subsidence becomes high.

Also, the increase of the number of reinforcing stages and the construction of the intermediate pile cause a problem that the workability is lowered and the construction cost is increased.

Therefore, in the conventional method of supporting the retaining structure, when the excavation area is large, the buckling phenomenon and twisting occur due to the long conversation of the strut, and there is a fear of the settlement of the surrounding ground and due to the installation work of the lacquer, strut, and anchor, There is a problem that cost and air are increased.

Disclosure of Invention Technical Problem [8] In order to solve the problems described above, the present invention has been made to solve the above-mentioned problems, and it is an object of the present invention to provide a soil- And to prevent the occurrence of overall displacement of the retaining structure.

It is another object of the present invention to provide an earth retaining structure capable of enabling excavation work even if a structure is located around the earth retaining wall and reducing air and construction cost.

The earth retaining structure according to the present invention comprises: an earth retaining wall inserted into the ground; A reinforcing file installed at a predetermined distance behind the earth retaining wall and inserted into the ground at predetermined intervals; And a connecting member connected between the retaining wall and the reinforcing pile and spaced apart from each other by a predetermined distance in the vertical direction.

In addition, one end of the connecting member is coupled through the through hole formed in the earth retaining wall body, and the other end of the connecting member is coupled through the through hole formed in the reinforcing pile.

The reinforcing file may be a concrete file or a steel pipe file, and the connecting member may be a reinforcing bar, a PC strand, or a steel bar.

According to the present invention, the reinforcing pile is installed in the back of the retaining wall, and the retaining wall and the reinforcing pile are supported by a plurality of connecting members, thereby dispersing the earth pressure and suppressing the occurrence of overall displacement of the retaining structure.

Also, the earth retaining structure according to the present invention is easy to construct and can shorten construction cost and construction period.

1 is a plan view showing an assembled state of a retaining structure according to an embodiment of the present invention;
2 is a plan view showing an assembled state of the earth retaining structure according to another embodiment of the present invention.
3 is a plan view showing an assembled state of the earth retaining structure according to another embodiment of the present invention.
4 is a view showing an installation state of a retaining structure according to the present invention;
5 is a view showing a reinforcement file of a retaining structure according to the present invention

BRIEF DESCRIPTION OF THE DRAWINGS The advantages and features of the present invention, and how to accomplish them, will become apparent by reference to the embodiments described in detail below with reference to the accompanying drawings.

However, the present invention is not limited to the embodiments described below, but may be embodied in various other forms.

The present embodiments are provided so that the disclosure of the present invention is thoroughly disclosed and that those skilled in the art will fully understand the scope of the present invention.

In addition, throughout the specification, like reference numerals refer to like elements, and the terms (mentioned) used herein are intended to illustrate the embodiments and not to limit the invention.

Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings.

FIG. 1 is a plan view showing an assembled state of the earth retaining structure according to an embodiment of the present invention, FIG. 2 is a plan view showing an assembled state of the earth retaining structure according to another embodiment of the present invention, and FIG. FIG. 7 is a plan view showing an assembled state of the earth retaining structure according to another embodiment. FIG. FIG. 4 is a view showing an installation state of the earth retaining structure according to the present invention, and FIG. 5 is a view showing a reinforcement file of the earth retaining structure according to the present invention.

1 to 4, the retaining structure includes a retaining wall 100, a reinforcing pile 200 disposed behind the retaining wall 100, and a reinforcing pile 200 connecting the piling wall 100 and the reinforcing pile 200 And a connecting member 300 for connecting the connecting member 300 and the connecting member 300.

The earth retaining wall body 100 may be vertically inserted into the ground, and the earth retaining wall body 100 may be variously provided as shown in FIGS. 1 to 3.

1, the earth retaining wall 100 according to an embodiment of the present invention may include an H-shaped file 110 and an earth retaining plate 120. The H-shaped file 110 may be formed in the ground And the earth retaining plate 120 is inserted into the ground in the longitudinal direction of the H-shaped file 110 between the H-shaped files 110 inserted into the ground.

 The earth retaining plate 120 may be a steel plate or a turntable made of wood. The earth retaining plate 120 may be fixed to the flange of the H-shaped pile 110 by welding or fastening means.

As shown in FIG. 2, the earth retaining wall 100 according to another embodiment of the present invention may be formed by a CIP method.

As shown in FIG. 2, the CIP method uses a punching machine to drill a predetermined diameter of the pit to a designed depth, inserts the steel assembly 124 into a drilled hole, pours concrete, The concrete piles are placed continuously with the outer circumferential surfaces in contact with each other to form a soil wall.

The H-shaped file 120 may be inserted in place of the reinforcing bar assembly 124 to increase the strength.

Meanwhile, the earth retaining wall 100 according to another embodiment of the present invention may be formed by the SCW method as shown in FIG.

The SCW method is a method for forming a cement pile by mixing soil with excavated soil while injecting cement after piercing the ground to a designed depth, and continuously constructing the cement pile in a superposed manner to form a soil wall. (130) can be inserted into the stress material to reinforce the strength.

The reinforcing pile 200 is spaced apart from the piling wall 100 by a predetermined distance and inserted vertically into the ground so that the piling wall 100 and the reinforcing pile 200 are connected by a connecting member 300, Are connected and fixed.

As shown in FIG. 3, the reinforcing file 200 may be installed by inserting the non-reinforced concrete file 210, the reinforced concrete file 220, the steel pipe file 230 and the like along the longitudinal direction into the ground.

4, one end of the connecting member 300 is fixed by the fastening member 320 through the retaining wall body 100 and the other end passes through the reinforcing pile 200 to be fastened to the fastening member 320 And the connecting member 300 may be installed at predetermined intervals along the longitudinal direction of the securing wall 100 and the reinforcing pile 200 in the ground.

The connecting member 300 may be made of a steel material such as a reinforcing bar, a steel bar, and a PC stranded wire. The connecting member 300 has one end inserted through the through hole 340 formed in the uprising wall body 100 And one end of the connecting member 300 is fixed to the stationary wall body 100 by a fastening member 320 such as a nut or an angle, .

The other end of the connecting member passes through the through hole 340 formed in the reinforcing pile 200 and can be fixed to the ground outside the reinforcing pile by the fastening member 320.

The fastening member 320 fixed to the reinforcing pile 200 is formed to have a wing member and is screwed to an end of the connecting member 300 so that the connecting member 300 is fastened to the fastening member 320, The fastening member 320 fixed to the connecting member 300 may be passed through the through hole 340 formed in the reinforcing pile 200. [

When the fastening member 320 fixed to the fastening member 320 is rotated, the fastening member 320 and the connecting member 300 are screwed and fixed, The wing member formed on the fastening member 320 is stably fixed to the ground so that the fastening member 320 can be fixed to the ground.

When the earth retaining wall member 100 is a concrete pile formed by a CIP method, a filler such as styrofoam is filled at a position where the connecting member 300 penetrates and is to be coupled, and the reinforcing bar assembly 124, After the concrete pile is completed by pouring concrete into the concrete pile, if the filler is removed, the through hole 340 through which the connecting member 300 penetrates the concrete pile can be formed.

A method of installing the retaining structure according to the present invention will be described.

First, the retaining structures shown in FIGS. 1 to 3 are vertically installed in the ground, and the reinforcing piles 200 are installed at a predetermined distance behind the retaining structures.

4, one end of the connecting member 300 is connected to the through hole 340 formed in the earth retaining wall body 100, and the other end of the connecting member 300 is connected to the through- Through holes (340) formed in the reinforcing pile (200).

The connecting member 300 includes a plurality of through holes 340 formed at predetermined intervals in the lengthwise direction of the earth retaining wall body 100 and a plurality of through holes 340 formed at predetermined intervals in the longitudinal direction of the reinforcing pile 200, A plurality of portions are provided at predetermined intervals.

The retaining structure according to the present invention includes a retaining wall 100 installed in the ground and a reinforcing pile 200 disposed at a predetermined interval behind the piling wall 100 to connect the retaining pavement 100 and the reinforcing pile 200 to a connecting member 300 to disperse the earth pressure behind the earth retaining wall 100 to reduce the overall displacement of the retaining structure.

The earthen block 100 and the reinforcing pile 200 are fastened to each other by a connecting member 300 so that the earthen block 100 and the reinforcing pile 200 are fastened to each other. Stability can be enhanced.

100: mattress wall 110: H-shaped file
120: a retaining plate 124: a reinforcing assembly
200: reinforcement file 300: connection member
320: fastening member 340: through-hole

Claims (4)

A retaining wall installed in the ground;
A reinforcing file installed at a predetermined distance behind the earth retaining wall and inserted into the ground at predetermined intervals; And
And a connecting member connected between the retaining wall and the reinforcing pile to be spaced apart from each other by a predetermined distance in a vertical direction.
The method according to claim 1,
Wherein one end of the connecting member is coupled through the through hole formed in the earth retaining wall body and the other end of the connecting member is coupled through the through hole formed in the reinforcing pile.
The method according to claim 1,
Wherein the reinforcing file is a concrete file or a steel pipe file.
The method according to claim 1,
Wherein the connecting member is one of a reinforcing bar, a PC strand, and a steel bar.
KR1020150159143A 2015-11-12 2015-11-12 Structure for protecting landslide KR20170055849A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020150159143A KR20170055849A (en) 2015-11-12 2015-11-12 Structure for protecting landslide

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020150159143A KR20170055849A (en) 2015-11-12 2015-11-12 Structure for protecting landslide

Publications (1)

Publication Number Publication Date
KR20170055849A true KR20170055849A (en) 2017-05-22

Family

ID=59050183

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020150159143A KR20170055849A (en) 2015-11-12 2015-11-12 Structure for protecting landslide

Country Status (1)

Country Link
KR (1) KR20170055849A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101995838B1 (en) * 2018-11-02 2019-07-03 주식회사 티앤테크 Constructron method of earth retaining wall

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101995838B1 (en) * 2018-11-02 2019-07-03 주식회사 티앤테크 Constructron method of earth retaining wall

Similar Documents

Publication Publication Date Title
KR101014796B1 (en) Top-down underground construction method using prefabricated concrete column member as temporary bridge column
KR100917044B1 (en) Concrete retaining wall construction method with dual wall jointed by anchor
KR101973565B1 (en) Sheathing method for constructing both sheathing wall and cutoff collar by welding cutoff plate to phc pile with longitudinal plate
JP2006291575A (en) Retaining wall and method of constructing the same
KR101612521B1 (en) Method for constructing underground structures restraining transformation and using external wall
KR100914158B1 (en) Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut
KR20130006420A (en) Method of constructing underground structure to be newly built
JP5986429B2 (en) Caisson and manufacturing method thereof
KR101195235B1 (en) Underground structure construction method using composite pile
JP5976373B2 (en) Pile foundation reinforcement structure and reinforcement method
KR102223856B1 (en) Foundation structure of waste landfill site and construction method thereof
KR101331219B1 (en) Method for constructing micro pile using reinforcing end bearing capacity
KR102490872B1 (en) Reinforced earth retaining wall and construction method using tensile force of steel rod piles
KR20110052321A (en) Steel pipe pile for sheet pile wall and construction method using that
KR102113291B1 (en) Soil retaining wall using phc pile and construction method thererof
JP5456627B2 (en) Connection structure and method of connection between pile and steel column
KR101649448B1 (en) An assembly for retaining sheet pile wall
KR102497458B1 (en) Cip Retaining Reinforcing Structure and Method Constructing the Same
KR20170055849A (en) Structure for protecting landslide
KR20170057808A (en) Composite pile
JP5777435B2 (en) Reinforcement method for foundations for small buildings
JP2016223208A (en) Pile foundation structure
KR20190142546A (en) Construction method of subsurface structure using outer shell suspension
KR101075922B1 (en) Metal tubing picket with reinforced tip for auger-drilled piling method
JP2015055105A (en) Underground structure, and method of reconstructing building structure with underground skeleton

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
AMND Amendment
E601 Decision to refuse application
AMND Amendment
J201 Request for trial against refusal decision
J301 Trial decision

Free format text: TRIAL NUMBER: 2018101000592; TRIAL DECISION FOR APPEAL AGAINST DECISION TO DECLINE REFUSAL REQUESTED 20180209

Effective date: 20190228